WEEKLY PROGRESS MEETING

Project Name : Modification of LP Separator Bridle Flushing System Date : November 17, 2019
Project Engineer : Syed Mateen ETC : December 7, 2020

1. PROGRESS

Description Overall Weightage (%) Activity Weightage (%) Activity Project Progress(%) Progress Weightage(%)

Procurement 30% 30.00%


Pipes, Flanges, Valves and Fittings 70% 21.00% 100.00% 21.00%
Tools and Consumables 30% 9.00% 100.00% 9.00%

Construction 55% 22.55%


Erect Scaffolding 30% 16.50% 100.00% 16.50%
Blasting and Coating of pipes 20% 11.00% 35.00% 3.85%
Fit-up, Welding and erection of Piping 40% 22.00% 10.00% 2.20%
Installation of Valves and Torquing 10% 5.50% 0.00% 0.00%
Comissioning 15% 0.00%
Hydrotest 80% 12.00% 0.00% 0.00%
Tie-In 20% 3.00% 0.00% 0.00%

TOTAL 100% 100% 52.55%

2. Major Accomplishments Past Week

1. Material Receiving Inspection of Replacement Pipes and fittings is completed by KJO.


2. Third party inspection for WPS and PQR is done.
3. Fabrication of 1-1/2’’ Pipe is in progress.

3. Work Status

1. Scaffolding is completed at site.


2. Material Receiving Inspection of all Pipes and fittings is completed by KJO.
3. Coating for 1-1/2’’ Pipe is done and Inspection is completed by KJO.
4. Blasting and coating of 1’’& 2’’ is planned on Saturday i.e. 16th Nov.
5. Third party inspection for Welder qualification is done , Awaiting for WPS and PQR.
6. Fabrication of 1-1/2’’ Pipe is in progress.