TEG - P/E/I/T/St/Saf HOOKUP WORKSHOP Minute Of Meeting

Project No: N0510

Project Title: EPC CONTRACT FOR TYRA REDEVELOPMENT PROJECT

The TEG hook-up workshop was conducted from 26th to 29th of August with Company and MDR engineering / hookup team
representatives. The below register identifies the discussion points and recommendations from Company with regards to Offshore hook-up
and associated work packages area.

Snapshot (SS)
Item No Area Comment Discipline Comment Resolution STATUS
Number

NODE 11_TEG : HOOK-UP WORK PACKAGE BETWEEN TEC PLATFORM TOPSIDE AND TECZ BRIDGE NORTH - NODE 11 (OFFSHORE INSTALLATION)
To ensure the alignment between Topside and Bridge piping, MDR to provide dimensional
reports confirming hookup strategy (straight lines - limited degree of freedom) for each
Convert the local co-ordinate into te global co-
1 SS No. 01 Common hookup Node with consideration of fabrication and installation tolarence. PIP Closed
ordinates. And Global Co-ordinates should match.
McDermott and COMPANY to be aligned on fabrication tolerances considering limited
degree of freedom.
Interface connection (flange/ Hub/ Butt-weld) for fire water lines (Node 11) between the TEC
2 SS No. 02 Node 11 PIP
hookup spool and the TECZ bridge should be verifed inline with WHRP. Double check and to be comphare with Package 1
Closed
Ensure tie-in flange connections on TEC side are inside the hazardous zone (Line No. DPS- (WHRP) Connection by Engineerin
3 SS No. 03 Node 11 PIP
8549 & DOS-8728)
Tie-in Connection between TECZ bridge and hookup spool to be welded type - Line NoPHS- Engineering to be Update the model, P&ID and
4 SS No. 04 Node 11 PIP Closed
0009, Line No-PHS-0008, -PHS-0007, Isometric
Flanges / Butt Welding at Bridge interface area to be staggered to facilitate space for
welding and welding point should clear support location (Typ) Engineering to be Update the model, P&ID and
5 SS No. 05 Common PIP Closed
For Butt welding connections highest wall thickness of the pipe to be provided on the Isometric
outside (1 of 2) for ease of welding. No re-routing is required for this purpose.
Dropped Object protection - Check the design requirement with material handling path and
6 SS No. 06 Node 11 STR
safety (DOP study)?
7 SS No. 07 Node 11 Interface junction box requirement for PTMS cableto be confirmed with COMPANY TEL
Check the lighting fixures / sockets location along the bridge with regards to consistency with
8 SS No. 08 Common ELEC
other bridges (for having cable ladders closer to the walk ways)
Misalignment (location / sizing / Bend radius requirement) of cable ladders in 3D Model at
Node 11
9 SS No. 09 the hook-up location (TECZ vs. TEC hookup) shall be checked and fixed. Cable ladder ELEC
TEC
supports shall be adjusted accordingly.
Consider moving the HV cable ladder as close as possible to the walk way handrail for easy
10 SS No. 10 Node 11 ELEC
access.
11 SS No. 11 Node 11 Electrical cable tray - chk the hookup colour, update accordingly ELEC

NODE 12_TEG : HOOK-UP WORK PACKAGE BETWEEN TEG PLATFORM TOPSIDE AND TECZ BRIDGE SOUTH - NODE 12 (OFFSHORE INSTALLATION)
To ensure the alignment between Topside and Bridge piping, MDR to provide dimensional
reports confirming hookup strategy (straight lines - limited degree of freedom) for each
Following Dimensional Procedure and report refer
1 SS No. 12 Common hookup Node with consideration of fabrication and installation tolarence. PIP Closed
to "DK-TEYY-QUA-PRO-000-10014" has approved.
McDermott and COMPANY to be aligned on fabrication tolerances considering limited
degree of freedom.
Flanges / Butt Welding at Bridge interface area to be staggered to facilitate space for
welding and welding point should clear support location (Typ) Engineering to be Update the model, P&ID and
2 SS No. 13 Common PIP Closed
For Butt welding connections highest wall thickness of the pipe to be provided on the Isometric
outside (1 of 2) for ease of welding. No re-routing is required for this purpose.
Check the lighting fixures / sockets location along the bridge with regards to consistency with
3 SS No. 14 Common ELEC
other bridges (for having cable ladders closer to the walk ways)

1 OF 5
Snapshot (SS)
Item No Area Comment Discipline Comment Resolution STATUS
Number
After the elbow, extend the hook up spool length beyond the elbow joint at Tie-in location.
Minimum green length shall be as per 7.2.1.3 MOTS-03. Engineering to be Update the model, P&ID and
4 SS No. 15 Node 12 PIP Closed
Note: TEG Jacket Installation co-ordinates will be provided to Contractor, based on this the Isometric
spool length will be calculated.
To ensure shielding gas eqipment and boroscopic inspection; Flanged spools to be provided
5 SS No. 16 Common PIP Engineering to be Update the model, Isometric Closed
part of hook-up spools for non hydrocarbon CRA and CS lines.
Offshore spools/ hookup items to be reviewed with regards to the installation methodology
6 SS No. 17 Common considering either temporary framing or temporary crane. Hookup
Include these considerations in the hook up work packages.
Temporary supports to be shown in the model. Color coding for these items to be identified
7 SS No. 18 Common ALL
for easy identification for removal at off-shore.
8 SS No. 19 Node 12 Provide Ladder to access bridge bearing maintainance platform STRUC
Pipe spool will be installed Layer by Layer starting from bottom.
Installation of spool will be from top using crane supported on Level 4.(To be studied further
with COMPANY)
Additional scaffolding platform to support the 2nd and 3rd layer of piping during installation.
9 SS No. 20 Node 12 STRUC
MDR to propose scheme (strong points).
The walkway will be installed later after all the piping spool are inplace.
Walkway - can be hinged type or lifted and installed, depending upon the length of the
walkway and clash check from the walkway. (to be aligned with T&I contractor)
Hook up to be finalized as per final cable ladder routing and lighting fixture.
10 SS No. 21 Node 12 Cable Ladder support to be reviewed by structural. E&I
Layout to be developed and agreed with the COMPANY.
The Cable minimum bending radius and maximum free span to be installed on TEG- TECZ
11 SS No. 22 Node 12 E&I
bridge interface to be verified with vendor and incorporated in the design
The Spliced Cables between TECZ Bridge to TEG Platform overrun length 5 meter to be
12 SS No. 23 Noted 12 located on the TEG Platform. Identify suitable location of cable coiling. This location will be a E&I
temporary scaffolding platform due to the NTE lift weight limitations on TEG topsides.
To ensure shielding gas eqipment and boroscopic inspection; Flange joint/ T-Joint with blind
PIP /
will be provided for hydrocarbon CRA lines closer to the platform edge where F& G and
13 SS No. 24 Noted 12 SAFETY / -
deluge is covered.
ELE
Area classification drawings to be revised accordingly.
14 SS No. 25 Common CE marking philosophy for hook up items to be developed. PED
Relocate the drain line (2"-PHS-034-0005) on to the TEG side instead on hook-up spool
considering the bridge movement,extend the line 24"-PHS-034-0045-DX towards south to
15 SS No. 26 Node 12 PIP Closed
accomadate the Drain point and the Tie in point of the 24"-PHS-034-0045-DX to be moved
to North.
With reference to SS No. 24,
16 SS No. 61 Node-12 Provide a Flange joint closer to the Elbow or replace the Elbow with TEE with blind flange for PIP Closed
lines 3"-DPS-050-0128-AX, 3"-DOS-050-0038-AX.

With reference to SS No. 24,


Provide a TEE with blind flange for lines 24"-PHS-034-0045-DX(TEE in North Dir.), 20"-PHS-
17 SS No. 62 Node-12 PIP Closed
034-0046-FX(TEE in South Dir.), 14"-PHS-034-0043-DO(TEE in South Dir..), 8"-GPS-034-
0112-DX(TEE in North Dir.) in the vertical section immidiately after bottom elbow.

With reference to SS No. 24,


Provide a TEE with blind flange for flare line 18"-FHS-040-0006-ASM tentatively on south
18 SS No.63 Node-12 PIP Closed
side considering the F&G coverage & accessability.

With reference to SS No. 24,


19 SS No.64 Node-12 Provide a TEE with blind flange for line 10"-GPS-043-0009-DX in the vertical piping facing PIP Closed
towards south.

2 OF 5
Snapshot (SS)
Item No Area Comment Discipline Comment Resolution STATUS
Number

NODE 13_TEG : HOOK-UP WORK PACKAGE ON TEG PLATFORM TOPSIDE - NODE 13 (OFFSHORE INSTALLATION)
1 SS No. 51 Node - 13 void
Clear access for splitter box/ spacer box to be provided for umbilical cable testing/
inspection.
2 SS No. 52 Node - 13 ELE / PIP open
Door opening volumes to be shown in the model.
Reroute the line in order to provide clear access to splitter box from East side escape route.
3 SS No. 53 Node - 13 Re-route the cable ladder at the back of splitter box
4 SS No. 54 Node - 13 Review concept for stilling tubes installation and provide padeyes as required. STR
5 SS No. 55 Node - 13 Re-route cable tray to be located away from the laydown area. ELE
Hook-up spool boundary for large bore pump dischare lines to be defined to demonstrate
Update the model, P&ID and Isometric to identify
6 SS No. 56 Node - 13 offshore installation considering the installation tolerances. PIP Closed
Hook-up part
Hook-up spools to be identifed with proper color coding.
Hook-up spool boundary for small bore (lube oil supply and anti-fouling lines) to be defined
Update the model, P&ID and Isometric to identify
7 SS No. 57 Node - 13 to demonstrate offshore installation considering the installation tolerances. PIP
Hook-up part
Hook-up spools to be identifed with proper color coding.
Jacket walkway access platform will be provided in pieces per below
- two separate ladders with 300 mm green length
- vertical hangers with 300 mm green length
8 SS No. 58 Node - 13 - main platform with welded handrails and bolted grating STR

South side stair access installation will require hook up clamps capacity to be provided for
beams below the laydown area.
Transport analysis of Piping including the piping connected to sensitive equipment and the
recommendations by McDermott to be discussed and agreed with COMPANY.
Vendor recommendations for the sensitive equipment and associated piping to be
9 SS No. 60 Node-13 PIP
considered while finalizing the transport analysis recommendations.
MDR to demonstrate the possibilty of adjustment of potential misalignment of sensitive
equipment piping after transportation and installation.

NODE 14_TEG : HOOK-UP WORK PACKAGE BETWEEN TEG PLATFORM TOPSIDE AND FLARE - NODE 14 (OFFSHORE INSTALLATION)
Flanged hook up spool to be provided for all flare tower lines.
1 SS No. 35 Node-14 Verify the flanged joints are covered by F&G. PIP / Safety Closed
Area classification drawings to be revised accordingly.
Hook-up spool to be designed with 2 directional adjustment to accommodate installation
2 SS No. 36 Node-14 PIP Closed
tolerances.
3 SS No. 37 Node-14 Handrail and Light-post to be shown as removable based on T&I provided markup. STR / ELE
The flare shall be fuly equipped with cables and equipment. Interface JB to be added at
4 SS No. 38 Node-14 E&I
flare. Wherever special cable is proposed, cable to be coiled at flare stair landing area
5 SS No. 39 Node-14 Ignition and Antenna cable type to be confirmed from vendor E&I

NODE 15_TEG : HOOK-UP WORK PACKAGE BETWEEN TEG PLATFORM TOPSIDE AND NEW JACKET - NODE 15 (OFFSHORE INSTALLATION)
To ensure the alignment between Topside and Caisson piping, MDR to provide dimensional
reports confirming hookup strategy (straight lines - limited degree of freedom) for each
1 SS No. 40 Common hookup Node with consideration of fabrication and installation tolarence. PIP Closed
McDermott and COMPANY to be aligned on fabrication tolerances considering limited
degree of freedom.

3 OF 5
Snapshot (SS)
Item No Area Comment Discipline Comment Resolution STATUS
Number
Demonstrate the caisson hook-up spool installation between the topsides and jacket with
consideration of following

- Provide installation sequencing for the flanged hook-up spool


Hook-up /
2 SS No. 41 Node-15 - Lifting of the upper section on topsides, beam capacity to be verified Closed
PIP
- Review support types for the pipes joining to the topsides section of the caisson for lifting
clearance
- Requirement of permanent and temporary supports (transportataion / Installation)

Requirement of supply of hook-up spools in pieces/ loose supply of all materials for hook-up
spools will be confirmed by COMPANY once the CE marking philosophy is finalized
3 SS No. 42 Common COMPANY
(between MDR and NOBO) for hook up spools.
This is applicable for all the hook-up spools at bridges, flare and jacket.
4 SS No. 43 Node-15 Provide a staright length (~300 mm) between the elbow and the flange at the hook-up joint PIP Closed
Preferreed to have flanged hook-up spools for the lines connected to the Sewage Caisson,
5 SS No. 44 Node-15 PIP Closed
and non-hazardous drain caisson.
Verify rerouting the 28"-DOS-050-0384 line by extending the line towards south before
turning towards east to enable to take the support from main beam.
6 SS No. 45 Node-15 PIP Closed
Preferreed to have flanged hook-up spool for the line (28"-DOS-050-0384) connected to the
deluge drain caisson.
Concept for cable pulling for 50MT load as per SOW is agreed.
MDR has to clear the clashes and mature the design as per below:
Cable pulling volume clearance required is 300mm diameter all the way upto the winch. This
7 SS No. 46 Node - 15 STR
clearance volume shall be cleared of any obstruction.
Height provided from top of flange to underside of pulley is 6.9m and considered adequate.

Current location of Winch shown on Level 4 -upper deck to be moved towards the south side
suitable length to allow spooling of wire.
8 SS No. 47 Node - 15 STR
MDR to provide base plates for the winch support to be bolted.
Winch clear distance from edge of platform will be 7m as confirmed by Company.
Contractor will only provide strong points (padeye, support plate). Consider accessibility for
9 SS No. 48 Node - 15 installing the sling. STR
Winches, Slings, Pulleys, sheave required for installation will be provided by Company.
10 SS No. 49 VOID
J-Tube to be designed as installed at Yard in 1 piece and lower down at offshore for hookup.
Clash check with cable ladder to be checked and if required do hookup of the clashing
11 SS No. 50 Node - 15 STR
items.
Seafastening concept for J-tube to be developed and agreed with Company.
12 SS No. 59 Node 15 Support to be permanent (yard installed) without obstructing no go zone. PIP Closed

NODE 16_TEG: HOOK-UP WORK PACKAGE BETWEEN TEG PLATFORM TOPSIDE AND TEHZ BRIDGE EAST - NODE 16 (OFFSHORE INSTALLATION)
To ensure shielding gas eqipment and boroscopic inspection; provide Tee joints with blind
1 SS No. 29 Node-16 flanges on the Hook-up spool for the Fire water lines WF-7004 & WF-7005, the Tie-in PIP closed
connections are welded type.
To ensure shielding gas eqipment and boroscopic inspection; Flanged spools to be provided
2 SS No. 30 Node-16 PIP closed
part of hook-up spools for non hydrocarbon CRA lines (except Fire Water Lines).
Safety to review and confirm that the introduction of flanged spool for the diesel hook-up line
3 SS No. 31 Node-16 Safety closed
at the TEG - TEHZ interface is acceptable.
Pipe support structure to clear the bridge installation volume and the design should optimize
4 SS No. 32 Node-16 STR
the off-shore hook-up.

4 OF 5
Snapshot (SS)
Item No Area Comment Discipline Comment Resolution STATUS
Number

Handling of Hook-up spools using the Level-2 laydown area on south side of the platform.
Trolley to be used to transfer the spools from laydown area to bridge landing area.
Beam clamps will be used for handling the spools, Structure to provide loading capacity of
5 SS No. 33 Node-16 STR
the beams for fixing the beam clamps.
Structure to provide the maximum area hook-up load that can be supported from Level-4
beams on West side.
Hook-up cable trays to be optimized considering the bridge installation volume in order to
6 SS No. 34 Node-16 reduce the cable ladder hook-up. ELE
Cable ladder supprot to be verified with regards to bridge movement lateral forces.
Investigate if the cable (1x3+E - 95 - Premeg) can be spliced and coiled in the TEG and
7 SS No. 65 Node-16 Hook-up
TEH. (ref. SS No 27 of NODE 17)

NODE 17_TEG : HOOK-UP WORK PACKAGE BETWEEN TEH PLATFORM TOPSIDE AND TEHZ BRIDGE WEST - NODE 17 (OFFSHORE INSTALLATION)
Investigate if the cable (1x3+E - 95 - Premeg) can be spliced and coiled in the TEG and
1 SS No. 27 Node-17 Hook-up Closed
TEH. (ref. SS No 65 of NODE 16)
Misalignment (location / sizing ) of cable ladders in 3D Model at the hook-up location (TEHZ
2 SS No. 28 Node-17 ELE
vs. TEH hookup) to be informed and agreed with Rosetti.

5 OF 5