Beruflich Dokumente
Kultur Dokumente
Document History
Ver Record of Changes Made Since Previous Version
00 Draft
Version Control
Version Status Originator / Validated Approved
Name & Date Date Date
00 IFR Geoffrey
Dawson
27/6/2017
1.0 Final Gaye Eley
24/10/2017
Table of Contents
Document History ............................................... 3
Version Control ................................................ 3
Table of Contents .............................................. 4
Starting Up ProjectLibre ....................................... 6
Create a Project ............................................... 7
Adding Tasks ................................................... 8
Saving a Project .............................................. 11
Reflection Moment ............................................. 11
Project Calendar .............................................. 12
Setting the Project Base Calendar ............................... 12
Change the Working Calendar ..................................... 13
Navigating around Changing Working Calendar ..................... 14
Changing Calendar Control View .................................. 14
Setting Schedule Model Durations ................................ 15
Setting Working Time ............................................ 15
Setting Non-Working Time ........................................ 16
Applying Updated Project Base Calendar .......................... 17
Applying Phase Durations ........................................ 17
Applying Task Dependencies .................................... 20
Adding Resources .............................................. 22
Grouping Resources .............................................. 23
Configuring Resources ........................................... 24
General Settings ................................................ 24
Costs Settings .................................................. 25
Resource Availability Settings .................................. 26
Tasks Settings .................................................. 26
Notes Settings .................................................. 26
Configuring Group Settings ...................................... 26
General Settings ................................................ 26
Resources Views ............................................... 27
Displaying Resource Breakdown Structure ......................... 27
Displaying Resource Usage ....................................... 28
Creating Child Activities/Tasks ............................... 28
Applying Task Information ....................................... 30
Task Views .................................................... 33
Displaying Gantt View ........................................... 33
Displaying Gantt Sub Views ...................................... 33
Network View .................................................... 34
WBS View ........................................................ 34
Task Usage View ................................................. 35
Task Management ............................................... 35
Reports ....................................................... 35
Table of Figures .............................................. 36
Table of Index ................................................ 37
Appendix A – Bespoke Publications – Operation Re-Birth – Project
Charter ....................................................... 38
Starting Up ProjectLibre
Select the Windows Flag bottom left corner of your screen.
Create a Project
Select the Create Project option shown on the Welcome to
ProjectLibre startup splash screen.
After clicking on ‘Create Project’ the New Project Dialog is
displayed.
To create a project requires some basic project details as seen
in the screen below.
Adding Tasks
After you enter your project details the ProjectLibre desktop
should be displayed like below.
Figure 13: Operation Re-birth – Select the Task Menu Indent Option
When the Indent option is applied the all selected entries now
have been configured as child tasks to Operation Rebirth as
illustrated below.
Saving a Project
Periodically throughout it is recommended that you save your
project.
Reflection Moment
Let’s step back a moment and review what we know. Gazetted
Public Holidays during the period the will affect Project
Schedule include:
Public Holiday 2017 2018
New Year’s Day 1/1/2017 1/1/2018
2/1/2017
Australia Day 26/2/2017 26/2/2018
Labour Day 6/3/2017 5/3/2018
Good Friday 14/3/2017 30/3/2018
Easter Monday 17/3/2017 2/4/2018
ANZAC Day 25/4/2017 25/4/2018
Western 5/6/2017 4/6/2018
Australia Day
© AiTT 2017 Project:ibre User Guide Page 11 of 39
ProjectLibre User Guide
Project Calendar
The Project Calendar can be configured to use:
Standard
Night Shift
24 Hour Working
The default calendar for projects is standard.
Setting the Project Base Calendar
To update the calendar setting go to File on the Program Menu,
then select the option Information.
The Project Information form will be displayed like below:
Description Date
Start Date 22 May 2017
Current Lease Vacation 2 February 2018
Date
Notice of Intention – 2 February 2018 – 90 days (3
Current Tenancy November 2017)
New Tenancy Report 2 February 2018 – 6 months (4
August 2017)
Relocation Go-NoGo 2 February 2018 – 14 days (15
January 2018)
Table 2: Confirmed Task Start Completion Dates
Adding Resources
The first task is to assemble a list of project resources that
are known to be required. Table 3. List of Primary Resources –
Project – Operation Re-Birth, provides a summary list.
Select the Name cell on the row 2 and type: Project Management
Select the Name cell on the row 3 and type: Project Sponsor
Select the Name cell on the row 4 and type: Project Manager
Select the Name cell on the row 5 and type: Project Administrator
Select the Name cell on the row 6 and type: ICT Management
Select the Name cell on the row 7 and type: ICT Manager
Select the Name cell on the row 8 and type: ICT Support
Select the Name cell on the row 9 and type: Network Engineer
Select the Name cell on the row 10 and type: Security Engineer
Select the Name cell on the row 11 and type: Painting
Select the Name cell on the row 12 and type: Painting Supervisor
Select the Name cell on the row 13 and type: Painting TA
Select the Name cell on the row 14 and type: Electrical
Select the Name cell on the row 15 and type: Electrical
Supervisor
Select the Name cell on the row 16 and type: Electrical TA
The entries will look as displayed in Figure 30: Operation Re-
Birth Resource Creation.
Grouping Resources
In this example the resources will be grouped in like activities.
Select the Row ID 15, engage CTRL and then Row ID 16, select the
Indent Option from the Resource Menu.
Select the Row ID 13, engage CTRL and then Row ID 12, select the
Indent Option from the Resource Menu.
Select the Row ID 10, engage CTRL and then Row ID 9, 8, and 7,
select the Indent Option from the Resource Menu.
Select the Row ID 14, engage CTRL and then Row ID 11, 6, and 2,
select the Indent Option from the Resource Menu.
© AiTT 2017 Project:ibre User Guide Page 23 of 39
ProjectLibre User Guide
Configuring Resources
Resource configuration data needs now to be applied using the
data in Table 3: List of Primary Resources – Project – Operation
Re-Birth
Select Row ID 3 for Project Sponsor and select the Resource
Application Menu Information Option
General Settings
At the General Tab update as follows:
Initials: PS
E-mail Address: project.sponsor@bespoke.com.au
Group: Project Management
RBS: 1.1.1
Base Calendar: Select Operation Re-Birth from the Option List
Once updated the Resource Information Entry Form for Project
Sponsor at the General Tab will as displayed in Figure 32:
Operation Re-Birth Project Sponsor Resource Information Form –
General.
Figure 32: Operation Re-Birth - Project Sponsor Resource Information Form – General
Costs Settings
Select the Costs Tab. Each Resource is able to be configured
for five (5) cost rates. Default Costs are recorded under Tab
A.
Update the Standard Rate to read $150 p/h
Leave Overtime Rate and Cost Per Use set to $0.00.
Select the Accrue At: option Prorated
Once updated the Resource Information Entry Form for Project
Sponsor at the Costs Tab will as displayed in Figure 33:
Operation Re-Birth Project Sponsor Resource Information Form –
Costs.
Figure 33: Operation Re-Birth - Project Sponsor Resource Information Form – Costs
Figure 34: Operation Re-Birth - Project Sponsor Resource Information Form – Resource
Availability
Tasks Settings
At this time no tasks have been applied to this resource.
Notes Settings
At this time no notes are to be applied to this resource.
Select the Close button
Complete the process for all of the entries at Table 3: List of
Primary Resources – Project – Operation Re-Birth
Configuring Group Settings
Double Click Row ID 14
General Settings
At the General Tab update as follows:
Group: Project Resources
RBS: 1.4
Base Calendar: Select Operation Re-Birth from the Option List
Select Close
© AiTT 2017 Project:ibre User Guide Page 26 of 39
ProjectLibre User Guide
Resources Views
Displaying Resource Breakdown Structure
Select the Application Resource Menu Option
Select the RBS Option
ProjectLibre will display Project Resources in Network Diagram
View similar to the display at Figure 36: Operation Re-Birth
Resource Breakdown Structure.
Select the Work: field enter the corresponding Work Hours from
Table 4: Prepare New Premises Activites – 20 hours
Select the Resources tab
Select Close
Repeat the entries for the remainder of the activities listed at
Table 4: Prepare New Premises Activities.
Select each child task and pair it with the successor child task
and link then update the dependency type by right clicking on the
link and select the dependency option as described in the 6.
Applying Task Dependencies.
Task Views
ProjectLibre provides capability to view project task data in
four views:
Gantt
Network
WBS (Work Breakdown Structure)
Task Usage
Task Usage
Resource Usage
Network View
To display Network View at any time select the Application View
Menu
Select Network Option within the Task Views Group
WBS View
To display WBS View at any time select the Application View Menu
© AiTT 2017 Project:ibre User Guide Page 34 of 39
ProjectLibre User Guide
Reports
ProjectLibre provides capability for various types of dedicated
reports including:
Project Details
Resource Information
Task Information
Who Does What
In addition, Screen Views are also able to be printed including:
Task Views of:
Project Schedule Model with Gantt Chart
Project Network Diagram
Project WBS
Resource Views of:
Project Resources
Project RBS
Table of Figures
Figure 1: Windows Menu Control ................................................................. 6
Figure 2: Windows Menu Programs Scroll Icon .................................................... 6
Figure 3: ProjectLibre - Application Icon ...................................................... 6
Figure 4: ProjectLibre - Desktop at Startup .................................................... 6
Figure 5: ProjectLibre - Welcome to ProjectLibre ............................................... 7
Figure 6: ProjectLibre - New Project ........................................................... 7
Figure 7: ProjectLibre - Example Completed New Project ......................................... 8
Figure 8: ProjectLibre - Schedule Model Desktop ................................................ 8
Figure 9: ProjectLibre – Project Schedule Heading .............................................. 9
Figure 10: Operation Re-birth – Project Phase Entry ........................................... 10
Figure 11: Operation Re-birth – Bulk Selection of Rows 2-7 .................................... 10
Figure 12: Operation Re-birth – Select the Task Menu .......................................... 10
Figure 13: Operation Re-birth – Select the Task Menu Indent Option ............................ 11
Figure 14: Operation Re-birth – Grouped Tasks ................................................. 11
Figure 15: Operation Re-birth – Project Information Entry Form ................................ 13
Figure 16: ProjectLibre – Change Working Calendar Entry Form .................................. 14
Figure 17: Creating a New Base Calendar ....................................................... 14
Figure 18: Creating a New Base Calendar ....................................................... 14
Figure 19: Operation Re-Birth - Change Working Calendar ....................................... 15
Figure 20: Operation Re-Birth - Change Working Calendar ....................................... 15
Figure 21: Operation Re-Birth - Change Working Calendar ....................................... 16
Figure 22: Operation Re-Birth - Working Calendar with Non-Working Time ........................ 16
Figure 23: Operation Re-Birth - Working Calendar with Non-Working Time ........................ 17
Figure 24: Operation Re-Birth - Working Calendar with Non-Working Time ........................ 20
Figure 25: Operation Re-Birth - Gantt Chart View without dependencies ......................... 20
Figure 26: Operation Re-Birth - Phase Link Selection .......................................... 21
Figure 27: Operation Re-Birth - Phase Link Selection .......................................... 21
Figure 28: Operation Re-Birth - Task Dependency Configuration ................................. 21
Figure 29: Operation Re-Birth - Task Dependency Options ....................................... 22
Figure 30: Operation Re-Birth - Resource Creation ............................................. 23
Figure 31: Operation Re-Birth - Grouped and Ordered Resources ................................. 24
Figure 32: Operation Re-Birth - Project Sponsor Resource Information Form – General ........... 25
Figure 33: Operation Re-Birth - Project Sponsor Resource Information Form – Costs ............. 26
Figure 34: Operation Re-Birth - Project Sponsor Resource Information Form – Resource Availability
.............................................................................................. 26
Figure 35: Operation Re-Birth - Project Sponsor Resource Information Listing .................. 27
Figure 36: Operation Re-Birth - Resource Breakdown Structure .................................. 28
Figure 37: Operation Re-Birth - Resource Usage ................................................ 28
Figure 38: Operation Re-Birth – Prep New Premises Child Activities ............................ 30
Figure 39: Operation Re-Birth – Task Information Entry Form ................................... 31
Figure 40: Operation Re-Birth – Task Information Entry Form - Resources ....................... 31
Figure 41: Operation Re-Birth - Assign Resources Button ....................................... 32
Figure 42: Operation Re-Birth – Task Information-Assigned Resources ........................... 32
Figure 43: Operation Re-Birth – Prep New Premises Child Activities ............................ 33
Figure 44: ProjectLibre – Application Menu – Views Ribbon ..................................... 33
Figure 45: ProjectLibre – Gantt-Histogram Sub View ............................................ 34
Figure 46: ProjectLibre – Gantt-Resource Usage Sub View ....................................... 34
Table of Index