Sie sind auf Seite 1von 52

ITEM DESCRIPTION QUANTITY UNITS

1 LAY OUT, SITE CLEARING AND TEMPORARY STRUCTURES 19500.00 sq.m


2 SOIL POISONING 19,500.00 sq.m
3 STRUCTURAL EXCAVATION 8,470.00 cu.m
4 GRAVEL BEDDING 19,500.00 sq.m
5 EMBANKMENT 10703.22 cu.m
6 FORMS & SCAFOLDING 16906.48 sq.m
7 REINFORCING STEEL BARS 53064.00 kg
8 CONCRETE WORKS 9884.84 cu.m
9 MASONRY WORKS 16466.65 sq.m
10 PLASTERING AND FINISHING WORKS 24383.04 sq.m
11 TILE WORKS 20,404.36 sq.m
12 PAINTING WORKS 24,713.00 sq.m
13 GLASS WORKS 76.00 pcs
14 PLUMBING WORKS & FIXTURES 2287.00 pcs
15 MECHANICAL WORKS 1.00 set
16 ELECTRICAL WORKS 23201 pcs
17 WATERPROOFING WORKS 120 sq.m
18 SOUNDPROOFING WORKS 3200 sq.m
19 LANDSCAPING WORKS 14380 sq.m
Total Cost
UNIT COST AMOUNT
13.66 266309.8
14.54 283600
91.87 778104
19.25 375308
5.31 56840
363.27 6414596.8
98.37 5219902.4
6564.44 64888398.08
215.94 3555833.1
131.54 3207368
728.18 14858085
133.64 3302693.12
39974 3034964
2973.82 6801137.41
20000000
6718.69 15459703.26
322.24 38668.24
112.25 315210
136.91 1968720
151,325,441.21
HT. Feliciano street,
Aguada, Ozamiz City

ITEM DESCRIPTION QTY. UNITS UNIT COST


1 LAYOUT, CLEARING OF SITE & TEMPORARY STRUCTURES 19500 sq. m.
LABOR COST: NO. OF WORKERS NO. OF DAYS RATE PER DAY
Project Engineer 1 7 800
Construction Foreman 1 7 600
Equipment Operator 2 4 500
Carpenter 4 7 350
Laborers 4 7 300
TOTAL LABOR COST

EQUIPMENT COST: QTY. DAYS RATE PER DAY


Grader 1 4 12000
Km. Travelled/Day Liters/Km. Diesel
Grader Comsumption 40 0.2 45
Dump Truck ( 5 cu.m/day) 1 4 5000
Km. Travelled/Day Liters/Km. Diesel
Dump Truck Comsumption 40 0.2 45
TOTAL EQUIPMENT COST

MATERIAL COST (Temporary Structures) QTY. UNITS UNIT COST


Container Van 4 pcs 12000
Coco Lumber 4” x 4” x 12’ 211 pcs 120
35 mm x 76 mm x 3 m Studs 126 pcs 60
Corrugated G.I. Sheet 21 sht. 280
Plywood; Marine ( 1/4"x4'x8') 118 sht. 680
Common Nails 3 kg 65
Umbrella Nails 2 kg 85
TOTAL COST

DIRECT COST

INDIRECT COST:
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/Demolization (1%)
VAT(12%)
TOTAL INDIRECT COST

TOTAL ITEM COST


UNIT COST
Feliciano street,
uada, Ozamiz City

TOTAL

5,600.00
4,200.00
4,000.00
9,800.00
8,400.00
32,000.00

48,000.00

1,440.00
20,000.00

1,440.00
70,880.00

25,320.00
7,560.00
5,880.00
80,240.00
195.00
170.00
119,365.00

222,245.00

11,112.25
22,224.50
2,222.45
8,505.60
44,064.80

266,309.80
13.66
2 SOIL POISONING 19500
LABOR COST: NO. OF WORKERS
Project Engineer 1
Construction Foreman 1
Laborers (240sq.m/day) 4
TOTAL LABOR COST

MATERIAL COST: QTY.


Soil Poison (CHLORDANE ANDREX) 132
TOTAL MATERIAL COST

DIRECT COST

INDIRECT COST:
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/Demobilization(1%)
VAT (12%)
TOTAL INDIRECT COST

TOTAL ITEM COST


UNIT COST
sq. m./GAL
NO. OF DAYS RATE PER DAY TOTAL
10 800 8,000.00
10 600 6,000.00
10 300 12,000.00
26,000.00

UNITS UNIT COST


gallon 1500 198,000.00
198,000.00

224,000.00

11,200.00
22,400.00
2,240.00
23,760.00
59,600.00

283,600.00
14.54
3 STRUCTURAL EXCAVATION 8470
LABOR COST: NO. OF WORKERS
Project Engineer 1
Construction Foreman 1
Laborers 4
Operator 4
TOTAL LABOR COST

EQUIPMENT COST: QTY.


Backhoe w/ Breaker (5cu.m/hr) 2
Km. Travelled/Day
Backhoe Comsumption 40
Dump truckr (25cu.m/hr) 2
Km. Travelled/Day
Dumptruck Comsumption 40
TOTAL EQUIPMENT COST

DIRECT COST

INDIRECT COST
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/ Demobilization (1%)
VAT (12%)
TOTAL INDIRECT COST

TOTAL ITEM COST


UNIT COST
cu. m.
NO. OF DAYS RATE PER DAY TOTAL
15 800 12,000.00
15 600 9,000.00
15 300 18,000.00
15 400 24,000.00
63,000.00

NO. OF DAYS RATE PER DAY


15 13000 390,000.00
Liters/Km. Diesel
0.2 45 5,400.00
15 5000 150,000.00
Liters/Km. Diesel
0.2 45 5,400.00
550,800.00

613,800.00

30,690.00
61,380.00
6,138.00
66,096.00
164,304.00

778,104.00
91.87
4 GRAVEL BEDDING 19500
LABOR COST: NO. OF WORKERS
Project Engineer 1
Construction Foreman 1
Compactor Operator 1
Laborers 4
TOTAL LABOR COST

MATERIAL COST: QTY.


Granular Material 390
TOTAL MATERIAL COST

EQUIPMENT COST: QTY.


Plate Compactor 1
Km. Travelled/Day
Plate Compactor Comsumption 40
TOTAL EQUIPMENT COST

DIRECT COST

INDIRECT COST
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/Demobilization (1%)
VAT (12%)
TOTAL INDIRECT COST

TOTAL ITEM COST


UNIT COST
sq. m
NO. OF DAYS RATE PER DAY TOTAL
5 800 4,000.00
5 600 3,000.00
5 400
5 300 6,000.00
13,000.00

UNITS UNIT COST


m³ 700 273,000.00
273,000.00

NO. OF DAYS RATE PER DAY


5 1500 7,500.00
Liters/Km. Diesel
0.2 45 1,800.00
9,300.00

295,300.00

14,765.00
29,530.00
2,953.00
32,760.00
80,008.00

375,308.00
19.25
5 EMBANKMENT 10,703.22
LABOR COST: NO. OF WORKERS
Project Engineer 1
Construction Foreman 1
Laborers 4
Equipment Operator 4
TOTAL LABOR COST

EQUIPMENT COST: QTY.


Plate Compactor 2
Km. Travelled/Day
Plate Compactor Comsumption 40
Backhoe w/ Breaker (5cu.m/hr) 2
Km. Travelled/Day
Backhoe Comsumption 40
TOTAL EQUIPMENT COST

DIRECT COST

INDIRECT COST
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/Demolization (1%)
VAT (12%)
TOTAL INDIRECT COST

TOTAL ITEM COST


UNIT COST
cu.m.
NO. OF DAYS RATE PER DAY TOTAL
4 800 3,200.00
4 600 2,400.00
4 500 8,000.00
4 400 6,400.00
20,000.00

NO. OF DAYS RATE PER DAY


4 1500 3,000.00
Liters/Km. Diesel
0.2 45 1,440.00
4 13000 26,000.00
Liters/Km. Diesel
0.2 45 1,440.00
29,000.00

49,000.00

2,450.00
4,900.00
490.00
-
7,840.00

56,840.00
5.31
6 FORMWORKS AND SCAFFOLDINGS 16,906.48
LABOR COST: NO. OF WORKERS
Project Engineer 1
Construction Foreman 1
Carpenter 20
Laborers 20
TOTAL LABOR COST

MATERIAL COST: QTY.


Assorted CW Nails 300
Formworks for Column: 2151
Plywood; Marine ( 1/4"x4'x8') 747
Coco Lumber (2"x2") 1344
Formworks for Slabs: 4375
Plywood; Marine ( 1/4"x4'x8') 1520
Coco Lumber (2"x2") 4560
Formworks for Beams 1926
Plywood; Marine ( 1/4"x4'x8') 669
Coco Lumber (2"x2") 936
Formworks for Girder 4261.2
Plywood; Marine ( 1/4"x4'x8') 1480
Coco Lumber (2"x2") 1608
Formworks for Foundation 4193.28
Plywood; Marine ( 1/4"x4'x8') 1456
Coco Lumber (2"x2") 224

Coco Lumber (2"x2") 11468


Coco Lumber (2"x3") 600
Nails 600
TOTAL MATERIAL COST

DIRECT COST

INDIRECT COST
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/ Demobilization (1%)
VAT (12%)
TOTAL INDIRECT COST

TOTAL ITEM COST


UNIT COST
sq.m.
NO. OF DAYS RATE PER DAY TOTAL
30 800 24,000.00
30 600 18,000.00
30 500 300,000.00
30 300 180,000.00
522,000.00

NO. OF DAYS RATE PER DAY


kg 70 21,000.00
sq.m.
sht. 680 507,960.00
Bd.ft. 15 20,160.00
sq.m.
sht. 680 1,033,600.00
Bd.ft. 15 68,400.00
sq.m.
sht. 680 454,920.00
Bd.ft. 15 14,040.00
sq.m.
sht. 680 1,006,400.00
Bd.ft. 15 24,120.00
sq.m.
sht. 680 990,080.00
Bd.ft. 15 3,360.00

Bd.ft. 15 172,020.00
Bd.ft. 15 9,000.00
kg 70 42,000.00
4,325,060.00

4,847,060.00

242,353.00
484,706.00
48,470.60
519,007.20
1,294,536.80

6,141,596.80
363.27
7 REINFORCING STEEL BARS 53,064.00
LABOR COST: NO. OF WORKERS
Project Engineer 1
Construction Foreman 1
Steel Man 8
Laborers 16
TOTAL LABOR COST

EQUIPMENT COST: QTY.


Bar Bender 2
Bar Cutter 2
Mobile Crane 1
Km. Travelled/Day
Mobile Crane Comsumption 40
TOTAL EQUIPMENT COST

MATERIAL COST: QTY


A. FOUNDATION 8512
28 mm Æ steel bar (6m) 1008
25 mm Æ steel bar (6m) 6720
12 mm Æ steel bar - TIES (6m) 784
#16 G.I. Tie wire 1890
B. BEAMS 6960
20 mm Æ steel bar (6m) 2593
12 mm Æ steel bar - TIES (6m) 4367
#16 G.I. Tie wire 617
C. GIRDERS 14104
20 mm Æ steel bar (6m) 6585
12 mm Æ steel bar- TIES (6m) 7519
#16 G.I. Tie wire 1376
D. SLAB 13328
12 mm Æ steel bar- TIES (6m) 13328
#16 G.I. Tie wire 711
E. COLUMN 4704
28 mm Æ steel bar (6m) 3248
12 mm Æ steel bar - TIES (6m) 1456
#16 G.I. Tie wire 1020
E. STAIRWAYS 692
STRAIGHT 452
12 mm Æ steel bar - TIES (6m) 452
#16 G.I. Tie wire 24
HELIX 240
12 mm Æ steel bar - TIES (6m) 240
#16 G.I. Tie wire 13
F. WALL 4708
12 mm Æ steel bar (6m) 4708
#16 G.I. Tie wire 250
G. SEPTIC TANK 56
12 mm Æ steel bar - TIES (6m) 56
#16 G.I. Tie wire 3
H. TEMPERATURE BARS 12
10 mm Æ steel bar - TIES (6m) 12
#16 G.I. Tie wire 0.5
TOTAL MATERIAL COST

DIRECT COST

INDIRECT COST
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/ Demolition (1%)
VAT (12%)
TOTAL INDIRECT COST

TOTAL ITEM COST


UNIT COST
pcs
NO. OF DAYS RATE PER DAY TOTAL
58 800 46,400.00
58 600 34,800.00
58 500 232,000.00
58 300 278,400.00
591,600.00

NO. OF DAYS RATE PER DAY


58 800 92,800.00
58 800 92,800.00
3 14800 44,400.00
Liters/Km. Diesel
0.2 45 1,080.00
231,080.00

UNIT UNIT COST


pcs
pcs 55 55,440.00
pcs 55 369,600.00
pcs 55 43,120.00
kg 70 132,300.00
pcs
pcs 55 142,615.00
pcs 55 240,185.00
kg 70 43,190.00
pcs
pcs 55 362,175.00
pcs 55 413,545.00
kg 70 96,320.00
pcs
pcs 55 733,040.00
kg 70 49,770.00

pcs 55 178,640.00
pcs 55 80,080.00
kg 70 71,400.00
pcs

pcs 55 24,860.00
kg 70 1,680.00
pcs
pcs 55 13,200.00
kg 70 910.00
pcs
pcs 55 258,940.00
kg 70 17,500.00
pcs
pcs 55 3,080.00
kg 70 210.00

pcs 55 660.00
kg 70 35.00
3,332,495.00

4,155,175.00

207,758.75
415,517.50
41,551.75
399,899.40
1,064,727.40

5,219,902.40
98.37
8 CONCRETE WORKS 9,884.84
LABOR COST: NO. OF WORKERS
Project Engineer 1
Construction Foreman 1
Mason 10
Laborers 20
TOTAL LABOR COST

EQUIPMENT COST: QTY


Transit Mixer (7.5 cu.m/day) 2
Km. Travelled/Day
Transiter Mixer Comsumption 40
Pumpcrete 1
Km. Travelled/Day
Pumpcrete Comsumption 40
Concrete Vibrator 1
Km. Travelled/Day
Concrete Vibrator Comsumption 40
TOTAL EQUIPMENT COST

MATERIAL COST QTY


A.) SLAB 6,347.74
Pre-Mixed Concrete 6347.74
B.) RC BEAMS 271.55
Pre-Mixed Concrete 271.55
C.) GIRDER 1172.57
Pre-Mixed Concrete 1172.57
C.) COLUMN 462.22
Cement (Class A-40 Kg) 4159.98
Washed Sand 231.11
Crushed Gravel 462.22
D.) STAIRS
STRAIGHT 7.85
Pre-Mixed Concrete 7.85
SPIRAL 11.73
Pre-Mixed Concrete 11.73
E.) TEMPORARY STRUCTURES 4.4
Cement (Class A-40 Kg) 39.6
Washed Sand 2.2
Crushed Gravel 4.4
F.) FOUNDATION 1606.78
Pre-Mixed Concrete 1606.78
MATERIAL COST TOTAL

DIRECT COST

INDIRECT COST:
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/ Demolization (1%)
VAT (12%)
TOTAL INDIRECT COST

TOTAL ITEM COST


UNIT COST
cu.m
NO. OF DAYS RATE PER DAY TOTAL
16 800 12,800.00
16 600 9,600.00
16 500 80,000.00
16 300 96,000.00
198,400.00

NO. OF DAYS RATE PER DAY


16 1200 38,400.00
Liters/Km. Diesel
0.2 45 5,760.00
16 750 12,000.00
Liters/Km. Diesel
0.2 45 5,760.00
16 750 12,000.00
Liters/Km. Diesel
0.2 45 5,760.00
61,920.00

UNIT UNIT COST TOTAL



m³ 5000 31,738,700.00

bags 5000 1,357,750.00

m³ 5000 5,862,850.00

bags 250 1,039,995.00
m³ 750 173,333.00
m³ 1000 462,220.00
1,675,548.00

m³ 5000 39,250.00

bags 5000 58,650.00

bags 250 9,900.00
m³ 750 1,650.00
m³ 1000 4,400.00

bags 5000 8,033,900.00
50,458,146.00

50,718,466.00

2,535,923.30
5,071,846.60
507,184.66
6,054,977.52
14,169,932.08

64,888,398.08
6,564.44
9 MASONRY WORKS 16,466.65
LABOR COST: NO. OF WORKERS
Project Engineer 1
Construction Foreman 1
Mason 1
Laborers 20
TOTAL LABOR COST

EQUIPMENT COST: QTY


Concrete Mixer (5cu.m) 2
Km. Travelled/Day
Concrete Mixer Comsumption 40
Mobile Crane 1
Km. Travelled/Day
Mobile Crane Comsumption 40
TOTAL EQUIPMENT COST

MATERIAL COST: QTY


D.) WALLS 7019.725
CHB (100x200x400mm) 92,134
Between Layer of Blocks + 4 holes
Cement (Class C Mortar) 2,369
Sand (River Sand) 263
E.) SEPTIC TANK 36.48
CHB (100x200x400mm) 479
Between Layer of Blocks + 4 holes
Cement (Class C Mortar) 12
Sand (River Sand) 1
F.) TEMPORARY STRUCTURES 126
CHB (100x200x400mm) 1,654
Between Layer of Blocks + 4 holes
Cement (Class A Mortar) 43
Sand (River Sand) 5
TOTAL MATERIAL COST

DIRECT COST

INDIRECT COST:
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/Demolization (1%)
VAT (12%)
TOTAL INDIRECT COST

TOTAL ITEM COST


UNIT COST
sq.m
NO. OF DAYS RATE PER DAY TOTAL
21 800 16,800.00
21 600 12,600.00
21 500 10,500.00
21 300 126,000.00
165,900.00

NO. OF DAYS RATE PER DAY


21 10500 441,000.00
Liters/Km. Diesel
0.2 45 7,560.00
3 14800 44,400.00
Liters/Km. Diesel
0.2 45 1,080.00
494,040.00

UNIT UNIT COST


sq.m
pcs 15 1,382,010.00

bags 250 592,250.00


cu.m. 650 170,950.00
sq.m.
pcs 8 3,832.00

bags 250 3,000.00


cu.m. 650 650.00
sq.m.
pcs 8 13,232.00

bags 250 10,750.00


cu.m. 650 3,250.00
2,179,924.00

2,839,864.00

141,993.20
283,986.40
28,398.64
261,590.88
715,969.12

3,555,833.12
215.94
10 PLASTERING AND FINISHING WORKS 24,383.04
LABOR COST: NO. OF WORKERS
Project Engineer 1
Construction Foreman 1
Mason 5
Laborers 5
TOTAL LABOR COST

MATERIAL COST: QTY


A.) WALLS 15060.2
Cement (Class C Plastering) 2,711
Sand (River Sand) 301
B.) SEPTIC TANK 38.4
Cement (Class C Mortar) 7
Sand (River Sand) 1
A.) BEAMS 2307.84
Cement (Class C Mortar) 415
Sand (River Sand) 46
B.) GIRDERS 4325.44
Cement (Class C Mortar) 779
Sand (River Sand) 87
C.) COLUMNS 2651.16
Cement (Class C Mortar) 477
Sand (River Sand) 53
TOTAL MATERIAL COST

EQUIPMENT COST: QTY


Shotcrete (5cu.m) 2
Km. Travelled/Day
Shotcrete Comsumption 40
TOTAL EQUIPMENT COST:

DIRECT COST

INDIRECT COST:
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/Demolization (1%)
VAT (12%)
TOTAL INDIRECT COST
TOTAL ITEM COST
UNIT COST
sq.m.
NO. OF DAYS RATE PER DAY TOTAL
45 800 36,000.00
45 600 27,000.00
45 500 112,500.00
45 300 67,500.00
243,000.00

UNIT UNIT COST


sq.m.
bags 250 677,750.00
cu.m. 650 195,650.00
sq.m.
bags 250 1,750.00
cu.m. 650 650.00
sq.m
bags 250 103,750.00
cu.m. 650 29,900.00
sq.m
bags 250 194,750.00
cu.m. 650 56,550.00
sq.m
bags 250 119,250.00
cu.m. 650 34,450.00
1,414,450.00

NO. OF DAYS RATE PER DAY


45 10500 945,000.00
Liters/Km. Diesel
0.2 45 16,200.00
961,200.00

2,618,650.00

130,932.50
261,865.00
26,186.50
169,734.00
588,718.00
3,207,368.00
131.54
11 TILE WORKS 20,404.36
LABOR COST: NO. OF WORKERS
Project Engineer 1
Construction Foreman 1
Mason 50
Laborers 50
TOTAL LABOR COST

EQUIPMENT COST: QTY


Tile Cutter 3
TOTAL EQUIPMENT COST

MATERIAL COST: QTY


A.) 60 x60 cm Granite Floor Tiles 20250.76
60 x60 cm Ceramic Floor Tiles 56,297
Cement (Class A Mortar) 1,742
Tile Joint Filler (5kg/bag) 10,125
Tile Adhesive 2,228
B.) 60 x 60 cm Ceramic Wall Tiles 153.6
60 x60 cm Ceramic Tiles 427
Cement (Class A Mortar) 13
Tile Joint Filler (5kg/bag) 77
Tile Adhesive 17
TOTAL MATERIAL COST

DIRECT COST

INDIRECT COST:
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/Demolization (1%)
VAT (12%)
TOTAL INDIRECT COST

TOTAL ITEM COST


UNIT COST
sq.m.
NO. OF DAYS RATE PER DAY TOTAL
60 800 48,000.00
60 600 36,000.00
60 500 1,500,000.00
60 300 900,000.00
2,484,000.00

NO. OF DAYS RATE PER DAY


60 1000 180,000.00
180,000.00

UNIT UNIT COST TOTAL


sq.m
pcs 155 8,726,035.00
bags 250 435,500.00
bags 250 2,531,250.00
bags 225 501,300.00
sq.m
pcs 155 66,185.00
bags 250 3,250.00
bags 250 19,250.00
bags 225 3,825.00
12,194,085.00

14,858,085.00

742,904.25
1,485,808.50
148,580.85
1,463,290.20
3,840,583.80

14,858,085.00
728.18
12 PAINTING WORKS 24,713.00
LABOR COST NO. OF WORKERS
Project Engineer 1
Construction Foreman 1
Painter 8
Laborers 8
TOTAL LABOR COST

MATERIAL COST QTY


Boysen Flat Latex #701 1,201
Boysen Flat Latex B-7501 (1gal/18sq.m) 1,201
Paint Thinner 400
Paint Roller 100
Paint Tray 100
Paint Brush 100
SAND 180 SAND PAPER 400
TOTAL MATERIAL COST

DIRECT COST

INDIRECT COST
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/Demolization (1%)
VAT (12%)
TOTAL INDIRECT COST

TOTAL ITEM COST


UNIT COST
sq.m.
NO. OF DAYS RATE PER DAY TOTAL
60 800 48,000.00
60 600 36,000.00
60 500 240,000.00
60 300 144,000.00
468,000.00
-
UNIT UNIT COST
gal. 802 963,202.00
gal. 802 963,202.00
liters 500 200,000.00
pcs. 50 5,000.00
pcs. 100 10,000.00
pcs. 67 6,700.00
pcs. 20 8,000.00
2,156,104.00

2,624,104.00

131,205.20
262,410.40
26,241.04
258,732.48
678,589.12

3,302,693.12
133.64
13 GLASS WORKS 76.00
LABOR COST NO. OF WORKERS
Project Engineer 1
Construction Foreman 1
Laborers 10
TOTAL LABOR COST

MATERIAL COST QTY.


Panic Door 5
Sound proof Door 10
Tempered Glass Door 51
Fiber Glass Door 8
Revolving Door 2
Tempered Glass (2000-5000 sq.m/panel) 1
TOTAL MATERIAL COST

DIRECT COST

INDIRECT COST
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/Demolization (2%)
VAT (12%)
TOTAL INDIRECT COST

TOTAL ITEM COST


UNIT COST
pcs
NO. OF DAYS RATE PER DAY TOTAL
8 800 6,400.00
8 600 4,800.00
8 300 24,000.00
35,200.00

UNIT UNIT COST


pcs. 8500 42,500.00
pcs. 14000 140,000.00
pcs. 5500 280,500.00
pcs. 9720 77,760.00
pcs. 540000 1,080,000.00
pcs. 700000 700,000.00
2,320,760.00

2,355,960.00

117,798.00
235,596.00
47,119.20
278,491.20
679,004.40

3,034,964.40
39,933.74
.

.
14 PLUMBING WORKS AND FIXTURES 2,287.00
LABOR COST NO. OF WORKERS
Project Engineer 1
Construction Foreman 1
Plumber 2
Laborers 2
TOTAL LABOR COST

MATERIAL COST QTY


100mmx100mm Elbow 90 8
100mmx100mm Wye 8
100mmx100mm Tee 13
75mmx100mm 45' Elbow 12
100mmx100mm 45' Elbow 1
25mm 90' elbow(G.I) 242
25mm Tee(G.I) 461
25mm(dia.)(G.I) 444
Plug 40
Water Meter 3
Water Tank(2000li) 3
powerhouse Water Pump w/ 5hp 3
Faucet; U.S 32
Gate Valve 3
Solvent Cement (50 ml) 5
Teflon Tape 89
Sprinkler Head w/ Plate 260
Smoke Detector 260
Clean-out 12
Lavatory W/ Selectronic Waterflow Sensor 32
Water Closet w/ Exposed Sensor Flush Valve 100
Urinal w/ Fittings 32
Floor Drain 9
Channel Drain 163
P-Trap 52
TOTAL MATERIAL COST

DIRECT COST

INDIRECT COST
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/Demolization (1%)
VAT (12%)
TOTAL INDIRECT COST

TOTAL ITEM COST


UNIT COST
pcs
NO. OF DAYS RATE PER DAY TOTAL
21 800 16,800.00
21 600 12,600.00
21 500 21,000.00
21 300 12,600.00
63,000.00

UNIT UNIT COST


pcs 110 880.00
pcs 130 1,040.00
pcs 130 143.00
pcs 120 1,440.00
pcs 100 100.00
pcs 200 48,400.00
pcs 120 55,320.00
pcs 150 66,600.00
pcs 90 3,600.00
pcs. 5800 17,400.00
pcs. 12000 36,000.00
pcs. 15859.95 47,579.85
pcs. 400 12,800.00
pcs. 541 1,623.00
can 100 500.00
roll 25 2,225.00
pcs 156 40,560.00
pcs 800 208,000.00
pcs 130 1,560.00
set 13000 416,000.00
set 37000 3,700,000.00
set 3500 112,000.00
pcs. 60 540.00
pcs. 2800 456,400.00
pcs. 492 25,584.00
5,256,294.85

5,319,294.85

265,964.74
531,929.49
53,192.95
630,755.38
1,481,842.56

6,801,137.41
2,973.82
15 MECHANICAL WORKS sq.m.
LABOR COST: NO. OF WORKERS NO. OF DAYS
Foreman 20
Technician 20
Laborer 20
TOTAL LABOR COST

MATERIAL COST Quantity Unit


Generator Set
Aircondition
Escalator
Elevator
TOTAL MATERIALS COST

DIRECT COST

INDIRECT COST:
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/Demolization (1%)
VAT (12%)
TOTAL INDIRECT COST

TOTAL ITEM COST


UNIT COST
RATE PER DAY TOTAL
600 -
500 -
350 -
-

Unit Cost
-
-
-
-

-
-
-
-
-

20,000,000.00
20,000,000.00
16 ELECTRICAL WORKS 2,301.00 sq.m.
LABOR COST: NO. OF WORKERS NO. OF DAYS
Project Engineer 1 21
Foreman 1 21
Technician 2 21
Laborer 2 21
TOTAL LABOR COST

MATERIAL COST: Quantity Unit


Pinlight 1400 pcs
Emergency Light 206 pcs
Flourescent 292 pcs
Flood Lights 12 pcs
Panel board 34 pcs
Outlet 155 pcs
ACU 132 pcs
Switch 70 pcs
Electrical Wire (305m/roll) 7 roll
Electrical Flexible Hose (100m/roll) 22 roll
Electrical Tape (16m/roll) 58 roll
TOTAL MATERIALS COST

DIRECT COST

INDIRECT COST:
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/Demolization (1%)
VAT (12%)
TOTAL INDIRECT COST

TOTAL ITEM COST


UNIT COST
RATE PER DAY TOTAL
800 16,800.00
600 12,600.00
500 21,000.00
350 14,700.00
65,100.00

Unit Cost
449.75 629,650.00
1400 288,400.00
4800 1,401,600.00
500 6,000.00
2000 68,000.00
200 31,000.00
80999 10,691,868.00
180 12,600.00
150 8,700.00
450 9,900.00
20 1,160.00
13,148,878.00

13,213,978.00

660,698.90
1,321,397.80
132,139.78
131,488.78
2,245,725.26

15,459,703.26
6,718.69
17 WATERPROOFING WORKS 120.00 sq.m.
LABOR COST: NO. OF WORKERS NO. OF DAYS
Project Engineer 1 7
Foreman 1 7
Laborer 1 7
TOTAL LABOR COST

MATERIAL COST Quantity Unit


BuscoSeal 32 gal
Brush 5 pc
TOTAL MATERIALS COST

DIRECT COST

INDIRECT COST:
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/Demolization (1%)
VAT (12%)
TOTAL INDIRECT COST

TOTAL ITEM COST


UNIT COST
RATE PER DAY TOTAL
800 5,600.00
600 4,200.00
350 2,450.00
12,250.00

Unit Cost
594 19,008.00
20 100.00
19,108.00

31,358.00

1,567.90
3,135.80
313.58
2,292.96
7,310.24

38,668.24
322.24
18 SOUNDPROOFING WORKS 3,200.00 sq.m.
LABOR COST: NO. OF WORKERS NO. OF DAYS RATE PER DAY
Project Engineer 1 7 800
Foreman 1 7 600
Laborer 1 7 350
TOTAL LABOR COST

MATERIAL COST Quantity Unit Unit Cost


Acoustic Foam 12''x12''x2'' (24pcs/pack) 1435 pack 2000
Glue 10 gal. 500
TOTAL MATERIALS COST

DIRECT COST

INDIRECT COST:
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/Demolization (1%)
VAT (12%)
TOTAL INDIRECT COST

TOTAL ITEM COST


UNIT COST
TOTAL
5,600.00
4,200.00
2,450.00
12,250.00

2,870,000.00
5,000.00
2,875,000.00

12,250.00

612.50
1,225.00
122.50
345,000.00
346,960.00

359,210.00
112.25
19 LANDSCAPING 14,380.00 sq.m.
LABOR COST: NO. OF WORKERS NO. OF DAYS
Project Engineer 1 15
Foreman 1 15
Laborer 4 15
TOTAL LABOR COST

MATERIAL COST Quantity Unit


Flowers etc
TOTAL MATERIALS COST

DIRECT COST

INDIRECT COST:
Overhead Cost (5%)
Contractor's Profit (10%)
Mobilization/Demolization (1%)
VAT (12%)
TOTAL INDIRECT COST

TOTAL ITEM COST


UNIT COST
RATE PER DAY TOTAL
800 12,000.00
600 9,000.00
350 21,000.00
42,000.00

Unit Cost
1,500,000.00
1,500,000.00

1,542,000.00

77,100.00
154,200.00
15,420.00
180,000.00
426,720.00

1,968,720.00
136.91

Das könnte Ihnen auch gefallen