Sie sind auf Seite 1von 71

CE155 – ESTIMATING AND VALUE ENGINEERING

INSTRUCTOR: LAMBERTO B. MARCIAL JR., M.S.C.M.


MEASURING QUANTITIES AND ITEMS OF
WORK IN BUILDINGS
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS

Structural works in construction are the works


related to constructing the building frame such as
foundations, columns, beams, girders, and slabs.

These includes:
Formworks Installation
Rebar installation
Concrete pouring
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS
CAST-IN-PLACE CONCRETE – It is concrete
deposited in the place where it is required to
harden as part of the structure.
Rules of Measurement:
- Concrete volume is measured by cubic meters and based
on the dimensions of each structural member.

- Deductions are not made for the following:


• Reinforcement
• Steel sections
• Voids < 0.05m3 in volume (except voids in troughed and coffered
slabs)
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS
FORMWORK– It is a temporary construction to
contain wet concrete in the required shape while it
is cast and setting.

This can be made of steel, wood, aluminum and/or


prefabricated forms.

Rules of Measurement:
- It is measured to the faces of all cast in place concrete
which requires to be supported while the concrete sets.
- No deductions shall be made for voids < 5.00m2.
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS
REINFORCING STEEL – It is a steel bar or mesh
of steel wires used in reinforced concrete and
masonry structures to strengthen and hold the
concrete in tension.

Rules of Measurement:
- Measure separately for different types of steel bar
- Measure separately for different size/diameter
- Forming hooks, tying wire, spacers, cutting/splicing and
bending are deemed included.
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS

CONCRETE COVER PROVISION

Concrete cover is the distance from the outer face


of an element to the outer girth of reinforcement
and is provided to ensure that there is adequate
protection to steel reinforcements that are not
exposed from the concrete and thus prevent
rusting.
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS

CONCRETE COVER PROVISION


MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS

ANCHORAGE & LAP SPLICE LENGTH

Lap length is the length of bar overlap when bars


are tied together for extending the reinforcement
length.

Anchorage length is the additional length of steel


required to be inserted from one structural member
into another structural member at the junction.
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS

ANCHORAGE & LAP SPLICE LENGTH


MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS

HOOKS

These are very significant especially when


measuring links or reinforcement that is bent up or
bent around another bar. These are usually given
as multiples of bar diameter or given as specific
lengths in tabulated form.
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS

HOOKS
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS

STEPS FOR MEASURING REINFORCEMENT

• Make sure to read the specifications or general


notes and checked all notes on plans you will be
using and all other relevant documents.

• Study carefully the drawings and details given.


Make sure that you understand clearly the
details given.
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS

STEPS FOR MEASURING REINFORCEMENT

• Check if there is enough information given to be


able to measure lengths. Be sure to check
specifications and general notes.

• Tick off or loop through bar marks measured to


check if all reinforcement for the particular
element has already been taken or measured.
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS

STEPS FOR MEASURING REINFORCEMENT

• If there are any uncertainties in the details, make


a query on this.

• Check for any assumptions made to be put in


measurement notes.
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS

STEPS FOR MEASURING REINFORCEMENT

• If there are any uncertainties in the details, make


a query on this.

• Check for any assumptions made to be put in


measurement notes.
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS

STEPS FOR MEASURING REINFORCEMENT

Unit weight of rebar per meter is calculated by the


surface area of steel multiply by the density of steel.

Thus,
Kg/m = (π D2/4) x 7850 kg/m3
Or simply:
Kg/m = D x D x 6165 Kg/m3
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS

STEPS FOR MEASURING BEAM REINFORCEMENT

• Typically, reinforcement to ordinary beams will


comprise of top bar reinforcement, bottom bar
reinforcement, links or stirrups and side bars.

• End conditions for beams are usually given with


anchorage length, either given lengths in
tabulated form or given as multiples of bar
diameter.
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS

STEPS FOR MEASURING BEAM REINFORCEMENT

• Pay particular attention where anchorage length


is measured from, which is usually from the
inner face of support or from the centerline of
support.
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS

STEPS FOR MEASURING BEAM REINFORCEMENT


MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS

STEPS FOR MEASURING BEAM REINFORCEMENT


MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS
COMPUTATION FOR LENGTHS & NUMBER OF STIRRUPS
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS
COMPUTATION FOR LENGTHS & NUMBER OF STIRRUPS

Computation for length of outer stirrups / links


S = 2 x (w + d) – 8 x cc + hook
where:
s = stirrup / link
w = width of beam
d = depth of beam
cc = concrete cover
hook = specified length or as multiples of stirrup diameter
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS
COMPUTATION FOR LENGTHS & NUMBER OF STIRRUPS

Computation for the number of outer stirrups / links


N = (L – 2 x cover from face of support) / spacing + 1
where:
N = number of stirrups / links
L = clear length
SAMPLE PROBLEM

Compute for the


concrete, formwork and
reinforcement of girders
G9 @GL A-B/5 AND
G1A @GL B-D/5

Given:
C1= 250x400mm
C2A = 250x550mm
C2B = 200x400mm
Slab Thickness = 100mm
SAMPLE PROBLEM

C1 C2A C2B

Given:
C1= 250x400mm
C2A = 250x550mm
C2B = 200x400mm
G9 = 300X600mm
G1A = 200X400mm
Slab Thickness = 100mm
SOLUTION:

FOR GIRDER G9 @GL A-B/5:

Concrete Volume = Clear Length X Beam Width X Beam Depth

Formworks:

To Soffit = Clear Length X Beam Width

To Sides(Internal) = Clear Length X (Beam Depth – Slab Thickness)

Total Formworks = (Sides + Soffit)


SOLUTION:

FOR GIRDER G9 @GL A-B/5:


Discontinuous @ left support
Continuous @ right support

Reinforcement Total Weight = No. of Bars x Total Length x Weight


Factor

For Main Top Bars:


Total length = clear length + anchorage length + C2A half-width
No. of bars =
Weight factor =
Total weight =
SOLUTION:

FOR GIRDER G9 @GL A-B/5:


Discontinuous @ left support
Continuous @ right support

Reinforcement Total Weight = No. of Bars x Total Length x Weight


Factor

For Main Top Bars:


Total length = clear length + anchorage length + C2A half-width
No. of bars =
Weight factor =
Total weight =
SOLUTION:

FOR GIRDER G9 @GL A-B/5:

For Extra Top Bars (discontinuous @ left support):


Total length = (0.25*L1)+ anchorage length
No. of bars =
Weight factor =
Total weight =

For Extra Top Bars (continuous @ right support):


Total length = (0.31*L1)+ C2A half-width
No. of bars =
Weight factor =
Total weight =
SOLUTION:

FOR GIRDER G9 @GL A-B/5:

For Main Bottom Bars:


Total length = Clear Length + Anchorage Length + C2A half-width
No. of bars =
Weight factor =
Total weight =

For Extra Middle Bottom Bars:


Total length = Clear Length - (0.125*L1) - (0.125*L2)
No. of bars =
Weight factor =
Total weight =
SOLUTION:

FOR GIRDER G9 @GL A-B/5:

For Web Bars:


Total weight = No. of Bars X Clear Length X Weight Factor

TOTAL WEIGHT (for 25-mm bars) =


SOLUTION:

FOR GIRDER G9 @GL A-B/5:

For Stirrups:
Total length = [(2xBeam width)+(2xBeam Depth)] – (8*concrete cover)
+ hooks
No. of bars @ rest = [Clear length – (no of bars * given spacing)] – 1
spacing @ rest
Note: Round off to determine no. of bars; if negative, this means there is no more stirrups @ rest part.

Total No. of Bars =


Weight factor (10mm) =

TOTAL WEIGHT (for 10-mm bars) =


MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS
MEASURING SLAB REINFORCEMENT

There are two general types of slabs with regards


to its load carrying capacity:

• One way slab - slab supported by beam / wall


support (parallel to the long span) and whose
reinforcement runs in one direction only, i.e. from
support to support.
• S/L < 0.50 : S = SHORT SPAN, L = LONG SPAN
REINFORCEMENT OF ONE-WAY SLAB
REINFORCEMENT OF ONE-WAY SLAB
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS
MEASURING SLAB REINFORCEMENT

• Two-way slab – slabs which are supported on


four sides and are reinforced in two directions.
Reinforcement is placed in such a way to
transmit loads to the four supporting beams.

• S/L > 0.50 : S = SHORT SPAN, L = LONG SPAN


REINFORCEMENT OF TWO-WAY SLAB
REINFORCEMENT OF TWO-WAY SLAB
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS
MEASURING SLAB REINFORCEMENT

• Always check if distribution bars have been


provided, especially for top bars. Unless top
bars are continuous from support to support,
there will always be distribution bars to main top
bars.

• Pay careful attention that spacing for bars are


not interchanged between the two directions.
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS
MEASURING SLAB REINFORCEMENT

• Extra details may be provided or adjustments


are to be made.
SAMPLE PROBLEM

Compute for the concrete,


formwork and reinforcement
of Slabs S-1 AND S-4

Given:
C1A = 200X400MM
CG1A = 200X400MM
G1 = 200X400MM
G1A = 200X400MM
G2 = 200X450MM
G6 = 250X600MM
G7 = 250X600MM
B2 = 200X450MM
Concrete Cover = 20MM
SAMPLE PROBLEM
SAMPLE PROBLEM
SAMPLE PROBLEM
SAMPLE PROBLEM
S-1(ONE-WAY):

SS = SHORT SPAN LS = LONG SPAN


Clear length @SS = 1.675 – C1A width Clear length @LS = 4.2 + 1.75 – CG1A width
= 1.675 – 0.2 = 1.475m = 4.2 + 1.75 – 0.2 = 5.75m
SAMPLE PROBLEM
For Slab (S-1):
Given: C1A: 200x400mm G6: 250x600mm
CG1A: 200x400mm G7: 250x600mm
G1: 200x400mm Concrete Cover = 20mm

Clear Length (CL):


CL @ Long Span = 4.2 + 1.75 – CG1A width
= 4.2 + 1.75 – 0.2 = 5.75m

CL @ Short Span = 1.675 – C1A width = 1.675 – 0.2 = 1.475m

𝑆𝑆 1.475
= = 0.26 < 0.5 ; 𝑂𝑛𝑒 − 𝑊𝑎𝑦 𝑆𝑙𝑎𝑏
𝐿𝑆 1.675
SAMPLE PROBLEM
For Slab (S-1):

Long Span:
No. of bars = (CL @ LS – 2* CC) + 1
Spacing @ LS (Top-End)

Top Bars (10-mm) @ left end = No. of bars x total length x weight factor
Total length = (CL @ SS)/3 + Anchorage length

Top Bars (10-mm) @ right end = No. of bars x total length x weight factor
Total length = (CL @ SS)/3 + G6 width/2

Bottom bars (10-mm) = No. of bars x total length x weight factor


Total length = CL@SS+ Anchorage Length + G6 Width / 2

Total weight @ Long Span =


SAMPLE PROBLEM
For Slab (S-1):

Short Span:
For top bars (Left and Right End):
No. of bars = ((CL @ SS / 3) – CC) + 1
Spacing @ SS (Top-End)

Top Bars (10-mm) @ left and right end = No. of bars x total length x weight factor
Total length = (CL @ LS) + (G7 Width / 2) + (CG1A Width / 2)

Bottom bars (10-mm) @left end = No. of bars x total length x weight factor
No. of bars = ((CL @ SS / 7) – CC) + 1
Spacing @ SS (Bottom-End)
Total length = (CL @ LS) + (G7 Width / 2) + (CG1A Width / 2)

Bottom bars (10-mm) @left end = No. of bars x total length x weight factor
No. of bars = ((CL @ SS / 5) – CC) + 1
Spacing @ SS (Bottom-End)
SAMPLE PROBLEM
For Slab (S-1):

Short Span:
For top bars (Left and Right End):
No. of bars = ((CL @ SS / 3) – CC) + 1
Spacing @ SS (Top-End)

Top Bars (10-mm) @ left and right end = No. of bars x total length x weight factor
Total length = (CL @ LS) + (G7 Width / 2) + (CG1A Width / 2)

Bottom bars (10-mm) @left end = No. of bars x total length x weight factor
No. of bars = ((CL @ SS / 7) – CC) + 1
Spacing @ SS (Bottom-End)
Total length = (CL @ LS) + (G7 Width / 2) + (CG1A Width / 2)

Bottom bars (10-mm) @left end = No. of bars x total length x weight factor
No. of bars = ((CL @ SS / 5) – CC) + 1
Spacing @ SS (Bottom-End)
SAMPLE PROBLEM
For Slab (S-1):

Short Span:

Bottom bars (10-mm) @ middle = No. of bars x total length x weight factor
No. of bars = ((CL @ SS) - (CL @ SS / 7) - ((CL @ SS / 5)) -1
Spacing @ SS (Bottom - Middle)
Total length = (CL @ LS) + (G7 Width / 2) + (CG1A Width / 2)

Total weight @ Short Span =


SAMPLE PROBLEM
For Slab (S-4):

SS = SHORT SPAN
Clear length @SS = 3.60m

LS = LONG SPAN
Clear length @LS = 6.20m
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS
MEASURING COLUMN REINFORCEMENT
Basically, column reinforcement is made up of
vertical bars and links.
Computation for vertical bars:
• When measuring vertical bars, always check the
end conditions of the bars and check for location
of laps / anchorage lengths. Floor to floor height
must be verified from the framing plans,
especially at termination points.
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS
MEASURING COLUMN REINFORCEMENT

Computation for links in column:


• Length of links – can be computed in similar way as the
links / stirrups in beam

Number of links:
• There are two (2) conditions to consider when computing
for number of links:
1. when links are to be provided at clear height only
2. when links are provided at entire floor height
including at intersections with other members
MEASURING ITEMS OF WORKS IN
BUILDING PROJECTS: STRUCTURAL WORKS
TYPICAL COLUMN DETAIL:
SAMPLE PROBLEM
Compute for the concrete, formwork and reinforcement of column C1 @GL
F/2 from ground to 2nd floor only. Assume: 3meters – Floor to floor height

FOUNDATION PLAN
SAMPLE PROBLEM
Compute for the concrete, formwork and reinforcement of column C1 @GL
F/2 from ground to 2nd floor only. Assume: 3meters – Floor to floor height

SECOND FLOOR FRAMING PLAN


SAMPLE PROBLEM
SAMPLE PROBLEM
SAMPLE PROBLEM
SAMPLE PROBLEM
For Column (C-1):
Given: C1: 200x400mm CG1A: 200x400mm
G1: 200x400mm floor to floor height = 3m
beam depth = 0.4m clear length = 3 – 0.4 = 2.6m
concrete cover @column & beams = 25mm

Vertical main bars (φ16mm) = no. of bars x floor to floor height x


weight factor

For confinement, lateral, and joint ties:

For confinement ties:

Confinement height as per column schedule = 0.5m


SAMPLE PROBLEM
For confinement ties:

Confinement height as per column schedule = 0.5m


No. of bars = Confinement Height – Concrete Distance from the face of support + 1
Spacing @ ties “a”

Outer ties (Φ10mm) @ confinement:


Top & Bottom = 2 x no. of bars x total length x weight factor
Total Length = same as stirrups

Inner ties (Φ10mm) @ confinement:


Total Length = width – 2*cc + hooks
SAMPLE PROBLEM
For Joint ties:
Joint Height = beam or slab depth
No. of bars = Joint Height - 2*cc @ beam or slab + 1
Spacing @ ties “a”

Outer ties (Φ10mm) @ joint:


Outer ties = no. of bars x total length x weight factor
Total Length =

Inner ties (Φ10mm) @ joint:


Inner ties = no. of bars x total length x weight factor
Total Length = width – 2*cc + hooks

TOTAL REINFORCEMENT @ COLUMN:


Φ16mm =
Φ10mm =
SAMPLE PROBLEM
Compute for the concrete, formwork and reinforcement of footing F6 @ GL –
D/1.

FOUNDATION PLAN
SAMPLE PROBLEM
SAMPLE PROBLEM
SAMPLE PROBLEM
For Footing F6 @ GL D/1:

For Bars ‘C’ = Bottom bars along L


Bars ‘C’ (Φ16mm) = no. of bars x total length x weight factor
No. of bars = per schedule
Total Length = Length of ‘W’ – 2*cc + anchorage length

For Bars ‘D’ = Bottom bars along W


Bars ‘D’ (Φ16mm) = no. of bars x total length x weight factor
No. of bars = per schedule
Total Length = Length of ‘L’ – 2*cc + anchorage length

Das könnte Ihnen auch gefallen