WITH NEW EQUIPMENT FOR THE MONTH OF 06/2019 TO 12/2019 IN RESPECT OF CE (AM) NTDC, LAHO
MONTHLY MAJOR WORK/PROGRESS REGARDING REPLACEMENT OF OLD GRID STATION & T/LINE EQUI
WITH NEW EQUIPMENT FOR THE MONTH OF 06/2018 TO 12/2018 IN RESPECT OF CE (AM) NTDC, LAHO
uipment
Remarks
Date of
Installation
13.11.2019
15.11.2019
uipment
Date of Remarks
Installation
STATEMENT OF CLEANING / WASHING & REPLACEMENT OF DISC. INSULATORS IN RESPECT
LAHORE FOR THE PERIOD OF 06-2019 TO 12/2019
TOTAL NIL
NIL NIL
NIL NIL
NIL NIL
2488 NIL
29968 NIL
31517 30
8120 NIL
72093 30
NIL NIL
5502 20
NIL NIL
3248 NIL
14252 1
12032 28
14112 154
49146 203
MONTHLY STATEMENT SHOWING DAMAGE E
Date of Date of
Date of Damage Remarks.
Installation Replacement
NIL
STATEMENT OF TRIPPINGS IN RESPECT OF CHIEF ENGINEER (AM)N, NTDC LAHORE FOR THE P
12/2019
TOTAL NO OF
Sr.No MONTH 500KV/220KV Trippings of
Transformers
4 Sep-19 220KV 1
7 Dec-19 220KV 2
STATEMENT OF TRIPPINGS IN RESPECT OF CHIEF ENGINEER (AM)N, NTDC LAHORE FOR THE P
12/2018
TOTAL NO OF
Sr.No MONTH 500KV/220KV Trippings of
Transformers
1 Jun-18 220KV 1
2 Jul-18 220KV 1
TOTAL NO OF
TRIPPINGS Of TOTAL
Transmission line
Nil 0
Nil 0
Nil 0
Nil 1
1 1
2 2
Nil 2
TOTAL NO OF
TRIPPINGS Of TOTAL
Transmission line
Nil 1
Nil 1
Nil 0
1 1
Nil 0
1 1
Nil 0