Sie sind auf Seite 1von 18

Page 1 of 18

C.C. 19th and Running Bill.


Cash Book Vr: No.____________ Date:-__________/2019.

Name of Works:- Conversion of 45 Judicial Lockup into Sub Jail one at Pindi Bhattian, District Hafizabad.
Agency: M/S Awan Builders Govt. Contractor
Authorithy:- E.E No.2882/CB, Dated. 18-06-2016.
D/O of Commencement: 18-06-2016.
Date of Completion: Work in progress.
Date of Billing

Unit Qty Sr. Item of Work Rate Amount

%0Cft 88354 1 Excavation in foundation of building bridges & other structure i/c dag,
belling, dressing, refilling around structure in ordinary soil lead upto one
chain.
5005.45 442252
% Cft 1035 2 P/L cement concrete brick or stone ballast 1½“ to 2” gauge (1:4:8). 13857.20 143422
% Cft 13017 3 P/L cement concrete brick or stone ballast 1½“ to 2” gauge (1:6:12). 12039.30 1567156
% Kg 152293 4 Fabrication of mild steel i/c cutting, bending, binding and laying in position
making joints i/c cost of binding iron D. Bars. 40 grade. 10470.10 15945229
P. Cft 12588 5 RCC (1:2:4) in raft/strip without shuttering. 263.10 3311903
% Cft 63559 6 Pacca brick work in cement sand mortar (1:5) in O.T.B. 17197.70 10930686
% Cft 45001 7 Pacca brick work in cement sand mortar (1:6) in F&P. 17050.10 7672716
% Sft 2611 8 P/L 1½“ thick DPC of cement concrete (1:2:4) i/c bitumen coating and
polythene sheet. 4097.70 106991
% Sft 1333 9 PL vertical DPC of cement sand plaster (1:4) 3/4" thick i/c bitumen coating
and polythene sheet 500 gauge. 2901.70 38680
%0 Cft 38124 10 Filling watering ramming earth under floor with surplus earth from
foundation. 2391.85 91187
%0 Cft 323405 11 Filling watering ramming earth under floor with new earth from outside
lead upto 3 mile. 8648.30 2796903
% Cft 26094 12 Pacca brick work (1:6) ground floor. 18037.50 4706705
P.Cft 14156 13 P/L RCC (1:2:4) roof slab beam, column lintel etc. (1:2:4). 344.05 4870372
% Sft 4277 14 1/2" thick cement sand plaster (1:4) i/c bitumen coating and polythene
sheet. 1870.25 79991
% Sft 666 15 P/L 3" thick DPC of cement concrete (1:2:4) i/c two coat of bitumen. 5918.45 39417
% Sft 1641 b P/L 1-1/2" thick DPC of cement concrete (1:2:4) i/c two coat of bitumen.
4624.90 75895
%0 Cft 125576 16 Filling borrowpit excavation from out side lead upto three miles. 6800.00 853917
% Cft 483 17 Pacca brick work (1:4) ground floor. 18181.80 87818
P.Rft 26406 18 S/E of pvc pipe for wiring purpose recessed in walls 1" dia. 40.50 1069443
P.Cft 212 19 P/L RCC (1:2:4) in roof slab beam column lintel 20' to 40' height. 361.85 76712
Page 2 of 18

P.Cft 106 20 P/L RCC (1:2:4) in roof slab beam column lintel 40' to 60' height. 397.45 42130
% Cft 14328 21 Pacca brick work (1:6) first floor. 18650.00 2672172
% Cft 391 22 Pacca brick work (1:4) first floor. 19473.50 76141
P.Cft 344 23 P/L RCC (1:1-1/2:3) in column etc First floor. 370.65 127504
P.Cft 344 b P/L RCC (1:1-1/2:3) in column etc 2nd floor. 370.65 127504
P.Cft 5904 24 P/L RCC (1:2:4) first floor in roof slab beam column lintel etc. 344.05 2031271
% Sft 22448 25 1/2" thick cement sand plaster (1:4) upto 20' height. 1484.25 333184
P.Cft 303 26 P/L RCC (1:2:4) roof slab beam colun linte upto 50' height. 397.45 120427
% Cft 407 27 Pacca brick work (1:4) 2nd floor. 20223.70 82310
% Cft 11561 28 Pacca brick work (1:6) 2nd floor. 19350.00 2237054
P.Cft 4462 29 P/L RCC (1:2:4) roof slab beam colun lintel 2nd floor. 367.85 1641347
% Sft 14043 30 Single layer of tiles 9"x4½"x1½" laid over 4" earth and 1" mud plaster
without Bhoosa, grouted with cement sand 1:3 on top of RCC roof slab,
provided with 34 lbs. per %Sft. or 1.72 Kg/Sq.m bitumen coating sand
blinded.
6323.50 888009
% Sft 676 b ….do…. First floor. 6500.00 43940
% Sft 6861 c ….do…. 2nd floor. 6800.00 466548
% Sft 410 d ….do…. 3rd floor. 7000.00 28700
Each 7 31 Top khurra on roof 2'x2'x1/2". 400.90 2806
P.Rft 1275 32 P/L G.I pipe cutting, jointing, testing 4" dia (M-quality). 566.75 722606
Each 4 33 P/F sluice valve 4" dia. 7781.00 31124
Each 1 34 P/F water level gauge. 25000.00 25000
P.Rft 214 35 P/F stair terrace railing consisting of 2" dia conduite pipe welded completel
in all respect. 575.85 123232
% Kg 1370 36 Fabrication of heavy steel work, with angle, tees, flat iron round iron and
sheet iron for making trusses, girders, tanks, etc., including cutting, drilling,
revitting, handling, assembling and fixing, but excluding erection in
position.
11364.70 155696
%Sft 8265 37 P/L 1/2" thick mosaic dado / skirting (1:3) complete. 7570.20 625677
% Sft 28913 38 3/8" thick cement sand plaster (1:3) under soffit of RCC roof slab. 1692.90 489468
% Sft 87547 39 1/2" thick cement plaster (1:5) upto 20' height.
1415.50 1239228
P.Rft 250 40 Direct Rotary/Reverse Rotary drilling of bore for tubewells, in all types of
soil except shingle, gravel and rock:- a) from ground level to 250 ft. (75 m)
below ground level:- i) 15" to 18" dia.
448.55 112138
P. Rft 200 41 Exceeding 250 ft. depth below ground level:- i) 15" to 18" dia 448.55 89710
Each 1 42 Providing strong substantially built box of deodar wood 4'x2½'x9" with
compartments, lock and locking arrangement, for preserving samples of
strata from bore hole.
12265.90 12266
P. Rft 100 43 Providing and installing, brass strainer in tubewell bore hole, i/c sockets,
special sockets, studs, etc. complete:- 6" dia, 3/16" thick. 1706.95 170695
Each 1 44 Providing and installing M.S. Bail plug in tubewell bore hole: e) 6" i/d, 2 ft.
(150 mm i/d 600 mm) long. 2310.95 2311
Page 3 of 18

P.Rft 120 45 Providing and installing M.S. blind pipe socketed/welded joint, M.S.
reducer (where necessary), in tubewell bore hole, including
jointing/welding with strainer, etc. complete12" dia, ¼" dia thick.
2259.40 271128
P.Rft 230 46 ….do… 6" dia, 3/16" thick. 935.15 215085
P.Hrs 72 47 Testing and developing of tubewell of size 6" (150 mm) i/d and above
continuously. i) upto 1.5 cs. Discharge
1100.55 79240
P. Cft 637 48 Shrouding with graded pea gravel 3/8" to 1/8" around tubewell in bore
hole. 86.55 55132
Each 1 49 P/F well cap 12'' dia comprising of 1/8'' thick M.S sheet on m.s flat 1-
1/2 x 1/8'' complete in all respects.
800.00 800
P.Rft 252 50 P/F welding 1/2'' dia M.S round bar longitudinally along strainer for
keeping the strainer in correct vertical position required at site of work as
approved by the Engineer incharge.
300.00 75600
Each 1 51 P/F M.S clamp made of 3''x3/8'' M.S flat 3' long on top of casing pipe to
avoid sunking i/c cost of Nut & bolt required size complete in all respects 4
No directed by the Engineer Incharge.
1800.00 1800
Each 1 52 P/I vertical line shaft turbine pump 1/2 cusic of KSB Pumps made coupled
with 20-H.P.A.C electric motor (Siemens) i/c bowl assembly columns pipe
against head 200-ft complete i/c making foundation and all fitting of turbine
pump and cost of delta star starter for electric motor, main switch, Amp:
meter, volt meter, and panel board i/c M.S base plate over foundation of
turbine having size 2-ft x 2-ft x3/8” with a central hole for column pipe
along with necessary clamp, nuts and bolts, pressure and vacuum gauge
with copper pipe a per required size with all accessories, earthing
complete in working order complete in all respects and as approved by
the Engineer Incharge.

2130000 2130000
P.Sft 3752 53 P/F steel win odw with openable glazed panes using beam section 1-
1/2x1-1/8x1/8" complete as per specification.
574.30
210.00 2154774
0
P.Sft
P.Sft 0
36 54
54 P/F
P/F m.s.
M.S.sheet
box hollow
sectionpressed
windowchowkat of 16
2x1-1/2" SWG
leave complete.
frame 1-1/2x1" frame U
shaped complete in all respect. 420.00 15120
% Cft 3304 55 Pacca brick work (1:6) in 3rd floor. 21049.50 695475
P.Cft 58 56 P/L RCC (1:1-1/2:3) in roof slab, beam column lintel 3rd storey. 404.00 23432
P.Cft 229 b P/L RCC (1:2:4) in roof slab, beam column lintel 3rd storey. 397.45 91016
% Cft 9654 57 Sand filling under floor. 1338.00 129171
%Cft 12696 58 P/L dry rammed brick or stone ballast 1-1/2" to 2" gauge. 6372.40 809040
P.Rft 26920 59 P/F marble strip for dividing the floor into panel size 1-1/2x3/8". 6.60 177672
P.Sft 3123 60 P/F angle iron chowkat 1-1/2x1-1/2x1/4" welded with m.s. flat 2x1/4"
complete.
140.00 437220
% Cft 12633 61 P/L cement concrete (1:6:18) 1-1/2" to 2" gauge. 11302.10 1427794
P.Sft 647 62 P/F m.s. door 1-1/2x1-1/2x1/4" complete. 500.00 323500
%0 Cft 37184 63 Rehandling of earth lead upto single through of kassi. 1188.00 44175
% Sft 27176 64 P/F 1-1/2" thick mosaic flooring consisting of one part of cement and
marble chips complete in all respect. 8264.30 2245906
% Sft 5488 b ….do… First floor. 8620.70 473104
% Sft 5488 c ….do… 2nd floor. 8977.10 492663
% Cft 3229 65 Pacca brick work (1:4) other than building. 18345.60 592379
Page 4 of 18

P.Sft 2325 66 P/F iron grating in window c.windows & Verandah opening comprising of
M.S angle iron frame 2"x2"x3/8" braes of M.S flat 2"x3/8" with M.S sq bar
3/4"x3/4" punched at 4" c/c i/c triangular shape 5"x5" size gusset plate of
M.S sheet 3/8" thick welded and riveted at four ccorners of frame holdfasts
of M.S flat 2"x1/2" embedded in plain cement concrete 1:2:4 ratio i/c three
coat of paint complete in all respect as per C.A drawing and as approved
by the Engineer Incharge.

900.00 2092500
P.Sft 56 67 P/F Steel grated door consisting of M.S angle iron 2"x2"x3/8" with 3/4" Sqr
bar @ 4" c/c and M.S flat 2"x3/8" 2 No welded at equal distance gusets
plate 7"x7"x3/8" with hold fast 12" long 2"x2"x3/8" complete with hinges i/c
painting all charges of labour and carriage as approved by the Engineer
Incharge.
1300.00 72800
Each 2 68 P/F main gate complete in all respect. 450000.00 900000
P.Sft 2184 69 P/F iron spickes jangla on boundary wall complete in all respect 725.00 1583400
%Sft 83971 70 Cement pointing deep struck joint with red oxide pigment (1:2). 1872.10 1572021
P.Rft 14 71 P/F m.s iron girder 9x4" complete. 700.00 9800
Each 19 72 S/E of panel board 18x24x6" duly poser coated with m.s. sheet 16 SWG
i/c 3 Nos volt meter 01 No ampere meter etc. complete. 31000.00 589000
Each 3 b ….do…. (24"x36"x6"). Main board. 70000.00 210000
P.Rft 1354 73 P/L RCC pipe 1:1-1/2:3) cement concrete moulded 12" dia. 376.30 509510
P.Rft 139 b P/L RCC pipe 1:1-1/2:3) cement concrete moulded 9" dia. 300.00 41700
P.Sft 353 74 Extra labor for shuttering RCC paragola as per C.A. drawing. 55.00 19415
% Sft 446 75 P/L conglomerate flooring two coat works with top layer of ½” thick of
stone chips lead over cement concrete (1:3:6½) i/c rubbing 1½" thick
complete.
3463.40 15447
P.Rft 81554 76 S/E of single core pvc sheated copper conductor cable 3/0.029" 10.60 864472
P.Rft 32244 b S/E of single core pvc sheated copper conductor cable 7/0.029" 14.90 480436
P.Rft 4548 c S/E of single core pvc sheated copper conductor cable 7/0.044" 30.90 140533
P.Rft 520 d S/E of pvc sheated copper conductor cable 7/0.064" twin core. 134.30 69836
P.Rft 1047 77 S/E of pvc sheated copper conductor cable 7/0.064. (4 core). 269.40 282062
P.Rft 414 78 S/E of pvc sheated copper conductor cable 19/0.083. (4 core). 1374.30 568960
Each 170 79 S/E of gaungeway plate (1-8) holes. 450.00 76500
Each 53 80 S/E of gaungeway plate (1-4) holes. 258.00 13674
Each 308 81 S/E of 3 pin wall socket 10/15 ampere. 400.00 123200
Each 199 82 S/E of ceiling fan dimmer Bush/Hilife. 275.00 54725
Each 548 83 S/E of button holder. 27.90 15289
Each 207 84 S/E of ceiling rose bakelite. 33.65 6966
Each 1185 85 S/E of swtich piano type. 50.00 59250
Each 373 86 S/E of 2 pin wall socket bush /hilife. 79.00 29467
Each 199 87 P/F m.s. box fan hook 5/8" pvc sheet box complete in all respect. 199.00 39601
Page 5 of 18

Each 19 88 Earthing with 8 swg copper wire i/c copper strip.60x10mm and G.I. Pipe
¾” dia 100’ long complete with sockets. 105 ft below from ground level i/c
making bore hole and filling with salt and charcoal mixture etc complete in
all respect as approved / directed by engineer incharge.

17500.00 332500
Each 9 89 S/E of sheet box of 16 SWG sheet 4" deep with bakelite 10x12". 448.90 4040
Each 8 b S/E of sheet box of 16 SWG sheet 4" deep with bakelite 8x10". 339.80 2718
Each 8 c S/E of sheet box of 16 SWG sheet 4" deep with bakelite 7x4". 182.85 1463
% Cft 2163 90 Dismantling glazed or encaustic tile. 1024.30 22156
% Cft 502 91 Dismentling of brickk work cement sand mortar. 2019.60 10138
% Cft 1020 92 Dismentling of plain cement conrete (1:2:4). 5277.20 53827
%0Cft 5862 93 Removal of malba of unsuitable from site all leads and light complete. 7500.00 0
P.Rft 4073 94 P/L PPRC pipe for wiring purpose recessed in wals of approved quality &
compancy complete 32 mm. 108.00 439884
P.Rft 1947 b ….do…. 25mm. 80.00 155760
P.Rft 1195 c ….do…. 40mm. 154.00 184030
Each 245 95 P/L PPRC specials of approved quality and company 32 mm. 80.00 19600
Each 94 b ….do…. 25mm. 61.00 5734
Each 46 c ….do…. 40 mm. 134.00 6164
Each 348 d PPRC equal tee 32 mm. 136.00 47328
Each 71 e ….do…. 25mm. 73.00 5183
Each 703 f PPRC elbow 32 mm. 105.00 73815
Each 236 g ….do…. 25 mm. 67.00 15812
Each 82 h ….do…. 40 mm. 175.00 14350
Each 100 i PPRC butterfly valve 32mm. 1035.00 103500
Each 7 j PPRC female threated tee 25x1/2". 345.00 2415
Each 8 k PPRC reducing tee 32x25" mm. 203.00 1624
Each 49 l PPRC threated elbow 25x3/4" 453.00 22197
Each 368 m ….do…. 25 x1/2". 303.00 111504
Each 18 n ….do…. 32 x1/2". 320.00 5760
Each 102 o PPRC cross over 32 mm. 148.00 15096
Each 27 p ….do…. 25 mm. 142.00 3834
Each 329 q PPRC end cap 32 mm. 83.00 27307
Each 71 r ….do…. 25 mm. 67.00 4757
Each 65 s PPRC reducing sockets 32x25" mm. 61.00 3965
Each 27 t PPRC reducing sockets 32x25" mm. 225.00 6075
P.Rft 4216 96 P/F pvc pipe for wiring 4" dia. 267.10 1126094
Each 71 97 P/F pvc socket 4" dia. 224.10 15911
Each 72 98 P/F pvc tee 4" dia. 1086.05 78196
Each 51 99 P/F P. trap 4" dia glazed. 124.20 6334
Each 51 100 P/F coloured glazed earthen ware water closet orrisa pattern combined
with foot rest. 1339.05 68292
Each 141 101 P/F floor trap 4x3". 384.80 54257
Each 363 102 P/F pvc bed 4" dia. 534.35 193969
% Cft 7801 103 P/L plain cement concrete (1:2:4) curing compacting complete. 23148.30 1805799
% Cft 317 104 Extra rate for benching of floor of manhole. 1325.75 4203
Each 90 105 P/F pvc plug tee 4" dia. 1250.00 112500
P.Rft 127 106 P/F Y-tee 4" dia. 1280.00 162560
Page 6 of 18

P.Rft 385 107 P/F stair railing of 5/8x5/8 Sq. bar 5-1/2" C/C 2'-9" height complete in all
respect. 776.70 299030
P.Rft 769 108 P/F angle iron edge protection nozing 1-1/2x1-1/2x1/4" complete 142.15 109313
%0 Cft 23512 109 Excavation in open cutting for manhole and sewer line. 4239.80 99686
% Sft 0 b P/L topping of cement concrete (1:2:4) curing finishing complete. 13470.00 0
%0 Cft 6840 110 Excavation of trenches in all in open cutting except shingle for water
supply piplelines upto 5-ft depth from ground level, etc, complete.
3569.30 24414
P.Rft 2111 111 P/L cutting, jointing testing G.I. pipe lne in trenches 1" dia. M quality. 121.95 257436
P.Rft 944 112 Wraping of polythene sheet i/c bitumen coating on pipe. 5.00 4720
P.Rft 2111 113 Wraping of polythene sheet i/c bitumen coating on pipe 1" dia. 3.00 6333
% Cft 259 114 Pacca brick work (1:5) other than building upto 20' to 30' height. 18487.20 47882
% Sft 316 115 Pacca flat brick 3" (75 mm ) thick, laid in reimbursement, in cement, sand
mortar, on sides of drains and in other works where required. All joints to
be completely filled and struck flush (1:3).
5413.65 17107
% Rft 421 116 Tega formed of pacca bricks on end, laid in and over cement sand mortar
projecting to a height of not more than 6" top of drain along the property
side where required, laid to lines, grades, slopes and shape according to
the Engineer's drawing:- (1:3) complete.
5566.40 23435
P.Rft 421 117 Constructing Punjab Standard Drains. of cement concrete 1:2½:5, with
cement concrete bedding ratio 1:6:12,complete, laid to lines, grades,
slopes and shapes, rendering exposed surface of concrete with 1:1
cement, sand mortar, ¼" (6 mm) thick, as per Engineer's drawing
(excluding excavation) type 1.
88.35 37195
P.Sft 2264 118 P/L Ceramic Tile (Master Or Equivalent) Light Colour Bello (BL) Sseries,
SB Class 10"X13" Size Laid Over A Bed Of 3/4" Thick C/Sand Mortar 1:2
I/C Filling Joints With White Cement Mixed With Matching Pigments
Complete As Approved By The Engineer Incharge.(FOR FLOOR).

136.00 307904
P.Sft 7834 119 …do… dado/skirting. 145.00 1135930
P. Rft 2486 120 Laying border of approved coloured/design glazed tile 10" long 3" wide
laid in white cement and over 3/4"thick cement plaster (1:2) ratio i/c filling
joints with white cement and matching pigment i/c surface finishing,
cleaning and washing complete.
125.00 310750
Each 48 121 Providing and fitting glazed earthen ware wash hand basin (22"x16") i/c
bracket set, waste pipe and waste coupling, etc. i) white, with pedestal.
2426.10 116453
P.Sft 472 122 Making/fixing steel grated door with 1/16" thick sheeting, including angle
iron frame 2"x2"x3/8" and ¾" square bars 4" centre to centre, with locking
arrangement.
850.00 401200
%0 Cft 2011 123 Wet Sinking of well in ordinary soil for below spring level within one chain
complete.
25696.55 51676
% Cft 377 124 Extra for circular masonry. 1325.25 4996
Each 9 125 Providing and fixing 1¼"x1¼"x3/16" angle iron step, in manhole chambers,
including carriage and setting the same in work to correct lines and levels.

234.90 2114
Page 7 of 18

Each 1 126 P/F non clogging horizontal pump 5”x4” having SS Shaft, SS Semi open
impeller, Gland paking coupled on fabricated base frame with 10 HP, 1450
RPM, 3-Phase golden electric motor (without accessories) for discharge
552-230 GPM @ 15-40 feet head, complete as approved by the engineer
incharge.
650000.00 650000
Each 1167 127 P/F of Razor wire having double sharp 4 Nos. pointer razor @ 1-1/4" c/c
making in circular shape 24" dia ring @ 3" c/c fixed with 2 No. M.S bar
1/2"x1/2" Sq welding horizontally and 1-Nos post of M.S angle iron 1-
1/2"x1-1/2"x3/16" vertically 18" high and 1' embedded in PCC 1:2:4 (4-
1/2"x4-1/2"x1') fixing at site i/c labour and carriage charges i/c painting 3-
coats as approved by the Engineer Incharge.
460.00 536820
P.Sft 983 128 Providing of wire netting of G.I. wire 12 SWG have with 1/4x1/4" meshes
wire m.s. flat of flat wires 2"x1/4" wire grating frame i/c screws etc
complete in all respect.
670.00 658610
Total 103462941
Part C Price Variation.
Price Variation as 2141/1066 page 62 . 2143998
Total= 2143998

General Abstruct.
Part A 103462941

Part B 2143998

Total 105606939
Page 8 of 18

Upto date work done. 105606939

D/d already paid C.C. 18th & R/B TMB 2141/1066 P 60


dated 10-04-2019 104173535
Total 1433404
Say Rs:- 1325000

D/d 05% Security. 66250

D/d 7.50 % I.Tax 99375

Total 165625

Net Total 1159375

Paid to contractor on Rs. _________________ vide cheque No. _______________ dated ______________

Paid to income tax Rs. ___________________ vide cheque No. _______________ dated _____________

SDO_______________
Page 9 of 18

Upto date work done. 105606939

D/d already paid C.C. 18th & R/B TMB 2141/1066 P 60


dated 10-04-2019 104173535
1433404

SINGATURE AND CERTIFICATE

Certified that all the measurement was made by Mr. Nasir Ali Sub Engineer Vide Measureme
Book No. 2141/1066, Page 73 to 135 dated 2019. No advance payment have been made
contractor with out detailed measurement also 100% checked by the undersigned and work complet
according to the PWD specification and entire the satisfaction of the Engineer Incharge.

Contractor Sub Engineer Sub Divisional Officer,


Building Sub Division
Pindi Bhattian.
Page 10 of 18

19th and Running Bill.

ockup into Sub Jail one at Pindi Bhattian, District Hafizabad.

S / Prev:

0
0
0

0
0
0
0

0
0
0

0
0
0
0

0
Page 11 of 18

0
0
0
0
0
0

0
0
0
0
0

0
0
0
0
0
0
0
0

5532

0
0
0
0

0
0

0
Page 12 of 18

0
0

30000

-73914
0

0
0
0
0
0
0
0

0
0
0
0

0
0
0
0
Page 13 of 18

1130900

0
0
0
0
0

0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Page 14 of 18

0
0
0
0
0
0
0
-43965

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
1671309
0
0
0
Page 15 of 18

0
0
0
-1945068

0
0
0
0
0

0
0

0
0

0
Page 16 of 18

658610
1433404

0
0

1433404

1433404
Page 17 of 18

e No. _______________ dated ______________

e No. _______________ dated _____________


Page 18 of 18

ment was made by Mr. Nasir Ali Sub Engineer Vide Measurement
ated 2019. No advance payment have been made to
nt also 100% checked by the undersigned and work completed
entire the satisfaction of the Engineer Incharge.

Sub Divisional Officer,


Building Sub Division