API 510 Section 4

1. Who is responsible to ensure that all of the requirements of API 510 are met?

a) AI
b) jurisdiction
c) manufacturer
d) owner/user
e) pressure vessel engineer
f) pressure equipment department manager

d)

2. Who is responsible to ensure that the Authorized Inspection Agency functions in


accordance with the requirements of API 510?

a) AI
b) jurisdiction
c) owner/user
d) pressure vessel engineer
e) pressure equipment department manager

c)

3. Each owner/user that uses API 510 must:

a) maintain a quality assurance inspection manual


b) employ (direct-hire) at least one pressure equipment engineer
c) maintain an "R" stamp for vessel repairs d) employ (direct-hire) at least one
qualified welder who can make repairs to pressure vessels

a)

4. Which of the following is not required to be in the owner/user's quality assurance


inspection manual?

a) training requirements for inspection personnel


b) calibration of NDE equipment
c) directions on how to document inspection results
d) specify approval process for calculations performed during vessel
alterations
e) establish vacation policy for authorized inspectors

e)
5. Which of the following is not a role for the API 510 inspector?

a) provide the owner/user assurance that all welding meet requirements


b) provide the owner/user assurance that all NDE examinations meet
requirements
c) provide the owner/user assurance that all inspections meet requirements
d) provide the owner/user assurance that all pressure testing meet
requirements

a)

6. During in-service vessel repairs, all examination results must be accepted by the:

a) NDE supervisor
b) AI
c) pressure vessel engineer
d) repair org

b)

7. Which of the following is a role for the API 510 inspector?

a) provide solutions when welding problems occur


b) train on-site NDE personnel
c) authorize substitution of pre-heat in lieu of PWHT during vessel repairs
d) evaluate and accept NDE results

d)

8. When repairs and alterations are being conducted, which individual or organization
is responsible for quality control?

a) Authorized Inspection Agency


b) Repair org
c) API 510 inspector
d) On-site pressure equipment department

b)

9. When repairs and alterations are being conducted, which individual or organization
is responsible for validating that the materials meet the requirements of API 510?

a) Authorized Inspection Agency


b) Repair org
c) API 510 inspector
d) On-site pressure equipment department

b)
10. When NDE is performed on in-service vessels, who must maintain a record of the
NDE personnel certification?

a) AI
b) employer
c) owner/user
d) repair org

b)