ID Task Task Name Duration Start Finish Predecessors Qtr 1, 2020 Qtr 2, 2020

Mode Jan Feb Mar Apr May Jun


1 CM & PM solutions 393 days Mon 2/3/20 Wed 8/4/21
for PAF Aircrafts
2 Ist Progress 70 days Mon 2/3/20 Fri 5/8/20
Report
3 Team Building 2 wks Mon 2/3/20 Fri 2/14/20
4 Equipment 1 wk Mon Fri 2/21/20 3
Procurement 2/17/20
5 Key parameters 2 wks Mon Fri 3/6/20 4
Identification 2/24/20

6 Statistical 2 wks Mon 3/9/20 Fri 3/20/20 5


Analysis on
Selected
7 parameters of
Identification 3 wks Mon Fri 4/10/20 6
ML Techniques 3/23/20
8 Application of 3 wks Mon Fri 5/1/20 7
ML Techniques 4/13/20
9 Validation of 1 wk Mon 5/4/20 Fri 5/8/20 8
applied ML
Techniques
10 Second Progress 70 days Mon Fri 8/14/20 2
Report 5/11/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Mon 11/25/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish Predecessors Qtr 1, 2020 Qtr 2, 2020
Mode Jan Feb Mar Apr May Jun
11 Anomaly 7 wks Mon Fri 6/26/20
detection 5/11/20
model
development
using time
series plots
12 Engine 7 wks Mon Fri 8/14/20 11
Condition 6/29/20
Monitoring
13 Model
Third Progress 69 days Mon Thu 10
report 8/17/20 11/19/20
14 Anomaly 4 wks Mon Fri 9/11/20
detection 8/17/20
model
development
for Predictive
15 maintenance
Seminar of 2 days Mon 9/14/20Tue 9/15/20 14
16 Using Neural 5 wks Wed Tue 15
Networks and 9/16/20 10/20/20
Artificial
Intelligence
techniques to
calculate RUL of
the hydraulic
system

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Mon 11/25/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Task Name Duration Start Finish Predecessors Qtr 1, 2020 Qtr 2, 2020
Mode Jan Feb Mar Apr May Jun
17 Seminar/Workshop 2 days Wed Thu 16
(Marketing) 10/21/20 10/22/20
18 Calculation of 4 wks Fri 10/23/20 Thu 17
Remaining 11/19/20
Useful Life of
Hydraulic
19 System
Fourth Progress 65 days Fri 11/20/20 Thu 2/18/21 13
Report
20 Anomaly 5 wks Fri 11/20/20 Thu
detection 12/24/20
model
development
for Predictive
21 maintenance
Using Neural of 4 wks Fri 12/25/20 Thu 1/21/21 20
Networks and
Artificial
Intelligence
techniques to
calculate RUL of
Engine
22 Calculation of 4 wks Fri 1/22/21 Thu 2/18/21 21
Remaining
Useful Life of
23 Engine
Fifth Progress 62 days Fri 2/19/21 Mon 19
Report 5/17/21

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Mon 11/25/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Task Task Name Duration Start Finish Predecessors Qtr 1, 2020 Qtr 2, 2020
Mode Jan Feb Mar Apr May Jun
24 Integration of 4 wks Fri 2/19/21 Thu 3/18/21
Modules of
Hydraulic
25 System
Integration of 4 wks Fri 3/19/21 Thu 4/15/21 24
Modules of
26 Engine
Seminar/Workshop2 days Fri 4/16/21 Mon 25
(Marketing) 4/19/21
27 Inhouse Testing 4 wks Tue 4/20/21 Mon 26
and Debugging 5/17/21
of Software
28 Final Closing 57 days Tue 5/18/21 Wed 8/4/21 23
Report
29 Seminar/Workshop2 days Tue 5/18/21 Wed
(Marketing) 5/19/21
30 Journal Paper & 4 wks Thu 5/20/21 Wed 29
Conference 6/16/21
31 paperManual
User 1 wk Thu 6/17/21 Wed 30
Development 6/23/21
32 Integration of 2 wks Thu 6/24/21 Wed 7/7/21 31
developed
software on
PAF’s live
33 system
Real-time 2 wks Thu 7/8/21 Wed 32
testing and 7/21/21
34 debugging
Maintenance 2 wks Thu 7/22/21 Wed 8/4/21 33

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Mon 11/25/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Mon 11/25/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Mon 11/25/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Mon 11/25/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Mon 11/25/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8