GOSALAMORE TO FATAPUKUR(MDR),24.

80KM SADAR BLOCK

GOSALA MORE JUNCTION WITH NH-31D


S.I DESIGNATION(AXB) SPAN (m) LENGTH

1 NEW BOX CULVERT,ch 0.221 km(3.0x3.0) 0.225 km

2 NEW BOX CULVERT,ch 2.999 km(3.0x2.0) 3.00 km

3 NEW BOX CULVERT,ch 3.323km(3.0x2.0) 3.325 km

4 NEW BOX CULVERT,ch 4.70km(3.0x2.0) 4.70 Km

5 NEW BOX CULVERT,ch 5.270km(3.0x2.0) 5.275km

6 NEW BOX CULVERT,ch 5.719km(3.0x2.0) 5.725 km

7 IRRIGATION CHANNEL TO BE RETAINED& 6.525 km


REPAIRED

8 7.80 km
NEW BOX CULVERT IRRIGATION BANDH
PORTION
9 NEW BOX CULVERT,ch 9.2135km(6.0X6.0) 9.200 km

10 NEW BOX CULVERT,ch 9.54km(3.0X2.0) 9.55 km

11 NEW BOX CULVERT,ch 9.54km(3.0X2.0) 9.950 km

12 NEW BOX CULVERT,ch 10.30km(3.0X2.0) 10.30 km

FOR NEPOTI BRIDGE ch-11.75km,


(length-82.00m) 11.700-12.025 km
13

14 NEW BOX CULVERT,ch 12.826km(3.0X3.0) 12.825 km

15 NEW BOX CULVERT,ch 13.368km(3.0X2.2) 13.368km

16 NEW BOX CULVERT,ch 13.6115km(3.0X2.5) 13.611km

17 NEW BOX CULVERT,ch 13.870km(3.0X2.2) 13.870 km

18 NEW BOX CULVERT,ch 14.035km(3.0X2.0) 14.035 km


IRRIGATION CULVERT-ch 14.444 14.444 km
19 RETAINED& TO BE REPAIRED
20 NEW BOX CULVERT,ch 14.81950km(3.0X2.5) 14.820 km

FOR MONTHONY BRIDGE,ch-15.20km,(span- 15.300-15.700km


21 35.75mx3.0 NO"S)

IRRIGATION BOX CULVERT RETAINED& 16.125 km


22 TO BE REPAIRED,ch-16.133

23 NEW BOX CULVERT,ch 16.530km(3.0X2.5) 16.529km

24 NEW BOX CULVERT,ch 16.787km(3.0X3.0) 16.787km

25 TO BE RETAINED & REPAIRED ,ch-17.337 17.336 km

BOX CULVERT ch -17.615(TO BE


26 RETAINED & REPAIRED) 17.615 km

27 AT BELACOBA BAZAR 18.5 km,0km

RLY CROSSING BELACOBA


28 19.450 km,0.950

29 BOX CULVERT 20.437 km,1.937km


START OF TALMA BRIDGE & END OF TALMA 21.350,2.850km-21.600km,3.1
30 BRIDGE ch-21.990km(length-71.00m)

31 CULVERT 24.566km,6.066km

24.80km
FATAPUKUR JUNCTION WITH NH-31D
ITEM THICKNESS
GSB DRAINAGE LAYER 150 MM
GSB 150MM
WMM 250 MM
DBM 125 MM
BC 40 MM
TOTAL 715 MM
.700-12.025 km
.300-15.700km

.5 km,0km

.450 km,0.950

.437 km,1.937km
.350,2.850km-21.600km,3.100km

4.566km,6.066km
HATIMORE TO AMBARIFALAKATA(MDR),7.45KM, RAJGANJ BLOC

S.I DESIGNATION(AXB) SPAN (m) LENGTH

1 0.810km
BOX CULVERT ch -0.8074km(6.0x3.0)

2 1.840km
BOX CULVERT ch -1.832km(3.0x2.50)

3 IRR. SLAB CULVERT ch- 2.130km


2.120km(6.0X2.0)

4 2.370km
BOX CULVERT ch -2.361km(3.0x2.50)

5 2.940km
BOX CULVERT ch -2.932km(3.0x2.0)

6 3.870km
BOX CULVERT ch -3.846km(3.0x2.3)

7 4.260km
BOX CULVERT ch -4.257km(3.0x2.0)

8 4.320km
SLAB CULVERT ch -4.312km(3.0x2.0)

9 CULVERT HUME PIPE TO BE RETAINED 4.650km


,PROTECTION TO BE
DONE,ch4.637km
10 SAHEB PARA BRIDGE-TO BE
RETAINED ,PROTECTION WORK 5.220km
NEEDED ch-5.297km

11 BOX CULVERT ch -5.811km(3.0x2.5) 5.820km

AMBARIFALAKATA(7.45KM)
, RAJGANJ BLOCK

ITEM THICKNESS
GSB DRAINAGE
LAYER 150 MM
GSB 150MM
WMM 250 MM
DBM 125 MM
BC 40 MM
TOTAL 715 MM