Beruflich Dokumente
Kultur Dokumente
Main objective after tank rehabilitation project was identified as community development.
Providing water storage of 256.1 ha.m for the area in dry season.
Improving the paddy cultivation of the area by providing water for both Yala and Maha seasons.
With rehabilitation of the tank farmers are supposed to increase their irrigable area up to 500
acres in Maha season and 120 acres in Yala season.
Enhancing the productivity of lands and improve the standard of the living of the farmers.
Educating the younger generation of farmers about new techniques and machineries used in
agriculture by establishing an agricultural institute.
Providing a housing unit, school, medical center and proper road network for the area in order to
settle people around the irrigable area.
Improving the drinking quality of water in the area and provide housing water supply for the
village.
Supporting livestock farming by establishing a milk collecting center in the village which gives
additional income in cattle farming.
Increasing the land value of the area.
Proposed project conditions are identified according to The National Environmental Act, No 47
of 1980.
Irrigation projects excluding minor irrigation works.
EIA required to carry out according to The National Environmental Act, No 47 Of 1980.
Forest department
Forest Department was decided to be the PAA as it is the agency with a high land area and a
high resource depletion due to the project.
The EIA has been carried out according to the TOR (Terms of Reference). And relevant impacts
need to mitigate with appropriate measures in order to carry out the project in more justifiable way.
1.5 Conditions laid down by state agencies in granting preliminary clearance for
the project
Required to obtain an EIA from the Forest Department
2 CHAPTER 02: DESCRIPTION OF PROPOSED PROJECT AND
REASONABLE ALTERNATIVES.
Then consider about the current location which is already choose for the community
development project. Existing land around the tank frequently subject to flooding. Therefore buildings
and structures are proposing to establish in upstream area rather than flood risk land in downstream.
Evaluating all impacts separately for 2 design alternatives with financial feasibility comes under a
conclusion of selecting the 2nd alternative among both alternatives.
The existing tank is not in a condition to use without any rehabilitation. All components
including Tank bund, sluice, Spillway, Canal system and all other structures in the community
development area.
Tank bund – existing tank bund breached at a section due to insufficient spillway length and
cracks developed in the bund. It has been found that existing soil conditions of the tank bund is
adequate to rehabilitate the existing one. Therefore existing tank bund can be use after
rehabilitant.
Spillway – Spillway designed according to the peak discharge. Existing spillway is not
sufficient in length. So that
Sluice – Sluice is proposed to develop as an orifice. And the design strategy contains three as
geometric, hydraulic and structural.
Canals and turnout structures – due to unsuitable soil conditions in existing soil for earthen
canal interrupts to construct earthen canal network. So that concrete canal system is proposing.
And the canal system is designed according to the topography of the area.
2.2.1.1 Permanent Structures
Road network – Road from Chenkaladi to Karadiyanaru junction is the existing main road.
And with the development of the area we are proposing a bituminous road from Karadyanaru
junction to reservoir while cement stabilize road as a village road network.
Community building, school, hospital, living quarters and housing scheme – All the structures are
designed to build as single story or two story. Main target is to build walls with 150mm thick earth
embedded walls and floor with concrete.
There are medium sized trees to bushes grown in the area. So trees which are need to remove in
the construction purposes are marked under the advice of the forest department and remove whenever
necessary by the State Timber Cooperation (STC). Bushes and small sized trees can be removed from
machines. The existing area covers with rock out crops and even the natural type spill way is a rock
made one. So that rocks and boulders can be removed blasting.
Required measures are taken to protect the tank bund. Upstream slope of the bund need to
protect from wave erosion by constructing a Rip rap. And in order to prevent fill material coming out
with seepage water a sand blanket and toe drain will be constructed. And downstream slope of the
bund dressed with turf. Required boulders and gravel can be obtained from the site itself which are
blasted in construction activities.
Construction of canals – Soil condition of the area does not suit to construct an earthen canal.
Therefore concrete laid canal is proposed to main canal while earthen canal for other distribution
network. So that cost of the canal network can be minimize. Canal network designed according to the
slope of the land. Canal slopes required to protect from erosion and for that pitching and turfing will be
done.
Spillway construction – spillway required to lengthen by changing the design from natural type to
labyrinth type spill way. For that concrete can be used as a material and rock blasting will be needed to
change the existing spillway. Machineries like excavators, dumpers, bulldozers and concrete mixers
will be occupy during construction stages.
Sluice construction – The Orifice type sluice gate can be restored and established for the tank.
Building construction – School, community building, Housing unit and Hospital are the main
structural buildings supposed to establish here. Preliminary site excavations and concrete works will be
carried out as usual. And walls will be made out from earth embedded walls.
.
2.2.2.3 Details of access roads to be built
Connecting the housing scheme Bituminous road Lane width = 3.3 m
Shoulder width = 1 m
area and the Karadiyanaru
Drain width = 0.7 m
junction
Connecting housing scheme Cement stabilized Earth Connecting the houses
Sandy clay can be used
Road
10% cement by volume to stabilize the
soil
150mm thickness
In detail, Bund construction will be done with using available soil in the site. And for the
sluice and spillway construction concrete can be used as a construction material. Again boulders and
rubble will be used as a construction material in bund, sluice and other structures. Earth embedded
walls are proposing instead of brick walls for the housing scheme. Soil stabilized road made with
existing soil will be constructed as a road to the housing scheme.
Earth: - Required earth material will be burrowed from the tank bed area and soil extracted in
excavations.
Gravel: - Sufficient gravel is available in the site due to blasting of rock outcrops in clearing activities.
Boulders: - Required amount of boulders will be obtained from tank bed area.
3.1.1 Topography
Topography of the area varies over a certain region with sudden variations at some places.
Therefore some rocks and hills exist in the upstream area. And most of the hills are isolated in flat
area. Irrigable land extends in a low terrain about 1000s’ of acres in the downstream.
3.1.2 Geology & Soil
Soil type of the area found as Clayey sand and sand layer on the land in dry seasons due to
dried up stream. Rock out crops present at many places. Soil parameters of the existing soil has been
found through carrying out tests.
3.1.3 Meteorology
3.1.3.1 Annual Rainfall & Rainfall Patterns
Annual rainfall pattern and data collected from the meteorology department shows average
values of 1650.9mm. Observed area, Eraur in Batticaloa is in tropical wet and dry climate. Therefore
according to prevailing rainfall pattern maximum rainfall received in November to December about
350mm – 400mm. And the average temperature is 250 C as it rises up to 320 C in temperate periods.
With high temperature existing Lawanya Aru dried up in the dry season.
3.1.3.2 Flood
Cyclic flood in rainy season is a considerable impact. Recently occurred major flood was in
December 1957 with maximum rainfall of 275mm. People in the area experienced annual flood since
1961. Main reasons for frequent flood have identified as,
Deforestation in the upper reaches of the catchments of streams and rivers resulting in flash floods.
Encroachment into stream reservations and drainage lines by agriculture and building activity.
Inadequate drainage across roadways.
Causeways across lagoons.
Silting of lagoons.
3.1.3.3 Drought
Batticaloa area annually receives rainfall of 1250mm to 1850mm. 52% of the annual rainfall
receive between December and February and 27% in October/November and the rest in April/May.
From May to September a near-drought condition prevails. During these months the mean daily
maximum temperature could be as high as 33.6 C. These five months of drought is an annual hazard
especially on Rugam region where tank located.
3.1.4 Hydrology
3.1.4.1 General description of the catchment areas of water bodies
Catchment area calculated with the use of topo sheet is 12.1 km2. Length of the main
stream is 5.1km and the stream slope is 0.3.
Flora types can be categorize mainly which are grown in dry climatic conditions. Common
types of flora observed are Karuwala, Weera, Milla, Hamilla, Kolon, Wara and Gandapana. And some
important habitats were found where commercially important and endemic species exist.
And fauna found within the affecting forest area have been identified through the community
survey. Some important species are elephants, wild bores and buffaloes. Animal adapted with dry
climate commonly surviving here.
People who live nearby area for cattle farming tend to use kerosene oil for their power
generation. And ground water for drinking and other water requirements. In the dry periods people
excavate holes at the stream bed and obtain water which are really not in the quality of drinking water
quality.
Currently farmers cultivate 300 acres in Maha season using rainwater and no cultivations done in Yala.
Therefore this project can give continuous water supply for the irrigable lands. Existing land can
cultivate even 1000s’ of acres in Maha season with rainwater. After rehabilitate the tank with
prevailing bund can cultivate 500 acres in Maha and 200 in Yala. And this project propose to raise 1m
from the bund. So that 750 acres in Maha and 350 acres in Yala. It will be a major impact on water
supply to the irrigable lands.
Solar or wind power electricity can be generate within the region itself.
Batticaloa low land region is receiving sufficient amount of sun light throughout the year. And high
wind condition even in rainy periods. So that most feasible and advantage solutions can be taken for
electricity for the proposed housing unit. Therefore it will be a great advantage from the project
location.
There are several positive impacts encouraging the proposing project of rehabilitation of
project with community development. In other hand many other negative impacts are their due to the
project. Therefore we are proposing some migratory measures for identified negative impacts during
designing, construction and operation stages.
Major Negative Impacts
Negative impacts can be severe, medium and low. When analysing such impacts mitigations
are taken considering their weightage of affecting the environment. Identified impacts can be listed as
below according to the strength of impacts as Severe, medium and low
Severe Impacts
Inundating the forest area for the reservoir due to increment of the tank bund from 1m.
Increasing the bund level from 1m increases the inundating area from a huge amount as given in the
table below. So that inundating area will be a loss to the forest.
Elevation Area Volume Cum capacity
34 921916 422977 1782723
35 1347034 609987.75 2896419
Contamination of water
Contamination of water may be due to improper sewage, waste water and solid waste disposal. During
the construction phase this problem rise severely. As temporary structures built on the site may not
have proper planning or system of waste disposal will collect to the water stream and downstream.
And again leakages and spills from machineries will pollute the water. Many vehicles and machines
will occupy in the construction site during construction stage.
Change and disruption in surface water flow
Obstructing the natural water path by constructing a dam is a major impact as it disturbs the natural
flow pattern. After reservoir constructed upstream will collects water to its full supply level and in dry
season existing natural stream end from the tank. It will limited the downstream environment and
water pattern. But water supply for the paddy cultivation might added to the downstream as seepage
flow. And after a heavy rain spilling can cause flood in the downstream. But flood level can be control
according to the functioning of the spillway.
Change and disruption in ground water flow and the water table
Due to the construction of the proposed tank, the ground water table will be increased and the seepage
flow could be increased in the downstream. However the toe filter and toe drain would function to
reduce seepages.
Impact on terrestrial fauna and flora due to loss and change of habitats
This project will not cause any fragmentation of any critical habitats. But it changes and loss habitats
within the forest. These forest habitats are important biodiversity repositories as was evident by the
species that were recorded in these habitats. This impact will be an irreversible affect as this will result
in permanent conversion of these habitats into a reservoir. The terrestrial species that were utilizing
this area will lose their habitat as such the terrestrial species assemblage in the inundation area will be
replaced by an aquatic species assemblage. Further, during the construction stage removal of
vegetation cover may result in loss of habitats (feeding, roosting and breeding sites) of animals. Thus it
can be concluded that terrestrial species occupying both natural and manmade habitats in the proposed
reservoir area will be adversely affected by the project due to habitat loss.
Medium Impacts
Land degradation
Land degradation is removing the fertility of lands. It can be due to site clearing for construction
purposes. Some trees have to remove in site clearing and vegetation removal also done in site
preparation. Barren lands and downstream open forest areas will gradually converted in to agricultural
lands.
Water logging
This issue will rise due to saturation of water. And that causes because of excessive irrigation on poor
draining soil. The raised water table results in the soils becoming waterlogged. When soils are water
logged, air spaces in the soil are filled with water, and plant roots essentially suffocate, lack oxygen.
Waterlogging also damages soil structure.
Air pollution
Air pollution is very common as is the case in all construction projects, particulates generated due to
land preparation, transport of construction material, emission from construction related vehicles. It can
adversely affect public health. However, the major construction activities occur within the forest and
so this impact is quite low.
Air pollution Borrowing construction cover borrowed earth properly from rain and
material and placement wind
moving of vehicles within the
use water to suppress dust
site
Limit the noise level more than 55dB.
construction activities of tank
Limit the noise generating works from 7am to
and buildings
6pm in order to minimize impact to fauna.
moving of vehicles within the proper maintenance for the vehicles to ensure
site the adherence to noise standards,
physical hazards for the construction activities of tank
Provide PPEs for all workers.
workers and buildings
make aware the villagers about health related
Using of fertilizers and problems with drinking water and provide
long term health issues
pesticides monitoring system to check the quality of
water
forest reserve will be lined with electric
fencing
Site clearance in forest area Identify the elephant moving path (corridor)
risk of elephant-human
and do not disturb the area in construction
conflicts
planning.
forest reserve will be lined with electric
construction of housing unit
fencing
5.2 Compensatory afforestation programme
5.2.1 Forest enrichment programme
As a remedial measure for loss the habitats of species, this would be a good option. Programme
can be implement with the help of the community. Flora species which are endemic to low country dry
zone and species which are mostly affected by the project should plant inside the forest area. Tree
planting should be commenced with the start of the monsoon rains. However species selection, nursery
establishment and tree planting should be carried out with the support of the Forest Department.
Frequency of monitoring
Parameters of considering
Responsible authorities and agencies
Whether technical and economical assistant available in relevant agencies
Sample locations to monitor
Reporting format and procedure for monitoring
Check/
category /
Impact Monitoring indicator cost Report Responsibility
parameter
frequency
Dust due to excavations, soil
contractors supervisor/site
compaction and transportation Public complains and visually weekly
engineer
with the effect of wind
Inspection cost and
Air quality air quality testing
emission of smoke and other Public complains and official cost contactors supervisor and if
harmful gaseous due to complains by environmental daily required environmental
machines and vehicles officers officer/site engineer
requirement of
disturbance to livelihood of client have to pay
public claims compensation cost the District
people compensation
social Secretary
reported incidents and public After any client have to pay
human - elephant conflict compensation cost
claims incident compensation
clearing the forest area
removal of trees other than Inspection and
flora and fauna check the marked trees weekly STC/ engineer
marked by the State Timber transportation cost
cooperation
7 Chapter 07 Conclusion and Recommendation
The above mentioned project benefit the village by rehabilitate the Puluddumaanodai tank with
the community development. So it enhances the farmers by encouraging them to cultivate 700acers in
Maha and 300acres in Yala season. Currently using irrigable lands can be extent and increase the
harvest. All significant impacts are discussed in previous chapters and suitable recommendations are
stated.
Major issues identified are encroachment of people in to the forest area, elephant-human
conflict, impoundment of water in the upstream, obstructing the natural water stream, removing and
clearing the forest area which affects existing flora and fauna. But this proposed project area is in low
country dry zone where there’s no high diversity of flora and fauna compared to the wet zone. And
most of the existing species are not endemic, rare or threatened other than elephants and some special
species.
During the survey we have identify such problems which can be arise with introducing new
environment to the existing area as changing the water quality, quantity, soil erosion, introducing
invasive species, quality of the air and noise and vibration level.
Proposed monitoring mechanism will identify the weightage and possibility of identified
impacts. Relevant responsible authorities or parties should involve in monitoring programme. And
monitoring should be carried out in frequent and specified time intervals in the monitoring plan.
By analysing the positive impacts with possibly happening negative impacts proves that
proposed project can be implement after taking required mitigations for identified environmental
issues.