1. Purpose
This procedure describes the activities for the execution and reporting of the inspection of welding
of pressure static equipment and piping.
2. Scope
This procedure applies to Quality Assurance (QA) and Quality Control (QC) for welding works
associated with pressure static equipment and piping
3. References
3.1 MNT_INTG-2005OP - Compliance with Workplace Safety and Health Act
Requirements.
3.2 MNT_INTG-2009OP - NDT Services by Site Based Contractor
3.3 ASTM B.31.3 - Process Piping
3.4 ASTM B.31.1 - Power Piping
3.5 ASME IX - Welding and Brazing Qualification
3.6 DEP 31.10.60.18 - Welding of Metals (additional to API RP 582)
3.7 DEP 31.22.20.31 - Unfired Pressure Vessels
3.8 DEP 31.38.01.31 - Shop and Field Fabrication of Piping
3.9 API 577 - Welding Inspection and Metallurgy
4. Definitions
4.1 DEP Design and Engineering Practice.
4.2 NDT/NDE Non-Destructive Testing.
4.3 PRIMOS Process Industries Skills Management System.
4.4 W-IMS Web-Integrity Management System
4.5 WPS Welding procedure specifications.
4.6 PQR Procedure qualification records.
4.7 PMI Positive Material Identification
4.8 ASME American Society of Mechanical Engineers
4.9 PWHT Post Weld Heat Treatment
4.10 HFA Hydrofluoric Alkylation (plant)
4.11 NACE National Association of Corrosion Engineers
5. Responsibility
The Asset Integrity Manager and the designated Inspection Engineers shall be responsible to
implement this procedure.
Document Status APPROVED
Page 1 of 43 The controlled copy of this document is in electronic format on the Shell Singapore Web. Issued by: Dept QSC
This hardcopy is uncontrolled and was printed on 19 January 202023 April 201913 August Approved by: DMA/122
2018
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
MNT_INTG-2007OP Welding Inspection August 2018
Revision: 10
6. Procedure
6.1 INSPECTION ROLE
The role of the Inspection Engineer is to:
To attend pre-fabrication – refer to appendix 1a/b for typical agenda of meeting.
Review all Welding, NDE and PWHT procedures, where necessary in consultation with the
Senior Materials/Corrosion Engineer.
Verify welders’ qualifications are current and qualified in the processes of the weld procedures
used.
Review and approve work/quality plans, including QA / QC and Inspection and Test Plans
(ITP) to ensure that Company requirements (e.g. DEPs) are incorporated and that the
contractor carrying out the work has a approved quality plan for the work to be conducted;
Where statutory equipment is involved, to liaise with Ministry of Manpower (MOM) (refer to
MNT_INTG-2005OP, Compliance with Workplace Safety and Health Act Requirements.);
Conduct inspection of welds;
Arrange for and review NDT results, where necessary – see section 6.8
Witness hydrostatic testing where applicable.
Retain all the appropriate documents, which are provided by the contractor or Maintenance
Section, and file into individual equipment record.
6.3 Documentations
The Contractor shall submit the following documents to the Inspection Engineer for review prior to
execution of work. Any documents or procedures not complying with company requirements shall
be returned to the contractor for revision.
Documents containing details of;
Contract No. / Title,
Welder Qualifications and ID No., plus PRIMOS qualification/certification
Weld Map and Joint No.,
Welding Procedure Specification No. plus revision and appropriate PQR.
Test Loops
Contractor’s quality and test plans, including an Inspection Test Plan, for approval by the
Inspection Engineer.
Note:
NDT, PMI, when necessary, and hydrostatic testing requirements are recorded by the
Inspection Engineer in the Inspection Test Plan
Shell approved sketches or isometrics/drawings
Materials mill certificates
Contract specifications, where applicable
Welders Procedure Qualification, where applicable
Where statutory equipment is involved, refer to MNT_INTG-2005OP, Compliance with Workplace
Safety and Health Act Requirements.
then proceed with inspection and arrange for NDT and PMI, if necessary, to be carried out. For
weld joints that are subjected to Radiographic Test, the Contractor shall input the test results into
their Welder Menu so that the performance of welders is being tracked. All NDT reports shall then
be incorporated in the test package, to be retained by the Inspection Engineer, for records.
6.5 Material:
For material colour coding, to refer to MNT_INTG-2013OP - Inward Goods Inspection Procedure.
The heat numbers shall be reflected onto the relevant shop fabrication isometric/weld map and
the Welding Inspection Results and Report sheet. The heat number shall be transferred by low
stress hard stamp or suitable permanent marker before materials are cut.
6.5.1 Consumables
i) Contractors shall have system to verify and demonstrate effective control of correct
consumables meeting specifications are used throughout the fabrication process. For filler
rods, sampling PMI to be done per box/tube
ii) Consumables requirement shall follow :
a) The relevant as built construction code for pressure static equipment or piping.
b) For HFA services - Alloy 400 welding,
i) Weld metal iron content shall be less than 5 wt%.
ii) Weld electrode titanium content should be less than 2.2 wt%.
6.7 Hardness
a) The extent of hardness testing shall follow DEP 31.38.01.31-Gen; Appendix 4
b) The acceptance criteria for hardness limit shall meet the appropriate code requirement as
outlined in
i) DEP 31.22.00.31-Gen UNFIRED PRESSURE VESSELS
ii) All weld procedures shall meet the hardness testing criteria and hardness limits for
carbon steel piping as outlined in DEP 31.38.01.31-Gen. “Shop and Field Fabrication of
Piping.”
6.8 NDT:
a) NDE procedures and technician competency are to be reviewed and approved by Inspection
Engineer.
b) For Extent of NDT, DEP 31.38.01.31-Gen; Appendix 4 shall be used plus the following
additional:
c) 100% PMI shall be done on each component including welds for all alloy steel. This shall
include valves body and all fittings. Writing PMI-OK beside the tested point is required.
i) For HF services - Low Temp Carbon Steel and Monel require PMI. For
acceptance criteria :
Low Temp Carbon steel -
For 0.18wt% <C <0.23wt%
Cu+Ni < 0.15wt%
For C< 0.18wt%
Cr+Cu+Ni <0.15%.
Document Status APPROVED
Page 6 of 43 The controlled copy of this document is in electronic format on the Shell Singapore Web. Issued by: Dept QSC
This hardcopy is uncontrolled and was printed on 19 January 202023 April 201913 August Approved by: DMA/122
2018
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
MNT_INTG-2007OP Welding Inspection August 2018
Revision: 10
Alloy 400 welding, Weld metal iron content shall be less than 5 wt% and Ti
<2.2%
d) For all tie-ins, the following additional requirement is required for all Hydrocarbon service
pipes:
i) Penetrant Test (PT) or Magnetic Particle Test (MT) of existing pipe tie-in weld
preparation
ii) Spot Ultrasonic Thickness Gauging (UTG) on existing pipe; adjacent to the weld
preparation in the following breakdown:
Diameter <4” = 2 points
Diameter 4 to 12” = 4 points
Diameter >12” = 8 points
iii) 100% Radiography Test (RT) of tie-in.
Note; Ultrasonic Test (UT) maybe use inplace of RT for branch connections if RT is not
possible.
e) HFA services NDT requirement shall follow “Severe Cyclic Conditions” as indicated in
Appendix 2
f) Acceptance criteria
i) Acceptance criteria for the NDT shall follow the relevant original construction code for
the pressure static equipment or piping.
ii) For HFA services, the acceptance criteria for the Piping shall meet the weld acceptance
criteria for “Severe Cyclic Conditions” as outlined in ASME B31.3 “Process Piping.”
7.0 Deviations :
Deviations from the requirements of this procedure shall be approved by the Asset Integrity
Manager, the deviation request form in Appendix 5 is to be used.
8. Records and related documents
2010
Jan 3. References Delete; MNT_INTG-2004OP and DEPs on Standard Vertical Tanks
2012 (non relevant)
Jan 4. Definitions Delete; Commissioner and MDR (non relevant)
2012 Added; ASME, PWHT, HFA, NACE
Jan 6.1 Inspection Added; Review welding and PWHT Procedures, Verify welders
2012 Role qualifications
Amended; included, QA/QC and ITPs and Review NDT Results.
Jan New 6.2 Added; Welder Qualifications as new requirements.
2012
Jan New 6.3 Amended; change heading.
2012 Added; Welder Qualifications and ID
Jan New 6.3.1 Added; new header - 6.3.1 Bukom Based Contractors
2012 Amended; actions for welders with 1% rejection rate.
Jan 6.4 to 6.8 Amended; re-arranged sections for clarity.
2012
Jan 6.5.1 Added; new section on controls of consumables
2012
Amended; To reflect current practice .
Nov Header Title
2012 Amended; to reflect current practice and procedure.Sep 2012
Nov
2012 1. To 3 Added; To attend pre-fabrication.To review NDE procedure
Nov
2012 Added; Weld Map.
Nov 6.1
2012 Added; To align expectation for document compilation.
Nov
6.3 Added; To align expectation for document compilation.
2012
Added; Statutory requirement for 3rd party Inspector.
6.3.
Nov 6.5.1 to 6.8 Monel PMI requirement from Consumable section to PMI section. HF
2012 service
Nov Appendix 2 Revised Appendix 2 from Extent of Inspection table to ITP for non CS
2012 welding
Section 6.8, a), i) Amended requirements for Low Temp Carbon Steel.
11. APPENDICES
Appendix 1a/b: Typical agenda cum Minute-of-Meeting of pre-fabrication meeting
Appendix 1a
Project :
Project Description :
Job No. :
Vendor Name :
Manufacturer :
Meeting Location :
Meeting Date :
Attendance:
Company Name Department Name Signature
Distribution:
SEPL Team SEPL Project Mrgr
i) PO date:
2. PREPARATION:
Pipe =
Valves =
Relief Valves =
Structural =
MOM informed?
NDT contractor =
= Contractor managed
PWHT contractor =
= Contractor managed
Painting =
= Contractor managed
Others……………….
Comments:
All schedule shall be forwarded to …….
4 REVIEW OF MATERIAL:
Supplier of material:
Pipes/Fittings =
Structural material =
Comments:
a) Mill certificate (Original or certified True-copy) to be made available for
inclusion into test packages.
Attention to:
Attention :
Tel No. :
E-mail :
Attention :
Tel No. :
E-mail :
E-mail :
Drawings
Relevant procedure
Repair procedure
7. COMMUNICATION CHANNELS:
(Construction Engineer)
Tel No. :
Fax No. :
e-mail :
CC:
Tel No.:
Fax No. :
e-mail :
e-mail :
Attention :
e-mail :
CC :
e-mail :
Attention :
Tel. :
E-mail :
CC :
Tel No. :
E-mail :
E-mail :
8.1 Organization
Is QC department independent from fabrication department?
Yes No
Comments:
9. SHOP TOUR:
Comments;
10. OTHERS:
10.2 Confirmation of Inspection and Test Plan (ITP) in line with 10.1 above.
Review ITP and incorporating Witness and HOLD points.
Incorporated MOM inspection point.
Comments:
1) Total of --- test packages ITP to be review during submission.
2) To submit all golden welds for approval before work start
NDT scope
a) Branch connection = UTG on run pipe (Run pipe = 6” 4spots >8” 12
spots). To be perform by SEPL on request by MS. PT of branch pipe’s
weld preparation. RT (5%)
b) Butt weld to existing = UTG of old pipe (Run pipe = 6” 4spots >8” 12
spots). To be perform by SEPL on request by MS. PT of branch pipe’s
weld preparation. 100% RT.
c) The rest of NDE will be based on Bukom’s Practice.
Dis-similar weld
a) Provide a calibration block of actual weld profile and welding
All site isometrics for erection shall be issued via official transmittal.
Revision to be indicated. Such document has to be approved by
Construction Engineer.
All pipes shall be provided with wear plate for location that sits on
support/sleepers. Round bars to be provided. To incorporated into
contractor sketches.
TFA compliance
Cleanliness compliance
Appendix 1b
Project :
Job No. :
Vendor Name :
Manufacturer :
Order Description :
Meeting Location :
Meeting Date :
Attendance:
Company Name Department Name Signature
Distribution:
Document Status APPROVED
Page 26 of 43 The controlled copy of this document is in electronic format on the Shell Singapore Web. Issued by: Dept QSC
This hardcopy is uncontrolled and was printed on 19 January 202023 April 201913 August Approved by: DMA/122
2018
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
MNT_INTG-2007OP Welding Inspection August 2018
Revision: 10
Fabricator Team
1.5 QC Instructions:
MOM required
Comments;- SEPL to have direct access to TPI and fabrication vendor and sub-vendors.
Confirmed based on PO
(Name of sub-vendor) :
Type of sub-order :
Location :
Contact point :
QA system :
Comments:
Attention to : (TPI)
4.4 Inspection Completion Notice (ICN) & Inspection Release Notice (IRN)
Confirm Format
5. Communication Channel
5.1 Shell Project Design Engineering Team, Singapore
Attention : (Project Engineer)
Tel No. :
E-mail :
CC : (Inspection Engineer)
Tel No. :
E-mail :
E-mail :
CC : (Inspection Engineer)
Tel No. :
E-mail :
Tel. :
E-mail :
Tel. :
E-mail :
Tel. :
E-mail :
Comments:
Comments:
Comments:
Comments:
Comments:
To be submitted by “YY/MM/DD”
Comments:
Others “ ”
a
8.2 Organization
Is QC department independent from fabrication department?
Yes No
8.5 QA Audit
Vendor to accept that Purchaser may perform “QA audit” at Purchaser’s option.
Accepted by Vendor
Comments:
Comments:
Comments;
11. Others
(Attached ITP)
b)
Cleanliness Check
a)
Others
b)
c)
Appendix 2 -
INSPECTION TEST PLAN FOR NON CS Welding
Work No :
TEST PACKAGE NO :
Dwg. / Line no :
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Initial / Date Disposition
Initial / Date
2 WPS / PQR H R
3 Welder Qualification H R
Electrode Storage /
4 M R
Baking Condition
5 FABRICATION
5.3 NDE
R/W R/W
5.3.1 RT
R/W R/W
5.3.2 PT/MT
R/W R/W
5.3.3 PMI 100%
R/W R/W
5.4 PWHT / HARDNESS
R/W R/W
6 INSTALLATION
6.9. Reinstatement H R
6.12.Insulation
By Other
APPENDIX 3
Work No :
INSPECTION TEST PLAN ( HFA PIPING )
This ITP only applicable for Piping Class 31310, 31311, 36081 Job No :
TEST PACKAGE NO :
Dwg. / Line no :
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Initial / Date Disposition
Initial / Date
If Monel 60 electrode
1.3 Electrode Monel 60 only H R/W is used
Ti <2.2 wt%
CS PEC-TD-WPS-
0034
2 WPS / PQR H R MONEL PEC-TD-
WPS-4020
3 Welder Qualification H R
Electrode Storage /
4 M R
Baking Condition
5 FABRICATION
5.3 NDE
R/W R/W
R/W R/W
6 INSTALLATION
6.8. Reinstatement H R
6.10 Painting
By Other
6.11.Insulation
By Other
Material
Issued
from
Warehous
e
To
Review PMI documentation to
Uncontrolled
ascertain material meet
Material Flow REJECTED specification prior to start of
(Point 2)
welding.
Inward Goods
For filler rods, sampling PMI to
Inspection
be done per box/tube.
Procedure
ACCEPTED
Start Welding
ACCEPTED
1 Deviation Requestor
2 Date :
Deviation Procedure
number (This is
3
referencing Inspection
Procedure)
4 Deviation Details
(Include attachments if applicable)
5 Deviation Justification
Risk Assessment
Demonstrating that
6 Process Safety Risks
are Managed to
ALARP.
Mitigation Proposal
7
(Operations/