Sie sind auf Seite 1von 29

CONTRACTOR:-___________

ABSTRACT OF BILLS
PROJECT:- CONSTRUCTION OF PCC 1:3:6 DRAIN KORANG TOWN ZONE-5 LOHIBEHER ISLAMABAD

IPC # ____

SUMM OF COST (IPC # )


WORK DON AMOUNT

DEDUCTION

10 % RETENTION MONEY 284,917.70

DEDUCTION

7.5 % INCOME TAX 213,688.27

NET PAYABLE AMOUNT 2,350,571.00

SAY 1,980,336.00
Add 10 % After Completion of Time period 2,265,253.70
DEVELOPMENT WORKS
KORANG TOWN
ZONE-5 LOHIBEHER ISLAMABAD
ENGINEERS ESTIMATE

Project :- Korang Town Islamabad PCC DRAIN 1:3:6


ITEM UNIT RATE
DESCRIPTION UNIT QTY.
No. (Rs.)
Bill no 2 R.C.C Box Culvert
1 EXCAVATION
Excavation of hard soil in open upto 5'-00"(1.5m)

depth for storm water chennels, drains, sullage drains

in open areas, road, streets, lanes, including under

pinnng of walls and shoring to protect existing

works. Cum 323.09 316.51


2 Excavation of Road
Excavation in open upto 5'-00"(1.5m) depth for storm

water chennels, drains, sullage drains in open areas,

road, streets, lanes, including under pinnng of walls

and shoring to protect existing works. Cum 74.00 548.47


3 Surplus Excavted Material
Surplus excavted material disposed of dressed with
in 1km lead. Cum 3456 246.40
4 P.C.C 1:4:8
Provide and lay, class 'C' (1:4:8) concrete Lean on the
bed of drains etc. as shown on drawings or as
directed by the Engineer. Cum 13.98 9923.27
5 P.C.C 1:3:6
Provide and lay, class 'C' (1:3:6) concrete of the wall
of drains etc. as shown on drawings or as directed by
the Engineer. Cum ### 16664.26
6 P.C.C 1:2:4 Pipe Culvert Top
Providing and laying reinforced cement concrete
using screened crushed stone graded aggregate 3/4
inch and down gauge having minimum works
cylinder crusing strength of 3000lbs per square inch
at 28 days with a mix not leaner 1:2:4 including from
work and its removal, compacting leveling and
crusing etc. complete but excluding the cost of
reinforcemnt as directed by the engineerincharge. Cum 57.46 15235.56
7 R.C.C Pipe 3' Dia
ITEM UNIT RATE
DESCRIPTION UNIT QTY.
No. (Rs.)
Rm 24.14 12387.50
8 Back Fill
Backfilling of trenches in all kinds of soil/material

compacted with suitable excavated material at

designated locations as approved by the Engineer. Cum 102.77 362.90


9 R.C.C 1:2:4
Providing and laying reinforced cement
concrete using screened crushed stone
graded aggregate 3/4 inch and down
gauge having minimum works cylinder
crusing strength of 3000lbs per square
inch at 28 days with a mix not leaner 1:2:4
including from work and its removal,
compacting leveling and crusing etc.
complete but excluding the cost of
reinforcemnt as directed by the
engineerincharge.
Bed Cum 3.74 16119.61
Walls/Slab Cum 6.25 21008.95
ITEM UNIT RATE
DESCRIPTION UNIT QTY.
No. (Rs.)
5 REINFORCEMENT
Providing and placing high tensile cold
worked deformed steel reinforcement
(grade-60) of various sizes/diameters
with and including the cost of
transportation, loading, unloading,
cutting, straightening, bending, binding,
wastage and overlapping, placing in
position by concrete spacers blocks or
M.S. chair, tying with binding wires, cost
of chairs and wires etc. in all kinds of RCC
works complete in all respects as shown
on drawings or as directed by the
Engineer. Kg. 1,281.32 195.19

Total Amount
10% overhead
35 % Exp Profit
7.5 Incom Tax

Without any addition %


With 10% overhead 7.5% I.Tax
With 10% overhead 7.5% I.Tax & 35% Profit
ELOPMENT WORKS
ORANG TOWN
OHIBEHER ISLAMABAD
NEERS ESTIMATE

PCC DRAIN 1:3:6 & RCC PIPE CULVERT


TOTAL AMOUNT
(Rs.)
2 R.C.C Box Culvert

102258.48

40585.68

851558.25

138701.00

379277.07

875440.73
TOTAL AMOUNT
(Rs.)
299021.53

37296.78

60243.16
131263.90
TOTAL AMOUNT
(Rs.)

250105.62

3,165,752
316,575.22
1,108,013.27
256,682.61
1,681,271.10
1,484,481.09
2057738.92378878
3165752.19044428
DEVELOPMENT WORKS
KORANG TOWN
ZONE-5 LOHIBEHER ISLAMABAD
Taking Of Sheet
P.C.C 1:3:6 Drain
MEAURMENT
SR NO. PARTICULARS OF WORK Unit
No. L W D

1 PCC Drain (1:3:6)


1.1 Excavation

Cft Cross Section Attached

Add 10% Contigency


Total Qty in Cft
Total Qty in Cum
1.2 P.C.C 1:4:8

Lean/Bed Cft 1 330 4 0.34

Add 10% Contigency


Total Qty in Cft

Total Qty in Cum


1.3 P.C.C 1:3:6

Walls Both Side Cft 2 290 2 0.63

Add 10% Contigency


Total Qty in Cft

Total Qty in Cum


1.4 Back Filling

Cft 2 330 2 2.5

Add 10% Contigency


Total Qty in Cft

Total Qty in Cum


DEVELOPMENT WORKS Page 9 of 29
KORANG TOWN
ZONE-5 LOHIBEHER ISLAMABAD
Taking Of Sheet
P.C.C 1:3:6 Drain
MEAURMENT
SR NO. PARTICULARS OF WORK Unit
No. L W D

1.5 RCC 1:2:4 Street Area

Bed Cft 1 40 4 0.75

Walls Cft 2 40 2 0.63

Slab Cft 1 40 5 0.5

Total RCC 1:2:4

Add 10% Contigency


Total Qty in Cft

Total Qty in Cum


DEVELOPMENT WORKS
KORANG TOWN
ZONE-5 LOHIBEHER ISLAMABAD
Taking Of Sheet
P.C.C 1:3:6 Drain
MEAURMENT
SR NO. PARTICULARS OF WORK Unit
No. L W D

2 Pipe Culvert
2.1 Excavation of Road

Dismentling Cft 1 72 6 5.5

Add 10% Contigency


Total Qty in Cft

Total Qty in Cum


2.2 R.C.C Pipe 3' Dia

Cross Dimension Rft 1 72

Add 10% Contigency


Total Qty in Rft

Total Qty in RM
2.3 P.C.C 1:2:4

Around Pipe to Road Top


Cft 1 72 6.5 5
Portion
Pipe Deduction Cft 𝜋 �^2/4

Total Qty in Cft

Add 10% Contigency

Total Qty in Cum


5 Steel

Barbending Schedule
Kg
Attached

Add 10% Contigency


Total Qty in Kg
DEVELOPMENT WORKS Page 11 of 29
KORANG TOWN
ZONE-5 LOHIBEHER ISLAMABAD
Taking Of Sheet
P.C.C 1:3:6 Drain
MEAURMENT
SR NO. PARTICULARS OF WORK Unit
No. L W D

Total Qty in Ton


QTY

10374

11411.4

11411.4

323.09

448.8

493.68

493.68

13.98

730.8

803.88

803.88

22.76

3300

3630

3630

102.77
Page 13 of 29

QTY

120

100.8

100

320.8

320.8

320.8

9.08
QTY

2376

2613.6

2613.6

74.00

72

79.2

79.2

24.14

2340

495

1845

2029.5

57.46

1164.84

1281.32
1281.32
Page 15 of 29

QTY

1.28
Page 29 of 16

DEVELOPMENT WORKS KORANG TOWN ZONE-5 LOHIBEHER


ISLAMABAD ( RATE ANYLISIS Excavation )
UNIT 1000 Cft Unit 28.31 Cum
SR NO. PARTICULARS OF WORK Unit Qty. RATE AMOUNT
A) Expence
1 Excavator Hour 1 2800 2800.00
Sub-Total (A) 2800.00
B) Labour
1 Dressing Labour Day 0.5 800 400.00
Sub-Total (B) 400.00
C) Miscelinous
1 Compactor Hour 1 0 0.00
Sub-Total ( C) 0.00
D) Sub Total ''A + B + C 3200.00

E) Add 10% OverHead 2940.00

F) Sub Total ''D + E" 6140.00

G) Add 35% Office Exp + Profit 2149.00

H) Sub Total " F + G" 8289.00

I) Add 7.5% Income Tax 672.08

J) Sub Total " H + I" 8961.08

Cost for 1 Cft ( RS ) 8.96

Cost for 1 Cum ( RS ) 317


Page 29 of 17

DEVELOPMENT WORKS KORANG TOWN ZONE-5 LOHIBEHER


ISLAMABAD ( RATE ANYLISIS Road Cutting )
UNIT 100 Cft Unit 2.83 Cum
SR NO. PARTICULARS OF WORK Unit Qty. RATE AMOUNT
A) Expence
1 Excavator Hour 1.5 2800 4200.00
2 Jack Hammer Hour 1 3500 3500.00
Sub-Total (A) 7700.00
B) Labour
1 Dressing Labour Day 0 800 0.00
Sub-Total (B) 0.00
C) Miscelinous
1 Compactor Hour 1 0 0.00
Sub-Total ( C) 0.00
D) Sub Total ''A + B + C 7700.00

E) Add 10% OverHead 2940.00

F) Sub Total ''D + E" 10640.00

G) Add 35% Office Exp + Profit 3724.00

H) Sub Total " F + G" 14364.00

I) Add 7.5% Income Tax 1164.65

J) Sub Total " H + I" 15528.65

Cost for 1 Cft ( RS ) 15.53

Cost for 1 Cum ( RS ) 548


Page 29 of 18

DEVELOPMENT WORKS KORANG TOWN ZONE-5 LOHIBEHER


ISLAMABAD ( RATE ANYLISIS DISPOSE OF )
UNIT 100 Cft Unit 2.83 Cum
SR NO. PARTICULARS OF WORK Unit Qty. RATE AMOUNT
A) Expence
1 Excavator loading Hour 0.3 2800 840.00
Sub-Total (A) 840.00
B) Labour
1 Dressing Labour Day 0 800 0.00
Sub-Total (B) 0.00
C) Miscelinous
1 Dumper carriage Trip 2 500 1000.00
Sub-Total ( C) 1000.00
D) Sub Total ''A + B + C 1840.00

E) Add 10% OverHead 2940.00

F) Sub Total ''D + E" 4780.00

G) Add 35% Office Exp + Profit 1673.00

H) Sub Total " F + G" 6453.00

I) Add 7.5% Income Tax 523.22

J) Sub Total " H + I" 6976.22

Cost for 1 Cft ( RS ) 6.98

Cost for 1 Cum ( RS ) 246


Page 29 of 19

DEVELOPMENT WORKS KORANG TOWN ZONE-5 LOHIBEHER


ISLAMABAD ( RATE ANYLISIS PCC 1:4:8
UNIT 100 Cft Unit 2.83 Cum
SR NO. PARTICULARS OF WORK Unit Qty. RATE AMOUNT
A) MATERIAL
1 CEMENT Bags 10 490 4900.00
2 SAND CFT 47 35 1645.00
3 AGGREGATE CFT 95 55 5225.00
4 WATER CHARGES GLN 120 2 240.00
Sub-Total 12010.00
Waistage 5% 600.50
Sub-Total (A) 12610.50
B) Labour

NOS 1.00 800 800


1 LABOUR

NOS 0.50 1500 750


2 MASON
Sub-Total (B) 1550.00
C) Miscelinous
1 Carrage + Loading/un loading Cft 150 6 900.00
2 MIXER MACHINE Day 0.5 2500 1250.00
3 SHUTRING FACTOR Sft 0 35 0.00
Sub-Total ( C) 2150.00
D) Sub Total ''A + B + C 16310.50

E) Add 10% OverHead 2940.00

F) Sub Total ''D + E" 19250.50

G) Add 35% Office Exp + Profit 6737.68

H) Sub Total " F + G" 25988.18

I) Add 7.5% Income Tax 2107.15

J) Sub Total " H + I" 28095.32

Cost for 1 Cft ( RS ) 280.95

Cost for 1 Cum ( RS ) 9923


Page 29 of 20

DEVELOPMENT WORKS KORANG TOWN ZONE-5 LOHIBEHER


ISLAMABAD ( RATE ANYLISIS PCC 1:3:6 Walls )
UNIT 100 Cft Unit 2.83 Cum
SR NO. PARTICULARS OF WORK Unit Qty. RATE AMOUNT
A) MATERIAL
1 CEMENT Bags 12.32 490 6036.80
2 SAND CFT 46.2 35 1617.00
3 AGGREGATE CFT 92.4 55 5082.00
4 WATER CHARGES GLN 150 2 300.00
Sub-Total 13035.80
Waistage 5% 651.79
Sub-Total (A) 13687.59
B) Labour

NOS 2.00 800 1600


1 LABOUR

NOS 0.50 1500 750


2 MASON
Sub-Total (B) 2350.00
C) Miscelinous
1 Carrage + Loading/un loading Cft 150 6 900.00
2 MIXER MACHINE Day 0.5 2500 1250.00
3 SHUTRING FACTOR Sft 320 35 11200.00
Sub-Total ( C) 13350.00
D) Sub Total ''A + B + C 29387.59

E) Add 10% OverHead 2940.00

F) Sub Total ''D + E" 32327.59

G) 11314.66

H) Sub Total " F + G" 43642.25

I) Add 7.5% Income Tax 3538.56

J) Sub Total " H + I" 47180.81

Cost for 1 Cft ( RS ) 471.81

Cost for 1 Cum ( RS ) 16664


Page 29 of 21

DEVELOPMENT WORKS KORANG TOWN ZONE-5 LOHIBEHER


ISLAMABAD ( RATE ANYLISIS PCC 1:2:4
UNIT 100 Cft Unit 2.83 Cum
SR NO. PARTICULARS OF WORK Unit Qty. RATE AMOUNT
A) MATERIAL
1 CEMENT Bags 18 490 8820.00
2 SAND CFT 88 35 3080.00
3 AGGREGATE CFT 176 55 9680.00
4 WATER CHARGES GLN 170 2 340.00
Sub-Total 21920.00
Waistage 5% 1096.00
Sub-Total (A) 23016.00
B) Labour

NOS 2.00 800 1600


1 LABOUR

NOS 0.50 1500 750


2 MASSON
Sub-Total (B) 2350.00
C) Miscelinous
1 Carrage + Loading/un loading Cft 0 6 0.00
2 MIXER MACHINE Day 0.5 2500 1250.00
3 SHUTRING FACTOR Sft 0 35 0.00
Sub-Total ( C) 1250.00
D) Sub Total ''A + B + C 26616.00

E) Add 10% OverHead 2940.00

F) Sub Total ''D + E" 29556.00

G) Add 35% Office Exp + Profit 10344.60

H) Sub Total " F + G" 39900.60

I) Add 7.5% Income Tax 3235.18

J) Sub Total " H + I" 43135.78

Cost for 1 Cft ( RS ) 431.36

Cost for 1 Cum ( RS ) 15236


Page 29 of 22

DEVELOPMENT WORKS KORANG TOWN ZONE-5 LOHIBEHER


ISLAMABAD ( RATE ANYLISIS RCC 36" PIPE )
UNIT 6 RFT Unit 1.83 Rm
SR NO. PARTICULARS OF WORK Unit Qty. RATE AMOUNT
A) MATERIAL
1 R.C.C PIPE COSTING X-factory Pipe 1 8500 8500.00
2 Jointing Material Pipe 1 220 220.00
Sub total 8720.00
Waistage 3% 261.60
Sub-Total (A) 8981.60
B) Labour

1 Labour Cost Pipe 1 600 600.00

Sub-Total (B) 600.00


C) Miscelinous

1 Excavator for Laying Pipe 1 1500 1500.00

2 CARRIAGE Pipe 1 1500 1500.00

Sub-Total ( C) 3000.00
D) Sub Total ''A + B + C 12581.60

E) Add 10% OverHead 2940.00

F) Sub Total ''D + E" 15521.60

G) Add 35% Office Exp + Profit 5432.56

H) Sub Total " F + G" 20954.16

I) Add 7.5% Income Tax 1698.99

J) Sub Total " H + I" 22653.15

Cost for 1 RFT ( RS ) 3775.52

Cost for 1 RM ( RS ) 12387


Page 29 of 23

DEVELOPMENT WORKS KORANG TOWN ZONE-5 LOHIBEHER


ISLAMABAD ( RATE ANYLISIS PCC 1:2:4 Bed )
UNIT 100 Cft Unit 2.83 Cum
SR NO. PARTICULARS OF WORK Unit Qty. RATE AMOUNT
A) MATERIAL
1 CEMENT Bags 18 490 8820.00
2 SAND CFT 88 35 3080.00
3 AGGREGATE CFT 176 55 9680.00
4 WATER CHARGES GLN 170 2 340.00
Sub-Total 21920.00
Waistage 5% 1096.00
Sub-Total (A) 23016.00
B) Labour

NOS 2.00 800 1600


1 LABOUR

NOS 0.50 1500 750


2 MASSON
Sub-Total (B) 2350.00
C) Miscelinous
1 Carrage + Loading/un loading Cft 0 6 0.00
2 MIXER MACHINE Day 0.5 2500 1250.00
3 SHUTRING FACTOR Sft 49 35 1715.00
Sub-Total ( C) 2965.00
D) Sub Total ''A + B + C 28331.00

E) Add 10% OverHead 2940.00

F) Sub Total ''D + E" 31271.00

G) Add 35% Office Exp + Profit 10944.85

H) Sub Total " F + G" 42215.85

I) Add 7.5% Income Tax 3422.91

J) Sub Total " H + I" 45638.76

Cost for 1 Cft ( RS ) 456.39

Cost for 1 Cum ( RS ) 16120


Page 29 of 24

DEVELOPMENT WORKS KORANG TOWN ZONE-5 LOHIBEHER


ISLAMABAD ( RATE ANYLISIS PCC 1:2:4 Walls Slab )
UNIT 100 Cft Unit 2.83 Cum
SR NO. PARTICULARS OF WORK Unit Qty. RATE AMOUNT
A) MATERIAL
1 CEMENT Bags 18 490 8820.00
2 SAND CFT 88 35 3080.00
3 AGGREGATE CFT 176 55 9680.00
4 WATER CHARGES GLN 170 2 340.00
Sub-Total 21920.00
Waistage 5% 1096.00
Sub-Total (A) 23016.00
B) Labour

NOS 2.00 800 1600


1 LABOUR

NOS 0.50 1500 750


2 MASSON
Sub-Total (B) 2350.00
C) Miscelinous
1 Carrage + Loading/un loading Cft 0 6 0.00
2 MIXER MACHINE Day 0.5 2500 1250.00
3 SHUTRING FACTOR Sft 320 35 11200.00
Sub-Total ( C) 12450.00
D) Sub Total ''A + B + C 37816.00

E) Add 10% OverHead 2940.00

F) Sub Total ''D + E" 40756.00

G) Add 35% Office Exp + Profit 14264.60

H) Sub Total " F + G" 55020.60

I) Add 7.5% Income Tax 4461.13

J) Sub Total " H + I" 59481.73

Cost for 1 Cft ( RS ) 594.82

Cost for 1 Cum ( RS ) 21009


Page 29 of 25

DEVELOPMENT WORKS KORANG TOWN ZONE-5 LOHIBEHER


ISLAMABAD ( RATE ANYLISIS PCC 1:2:4 Walls Slab )
UNIT 1000 KG Unit 1 Ton
SR NO. PARTICULARS OF WORK Unit Qty. RATE AMOUNT
A) MATERIAL
1 Steel Kg 1000 116 116000.00
2 Binding Wire Kg 4 120 480.00
Sub-Total 116480.00
Waistage 5% 5824.00
Sub-Total (A) 122304.00
B) Labour

Kg 1000.00 7 6500
1 LABOUR
Sub-Total (B) 6500.00
C) Miscelinous
1 Carrage + Loading/un loading Kg 1000 2 2000.00
Sub-Total ( C) 2000.00
D) Sub Total ''A + B + C 130804.00

E) Add 10% OverHead 2940.00

F) Sub Total ''D + E" 133744.00

G) Add 35% Office Exp + Profit 46810.40

H) Sub Total " F + G" 180554.40

I) Add 7.5% Income Tax 14639.55

J) Sub Total " H + I" 195193.95

Cost for 1 Cft ( RS ) 195.19

Cost for 1 Cum ( RS ) 195194


PCC 1:3:6 DRAIN
. BAR BENDING SCHEDULE 40' Length Street

No of Total
Dia Spacing No. of Unit
S# Description items No.of Cut Length Total Length weight
Bars Bars

1 Street Area BED/Walls

i Bot Bar #4 8" C/C 62 1 62 7.75 480.50 0.303

ii Top Bar #4 8" C/C 62 1 62 4.91 304.42 0.303

iv Striups #4 3' C/C 15 3 45 4.25 191.25 0.303

v Dis Bar Top & Bot #4 8" C/C 7 2 14 40 560 0.303

v Dis Bar Walls #4 8" C/C 4 2 8 40 320 0.303

Total
1 Street Area Slab

i Bot Bar #4 6" C/C 81 2 162 5.66 916.92 0.303

ii Dist Bar #4 6" C/C 11 2 22 40 880 0.303

iv Striups #4 3' C/C 15 3 45 4.25 191.25 0.303

Total
TOTAL NET WAIGHT IN KG
N
gth Street Area

Total Weight (kg) Shape

145.592 2' 2'

3.75
3.75
92.239 7" 7"

57.949

40'
169.680

40'
96.960

562.420

277.827 4" co 4"

5'
40'
266.640

57.949

602.416
1164.835
Page 29 of 28

DEVELOPMENT WORKS KORANG TOWN ZONE-5 LOHIBEHER


ISLAMABAD ( RATE ANYLISIS PCC 1:2:4 Walls Slab )
UNIT 1000 KG Unit 1 Ton
SR NO. PARTICULARS OF WORK Unit Qty. RATE AMOUNT
A) MATERIAL
1 Steel Kg 1000 116 116000.00
2 Binding Wire Kg 4 120 480.00
Sub-Total 116480.00
Waistage 5% 5824.00
Sub-Total (A) 122304.00
B) Labour

Kg 1000.00 7 6500
1 LABOUR
Sub-Total (B) 6500.00
C) Miscelinous
1 Carrage + Loading/un loading Kg 1000 2 2000.00
Sub-Total ( C) 2000.00
D) Sub Total ''A + B + C 130804.00

E) Add 10% OverHead 2940.00

F) Sub Total ''D + E" 133744.00

G) Add 35% Office Exp + Profit 46810.40

H) Sub Total " F + G" 180554.40

I) Add 7.5% Income Tax 14639.55

J) Sub Total " H + I" 195193.95

Cost for 1 Cft ( RS ) 195.19

Cost for 1 Cum ( RS ) 195194


Page 29 of 29

DEVELOPMENT WORKS KORANG TOWN ZONE-5 LOHIBEHER


ISLAMABAD ( RATE ANYLISIS Back Filling )
UNIT 100 Cft Unit 2.83 Cum
SR NO. PARTICULARS OF WORK Unit Qty. RATE AMOUNT
A) Expence
1 Tractor Hour 1 1500 1500.00
Sub-Total (A) 1500.00
B) Labour
1 Dressing Labour Day 1 800 800.00
Sub-Total (B) 800.00
C) Miscelinous
1 Compactor Hour 2 400 800.00
2 Watering Gal 500 2 1000.00
Sub-Total ( C) 1800.00
D) Sub Total ''A + B + C 4100.00

E) Add 10% OverHead 2940.00

F) Sub Total ''D + E" 7040.00

G) Add 35% Office Exp + Profit 2464.00

H) Sub Total " F + G" 9504.00

I) Add 7.5% Income Tax 770.59

J) Sub Total " H + I" 10274.59

Cost for 1 Cft ( RS ) 10.27

Cost for 1 Cum ( RS ) 363

Das könnte Ihnen auch gefallen