Procurement Timelines – Goods

* The pre-bid conference shall be held at least twelve (12) calendar days before the deadline for the
submission and receipt of bids, but not earlier than seven (7) calendar days from the PhilGEPS posting of
the Invitation to Bid or Bidding Documents and in the case of Consulting Services, from the
determination of the shortlisted consultants. If the Procuring Entity determines that, by reason of the
method, nature, or complexity of the contract to be bid or when international participation will be more
advantageous to the GoP, a longer period for the preparation of bids is necessary, the pre-bid
conference shall be held at least thirty (30) calendar days before the deadline for the submission and
receipt of bids

Procedure Deadline Duration


Advertisement From date of posting until last 7 days
day of posting
Pre-Bid Conference 12 days before submission of 1 day
Bids but not earlier 7 days from
PhilGEPS posting of Invitation to
Bid OR the pre-bid conference
shall be held at least thirty (30)
calendar days before the
deadline for the submission and
receipt of bids

Submission of Bids 12 days after Pre-Bid Conference 1 day


Bid evaluation 7 days after Submission of Bidsvc 1 day
Post qualification 1 day
Issuance of Notice of Award 1 day
Contract Preparation and Signing 1 day
Approval by Higher Authority 1 day
Issuance of Notice to Proceed 1 day

Advertisement : 7 days
Procurement Timelines – Infrastructures below 50 million
Procurement Timelines – Infrastructures above 50 million