Sie sind auf Seite 1von 2

SUBJECT: BILLING OF MATERIALS

PROJECT: BULACAN CADASTRE


ADDRESS: 14-05-003, BAMBANG, BULACAN, BULACAN
CLIENT: MS. EMMA GONZALES
PACKAGE: BOQ
DATE: 09-10-2019

ITE MATERIA
MATERIA LABOR SUBTOTAL
M ITEM QTY. UNIT L UNIT
L COST COST (Php)
NO. COST

I. GENERAL REQUIREMENTS

Mobilization and Demobilization (Cost of transportation of site


personnel, daily site operations and other expeneses concerning 1.00 lot 100,000.00
manpower)

Project Management (Cost of supervision of site personnel, daily or


periodical visits of architects and engineers, and professional fee of 1.00 lot
overall management expertise)
Hauling and Delivery (Transportation and delivery fees concerning
the delivery of required materials and equipment on site, and truck 1.00 lot 10,000.00
fees on hauling of debris)
Shop Drawings and As-Built Drawings (Drawings made during
construction process and final drawings post construction reflecting 1.00 lot 4,000.00
actual built dimensions, BOQ)
Tools and Equipment (Purchases or rentals of scaffoldings, , blue
sacks and other power tools required to complete the project) 1.00 lot

SUB-TOTAL FOR GENERAL REQUIREMENTS 114,000.00


II. FOOTING (35)

Gravel Bed 1.00 cbm 1,010.00 1,010.00 303.00 1,313.00


12mm THK. RSB (10ft) 52.00 pcs 223.00 11,596.00 3,478.80 15,074.80
Cement (class B, 40kg) 19.00 bags 260.00 4,940.00 1,482.00 6,422.00
Sand 2.00 cbm 1,035.00 2,070.00 621.00 2,691.00
Gravel 3.00 cbm 1,010.00 3,030.00 909.00 3,939.00
SUNDRIES (Tile spacers, float, nylon strings and other
consumable materials and equipment for tile installation) lot 2,943.98
SUB-TOTAL FOR DEMOLITION WORKS 32,383.78
III. TIE BEAMS

12mm THK. RSB (10ft) 187.00 pcs 223.00 41,701.00 12,510.30 54,211.30
Cement (class B, 40kg) 34.00 bags 260.00 8,840.00 2,652.00 11,492.00
Sand 3.00 cbm 1,035.00 3,105.00 931.50 4,036.50
Gravel 5.00 cbm 1,010.00 5,050.00 1,515.00 6,565.00
SUNDRIES (Tile spacers, float, nylon strings and other
consumable materials and equipment for tile installation) lot 7,630.48
SUB-TOTAL FOR MASONRY WORKS 83,935.28
IV. COLUMNS

10mm THK. RSB (10ft) 221.00 pcs 156.00 34,476.00 10,342.80 44,818.80
Cement (class B, 40kg) 18.00 bags 260.00 4,680.00 1,404.00 6,084.00
Sand 2.00 cbm 1,035.00 2,070.00 621.00 2,691.00
Gravel 3.00 cbm 1,010.00 3,030.00 909.00 3,939.00
SUNDRIES (Tile spacers, float, nylon strings and other
consumable materials and equipment for tile installation) lot 5,753.28
SUB-TOTAL FOR CARPENTRY WORKS 63,286.08
V. PERIMETER WALL

10mm THK. RSB (10ft) 186.00 pcs 157.00 29,202.00 8,760.60 37,962.60
CHB (400 x 200 x 100) 1,735.00 pcs 10.00 17,350.00 5,205.00 22,555.00
Cement (class B, 40kg) 3.00 bags 260.00 780.00 234.00 1,014.00
Sand 1.00 cbm 1,232.00 1,232.00 369.60 1,601.60
SUNDRIES (Consumable materials and equipment) 1.00 lot 6,313.32
SUB-TOTAL FOR CEILING AND DRYWALL 69,446.52
VI. STEEL MATTING

2" x 4" x 3meters Galvanized Tubular 16.00 pcs 345.00 5,520.00 1,656.00 7,176.00
2.8mm Thk. with 2x2" Mesh, 4x8' Sheet Steel Matting 34.00 sqm. 450.00 15,300.00 4,590.00 19,890.00
SUNDRIES (Consumable materials and equipment) 1.00 lot 2,706.60
SUB-TOTAL FOR PAINTING WORKS 29,772.60
Total Direct Cost 392,824.26

Terms and Conditions:


1. Electricity and Water shall be free on site
2. Workers will not stay-in
3. 50 Working Days without overtime (No Sundays)

Prepared by:
Giannerica Gonzales
Jr. Architect

Approved by:
Name
Proffession

Conforme:
Emma Gonzales
Client / Owner