ITE MATERIA
MATERIA LABOR SUBTOTAL
M ITEM QTY. UNIT L UNIT
L COST COST (Php)
NO. COST
I. GENERAL REQUIREMENTS
12mm THK. RSB (10ft) 187.00 pcs 223.00 41,701.00 12,510.30 54,211.30
Cement (class B, 40kg) 34.00 bags 260.00 8,840.00 2,652.00 11,492.00
Sand 3.00 cbm 1,035.00 3,105.00 931.50 4,036.50
Gravel 5.00 cbm 1,010.00 5,050.00 1,515.00 6,565.00
SUNDRIES (Tile spacers, float, nylon strings and other
consumable materials and equipment for tile installation) lot 7,630.48
SUB-TOTAL FOR MASONRY WORKS 83,935.28
IV. COLUMNS
10mm THK. RSB (10ft) 221.00 pcs 156.00 34,476.00 10,342.80 44,818.80
Cement (class B, 40kg) 18.00 bags 260.00 4,680.00 1,404.00 6,084.00
Sand 2.00 cbm 1,035.00 2,070.00 621.00 2,691.00
Gravel 3.00 cbm 1,010.00 3,030.00 909.00 3,939.00
SUNDRIES (Tile spacers, float, nylon strings and other
consumable materials and equipment for tile installation) lot 5,753.28
SUB-TOTAL FOR CARPENTRY WORKS 63,286.08
V. PERIMETER WALL
10mm THK. RSB (10ft) 186.00 pcs 157.00 29,202.00 8,760.60 37,962.60
CHB (400 x 200 x 100) 1,735.00 pcs 10.00 17,350.00 5,205.00 22,555.00
Cement (class B, 40kg) 3.00 bags 260.00 780.00 234.00 1,014.00
Sand 1.00 cbm 1,232.00 1,232.00 369.60 1,601.60
SUNDRIES (Consumable materials and equipment) 1.00 lot 6,313.32
SUB-TOTAL FOR CEILING AND DRYWALL 69,446.52
VI. STEEL MATTING
2" x 4" x 3meters Galvanized Tubular 16.00 pcs 345.00 5,520.00 1,656.00 7,176.00
2.8mm Thk. with 2x2" Mesh, 4x8' Sheet Steel Matting 34.00 sqm. 450.00 15,300.00 4,590.00 19,890.00
SUNDRIES (Consumable materials and equipment) 1.00 lot 2,706.60
SUB-TOTAL FOR PAINTING WORKS 29,772.60
Total Direct Cost 392,824.26
Prepared by:
Giannerica Gonzales
Jr. Architect
Approved by:
Name
Proffession
Conforme:
Emma Gonzales
Client / Owner