MONTHLY CONSTRUCTION

SCHEDULE

For the Month: Cumulative Month:


Project Name:
Location:
Date Start: Target Completion:
Planned Activities:
Material Qty
Item No. Required Work Description Duration Weekly Schedule
Balance Projected W1 W2 W3 W4 W5
SHORING AND OTHER RELATED
103(5)b 30 WORKS (ASSUME FOOTING AREA=55 20 days ⩗ ⩗ ⩗ ⩗
SQ.M)
REINFORCING STEEL BAR, GRADE 40
404a 1500.00 (BRIDGE STRUCTURE & OTHER 30 days ⩗ ⩗ ⩗ ⩗ ⩗
MAJOR)
REINFORCING STEEL BAR, GRADE 60
404b 5000.00 (BRIDGE STRUCTURE & OTHER 30 days ⩗ ⩗ ⩗ ⩗ ⩗
MAJOR)
STRUCTURAL CONCRETE CLASS A
405(2) 50 (MAJOR STRUCTURE)-BRIDGE SUPER 2 days - - - ⩗ -
STRUCTURE, 27 MPA
STRUCTURAL CONCRETE CLASS A
405(3) 4 (LEAN CONCRETE-MINOR 1 day - - - ⩗ -
STRUCTURE)
507 50 RUBBLE CONCRETE 30 days ⩗ ⩗ ⩗ ⩗ ⩗
508 150 HANDLAID ROCK EMBANKMENT 30 days ⩗ ⩗ ⩗ ⩗ ⩗
Equipment Requirement
Estimated Schedule Other
Description Quantity Duration
W1 W2 W3 W4 W5 Information:
BACKHOE 1 27 DAYS ⩗ ⩗ ⩗ ⩗ ⩗
TRANSIT MIXER 2 3 DAYS - - - ⩗ -
PORTABLE VIBRATOR 1 3 DAYS - - - ⩗ -

Manpower Requirement
Estimated Schedule Remarks:
Designation Number Duration
W1 W2 W3 W4 W5
Foreman 1 30 days ⩗ ⩗ ⩗ ⩗ ⩗
Carpenter 2 30 days ⩗ ⩗ ⩗ ⩗ ⩗
Masons 5 30 days ⩗ ⩗ ⩗ ⩗ ⩗
Laborers 6 30 days ⩗ ⩗ ⩗ ⩗ ⩗

FM-CON-002
Rev 0 Jan. 13, 2014