Beruflich Dokumente
Kultur Dokumente
Location KIIC
Remark
Approval
P.D V.P.D O.D F.D G.M SEC. M EST PIC
FM/OPR-024 Rev-0
FM/OPR-024 Rev-0
ESTIMATION NOTES & CONDITIONS
NAME OF PROJECT : XXX PROJECT
---------------------------------------------------------------------------------------------------------------------------------------------
6. Insurance ( ) : Included
(O) : Excluded
Civil Request
10. Foundations for the following: ( ) : Included
(O) : Excluded
A/C Equipment
Generator , Tank
Antenna
Pumps
Cable Trenches, Pit
Electrical
23. Main Feeder from Power Company (O) : Included
To S/S Panel ( ) : Excluded
E. Terms of Payment
1. Conditions ( ) : Performance Bond ( %)
(O) : Down Payment ( 30% )
(O) : Progress Payment/Month ( 70% )
( ) : Delivery on Site ( %)
( ) : Completion Rate
as your Approval ( %)
( ) : Retention Bond ( %)
XXX PROJECT
--------------------------------------------------------------------------------------------------------------------------------------------------------------
TOTAL COST
Rp
Masayuki Nishimori
----------------------------------
President Director
A- 3 Approved Checked Prepared
SUBMIT TO :
2016 - KDI - XXXX
XXX PROJECT D E S C R I PT I O N
PT. INDONAKANO
ESTIMATION PRICE NET PRICE 1st AMEND (1) PAYMENT CURRENCIES (4) CATEGORY
(E) 4,788,900,000 27.5% 4,107,887,365 23.6%
MATERIALS
(M) 6,814,583,800 39% 6,089,357,400 35% US $ % 1. BUILDING
(E) 890,900,000 5.1% 730,040,000 4.2%
LABOUR
(M) 887,716,200 5% 752,301,900 4%
(b) SUB - CON TOTAL 240,700,000 1.4% 181,055,700 1.0% Rp. % 3. OTHERS
(c) SUB - TOTAL ( a ) + ( b ) 13,622,800,000 78.3% 11,860,642,365 68.2%
Provision
E Transportation 0.30%
X Drawing 1.00%
P Temporary.F 0.25%
E Application (2) PAYMENT CONDITION (5) TOTAL FLOOR AREA 7,777 M2
N Mobil 0.55%
S Tools.Fee 0.35% DOWN PAYMENT
E Dormitory 0.55%
S Stationary 0.25% 30 %
Site Expense 1.45% 940,000,000 (6) LOCATION KIIC
Entertainment 0.30% PROGRESS PAYMENT
(d) EXP - TOTAL - 0.0% 940,000,000 5.4%
(d)+(f)
- 2,158,000,000 12.4%
EXPENSES TOTAL
(g) JAPANESE S/V 7.5% 1,305,000,000 7.5%
(e)+(f)+(g)
(h) 13,622,800,000 15,323,642,365 88.1%
TOTAL DIRECT COST
ADM DRWNG 6.5% 1,131,000,000 6.5% (3) EXCHANGE RATE
O CONST. SERVICE 3.0% 522,000,000 3.0%
H 0.0% 1 YEN = Rp.
0.0%
Materials Labour
No Description Unit Q'ty Cost Cost
Rp Rp
ELECTRICAL WORK
1 Incoming Work
MVMDB
Medium Voltage Panel Incoming LBS Ea 1 35,126,300 35,126,300
Medium Voltage Panel Cubicle VT Ea 1 41,905,000 41,905,000
Medium Voltage Panel Protection VCB Ea 1 198,769,100 198,769,100
Medium Voltage Panel Cubicle CT Ea 1 38,267,900 38,267,900
Medium Voltage Panel Outgoing LBS Ea 1 53,428,900 53,428,900
UPS 300-500VA Ea 1 2,834,800 2,834,800
LVMDB
Low Voltage Panel ACB 3P 1600A Ea 1 78,040,800 78,040,800
Low Voltage Panel Feeder Ea 1 42,015,200 42,015,200
Low Voltage Panel Capacitor Panel 3 x 100kVAR, 440V w/ SR Ea 1 189,805,500 189,805,500
CONTINUE
8 Telephone Work
12 CCTV Work
Main Equipment
Dome Camera, Resolution of 1.3MP, IP 66 Fixed Lense 2.8mm Ea 34 3,850,000 130,900,000
NVR 16Ch Ea 2 21,725,000 43,450,000
NVR 4Ch Ea 1 14,850,000 14,850,000
32" LED Monitor Ea 2 4,950,000 9,900,000
23" LED Monitor Ea 1 3,520,000 3,520,000
HDMI Cabkle 3m Ea 3 396,000 1,188,000
UPS-SMC1000i Ea 3 4,950,000 14,850,000
Hard Disk (@4TB) Ea 10 3,850,000 38,500,000
Repeater-1PEUP Ea 2 1,089,000 2,178,000
Installation Material Lot 1 48,847,700 48,847,700
(Cable UTP, Cable NYMHY, Pipe, Flexible, Cable Jack, Ducting, ect)
Supporting Material Lot 1 24,655,000
Miscellaneous Lot 1 16,561,300
TERMINATION
Cable Termination 500 mm2 Compression Type Ea 205.00 2,870,000 20.50
Cable Termination 400 mm2 Compression Type Ea 115.00 1,610,000 11.50
Cable Termination 300 mm2 Compression Type Ea 76.85 1,075,900 7.69
Cable Termination 240 mm2 Compression Type Ea 68.44 958,125 6.84
Cable Termination 185 mm2 Compression Type Ea 53.94 755,125 5.39
Cable Termination 150 mm2 Compression Type Ea 48.91 684,775 4.89
Cable Termination 120 mm2 Compression Type Ea 38.81 543,375 3.88
Cable Termination 95 mm2 Compression Type Ea 32.23 451,150 3.22
Cable Ladder W = 200 Inside Riser c/w Cover Ea 19.39 271,500 7.50
EFLEX CONDUIT
Eflex Conduit 150 mm m 27.27 381,780 15.00
Eflex Conduit 100 mm m 12.22 171,080 8.50
Eflex Conduit 50 mm m 4.24 59,360 3.00
Eflex Conduit 30 mm m 2.93 41,020 1.90
PVC CONDUIT
PVC Conduit 150 mm m 9.56 133,838 4.00
PVC Conduit 100 mm L = 4,000 Ea 17.13 239,800 12.80
PVC Conduit 25 mm m 0.58 8,163 1.40
PVC Conduit 50 mm m 1.39 19,443 2.20
PVC Conduit 40 mm m 1.05 14,700 2.20
PVC Conduit 25 mm L = 2,900 Ea 1.05 14,700 4.19
PVC Conduit 20 mm m 0.26 3,605 1.10
PVC Conduit 25 mm Addapter Ea 0.89 12,451 0.50
PVC Conduit 20 mm Addapter Ea 0.85 11,858 0.50
T - Dus 20mm 3 Way Ea 0.43 6,000 0.50
UPVC Ducting 100 x 25 x 3.2 mm m 3.71 52,000 4.00
BOXES
PULLBOX
Pull Box 100 x 100 x 50 Ea 5.09 71,250 12.00
Pull Box 150 x 150 x 150 Ea 8.04 112,500 12.00
Pull Box 200 x 200 x 100 Ea 9.11 127,500 12.00
Pull Box 200 x 200 x 200 Ea 9.64 135,000 12.00
Pull Box 300 x 300 x 300 Ea 24.11 337,500 12.00
OUTLET BOX
CIRCULAR BOX
LIGHTING FIXTURES
Lighting Fixture FL 36 W - 1 V-Shape Ea 34.03 476,471 7.00
Lighting Fixture FL 36 W - 1 V-Shape c/w Battery Ea 121.70 1,703,771 7.00
Lighting Fixture FL 36 W - 2 V-Shape Ea 41.85 585,882 8.50
Lighting Fixture FL 36 W - 2 V-Shape c/w Battery Ea 129.51 1,813,182 10.50
Lighting Fixture FL 36 W - 1 Reflector Ea 21.52 301,250 7.00
Lighting Fixture FL 36 W - 1 Reflector c/w Battery Ea 109.18 1,528,550 7.00
Lighting Fixture FL 36 W - 2 Reflector Ea 27.99 391,800 10.00
Lighting Fixture FL 36 W - 2 Reflector c/w Battery Ea 115.65 1,619,100 12.00
Lighting Fixture FL 36 W - 1 Indirect Ceiling Batten Ea 17.59 246,250 7.00
Lighting Fixture FL 36 W - 1 Batten Ea 17.59 246,250 7.00
Lighting Fixture FL 36 W - 1 Batten c/w Battery Ea 105.25 1,473,550 7.00
Lighting Fixture FL 36 W - 2 Batten Ea 23.38 327,300 7.00
Lighting Fixture FL 36 W - 2 Batten c/w Battery Ea 111.04 1,554,600 7.00
Lighting Fixture LED 200 W - 1 High Bay Light Ea 357.14 5,000,000 16.40
Lighting Fixture CM 400 W - 1 Ceramic Metal Halide High Bay Light Ea 164.57 2,304,000 16.40
Lighting Fixture HPI 250 W - 1 Metal Halide High Bay Light (IP65) Ea 457.43 6,404,000 12.10
Lighting Fixture HPI 400 W - 1 Metal Halide High Bay Light (IP65) Ea 457.53 6,405,400 16.40
Lighting Fixture HPI 250 W - 1 Metal Halide High Bay Light (IP20) Ea 164.23 2,299,150 12.10
Lighting Fixture HPI 400 W - 1 Metal Halide High Bay Light (IP20) Ea 164.57 2,304,000 16.40
Lighting Fixture HPI 250 W Flood Light Metal Halide Ea 152.30 2,132,250 8.50
Lighting Fixture HPI 400 W Flood Light Metal Halide Ea 165.11 2,311,600 12.20
Lighting Fixture SON 250 W - 1 Outdoor Light Ea 154.44 2,162,100 17.20
Lighting Fixture SON 400 W - 1 Outdoor Light Ea 265.76 3,720,600 22.30
Lighting Fixture LED 150 W - 1 Outdoor Light Ea 500.00 7,000,000 17.20
Lighting Fixture LED 1 x 40W, Outdoor Signage Light Ea 242.86 3,400,000 25.00
Lighting Fixture Hf 250 W - 1 Mercury High Bay Light Ea 138.88 1,350,000 12.20
Lighting Fixture NH 250 W - 1 Sodium High Bay Light Ea 192.22 1,350,000 12.20
Lighting Fixture HID 250 W - 1 Metal Halide High Bay Light Ea 205.00 2,475,000 12.20
Lighting Fixture CM 230 W - 1 Ceramic Metal Halide High Bay Light Ea 261.11 3,764,800 12.20
Lighting Fixture Hf 400 W - 1 Mercury High Bay Light Ea 150.00 1,350,000 12.20
Lighting Fixture NH 400 W - 1 Sodium High Bay Light Ea 263.77 1,350,000 12.20
Lighting Fixture HID 400 W - 1 Metal Halide High Bay Light Ea 215.00 2,475,000 12.20
Lighting Fixture CM 360 W - 1 Ceramic Metal Halide High Bay Light Ea 323.53 3,882,400 16.40
STREET LIGHT
Lighting Fixture Hf 250 W - 1 Mercury High Bay Light Ea 177.77 1,350,000 20.40
Lighting Fixture NH 250 W - 1 Sodium High Bay Light Ea 238.88 1,350,000 20.40
Lighting Fixture HID 250 W - 1 Metal Halide High Bay Light Ea 244.44 2,475,000 20.40
Lighting Fixture CM 230 W - 1 Ceramic Metal Halide High Bay Light Ea 272.22 2,175,000 20.40
Lighting Fixture Hf 400 W - 1 Mercury High Bay Light Ea 194.44 1,350,000 26.90
Lighting Fixture NH 400 W - 1 Sodium High Bay Light Ea 255.55 1,350,000 26.90
Lighting Fixture HID 400 W - 1 Metal Halide High Bay Light Ea 261.11 2,475,000 26.90
Lighting Fixture CM 360 W - 1 Ceramic Metal Halide High Bay Light Ea 283.33 2,475,000 26.90
FLOOD LIGHT
Lighting Fixture NH 150 W - 1 Flood Light Sodium Ea 257.22 1,350,000 7.90
Lighting Fixture NH 250 W - 1 Flood Light Sodium Ea 281.66 1,350,000 8.50
Lighting Fixture NH 400 W - 1 Flood Light Sodium Ea 355.00 2,475,000 12.20
Lighting Fixture NH 150 W - 1 Flood Light Metal Halide Ea 262.77 1,350,000 7.90
Lighting Fixture NH 250 W - 1 Flood Light Metal Halide Ea 287.22 1,350,000 8.50
Lighting Fixture NH 400 W - 1 Flood Light Metal Halide Ea 360.55 2,475,000 12.20
WIRING DEVICES
Plate Switch 1P15A x 1 Ea 4.59 64,300 2.50
Plate Switch 1P15A x 1 3 W Ea 5.14 71,900 3.50
Plate Switch 1P15A x 1 4 W Ea 11.84 165,700 4.00
Plate Switch 1P15A x 2 Ea 5.52 77,300 3.50
Plate Switch 1P15A x 1 ( WP ) Ea 19.16 268,200 3.25
Plate Switch 1P15A x 2 3W Ea 6.61 92,600 7.00
Plate Switch 1P15A x 1 c/w Lamp Ea 16.26 227,700 2.50
Receptacle 2P16A + E Ea 6.04 84,500 2.00
Receptacle 2P16A + E x 2 Ea 12.07 169,000 2.00
Receptacle 2P16A + E x 2 w/Cover Ea 25.52 357,300 2.00
Receptacle 2P16A + E Floor Type Ea 44.54 623,600 2.50
Receptacle 2P16A + E x 2 Floor Type Ea - 2.00
Receptacle 2P16A + E Explosion Type Ea 32.14 450,000 2.00
Receptacle 2P16A + E ( WP ) Ea 21.37 299,200 2.00
Receptacle 2P16A + E for Emergency Light Ea 6.04 84,500 2.00
Receptacle 2P16A + E for Machine Ea 6.04 84,500 2.00
Receptacle 2P16A + E for AC Indoor Ea 6.04 84,500 2.00
Receptacle 2P16A + E for Hand Dryer Ea 6.04 84,500 2.00
Receptacle 2P16A + E c/w Tel and LAN Floor Type Ea 49.71 696,000 5.00
Receptacle 3P 32A + E w/ Plug Ea 32.85 459,900 3.29
Receptacle 2P16A + E x 4 Extension Type Ea 2.11 29,500
BREAKER BOX
Addressable Panel
Addressable Fire Alarm Panel 8 Loop / 1020 Address Ea 21,000.00 294,000,000 2,100.00
Extended Power Supply Module + Bettery Ea 1,200.00 16,800,000 120.00
Alarm Printer and Interfacing Ea 350.00 4,900,000 35.00
Addressable Fire Alarm Panel 4 Loop / 1020 Address Ea 10,200.00 142,800,000 1,020.00
Annunciator Panel for 4 Loop / 1020 Address Ea 1,138.00 15,932,000 113.80
Addressable Detector
Photoelectric Smoke Detector Addressable Type Ea 101.00 1,414,000 10.10
ROR Heat Detector Addressable Type Ea 93.00 1,302,000 9.30
Fixed Temp Detector 65C Addressable Type Ea 93.00 1,302,000 9.30
TERMINATION KIT
Control Box 400 x 400 x 600 c/w Cover Ea 35.71 500,000 3.57
TELEPHONE SYSTEM
KX-TDE100 Series Ea
PABX 8 In Ext 80 Ea - -
PABX 3 In Ext 32 Ea 3,674.00 51,436,000 100.00
PABX 8 In Ext 64 Ea 6,478.00 90,692,000 100.00
PABX 4 In Ext 64 Ea 6,478.00 90,692,000 100.00
PABX 3 In Ext 48 Ea 6,633.00 92,862,000 100.00
PABX 8 In Ext 32 Ea 3,674.00 51,436,000 100.00
PABX 4 In Ext 24 Ea 2,903.00 40,642,000 100.00
PABX 5 In Ext 10 Ea 744.64 10,425,000 100.00
DSS Console Ea 257.00 3,598,000 25.70
4 pcs LSA + 2 pcs Frame + 1 pcs Arrester + 1 pcs Protection Ea 80.00 1,120,000 8.00
10 pcs LSA + 2 pcs Frame + 1 pcs Arrester + 1 pcs Protection Ea 107.14 1,500,000 10.71
20 pcs LSA + 2 pcs Frame + 1 pcs Arrester + 1 pcs Protection Ea 142.86 2,000,000 14.29
UPS for PABX Back up time 10menits Ea 264.29 3,700,000 26.43
UPS for PABX Back up time 1hours Ea 650.00 9,100,000 65.00
Telephone Hand Set 3 Line LCD Display Digital Phone Ea 247.00 3,458,000 24.70
Telephone Hand Set 1 Line LCD Display Digital Phone Ea 189.00 2,646,000 18.90
Telephone Hand Set Single Line Phone Ea 50.00 700,000 5.00
LAN SYSTEM
MATV SYSTEM
Antenna
Antenna Parabola 6 Feet c/w FH Double & Tower Ea 321.43 4,500,000 32.14
VHF Antenna merk Televes 7 elemen Ea 58.93 825,000 5.89
UHF Antenna merk Televes 45 elemen Ea 153.57 2,150,000 15.36
Booster VHF / UHF Ea 51.07 715,000 5.11
If Active Splitter 8 way merk Televes (Power Divider) Ea 113.57 1,590,000 11.36
Receiver Digital merk - Televes Ea 220.00 3,080,000 22.00
Domestic Modular Televes Ea 139.29 1,950,000 13.93
Mashead Amplifier merk Televes Ea 35.71 500,000 3.57
Avant merk Televes for Local Program 10 Channel Ea 1,035.71 14,500,000 103.57
Passive Combiner Ea 117.50 1,645,000 11.75
Professinal Headend Rack Open Ea 569.64 7,975,000 56.96
System Distribution
Directional Coupler / tap off way F-Type Ea 10.71 150,000 1.07
Splitter 2 way F-Type merk Televes Ea 8.21 115,000 0.82
Broad band Distribution Amplifier merk Televes Ea 227.14 3,180,000 22.71
EXPLOSION PROOF
CCTV Work
32CH NVR Full HD Without HDD TN 3232 Ea 1,587.14 22,220,000 158.71
3D, Internet, Full HD, HDMI Port LED Sony 55 x 9004 Ea 23,144.00 324,016,000 2,314.40
Proc. Core i5 4570, RAM4GB, 500GB, Slim Line, Win7Pro PC Lenovo Ea 2,475.00 34,650,000 247.50
ABBA Rack Close 19" 42U Dept 900mm ABBA Rack 42U-900 Ea 2,588.14 36,234,000 258.81
UPS APC SUA 3000iVA, icl. Stabilizer Ea 4,305.71 60,280,000 430.57
Kabel HDMI 30m BAFO Ea 326.86 4,576,000 32.69
Wall Bracket for LCD Monitor 55" Bracket "55" Ea 110.00 1,540,000 11.00
DD 3TB Seagate HDD 3TB Seagate Ea 644.29 9,020,000 64.43
Camera, 2M IR Dome, 1080p 3.3-12mm TD 20SV-15 Ea 575.14 8,052,000 57.51
Camera 2M IR Bullet, 1080p, 3.3-12mm, IP66 TB20S1-20 Ea 510.71 7,150,000 51.07
Network Colour Dome Cam D/N+HD/1280x960 H.264+adp WV-SF335 Ea 970.00 13,580,000 97.00
Network Colour Cam D/N+HD/1280x960 H.264+adp WV-SP305 Ea 799.00 11,186,000 79.90
Bracket & Housing for Indoor IHB-205 & ICH - 603 Ea 35.00 490,000 3.50
Cable HDMI 5M Ea 20.00 280,000 2.00
HDD 3TB Seagate HDD 3TB Seagate Ea 456.00 6,384,000 45.60
Bracket & Housing for Outdoor IHB-205 & L - 606 Ea 92.00 1,288,000 9.20
TV LG LED 22" LCD M227WAP LG 22" Ea 479.00 6,706,000 47.90
Wall Bracket for LCD Monitor Bracket Ea 110.00 1,540,000 11.00
Mouse Logitech USB Ea 17.00 238,000 1.70
Variable Focal Lenses 2.8-8mm WV-LZA63/3 Ea 95.00 1,330,000 9.50
UPS APC SUA 3000iVA, icl. Stabilizer APC SUA 3000iVA Ea 3,045.00 42,630,000 304.50
Network Disk Recorder WJ-NV200 Ea 4,035.00 56,490,000 403.50
Proc. Core i5 4570, RAM4GB, 500GB, Slim Line, Win7Pro PC Lenovo Ea 1,750.00 24,500,000 175.00
Access Control
Suprema BLN-OC (Bio Lite NET (MiFare)) Ea 521.43 7,300,000 52.14
Suprema BEWM-OC (Bio Entery W (MiFare)) Ea 422.14 5,910,000 42.21
Allied Telesis AT-GS950/10PS (Wesmart switch 10 port Poe) Ea 640.71 8,970,000 64.07
S/W Bio Star SE Ea 357.86 5,010,000 35.79
Exit Button Ea 7.14 100,000 0.71
Pole H = 5 meters Ea 171.43 2,400,000 50.20
Main Equipment
IP Fix Lens Micro Dome Camera HD Ea 320.71 4,490,000 32.07
IP Bullet Camera HD Ea 791.43 11,080,000 79.14
NVR DIVAR IP 3000 2x2TB Ea 2,124.29 29,740,000 212.43
24Port PoE Switch Ea 621.43 8,700,000 62.14
PoE Extender Ea 70.71 990,000 7.07
Standing Close Rack (20U) Ea 557.14 7,800,000 55.71
32" LED Monitor Ea 321.43 4,500,000 32.14
HDMI Cabkle 3m Ea 25.71 360,000 2.57
UPS-SMC1000i Ea 321.43 4,500,000 32.14
Main Equipment
Dome Camera, Resolution of 1.3MP, IP 66 Fixed Lense 2.8mm Ea 250.00 3,500,000 25.00
NVR 16Ch Ea 1,410.71 19,750,000 141.07
NVR 4Ch Ea 964.29 13,500,000 96.43
23" LED Monitor Ea 228.57 3,200,000 22.86
Hard Disk (@4TB) Ea 250.00 3,500,000 25.00
Repeater-1PEUP Ea 70.71 990,000 7.07
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
102 Nichifu
109 Tri Abadi
109 Tri Abadi
109 Tri Abadi
109 Tri Abadi
109 Tri Abadi
109 Tri Abadi
142
112 Furukawa
112 Furukawa
112 Furukawa
112 Furukawa
112 Furukawa
112 Furukawa
112 Furukawa
112 Furukawa
104 laksmanakarya
104 laksmanakarya
Update 2015, September 30 104 laksmanakarya
Update 2015, September 30 104 laksmanakarya
104 laksmanakarya
104 laksmanakarya
Update 2015, September 30 104 laksmanakarya
105 laksmanakarya
105 laksmanakarya
105 laksmanakarya
104 laksmanakarya
111 Genetek March 1 2012 Quotation
111 Genetek
111 Genetek
111 Genetek
111 Genetek
111 Genetek
111 Genetek
111 Genetek
111 Genetek
108 Sahabat
115
115
Update 2015, September 9 115 Philips
Update 2015, September 9 116 Philips
115
115
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
141 Kinden
141 Kinden
141 Kinden
141 Kinden
141 Kinden
141 Kinden
115 Cakra
115 Cakra
115 Cakra
Update 2015, August 19 115 Cakra
115 Cakra
115 Cakra
115 Cakra
Update 2015, August 19 115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
115 Cakra
116 Cakra
116 Cakra
116 Cakra
116 Cakra
116 Cakra
116 Cakra
116 Cakra
116 Cakra
116 Cakra
116 Cakra
116 Cakra
116 Cakra
116 Cakra
116 Cakra
135 jalamas
140 Kinden
135 jalamas
129 Multicord
129 Multicord
Update 05/5/2015 129 Multicord
Update 05/5/2015 129 Multicord
129 Multicord
129 Multicord
129 Multicord
129 Multicord
129 Multicord
129 Multicord
129 Multicord
Update 05/5/2015 129 Multicord
Update 05/5/2015 129 Multicord
Update 05/5/2015 129 Multicord
129 Multicord
129 Multicord
129 Multicord
130 KDDI
Update 02/17/2015 130 KDDI
130 KDDI
130 KDDI
130 KDDI
130 KDDI
130 KDDI
130 KDDI
130 KDDI
130 KDDI
130 KDDI
130 KDDI
130 KDDI
130 KDDI
130 KDDI
101 KDDI
130 KDDI
130 KDDI
134 SECOM
134 SECOM
134 SECOM
134 SECOM
134 SECOM
Update 03/27/2015 134 SECOM
Update 03/27/2015 134 SECOM
134 SECOM
131 SECOM
131 SECOM
131 SECOM
131 SECOM
131 SECOM
131 SECOM
131 SECOM
131 SECOM
131 SECOM
131 SECOM
131 SECOM
131 SECOM
131 SECOM
131 SECOM
131 SECOM
131 SECOM
131 SECOM
WIRING DEVICE Trias Mondial Jaya (Gira) Net 10% Hendarmin 5811386
Gunungsari Widitama Net 15% Fauziah 6294904
Global Sigma Mandiri 25% 20% Alvin 39845980
Legrand 20% Mulya Martendi 5250608
Australindo Graha Nusa 30% Andy Togo 5605678
Maju Makmur Bahagia 25% 25% Herayati 6121982/6121983
Iwika Karya Sejahtera 25% Wikantiningsih/Fitri 6316528/6315904
Anugrah Terang Abadi 25% 30% Yakup 081219916768
Building Automation System Azbil Berca Indonesia 25% Benny Tobing/Siska 2305538
Greenoble Enjineering (Schneider) Bambang Basuki 53164785
Duta Fuji Electric Mulyotito Marthias 3840834
Mitsubishi Electric Christian Arthur 31926461
ELECTRICAL
E-4 Bus duct Henikwon, Schneider, NISSHIN THAILAND Malaysia, China, Thailand
E-5 Generator Mitsubishi, Denyo, MAN, Cummins, Perkins Japan, Germany, China, UK
E-15 Lightning Protection EF, Duval Messein, Furse, KURN Switzerland, French, UK, IND
E-18 Steel Conduit Pipe Sumitomo, Panasonic, Wahana, Elpro Indonesia, Thailand
1 New office regulation, All Bq in Rupiah Currency, if possible just prepare supplier quotation on Rupia
But Still typing currency on column for future information.
2 From Supporting - Excavation Back Feeling already make on uniform type, so just follow.
4 Please change tab color for submit BQ with green color, for mark SUBMIT BQ and ORIGINAL BQ di
5 In A2, if ME Work, Please Delete Coloum P44 until S73 (Indirect Cost)
6 Government Permitt : Incoming System, Generator, Fire Alarm & Lightning Protection.
Please write your positive comment (About this BQ Format) here (if Any) and return this file to us.
1
2
3
4
5
6
7
8
9
10
ing Protection.
1 2 3 4 5
EJIP / DELTA
NAME OF INDUSTRY MM2100 GIIC KIIC
JABABEKA SILICON
ELECTRICAL
DIMENSION (mm)
NO. CIVIL REQUEST DISCRIPTION NAME WORK LOCATION WIDE LENGTH HIGH
1 CONCRETE DUCTBANK PROTECTION MAIN FEEDER WORK INCOMING CROSSING ROAD 1,200 15,000 300
2 FOUNDATION FOR PP - PUMP MAIN FEEDER WORK PUMP ROOM 800 300 100
3 FOUNDATION FOR PP - JOCKEY PUMP MAIN FEEDER WORK PUMP ROOM 800 300 100
4 HEAVY LOADING (CRANE) FOR LIGHTNING PROTECTION LIGHTNING PROTECTION WORK OUTDOOR
5 WALL OPENING FOR CABLE LADDER MAIN FEEDER WORK ANALISYS ROOM 700 150
6 EXCAVATION & BACKFILLING MAIN FEEDER WORK BUILDING to LVMDB 1,200 15,000 600
7 EXCAVATION & BACKFILLING OUTDOOR LIGHTING WORK OUTDOOR 500 140,000 600
8 EXCAVATION & BACKFILLING LIGHTNING PROTECTION WORK OUTDOOR 2,700 2,700 1,500
9 FOUNDATION for LIGHTING POLE OUTDOOR LIGHTING WORK OUTDOOR 800 800 1,200
10 FOUNDATION for LIGHTNING PROTECTION POLE LIGHTNING PROTECTION WORK OUTDOOR 2,700 2,700 1,500
1/9/2020
QTY
1
1
1
1
1
1
1
1
5
1
Q&A
XXX PROJECT
ELECTRICAL
DOCUM
ITEM QUESTION
ENT No.
E-1
E-2
E-3
E-4
E-5
E-6
E-7
E-8
1/9/2020
ANSWER
VECD LIST 1/9/2020
XXX PROJECT
ELECTRICAL
E-1
E-2
E-3
E-4
E-5
E-6
E-7
E-8
SCHEDULE MAKING QUOTATION REMARKS
DATE 1 2 3 4 5 6 7 8 9 10 11 12 13 14
4 POWER SUPPLY
5 LIGHTING
6 RECEPTACLE
7 TELEPHONE
8 LAN
9 SOUND
10 MATV
11 CCTV
12 FIRE ALARM
13 LIGHTNING PROTECTION
14 GENERATOR
15 MAIN FEEDER FOR PRO
17 BMS
18 SECURITY
19 ACCESS DOOR
20 SMOKE CONTOROL
21 INTERCOM
22 PARKING CONTROL
23 BATTERY
24
25
提出前チェックリスト
CHECK POINT LIST BEFORE SUBMISSION UPDATE 17-JUN-2016
Quotation Check site expense for far project. (Transportation for Material & staff & worker, Testing fee, Domitory, Mafia, Car, HP, Micellouneus)
29 見積 遠隔地の資材購入方法、日雇い労働者の賃金、サブコンの有無を確認したか。
Quotation Check how to buy material, salary for worker, subcon.
30 見積 安い配線器具の検討をしたか。(アパート等)
Quotation Study cheaper wiring device. (For apartment etc)
31 見積 見積書の表紙の材料と労務を合算したか。
Quotation Combine Material total and Labor total.
32 見積 五洋建設の工事用仮設発電機は見込んだか。
Quotation Include temporary generator for Penta ocean.
33 GS ゼロチェックの確認を行ったか。
ZERO Check
34 GS 原価数量表を打ち出したか。
Check Export BOQ
35 見積 防爆の仕様を確認したか。
Quotation Check explosion proof level.
36 見積 A2の右欄を確認したか。
Quotation Check right colom at A2
37 見積 A2のメーカ名を確認したか。
Quotation Check Maker name at A2
38 見積 A2の提出、原価引き率を確認したか。
Quotation Check Discount list for submit and NET
39
40
UPDATE 17-JUN-2016
注記
REMARKS
大成のみ
Taisei only
特に大和。
高層案件注意。
太陽シナールは図面にサイズ記載。
竹中標準。
Takenaka only
竹中標準。
Takenaka only
竹中標準。
Takenaka only
大成建設
Taisei only
五洋標準。
Penta
Name of File
FOLDA NAME CONTENT How to make name of folda & data
フォルダ名 内容 データ、フォルダの名前の付け方 例
▲DATA Data received from customer Data / Content / From who
客先から受領したデータ 日付 / 内容 / 誰から
For example
20160310 SPEC TAKENAKA
▼SUBMIT-BQ, DOCUMTNT▼ Data which Kinden submit to customer Content / Rev / To who / data
客先に提出するデータ 内容 / 改訂 / 誰に / 日付
For example
E-BQ (SUBMIT) AJINOMOTO COAL BOILER - PP-TAISEI - 8,DEC
2016-KDI-0513 COVER & CONDITION
★ORIGINAL BQ★ Internal BQ data Content / Rev / To who / data
内部見積BQデータ 内容 / 改訂 / 誰に / 日付
For example
E-BQ (ORIGINAL) DENSO INDONESIA - PP. TAISE - 7MARCH2016
Sign :
Sign :
Sign :
Sign :
Sign :
Remarks :
BAF工事概要書
6/13/2016
電気設備工事概要書
1 引込ケーブル工事
本工事は電力会社ガルードより電気室内高圧配電盤までの引込ケーブル工事と致します。
ケーブルはN2XSEBY 3C-120mm2と致します。
車両が通行部はPVC電線管及びコンクリートにて保護致します。
2 受変電設備工事
本工事は電気室に高圧配電盤、変圧器、低圧配電盤を設置する工事と致します。
本工事は接地工事も含みます。
高圧配電盤の構成は下記と致します。
引込盤 DS 1面
主開閉器盤 VCB 1面
送出し盤 LBS + ヒューズ 1面
変圧器は下記と致します。
3相4線式20kV/400V-230V、油式、kVA 1台
変圧器容量計算方法は下記と致します。
面積 x 想定電力消費原単価 x 余裕率
13,638m2 x 150VA/m2 x 1.2 = 2,500kVA
変圧器2次側配電方法は下記と致します。
バスダクト AL,4W,4000A
低圧配電盤主遮断器は下記と致します。
ACB3P+N 4000AF/4000AT
3 発電機設備工事
本工事は発電機、発電機制御盤設置工事と致します。
本工事は接地工事も含みます。
ケ-ブルはNYYケ-ブルをケ-ブルラック上に敷設致します。
発電機盤も本工事と致します。
発電機容量は全バックアップとし、変圧器と同様と致します。
仕様は下記と致します。
3相4線式400V-230V、2500kVA、ディーゼル、プライム、防音タイプ
オイルタンクは8時間運転分と想定し、4000ℓと致します。
本工事はオイルポンプ、オイル配管工事、排煙ダクト、消音器も含みます。
防振架台、防音壁は別途工事と致します。
4 幹線設備工事
本工事は照明盤、各種動力盤への幹線敷設工事と致します。
(空調盤、コンプレッサ-盤、チラー盤、ポンプ盤、ファン盤)
ケ-ブルはNYYケ-ブルをケ-ブルラック上に敷設致します。
各盤も本工事と致します。
PANEL ROOM内に縦ケーブルラックを設置し、各階に電灯分電盤を設置致します。
5 一般動力設備工事
本工事は照明盤、各種動力盤より、各負荷までの配管、配線工事と致します。
(空調盤、コンプレッサ-盤、チラー盤、ポンプ盤、ファン盤)
ケ-ブルはNYYケ-ブルを敷設致します。
各モ-タ-、ポンプへの接続はフレキシブル電線管にて接続致します。
6 照明及びコンセント設備工事
本工事は各照明盤より、照明器具及びコンセントまでの配管、配線工事と致します。
主器具は下記と致します。
直管型器具 LED
ダウンライト LED
非常照明と致しまして、別置型照明器具を設置致します。
誘導灯は必要個所に設置致します。
7 屋外照明設備工事
本工事は建屋周囲にポール灯を30から40m間隔で設置する工事と致します。
主器具は下記と致します。
屋外照明器具 LED
8 電話設備工事
本工事は電話配管、配線工事と致します。
電話交換機は別途と致します。
電話機は別途と致します。
電話機は2つの机に1つ設置すると致します。
9 LAN設備工事
本工事はLAN用配管工事と致します。
主要機器は別途と致します。
LANアウトレットは1つの机に1つ設置すると致します。
10 放送設備工事
本工事は各箇所にスピ-カ-を設置する工事と致します。
直天井部屋内はホーンスピ-カ-もしくはボックススピーカー、
天井あり室内はシーリングスピーカーを設置致します。
放送用主要機器を設置する工事と致します。
11 火災報知設備工事
本工事は各箇所に感知器、呼び出しベル、表示灯、押しボタンを設置する工事と致します。
主受信機は新規に設置するものと致します。
主受信機はP型と致します。
本工事はインドネシアの法規に準拠し、設置致します。
12 避雷針設備工事
本工事は回転球体法に従い、避雷突針を設置する工事と致します。
また下部への引き下げ導体は鉄筋を使用すると致します。
地上にて鉄筋からクランプにて引出し、2箇所接地するものと致します。
BAF OUTLINE
6/13/2016
ELECTRICAL WORK OUTLINE
1 Incoming Work
TR specification is below
3Φ4W 20kW/400V-230V, Oil, 2500kVA 1Ea
TR caluculation is below.
Floor area x Unit price per m2 x Safety factor
13,638m2 x 150VA/m2 x 1.2 = 2,500kVA
3 Generator Work
This work is to install LP panel, PP panel and main feeder cable to each panel.
(AC panel, Compressor panel, Chiler panel, Pump panel, Fan panel)
Cable is NYY cable on ladder.
Each panel also this work
5 Power Supply Work
This work is cable and pipe to each lighting fixture and receptacle.
Main lighting fixture is
Tube type is LED.
Down light is LED.
Emergency light is lighting fixture with BT.
Exit light is installed.
This work is cable and pipe to each lighting fixture and receptacle.
Main lighting fixture is
Tube type is LED.
8 Telephone work
9 LAN Work
12 Lightning Protection
SUBMIT TO :
2016 - KDI - XXXX
XXX PROJECT D E S C R I PT I O N
PT. INDONAKANO
ESTIMATION PRICE NET PRICE 1st AMEND (1) PAYMENT CURRENCIES (4) CATEGORY
(E) 4,788,900,000 27.5% 4,107,887,365 23.6%
MATERIALS
(M) 6,814,583,800 39% 6,089,357,400 35% US $ % 1. BUILDING
(E) 890,900,000 5.1% 730,040,000 4.2%
LABOUR
(M) 887,716,200 5% 752,301,900 4%
(b) SUB - CON TOTAL 240,700,000 1.4% 181,055,700 1.0% Rp. % 3. OTHERS
(c) SUB - TOTAL ( a ) + ( b ) 13,622,800,000 78.3% 11,860,642,365 68.2%
Provision
E Transportation 0.30%
X Drawing 1.00%
P Temporary.F 0.25%
E Application (2) PAYMENT CONDITION (5) TOTAL FLOOR AREA 7,777 M2
N Mobil 0.55%
S Tools.Fee 0.35% DOWN PAYMENT
E Dormitory 0.55%
S Stationary 0.25% 30 %
Site Expense 1.45% 940,000,000 (6) LOCATION KIIC
Entertainment 0.30% PROGRESS PAYMENT
(d) EXP - TOTAL - 0.0% 940,000,000 5.4%
(d)+(f)
- 2,158,000,000 12.4%
EXPENSES TOTAL
(g) JAPANESE S/V 7.5% 1,305,000,000 7.5%
(e)+(f)+(g)
(h) 13,622,800,000 15,323,642,365 88.1%
TOTAL DIRECT COST
ADM DRWNG 6.5% 1,131,000,000 6.5% (3) EXCHANGE RATE
O CONST. SERVICE 3.0% 522,000,000 3.0%
H 0.0% 1 YEN = Rp.
0.0%
Subcontract
133 Fire Alarm 36,134,000.00 100.0 85.0 30,713,900.00 Jaya Teknik
135 Lightning Protection 71,000,000.00 100.0 100.0 71,000,000.00 Kuarta
101 Cables 1,029,593,565.00 100.0 95.0 978,337,534.00 Sumi Indo
103 Bus Duct 195,454,700.00 100.0 94.0 183,760,000.00 Setsuyo Astec
106 Steel Conduit Pipe 97,078,060.00 100.0 80.0 77,670,080.00 Sahabat
104 PVC Conduit Pipe 19,079,077.00 100.0 85.0 16,221,059.00 Laksamana
112 Flexible 7,484,820.00 100.0 80.0 5,987,906.00 Sahabat
(3)
Materials ( A )
Labor
(4)
Expenses
Indirect cost
143 Pole 19,300,000.00 100.0 100.0 19,300,000.00
137 Earthing/GroundingSystem 77,400,764.00 100.0 110.0 85,142,086.00
146 Others 6,000,000.00 100.0 100.0 6,000,000.00
149 Safety 2,000,000.00 100.0 100.0 2,000,000.00 Temprary Cable Route
139 Miscellaneous Material 61,457,168.55 100.0 95.0 58,406,340.73
TOTAL AMOUNT / LOCAL TAX CURRENCY RATE Rate Data on : 2016/Feb/01 Local & Foreign Portion AMOUNT
Total Amount USD 1.00000000 = IDR 13500.00000000 IDR Portion :
Local Tax USD Portion : Check by:
GRAND TOTAL Prepared by:
Site Address
Subcontract
Terms of Payment
Down Payment
Progress
Retention
Consultant
Subcontract Total ( 2 ) 161,658,960.00 100.0 161,666,000.00
( 3 ) 301 Electrical Worker Cost 1,597,879,800.00 100.0 1,597,892,000.00
Civil Worker Cost 7,830,000.00 Building / Civil Contrac
505 Transportation Fee 47,936,394.00 100.0 47,956,000.00
Labor
Estimation Man-day
JPN Worker Man-day =
Adj. Factor =
Labor Total ( 3 ) 1,653,646,194.00 99.6 1,645,848,000.00 Eff. Factor =
(4) Ele Worker Man-day =
Est. Man-day per day =
0.00 Unit price =
Scope of Works
Term of Supply
Delivery Term
Expenses
Shipping Volume
Project Data
RC / SRC / S :
Basement :
Story :
Penthouse :
Type of Building
Expenses Total ( 4 )
(5) Floor Area
Power Supply
Incoming
S/V
Distribution
Project Profit
TOTAL COST
Indirect Cost Total ( 6 ) 2,718,257,742.13
Total Cost ( 1 )+( 2 )+( 3 )+( 4 )+( 5 )+( 6 ) 13,092,710,169.03
Profit ( % ) -15.6 TOTAL AMOUNT
Profit -1,766,636,243.60
Total Amount 11,326,073,925.43 9,446,177,000.00
Check by: TOKIWA
Prepared by: FINA
4/9/2016 16:34
Outline
TOTAL AMOUNT / LOCAL TAX CURRENCY RATE Rate Data on : 2016/Feb/01 Local & Foreign Portion AMOUNT
Total Amount 8,607,816,183.32 USD 1.00000000 = IDR 13500.00000000 IDR Portion : 8,607,816,183.3
Local Tax 860,781,618.34 USD Portion : 0.0
GRAND TOTAL 9,468,597,801.66
Jaya Teknik
Kuarta
Sumi Indo
Setsuyo Astec
Sahabat
Laksamana
Sahabat
Expenses Total ( 4 )
(5)
Sahabat
Laksamana
Sahabat
S/V
Triabadi
Triabadi
S/V Total ( 5 )
Gunungsari Direct Cost ( 1 ) + ( 2 ) + ( 3 ) + ( 4 ) + ( 5 ) 10,374,452,426.90 76.0 8,607,816,183.32 100.0 8,607,816,183.32
( 6 ) a) Rent & Depreciation(4.5%) 509,673,326.65 4.5 509,673,326.65 0.00
b) KC Commission (2.5%) 283,151,848.14 2.5 283,151,848.14 0.00
c) S/V Fee (7.5%) 849,455,544.41 7.5 849,455,544.41 0.00
d)Administrative&Drawing(6.5%)
Indirect cost 736,194,805.16 6.5 736,194,805.16 0.00
e) Cost Service(3%) 339,782,217.77 3.0 339,782,217.77 0.00
Remarks Outline
Construction Period
8.9 -Month(s)
Commencement
2016/May/01
Completion
2017/Jan/30
Site Address
CIKAMPEK
Terms of Payment
Down Payment 30%
Progress 70%
Retention 0%
Consultant
Estimation Man-day
JPN Worker Man-day = 887.8
Adj. Factor = 100%
Eff. Factor = 400%
Ele Worker Man-day = 3,551.2
Est. Man-day per day = 11.4
Unit price = IDR 450,000 / Man-day
Scope of Works
ELECTRICAL WORKS
Term of Supply
Delivery Term
Shipping Volume
Project Data
RC / SRC / S : SRC
Basement : 0 FL
Story : 1 FL
Penthouse : 0 FL
Type of Building
Floor Area
9,414.0 m2
Power Supply
Incoming 20.00 KV
Distribution 400 V
230 V
Primary Transformer 315 KVA
Generator V
R.P.M.
PS
0 KVA
0 UNIT/S
Battery/UPS V
Ah
Project Profit
0.0%
TOTAL COST
1,203,110 / m²
35,955,790 / KVA
TOTAL AMOUNT
914,363 / m²
27,326,401 / KVA
1 Decimal :
1
A-2
NET - STATEMENT FOR QUOTATION
QUOTATION NO. : NAME OF PROJECT :
SUBMIT TO :
PT. TAKENAKA INDONESIA
SUPPLIER ESTIMATION
CODE MAT E R IAL %
PRICE PRICE
101 Cables Sumi Indo - 978,337,534 95.0 1.0
102 Cable Accessories #N/A - - - -
103 Bus Duct Setsuyo Astec - 183,760,000 94.0 1.0
104 PVC Conduit Pipe Sumi Indo - 16,221,059 85.0 1.0
105 PVC Accessories Laksamana - 810,900 85.0 1.0
106 Steel Conduit Pipe Sahabat - 77,670,080 80.0 1.0
107 Steel Conduit Acc Sahabat - 3,884,050 80.0 1.0
108 Floor Duct + Box #N/A - - - -
109 Cable Rack Triabadi - 176,559,300 70.0 1.0
110 Cable Rack Acc Triabadi - 17,653,810 70.0 1.0
111 Boxes Sahabat - 34,461,560 80.0 1.0
112 Flexible - 5,987,906 80.0 1.0
113 Wiring Device Gunungsari - 27,589,600 95.0 1.0
114 Switch Box #N/A - - - -
115 Lighting Fixture Cakra - 874,078,600 80.0 1.0
116 Special Lighting Hikari - 13,446,000 80.0 1.0
117 HV Panel Mitraida - 829,949,000 110.0 1.0
118 LV Panel Mitraida - 2,818,221,837 100.0 1.0
119 Terminal Board Mitraida - 5,854,000 75.0 1.0
120 Transformer & Acc Trafoindo - 826,200,000 60.0 1.0
121 Modification Works #N/A - - - -
122 Generator & Acc #N/A - - - -
123 Battery [UPS] #N/A - - - -
124 Factory Line and Acc #N/A - - - -
125 Sound System Elsiscom - 22,189,300 85.0 1.0
126 Clock Eq. System #N/A - - - -
127 Intercom #N/A - - - -
128 MATV / T V. Equipment #N/A - - - -
129 Telephone System #N/A - - - -
130 LAN System #N/A - - - -
131 CCTV/Alarm Eq. System #N/A - - - -
132 B.A.S. Equipment #N/A - - - -
133 Fire Alarm Jaya Teknik - 30,713,900 85.0 1.0
134 Security System #N/A - - - -
135 Lightning Protection Kuarta - 71,000,000 100.0 1.0
136 Supporting - 159,918,690 80.0 1.0
137 Earthing/Grounding Syst - 85,142,086 110.0 1.0
138 Terminating & Acc - 62,046,309 100.0 1.0
139 Miscellaneous Material - 58,406,341 95.0 1.0
140 Concrete & Foundation - 83,259,798 100.0 1.0
141 Manhole - 49,200,000 100.0 1.0
142 C - Channel - 52,931,340 100.0 1.0
143 Poles - 19,300,000 100.0 1.0
144 Exp. Proof Materials #N/A - - - -
145 Instrumentation & Device #N/A - - - -
146 Others - 6,000,000 100.0 1.0
147 Mechanical Equipment - 45,870,000 110.0 1.0
148 Tools #N/A - - - -
149 Safety Temprary Cable - 2,000,000 100.0 1.0
150 Contingency #N/A - - - -
K - 2 Material
1.材料コードに応じた提出掛
2.材料コードに応じた
4.提出掛け率から引き率へ変換
5.文字列を数値へ変換
業者見積を材料項目毎に集計
提出金額を材料項目毎に集計
(3)
(l)
% BUSINESS PROFIT
-
-
-
-
-
-
7,638,663,000
- 25% - 19%
- 26% - 20%
- 27% - 21%
- 28% - 22%
- 29% - 23%
- 30% - 24%
提出金額を材料項目毎に集計
1 1.00
1 Name of Project --
2 Site Address --
3 Submit to --
Submit Date --
4 Quotation No. --
5 Month of Construction --
REMARKS PARTICULARS
6 Total FloorArea --
7 Transformer --
SITE ADDRESS : --
--
CIKAMPEK
9 Genset --
9,414 m2
315
2016/May/01
2017/Jan/30
887.8
Supplier Disc
Supplier Name
(%)
Sumi Indo 15 %
#N/A 15 %
Setsuyo Astec 10 %
Sumi Indo 25 %
Laksamana 25 %
Sahabat 35 %
Sahabat 35 %
#N/A 40 %
Triabadi 45 %
Triabadi 45 %
Sahabat 20 %
35 %
Gunungsari 15 %
#N/A %
Cakra %
Hikari %
Mitraida 20 %
Mitraida 20 %
Mitraida 30 %
Trafoindo 50 %
#N/A %
#N/A %
#N/A 20 %
#N/A %
Elsiscom 25 %
#N/A %
#N/A %
#N/A 15 %
#N/A 15 %
#N/A %
#N/A %
#N/A %
Jaya Teknik 25 %
#N/A %
Kuarta 10 %
30 %
%
5 %
30 %
20 %
%
10 %
20 %
#N/A %
#N/A %
%
10 %
#N/A %
Temprary Cable Route %
#N/A %