MAAN STEEL & POWER LTD

09/08/2017 Rev.: 4
1 X 12MW STG SET
IN_002682

Performance Guarantee

Conditions for Performance Guarantee

Only those parameters in this chapter and its subchapters, which are explicitly marked as
‘Guarantees subject to Liquidated Damages’ shall be defined and considered as binding. All
other values in this offer and its attachments are classified as non binding design criteria
and guidance values for information only.
The Guarantee Values are valid for new equipment at steady state operating conditions,
deposit-free blading and clean surfaces of the cooling equipment.
Furthermore, the Guarantee Values are only valid if the delivered equipment is permanently
handled and operated according to Siemens instructions for installation, commissioning,
operation and maintenance.
The legal consequences, if any of the Guarantee Values are not achieved, are solely and
conclusively defined in the commercial contract documents.

1.00 Guarantees subject to Liquidated Damages

1.01 Generator output in kW

Guarantee Point : : 15,000 kW


Load Point Design Guarantee
ST
HBD-03 Rev B dated 01 Aug 2017 (sheet no 1 of 7).

1.02 Turbine heat rate in kCal/KWh with given steam


condition : 2554.84 KCal/kWh
Load Point Design Guarantee
ST
HBD-03 Rev B dated 01 Aug 2017 (sheet no 1 of 7). 2554.12

1.03 Auxiliary Power Consumption in kW for the continuous


running drives as per point no 15 below & at Load Point : 38 kW
Design Guarantee
ST
HBD-03 Rev B dated 01 Aug 2017 (sheet no 1 of 7).

SIEMENS LIMITED Energy Sector Page


Power Generation Division 1 of 4
12_Performance Guarantee_Maan_R4.doc

All copyrights, titles and patents shall remain vested in Siemens AG. We therefore reserve all rights and titles in this document and in the information contained therein.
This document or parts of it may not be reproduced in any form or by any means whether electronically, mechanical or by photocopying, recording or otherwise and may
not be modified, shown or distributed to third parties without prior written permission of Siemens AG.
MAAN STEEL & POWER LTD
09/08/2017 Rev.: 4
1 X 12MW STG SET
IN_002682

Note

1) The turbine heat rate has been calculated based on following formula :

(Steam enthalpy at Steam turbine Inlet – Enthalpy at HPH Outlet) x


Feed water Flow at HP heater outlet +
(Steam Enthalpy at Steam Turbine Inlet – Enthalpy before WHRB) x
Total Flow to WHRB + (make up enthalpy x make up flow)
Heat Rate = ------------------------------------------------------------------------------------------------------------
Power at generator terminals

2) Enthalpy is in Kcal/Kg.
3) For equipments not in Siemens scope, customer shall provide necessary
measurements from power cycle for heat rate calculation
4) SJAE steam flow has not been considered.

Conditions for Performance Guarantee (DIN1943)


1) The guaranteed values are given above will be applicable for new equipment at steady
state operating conditions, deposit-free blading and clean surfaces of the cooling
equipment. Steam quality requirement which will be by Siemens needs to be
demonstrated by Purchaser on continuous basis for achieving the above performance of
TG set.

2) The turbo-set performance shall be verified in accordance with DIN1943. Test


instruments to be used for the verification of the Performance guarantees shall be plant
operating instruments. The mass flow devices are to be provided by the party
responsible for BOP scope / Purchaser has to meet the requirements of IEC 953 and
has to be calibrated by a mutually agreed upon and officially authorized calibration
laboratory. Calibration protocols shall be provided to all concerned parties prior to the
test.

3) The calculation for verification of the performance will be done according to DIN1943
and its supplement VDI 2042.

4) Fulfillment of above performance parameters are subjected to the achievement of all


boundary parameters by Purchaser as specified the guarantee load point parameter
table & the guarantee HBD submitted by Siemens. In case on non-achievement of any
parameter necessary correction curve will be considered during evaluation of PG test
values.

5) Performance guarantee test shall be carried out based on the test procedure prepared
by Siemens. All necessary correction curves required for PG test will be prepared by
Siemens. All performance curves will be used to evaluate the above performance
values.

SIEMENS LIMITED Energy Sector Page


Power Generation Division 2 of 4
12_Performance Guarantee_Maan_R4.doc

All copyrights, titles and patents shall remain vested in Siemens AG. We therefore reserve all rights and titles in this document and in the information contained therein.
This document or parts of it may not be reproduced in any form or by any means whether electronically, mechanical or by photocopying, recording or otherwise and may
not be modified, shown or distributed to third parties without prior written permission of Siemens AG.
MAAN STEEL & POWER LTD
09/08/2017 Rev.: 4
1 X 12MW STG SET
IN_002682

6) The Performance Guarantees are only valid if the delivered equipment is permanently
operated according to Siemens instructions for installation, commissioning, operation
and maintenance and if the below indicated requirements for Operational Conditions are
duly fulfilled.
7) Performance guarantees are based on new and clean conditions, so the performance
test of the STG shall be conducted immediately after commissioning. If PG Test doesn’t
occur within 4 months from first admission of steam to turbine, then tolerance for ageing
shall be considered during performance guarantee evaluation. The ageing tolerances
will be calculated based on ageing formula / curve or value provided by Siemens.

8) In case the PG test is not carried out within 4 months after the initial start-up (First
Steam admission) 120 days from the date of last major supply due to no fault of
Siemens or if the equipment is put to commercial use (other than for commissioning and
testing), whichever is earlier, in such event the PG test shall be deemed to be completed
and the Unit taken over by Purchaser.

9) The thermodynamic values are calculated according to the Steam table IAWPS IF97 /
IFC 67
10) Formulation for Industrial Use for the Thermodynamic Properties of Water and Steam.

11) A test tolerance equal to test measurement uncertainty will be applied to all
performance test results for the demonstration of meeting contractual guarantee
requirements due to the installation, test conditions and instruments errors etc. shall be
estimated using the procedures in IEC. The calculated measuring uncertainty and the
deterioration calculated in accordance with IEC 953-2 (first edition 1990 – 12) if
necessary will be taken into account on supplier side for the comparison between the
measured and the guaranteed values.

Pcorrected + tolerance > Pguarantee (Power Guarantee is fulfilled)


HRcorrected - tolerance < HRguarantee (Heat Rate Guarantee is fulfilled)

12) In case of nonperformance of equipment, Siemens reserves the right to conduct the
performance test with calibrated instruments. The purchaser has to provide plant
operation to facilitate installation of equipment. Availability of consumables, steam,
water, labour, etc. at site and electrical load shall be arranged and ensured by the
purchaser free of cost for the purpose of tests. The purchaser will be provided
calibration certificates of the installed instrument prior to conduct the test for verification.

13) The legal consequences, if any of the guarantee values are not achieved, are solely and
conclusively defined in the commercial contract document.

SIEMENS LIMITED Energy Sector Page


Power Generation Division 3 of 4
12_Performance Guarantee_Maan_R4.doc

All copyrights, titles and patents shall remain vested in Siemens AG. We therefore reserve all rights and titles in this document and in the information contained therein.
This document or parts of it may not be reproduced in any form or by any means whether electronically, mechanical or by photocopying, recording or otherwise and may
not be modified, shown or distributed to third parties without prior written permission of Siemens AG.
MAAN STEEL & POWER LTD
09/08/2017 Rev.: 4
1 X 12MW STG SET
IN_002682

14) Boundary / Performance Parameters at Guarantee Design Load Point

Operating conditions As per HBD’s 03 dated – 01.08.2017,


Rev-B, sheet 1 of 7
Steam Inlet to Turbine at ESV Inlet
Pressure ata 84.000
Temperature °C 515.0
Mass flow T/h 58.32 57.77

Bleed to HP Heater
Pressure at Turbine port ata 15.197 15.997
Temperature °C 310.4 311.3
Mass flow T/h 3.258

Bleed to Deaerator
Pressure at Turbine port ata 8.425
Temperature °C 351.5
Mass flow T/h 0.672

Bleed to LP Heater
Pressure at Turbine port ata 2.194
Temperature °C 122.6
Mass flow T/h 5.732

Exhaust steam at Turbine exhaust


Pressure ata 0.170
Temperature °C 56.24
Mass flow T/h 48.11

Voltage kV 11
Power factor P.F 0.80
Frequency Hz 50
Turbine Speed RPM 8300
Generator Speed RPM 1500

15) List of Consumers for Auxiliary Power Consumption:


S. Consumer Number Number of Unit operating during
N of Unit Guarantee Design Load Point:
st
installed HBD-03 Rev B dated 1 Aug 2017
(sheet no 1 of 7).
1 Oil Vapour Extraction Fan 2 1
2 Main Oil Pump 2 1
3 GSC Exhaust Fan 2 1

SIEMENS LIMITED Energy Sector Page


Power Generation Division 4 of 4
12_Performance Guarantee_Maan_R4.doc

All copyrights, titles and patents shall remain vested in Siemens AG. We therefore reserve all rights and titles in this document and in the information contained therein.
This document or parts of it may not be reproduced in any form or by any means whether electronically, mechanical or by photocopying, recording or otherwise and may
not be modified, shown or distributed to third parties without prior written permission of Siemens AG.

Das könnte Ihnen auch gefallen