Solar Power Plant Bid Evaluation and Analysis – R1

Sl Items Sunshade Aaakar Energy Remarks Grading


No. (out of 5)
Aakar Sunshade
1 Contract Sign- Contract will be signed with Contract will be signed with main 1) Both Contractors seems to be equally
off, Sunshade. Havells will only back Contractor. All contractual liabilities for will competent for Solar Project. However, the
Engineering, them with a letter of similarly lie with the main Contractor and installation by Sunshade did not have
Execution & confirmation for ‘Authorised in their absence we have to approach the quality finish in terms of overall
Support during dealer/channel partner for product OEM in case any problem. installation and dressing.
25yrs of inverters’ only when we use 2) Irrespective of the Contractor, in both
warranty period Havells inverter in the project. cases, we cannot completely rely on the
of the However, Havells won’t take Contractor as like any other project. As a
comprehensive any direct contractual liabilities client, it is our responsibility to
system. of the overall project. meticulously supervise the project and
As Havells is not our unanimous make Contractor incorporate all pertinent
choice, it will be like any other details from conceptual to detail
independent project, where the engineering and to site installation until
Client is supposed to approach handover with all our inter-departmental
the main Contractor and in their technical know-how.
absence, have to approach the 3) Both Contractor will get all the works
product OEM in case of any outsourced through other sub-contractors
problem. as they do not have their own full-fledged
front or back office specialist team. The
same was observed during our site visit to
both Contractor’s offices. Hence
dependability, quality of project
management, engineering, execution and
long term support cannot be guaranteed.
However, project of this size will have to
be executed through such Contractors
only, else the project cost will escalate
and no big EPC Companies would work at
this price level. So we have limited
options.
4) Following lines shall be included in the
Contract to safeguard our Contract against
any issues and disputes in-case of
conflicts. “All documents, designs,
engineering, calculations, datasheets,
materials, installations, commissioning,
Pg 1 of 7
Solar Power Plant Bid Evaluation and Analysis – R1

Sl Items Sunshade Aaakar Energy Remarks Grading


No. (out of 5)
Aakar Sunshade
method statements/ work procedures,
checklists, work permits, plant
performance review, Site acceptance
Tests, Factory Acceptance Tests, plant
operation, log sheets and safety standards
etc. shall be submitted for Client’s
approval and all works on site shall be
carried out based on approved document
only.
All work shall be carried out in full
compliance to national and international
standards and to Client’s satisfaction. In-
case of conflicts of standards, client’s
specification shall supersede all standards
and any work without Client’s approval is
not liable for payment and stands
rejected.
Contractor shall submit list of all
deliverables and project progress chart
linked with tasks and deliverables, which
shall be regularly updated for monitoring
the project progress.”
2 Offer content Quality of proposal is not to the Have comparatively more in content and
and quality mark. Quality of content and quality.
detailing is comparatively low.
3 Project Do not have any form of Aakar did present the Company synopsis of 1) As a professional company, it is expected
Experience documentation or summary of their accomplishments on Solar power to document the project lists which was
all projects accomplished or plant until date. not in the case of Sunshade.
ongoing, though was verbally As documented, Aakar has more number
briefed in the meeting by of projects with multi-vendor PV Panels
Sunshade. and Inverters OEMs.
Could not produce the list of
projects. However, they seem
to have less number of projects
with different PV Panel and
Inverter OEMs.
Pg 2 of 7
Solar Power Plant Bid Evaluation and Analysis – R1

Sl Items Sunshade Aaakar Energy Remarks Grading


No. (out of 5)
Aakar Sunshade
4 Range(kW) of Maximum range is 500kW. Maximum range is 540kW
Project
5 Site Survey Visited two Solar plants: Visited four Solar Plants, all having 1) Sunshade’s Solar Plant output was not at
1) 250kW * 2: Solar Edge different make inverters and PV modules: optimum level due to weather conditions
Inverters with Waree 1) 125kW + 75 kW: Sungrow Inverters and all inverters output data were not
Panels. with Adani panels. fully displayed on the HMI due to some
2) 30kW: Havells Inverters. 2) 100kW: ABB Inverters with Canadian issues.
PV Panels. 2) Aakar’s Solar Plant output were
3) 75kW: ABB inverters with Vikram PV reasonably at optimum level but cannot
Panels. be exactly compared due to difference in
4) 50kW: Sungrow Inverters with weather conditions at both locations.
Powertech PV Panels. 3) Sunshade’s Solar plant annual
performance data were not available for
review. However, Aaakar’s Solar plants
data were made available for review and
comparison purposes which seems to be
reasonably OK.
4) Clients feedbacks for both Contractors
were reasonably OK but we have to note
that Aakar’s sites were comparatively
older than Sunshade’s sites and Aaakar
has comparatively more number of such
projects.
5) Aakar had comparatively better
installation quality.
6 Years of Running sites are about a year Running sites are comparatively older by a 1) Aakar’s installations are comparatively
Running sites or plus old. year or plus. older than Sunshade.
7 Versatility of Sunshade has installations with Aakar has installations of different PV Based on their projects list, it is apparent that
products Waree PV Panels and Solar Edge panels and Inverter vendors such as Aakar has comparatively more outreach to
Installations (Havells). Waree, Gautam, PV Power Tech, Adani, multiple vendors and so is expected to have a
Vikram, Candian PV Panels and Sungrow, better liaising company with renowned
Delta, ABB, Jackson for Inverters are vendors. It is therefore expected to fetch us
better and faster support from product OEM
during crisis situation.

Pg 3 of 7
Solar Power Plant Bid Evaluation and Analysis – R1

Sl Items Sunshade Aaakar Energy Remarks Grading


No. (out of 5)
Aakar Sunshade
8 DG Sunshade had implemented Aakar had done direct hardwired 1) Both methods of implementation are OK
Synchronisation PLC/HMI based DG synchronisation with Inverter without as far as synchronisation is considered but
(for 200kW synchronisation intermittent control panel. Sunshade’s installation is similar to our
Solar System) requirement. A PLC/HMI based system has
more controlling, monitoring and
diagnostic features. However, DG
synchronisation being a specialised task,
can be implemented only by a specialist
company subcontracted by any main EPC
Contractor. So it won’t make any
difference. As a Client, we should ask the
Contractor to propose the list of such
specialist vendors like for PV panels and
Inverters and determine the selection of
the DG synchronisation Vendor carefully
to avoid any issues later.
9 Company Agra Agra 1) Location wise, both are easily reachable
Location and accessible.
10 Price Inclusive Inclusive No difference.
(GST and FOR
inclusive)
11 With Rs. 70, 00, 000.00 Rs. 69, 50, 000.00 1) Aakar’s quotation is comparatively
Polycrystalline economical.
PV Solar Panels
12 Payment Terms
A Advance 20% with PO. 20% with PO. No difference. - -
Payment
B Structure 20% after Delivery of Structure. 20% after Delivery of Structure. No difference. - -
Payment
C Modules 30% after dispatch of Modules. 30% before dispatch of Modules. 1) Aakar requirement is 30% before dispatch
Payment (To be confirmed in writing) and Sunshade’s requirement is 30% post-
dispatch of Modules. Aakar’s payment
terms will create a difference in
opportunity cost which could arise from

Pg 4 of 7
Solar Power Plant Bid Evaluation and Analysis – R1

Sl Items Sunshade Aaakar Energy Remarks Grading


No. (out of 5)
Aakar Sunshade
the interest period of three to seven days
max which is marginal.
D Inverter 10% after delivery of Inverter. 10% after delivery of Modules/ Inverter. No difference. - -
Payment (To be confirmed in writing)
E Commissioning 15% after commissioning. 15% after commissioning within 7 days. No difference. - -
Payment (To be confirmed in writing)
F Security 5% Security deposit for 5 yrs 5% Security deposit for 5 yrs without PDCs. 1) Not significant difference but in Sunshade
Deposit with 5 post-dated cheques of 1% successive payment per year till 5 yrs. case, since PDCs are already issued, a legal
1% each per year. case may arise during dispute due to
(To be confirmed in writing) untoward reasons whereas in Aakar’s case
we can hold the payment until the
rectification work is fully done. However,
we have to take it in writing from both the
Contractors that they are legally bound by
the Contract and all those related
conditions for holding the payment shall
be clearly mentioned in the Contract in
detail to defeat their claims contractually
in case of speculative disputes.
13 Comprehensive 5 yrs 10 yrs 1) Aakar is giving comparatively more 5 yrs
AMC of comprehensive AMC support. However,
in both cases we have to clarify that it
included fully free service visits by EPC
Contractor and product OEM during the
AMC period for problem resolution.
14 Net metering
A Option 1 1) 20% advance with PO. 1) 20% advance (negotiable to 15%) with 1. Net metering assurance cannot be - -
Contractor will initiate both PO. guaranteed as it is very subjective and is
Net metering approval Same as Sunshade but need to get therefore uncertain in either case.
process and project confirmation in writing for Net
execution simultaneously metering fees and penalty clause.
with assurance of project
completion within two
months from the date of
PO. In-case they are unable

Pg 5 of 7
Solar Power Plant Bid Evaluation and Analysis – R1

Sl Items Sunshade Aaakar Energy Remarks Grading


No. (out of 5)
Aakar Sunshade
to handover the project
within two months plus a
grace period of 15 days,
then the Contractor is liable
for penalty for 15 days then 2) Same as Sunshade but need to get
onwards. confirmation in writing.
2) Contractor has agreed for,
Netmetering fees of max Rs
3.0 Lacs which is to be paid
once the confirmation letter 3) Same as Sunshade but need to get
is received. confirmation in writing.
3) Also, if the Contractor is
unable to get the Net
metering approval within
the completion period, then
the Contractor would install
Zero export device free of
cost and we can start
production immediately.
However, the Net metering
approval will be in process
and once received can
replace the zero export
device with a net-metering
device.
B Option 2 Only PO with a token money of No option proposed by Aakar as they have Option 2 is not under consideration, so is not - -
Rs 1001.00 to initiate the Net first proposition only. under consideration.
metering approval process and
once the approval is received,
we have to pay the additional
amount of approx. Rs 3.0 Lacs in
mutually agreed mode of
transaction.
15 PV panels Vikram Vikram No difference. - -
16 Inverters Delta, ABB, Sungrow, Havells Delta, ABB, Sungrow, Havells Both are open to any product OEM but we
have to get confirmation for number of years
Pg 6 of 7
Solar Power Plant Bid Evaluation and Analysis – R1

Sl Items Sunshade Aaakar Energy Remarks Grading


No. (out of 5)
Aakar Sunshade
for product warranty and remote cloud
access.
No difference.
17 Structures In full compliance to required In full compliance to required specification. No difference but to take written - -
specification. confirmation.
18 Roof top Will occupy two roofs (Seva Will occupy one roof (Seva Kunj) for 200kW Power distribution to be reviewed during -
capacity Kunj + Ladli Kunj) for 200kW plant. However, will confirm exact power detail design stage.
plant. Need exact confirmation distribution based on actual software Hence, cannot be graded now.
of roof top calculation. calculation.
19 Issue Payment mode for Net Payment mode for Net metering to be -
metering to be finalised. finalised.

5 points grading System:

1: Not Acceptable.
2: Below Acceptable
3: Acceptable.
4: Good.
5: Excellent.

Pg 7 of 7