Beruflich Dokumente
Kultur Dokumente
DETAILED ESTIMATES
ITEM 1 Excavation
Est. Qty. 57.60 cu.m
I. Others
96.00 sq.m Clearing and Grubbing @ 40.00 3,840.00
57.60 cu.m Cost of Excavation @ 245.00 14,112.00
57.60 cu.m Disppossal of Excavated Materials @ 205.00 11,808.00
cost: 29,760.00
ITEM 5 Gutter
Est. Qty. 5.34 cu.m
I. Materials
49.00 bag Portland Cement @ 245.00 12,005.00
6.00 cu.m Gravel Crushed 3/4 @ 1,195.00 7,170.00
3.00 cu.m Albay Sand @ 575.00 1,725.00
Cost Of Materials: 20,900.00
Labor: 6,270.00
ITEM 6 Gutter
Est. Qty. 19.00 units
I. Materials
4.00 pcs Paint Brush 2" @ 35.00 140.00
3.00 kls Welding Rod @ 120.00 360.00
5.00 pcs Angle Bar 2x2x1/4 @ 1,495.00 7,475.00
5.00 pcs Flat Bar @ 345.00 1,725.00
1.00 gal Albay Sand @ 495.00 495.00
Cost Of Materials: 10,195.00
Labor: 3,058.50
SUMMARY OF ESTIMATES
AIDA .C DUMAWAL
OWNER
A.D. CONSTRUCTION
006328-0000-00
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Drainage
Garnet St. Calauag, Naga City
DETAILED ESTIMATES
ITEM 1 Excavation
Est. Qty. 57.60 cu.m
I. Others
96.00 sq.m Clearing and Grubbing @ 44.50 4,272.00
57.60 cu.m Cost of Excavation @ 249.80 14,388.48
57.60 cu.m Disppossal of Excavated Materials @ 209.80 12,084.48
cost: 30,744.96
ITEM 5 Gutter
Est. Qty. 5.34 cu.m
I. Materials
49.00 bag Portland Cement @ 248.00 12,152.00
6.00 cu.m Gravel Crushed 3/4 @ 1,198.00 7,188.00
3.00 cu.m Albay Sand @ 578.00 1,734.00
Cost Of Materials: 21,074.00
Labor: 6,322.20
ITEM 6 Gutter
Est. Qty. 19.00 units
I. Materials
4.00 pcs Paint Brush 2" @ 38.00 152.00
3.00 kls Welding Rod @ 124.00 372.00
5.00 pcs Angle Bar 2x2x1/4 @ 1,498.00 7,490.00
5.00 pcs Flat Bar @ 348.00 1,740.00
1.00 gal Albay Sand @ 498.00 498.00
Cost Of Materials: 10,252.00
Labor: 3,075.60
S U M MARY O F E S T I MAT E S
RENATO S. DELOVINO
OWNER
R.S. DELOVINO BUILDERS AND SUPPLIES
006328-0000-00
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Drainage
Garnet St. Calauag, Naga City
DETAILED ESTIMATES
ITEM 1 Excavation
Est. Qty. 57.60 cu.m
I. Others
96.00 sq.m Clearing and Grubbing @ 42.00 4,032.00
57.60 cu.m Cost of Excavation @ 247.00 14,227.20
57.60 cu.m Disppossal of Excavated Materials @ 206.00 11,865.60
cost: 30,124.80
ITEM 5 Gutter
Est. Qty. 5.34 cu.m
I. Materials
49.00 bag Portland Cement @ 247.00 12,103.00
6.00 cu.m Gravel Crushed 3/4 @ 1,197.00 7,182.00
3.00 cu.m Albay Sand @ 576.00 1,728.00
Cost Of Materials: 21,013.00
Labor: 6,303.90
ITEM 6 Gutter
Est. Qty. 19.00 units
I. Materials
4.00 pcs Paint Brush 2" @ 37.00 148.00
3.00 kls Welding Rod @ 122.00 366.00
5.00 pcs Angle Bar 2x2x1/4 @ 1,496.00 7,480.00
5.00 pcs Flat Bar @ 346.00 1,730.00
1.00 gal Albay Sand @ 500.00 500.00
Cost Of Materials: 10,224.00
Labor: 3,067.20
SUMMARY OF ESTIMATES
ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL
DETAILED ESTIMATES
ITEM 1 Drainage
Est. Qty. 68.00 cu.m
I. Materials
5.00 kls CWN 3" @ 65.00 325.00
51.00 kls Tie Wire #16 @ 58.00 2,958.00
290.00 bags Portland Cement @ 248.00 71,920.00
3.00 cu.m Gravel 1" @ 1,058.00 3,174.00
14.00 cu.m Gravel 3/4 @ 1,078.00 15,092.00
### pcs ChB 4" @ 11.00 18,700.00
17.00 pcs Plywood 1/4 @ 430.00 7,310.00
17.00 cum Albay Sand @ 678.00 11,526.00
282.00 pcs RSB 12mm @ 245.00 69,090.00
120.00 Pcs Covo Lumber 2x3x12 @ 174.00 20,880.00
Cost Of Materials: 220,975.00
Labor: 66,292.50
ITEM 2 Excavation
Est. Qty. 26.04 cu.m
SUMMARY OF ESTIMATES
RENATO S. DELOVINO
OWNER/PROPRIETOR
R.S. DELOVINO BUILDERS AND SUPPLIES
006457-0000-00
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Drainage and Road Widening
Temporo Dy St., Dayangdang, Naga City
DETAILED ESTIMATES
ITEM 1 Drainage
Est. Qty. 68.00 cu.m
I. Materials
5.00 kls CWN 3" @ 66.00 330.00
51.00 kls Tie Wire #16 @ 59.00 3,009.00
290.00 bags Portland Cement @ 249.00 72,210.00
3.00 cu.m Gravel 1" @ 1,059.00 3,177.00
14.00 cu.m Gravel 3/4 @ 1,079.00 15,106.00
1,700.00 pcs ChB 4" @ 11.00 18,700.00
17.00 pcs Plywood 1/4 @ 431.00 7,327.00
17.00 cum Albay Sand @ 679.00 11,543.00
282.00 pcs RSB 12mm @ 246.00 69,372.00
120.00 Pcs Covo Lumber 2x3x12 @ 175.00 21,000.00
Cost Of Materials: 221,774.00
Labor: 66,532.20
ITEM 2 Excavation
Est. Qty. 26.04 cu.m
SUMMARY OF ESTIMATES
AIDA C. DUMAWAL
OWNER/PROPRIETOR
A.D. CONSTRUCTION
006457-0000-00
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Drainage and Road Widening
Temporo Dy St., Dayangdang, Naga City
DETAILED ESTIMATES
ITEM 1 Drainage
Est. Qty. 68.00 cu.m
I. Materials
5.00 kls CWN 3" @ 67.00 335.00
51.00 kls Tie Wire #16 @ 60.00 3,060.00
290.00 bags Portland Cement @ 248.00 71,920.00
3.00 cu.m Gravel 1" @ 1,060.00 3,180.00
14.00 cu.m Gravel 3/4 @ 1,079.00 15,106.00
1,700.00 pcs ChB 4" @ 11.00 18,700.00
17.00 pcs Plywood 1/4 @ 430.00 7,310.00
17.00 cum Albay Sand @ 679.50 11,551.50
282.00 pcs RSB 12mm @ 247.00 69,654.00
120.00 Pcs Covo Lumber 2x3x12 @ 177.00 21,240.00
Cost Of Materials: 222,056.50
Labor: 66,616.95
ITEM 2 Excavation
Est. Qty. 26.04 cu.m
S U M MARY O F E ST I MAT E S
DETAILED ESTIMATES
Item 1 Excavation
Est. Qty. 28.80 cu.m
Item 6 Hauling
Est. Qty. 1.00 lot
S U M MAR Y O F E ST I MAT E S
RENATO S. DELOVINO
OWNER/PROPRIETOR
R.S. DELOVINO BUILDERS AND SUPPLIES
006495-2019-01
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Mini-Dam
Zone 3, Sitio Almeda, Pacol, Naga City
DETAILED ESTIMATES
Item 1 Excavation
Est. Qty. 28.80 cu.m
Item 6 Hauling
Est. Qty. 1.00 lot
SUMMARY OF ESTIMATES
ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL
AIDA C. DUMAWAL
OWNER/PROPRIETOR
A.D. CONSTRUCTION
006495-2019-01
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Mini-Dam
Zone 3, Sitio Almeda, Pacol, Naga City
DETAILED ESTIMATES
Item 1 Excavation
Est. Qty. 28.80 cu.m
Item 6 Hauling
Est. Qty. 1.00 lot
SUMMARY OF ESTIMATES
DETAILED ESTIMATES
Item 1 Construction Safety and Health
Est. Qty. 1.00 ls
Item 11 Demolition
Est. Qty. 1.00 lot
SUMMARY OF ESTIMATES
AIDA C. DUMAWAL
OWNER/PROPRIETOR
A.D. CONSTRUCTION
006326-2018-03
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Improvement of Multi-Purpose Building
Vilmar Homes, Calauag, Naga City
DETAILED ESTIMATES
Item 1 Construction Safety and Health
Est. Qty. 1.00 ls
Item 11 Demolition
Est. Qty. 1.00 lot
S U M MAR Y O F E ST I MAT E S
RENATO S. DELOVINO
OWNER/PROPRIETOR
R.S. DELOVINO BUILDERS AND SUPPLIES
006326-2018-03
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Improvement of Multi-Purpose Building
Vilmar Homes, Calauag, Naga City
DETAILED ESTIMATES
Item 1 Construction Safety and Health
Est. Qty. 1.00 ls
Item 11 Demolition
Est. Qty. 1.00 lot
SUMMARY OF ESTIMATES
DETAILED ESTIMATES
Item 1 Clearing and Grubbing
Est. Qty. 96.00 sq.m
ITEM 2 Earthworks
Est. Qty. 60.00 cu.m
RENATO S. DELOVINO
OWNER/PROPRIETOR
R.S. DELOVINO BUILDERS AND SUPPLIES
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Fencing
San Rafael ES, Cararayan, Naga City
DETAILED ESTIMATES
Item 1 Clearing and Grubbing
Est. Qty. 96.00 sq.m
ITEM 2 Earthworks
Est. Qty. 60.00 cu.m
SUMMARY OF ESTIMATES
AIDA C. DUMAWAL
OWNER/PROPRIETOR
A.D. CONSTRUCTION
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Fencing
San Rafael ES, Cararayan, Naga City
DETAILED ESTIMATES
Item 1 Clearing and Grubbing
Est. Qty. 96.00 sq.m
ITEM 2 Earthworks
Est. Qty. 60.00 cu.m
SUMMARY OF ESTIMATES
DETAILED ESTIMATES
ITEM 1 Excavation
Est. Qty. 150.50 cu.m
I. Others
215.00 sq.m Clearing and Grubbing @ 43.00 9,245.00
150.50 cu.m Cost of Excavation @ 248.00 37,324.00
150.50 cu.m Dispossal of Excavated Materials @ 208.00 31,304.00
cost: 77,873.00
ITEM 4 Gutter
Est. Qty. 12.90 cu.m
I. Materials
117.00 bag Portland Cement @ 246.00 28,782.00
7.00 cu.m Gravel Crushed 3/4 @ 1,190.00 8,330.00
13.00 cu.m Albay Sand @ 570.00 7,410.00
Cost Of Materials: 44,522.00
Labor: 13,356.60
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ day 1,000.00
for 1 day
SUMMARY OF ESTIMATES
AIDA .C DUMAWAL
OWNER
A.D. CONSTRUCTION
006329-0000-00
BILL OF MATERIALS AND COST EST
Proposed Drainage
Emerald St. Calauag, Nag
DETAILED ESTIMATE
ITEM 1 Excavation
Est. Qty.
I. Others
215.00 sq.m Clearing and Grubbing
150.50 cu.m Cost of Excavation
150.50 cu.m Dispossal of Excavated Materials
ITEM 4 Gutter
Est. Qty.
I. Materials
117.00 bag Portland Cement
7.00 cu.m Gravel Crushed 3/4
13.00 cu.m Albay Sand
1 Excavation
2 CHB Covered Drainage
3 Formworks and Scaffoldings
4 Gutter
5 Fabrication And Installation of Inlets
6 Sign Board
AIDA .C DUMAWAL
OWNER
A.D. CONSTRUCTION
006329-0000-00
OF MATERIALS AND COST ESTIMATES OF THE
Proposed Drainage
Emerald St. Calauag, Naga City
DETAILED ESTIMATES
150.50 cu.m
@ 25.00
@ 200.00
@ 180.00
cost:
215.00 mtrs
@ 230.00
@ 13.00
@ 68.00
@ 1,150.00
@ 545.00
@ 50.00
@ 210.00
Cost Of Materials:
Labor:
el, oil & lubricants:)
@ 800.00/ day
for 7 days
1.00 ls
@ 420.00
@ 60.00
@ 15.00
Cost of materials:
Labor:
12.90 cu.m
@ 230.00
@ 1,150.00
@ 550.00
Cost Of Materials:
Labor:
el, oil & lubricants:)
@ 800.00/ day
for 1 day
44.00 units
@ 23.00
@ 100.00
@ 1,330.00
@ 300.00
@ 410.00
Cost Of Materials:
Labor:
@ 772.00
MARY OF ESTIMATES
62,565.00
11,180.00
73,745.00
490.00
232,070.00
51,363.00
3,604.00
62,100.00
31,065.00
1,350.00
219,450.00
601,002.00
150,250.50
5,600.00
756,852.50
135,703.50
892,556.00
4,151.42
12,600.00
600.00
2,850.00
16,050.00
4,012.50
20,062.50
3,596.50
23,659.00
23,659.00
26,910.00
8,050.00
7,150.00
42,110.00
10,527.50
800.00
53,437.50
9,581.34
63,018.84
4,885.18
92.00
500.00
14,630.00
3,300.00
410.00
18,932.00
4,733.00
23,665.00
4,243.00
27,908.00
634.27
772.00
772.00
228.00
1,000.00
1,000.00
TOTAL
73,745.00
892,556.00
23,659.00
63,018.84
27,908.00
1,000.00
1,081,886.84
006341-2018-02
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Drainage and Road Widening
Side of NPS, Ateneo Avenue, Bagumbayan Sur, Naga City
DETAILED ESTIMATES
ITEM 1 Demolition
Est. Qty. 197.00 cu.m
ITEM 2 Excavation
Est. Qty. 400.00 cu.m
ITEM 7 Reblocking
Est. Qty. 13.50 cu.m
I. Materials
122.00 bags Portland Cement @ 240.00 29,280.00
5.00 gal Gloss Latex Boysen @ 460.00 2,300.00
5.00 pcs RSB (12mmØ x 6.0m) @ 200.00 1,000.00
7.00 cum Albay Sand @ 550.00 3,850.00
256.00 bd.f Coco Lumber @ 13.00 3,328.00
14.00 cum G-1 Crushed Gravel @ 950.00 13,300.00
Cost of Materials: 53,058.00
Labor: 15,917.40
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 800.00/day 1,600.00
for 2 days
1.00 unit Plate Compactor @ 2,400.00/ day 4,800.00
for 2 days
TOTAL DIRECT COST 75,375.40
PLUS MARK-UPS 13,508.60
TOTAL ITEM COST 88,884.00
UNIT COST 6,584.00
SUMMARY OF ESTIMATES
AIDA C. DUMAWAL
OWNER/PROPRIETOR
A.D. CONSTRUCTION
006274-2018-13
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Rehabilitation of Drainage
Jacob Putol Site 1, Bagumbayan Sur, Naga City
DETAILED ESTIMATES
ITEM 1 Demolition
Est. Qty. 25.83 cu.m
I. Others
25.83 cu.m Cost of Demolition @ 2,800.00 72,324.00
ITEM 2 Excavation
Est. Qty. 160.20 cu.m
I. Others
160.20 cu.m Cost of Excavation @ 200.00 32,040.00
ITEM 4 Drainage
Est. Qty. 170.00 ln.m
I. Materials
988.00 bags Portland Cement @ 220.00 217,360.00
4,017.00 pcs CHB 6" @ 11.00 44,187.00
39.00 kgs Tie wire #16 @ 60.00 2,340.00
43.00 cum Crushed Gravel 3/4 @ 1,120.00 48,160.00
56.00 cum Albay Sand @ 530.00 29,680.00
39.00 pcs Hacksaw Blade @ 60.00 2,340.00
764.00 pcs RSB 12mmØ x 6.0m @ 200.00 152,800.00
7.00 pcs PVC Pipe 2" @ 210.00 1,470.00
Cost Of Materials: 498,337.00
Labor: 149,501.10
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,800.00/ day 25,200.00
for 14 day
S U M MARY O F E S T I MAT E S
DETAILED ESTIMATES
Item 3 Hauling
Est. Qty. 1.00
ITEM 4 Forms
Est. Qty. 1.00
I. Materials
18.00 pcs Plywood 1/4
1,344.00 bdft Cocolumber Formworks
15.00 kls Asst. CW Nails
RENATO S. DELOVINO
OWNER/PROPRIETOR
R.S. DELOVINO BUILDERS AND SUPPLIES
06550-2019-01
AND COST ESTIMATES OF THE
ed Pathwalk Topping
, Tabuco, Naga City
ILED ESTIMATES
cu.m
@ 245.00 118,825.00
@ 1,145.00 61,830.00
@ 590.00 15,930.00
Cost Of Materials: 196,585.00
Labor: 58,975.50
il & lubricants:)
@ 1,400.00/day 8,400.00
for 6 days
263,960.50
47,300.36
311,260.86
5,778.00
cu.m
@ 445.00 37,602.50
Cost Of Materials: 37,602.50
Labor: 11,280.75
il & lubricants:)
@ 2,300.00/day 4,600.00
for 2 days
53,483.25
9,553.75
63,037.00
746.00
ls
@ 13,000.00 13,000.00
Cost of Materials: 13,000.00
13,000.00
2,330.00
15,330.00
15,330.00
ls
@ 375.00 6,750.00
@ 20.00 26,880.00
@ 60.00 900.00
Cost of Materials: 34,530.00
Labor: 10,359.00
44,889.00
8,048.00
52,937.00
52,937.00
mo
@ 1,500.00 3,000.00
Cost of Materials: 3,000.00
3,000.00
537.00
3,537.00
1,768.50
@ 1,272.00 1,272.00
1,272.00
228.00
1,500.00
1,500.00
E STI MATE S
DETAILED ESTIMATES
Item 3 Hauling
Est. Qty. 1.00
ITEM 4 Forms
Est. Qty. 1.00
I. Materials
18.00 pcs Plywood 1/4
1,344.00 bdf Cocolumber Formworks
15.00 kls Asst. CW Nails
SUMMARY OF ESTIMATES
AILED ESTIMATES
cu.m
@ 246.00 119,310.00
@ 1,146.00 61,884.00
@ 593.00 16,011.00
Cost Of Materials: 197,205.00
Labor: 59,161.50
lubricants:)
@ 1,430.00/day 8,580.00
for 6 days
264,946.50
47,504.89
312,451.39
5,800.10
cu.m
@ 446.00 37,687.00
Cost Of Materials: 37,687.00
Labor: 11,306.10
lubricants:)
@ 2,350.00/day 4,700.00
for 2 days
53,693.10
9,626.98
63,320.08
749.35
ls
@ 13,100.00 13,100.00
Cost of Materials: 13,100.00
13,100.00
2,348.83
15,448.83
15,448.83
ls
@ 376.00 6,768.00
@ 21.00 28,224.00
@ 63.00 945.00
Cost of Materials: 35,937.00
Labor: 10,781.10
46,718.10
8,376.55
55,094.65
55,094.65
mo
@ 1,600.00 3,200.00
Cost of Materials: 3,200.00
3,200.00
573.76
3,773.76
1,886.88
@ 1,372.00 1,372.00
1,372.00
228.00
1,600.00
1,600.00
ESTIMATES
DETAILED ESTIMATES
Item 3 Hauling
Est. Qty. 1.00
ITEM 4 Forms
Est. Qty. 1.00
I. Materials
18.00 pcs Plywood 1/4
### bdft Cocolumber Formworks
15.00 kls Asst. CW Nails
SUMMARY OF ESTIMATES
ILED ESTIMATES
cu.m
@ 248.00 120,280.00
@ 1,148.00 61,992.00
@ 595.00 16,065.00
Cost Of Materials: 198,337.00
Labor: 59,501.10
uel, oil & lubricants:)
@ 1,480.00/day 8,880.00
for 6 days
266,718.10
47,822.36
314,540.46
5,838.88
cu.m
@ 448.00 37,856.00
Cost Of Materials: 37,856.00
Labor: 11,356.80
uel, oil & lubricants:)
@ 2,350.00/day 4,700.00
for 2 days
53,912.80
9,666.69
63,579.49
752.42
ls
13,000.00
2,330.00
15,330.00
15,330.00
ls
@ 375.00 6,750.00
@ 22.00 29,568.00
@ 60.00 900.00
Cost of Materials: 37,218.00
Labor: 11,165.40
48,383.40
8,675.14
57,058.54
57,058.54
mo
@ 1,650.00 3,300.00
Cost of Materials: 3,300.00
3,300.00
591.70
3,891.70
1,945.85
@ 1,472.00 1,472.00
1,472.00
228.00
1,700.00
1,700.00
ESTIMATES
DETAILED ESTIMATE
ITEM 1 Safety and Health Program
Est. Qty.
I. Others
3.00 mo Safety and Health Program
ITEM 2 Demolition
Est. Qty.
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Jack Hammer with Compressor
ITEM 3 Formworks
Est. Qty.
I. Materials
8.00 kgs CW Nails
15.00 pcs Marine Plywood 1/4
600.00 bd.f Formworks Coco Lumber
2.00 rolls Caution Tape
ITEM 4 Excavation
Est. Qty.
188.00 cu.m Cost of excavation
SUMMARY OF ESTIMATES
DETAILED ESTIMATES
3.00 mo
@ 1,500.00
cost:
52.00 cu.m
el, oil & lubricants:)
@ 4,950.00/ day
for 6 days
1.00 lot
@ 80.00
@ 475.00
@ 24.00
@ 670.00
Cost of materials:
Labor:
26.00 cu.m
@ 175.00
Cost Of Materials:
215.00 ln.m
@ 247.00
@ 445.00
@ 75.00
@ 1,077.00
@ 597.00
@ 208.00
@ 378.00
Cost Of Materials:
Labor:
@ 1,272.00
MARY OF ESTIMATES
3.00 mo 1,768.00
52.00 m 673.00
1.00 ls 36,035.00
26.00 cu.m 1,492.00
215.00 units 3,575.00
1.00 pc. 1,500.00
grand total:
4,500.00
4,500.00
4,500.00
804.00
5,304.00
1,768.00
29,700.00
29,700.00
5,296.00
34,996.00
673.00
640.00
7,125.00
14,400.00
1,340.00
23,505.00
7,051.50
30,556.50
5,478.50
36,035.00
36,035.00
32,900.00
32,900.00
32,900.00
5,892.00
38,792.00
1,492.00
181,051.00
25,810.00
6,000.00
87,237.00
23,880.00
109,200.00
56,700.00
489,878.00
146,963.40
15,000.00
651,841.40
116,783.60
768,625.00
3,575.00
1,272.00
1,272.00
228.00
1,500.00
1,500.00
TOTAL
5,304.00
34,996.00
36,035.00
38,792.00
768,625.00
1,500.00
885,252.00
006554-2019-01
BILL OF MATERIALS AND COST ES
Proposed Rehabilitation of Exis
Cacao and Canda St., Right Side, Clup
DETAILED ESTIMAT
ITEM 1 Safety and Health Program
Est. Qty.
I. Others
3.00 mo Safety and Health Program
ITEM 2 Demolition
Est. Qty.
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Jack Hammer with Compressor
ITEM 3 Formworks
Est. Qty.
I. Materials
8.00 kgs CW Nails
15.00 pcs Marine Plywood 1/4
600.00 bd.ft Formworks Coco Lumber
2.00 rolls Caution Tape
ITEM 4 Excavation
Est. Qty.
188.00 cu.m Cost of excavation
RENATO S. DELOVINO
OWNER
R.S. DELOVINO BUILDERS AND SUPPLY
006554-2019-01
MATERIALS AND COST ESTIMATES OF THE
osed Rehabilitation of Existing Drainage
Canda St., Right Side, Clupa, Calauag, Naga City
DETAILED ESTIMATES
3.00 mo
@ 1,680.00
cost:
52.00 cu.m
fuel, oil & lubricants:)
@ 4,990.00/ day
for 6 days
1.00 lot
@ 84.00
@ 479.00
@ 24.00
@ 674.00
Cost of materials:
Labor:
26.00 cu.m
@ 178.00
Cost Of Materials:
215.00 ln.m
@ 247.00
@ 448.00
@ 78.00
@ 1,079.00
@ 598.00
@ 209.00
@ 379.00
Cost Of Materials:
Labor:
fuel, oil & lubricants:)
@ 1,500.00/ day
for 10 days
@ 1,372.00
3.00 mo 1,981.22
52.00 m 679.00
1.00 ls 36,188.58
26.00 cu.m 1,517.85
215.00 units 3,584.63
1.00 pc. 1,600.00
grand total:
5,040.00
5,040.00
5,040.00
903.66
5,943.66
1,981.22
29,940.00
29,940.00
5,368.00
35,308.00
679.00
672.00
7,185.00
14,400.00
1,348.00
23,605.00
7,081.50
30,686.50
5,502.08
36,188.58
36,188.58
33,464.00
33,464.00
33,464.00
6,000.10
39,464.10
1,517.85
181,051.00
25,984.00
6,240.00
87,399.00
23,920.00
109,725.00
56,850.00
491,169.00
147,350.70
15,000.00
653,519.70
117,175.75
770,695.45
3,584.63
1,372.00
1,372.00
228.00
1,600.00
1,600.00
TOTAL
5,943.66
35,308.00
36,188.58
39,464.10
770,695.45
1,600.00
889,199.79
006554-2019-01
BILL OF MATERIALS AND COST ES
Proposed Rehabilitation of Exi
Cacao and Canda St., Right Side, Clup
DETAILED ESTIMAT
ITEM 1 Safety and Health Program
Est. Qty.
I. Others
3.00 mo Safety and Health Program
ITEM 2 Demolition
Est. Qty.
II. Equipments(Inclusive of Operator, fuel, oil & lubricant
1.00 unit Jack Hammer with Compressor
ITEM 3 Formworks
Est. Qty.
I. Materials
8.00 kgs CW Nails
15.00 pcs Marine Plywood 1/4
600.00 bd.ft Formworks Coco Lumber
2.00 rolls Caution Tape
ITEM 4 Excavation
Est. Qty.
188.00 cu.m Cost of excavation
SUMMARY OF ESTIMAT
DETAILED ESTIMATES
3.00 mo
@ 1,690.00
cost:
52.00 cu.m
ator, fuel, oil & lubricants:)
@ 4,980.00/ day
for 6 days
1.00 lot
@ 84.00
@ 479.00
@ 25.00
@ 674.00
Cost of materials:
Labor:
26.00 cu.m
@ 179.00
Cost Of Materials:
215.00 ln.m
@ 248.00
@ 448.00
@ 78.00
@ 1,078.00
@ 598.00
@ 210.00
@ 380.00
Cost Of Materials:
Labor:
ator, fuel, oil & lubricants:)
@ 1,500.00/ day
for 10 days
@ 1,472.00
RY OF ESTIMATES
3.00 mo 1,993.02
52.00 m 677.64
1.00 ls 37,084.85
26.00 cu.m 1,526.38
215.00 units 3,594.09
1.00 pc. 1,700.00
grand total:
5,070.00
5,070.00
5,070.00
909.06
5,979.06
1,993.02
29,880.00
29,880.00
5,357.28
35,237.28
677.64
672.00
7,185.00
15,000.00
1,348.00
24,205.00
7,261.50
31,466.50
5,618.35
37,084.85
37,084.85
33,652.00
33,652.00
33,652.00
6,033.88
39,685.88
1,526.38
181,784.00
25,984.00
6,240.00
87,318.00
23,920.00
110,250.00
57,000.00
492,496.00
147,748.80
15,000.00
655,244.80
117,484.55
772,729.35
3,594.09
1,472.00
1,472.00
228.00
1,700.00
1,700.00
TOTAL
5,979.06
35,237.28
37,084.85
39,685.88
772,729.35
1,700.00
892,416.42
006519-0000-00
BILL OF MATERIALS AND COST ES
Proposed Earthfilli
Bagong Silang (Poro), San Fel
DETAILED ESTIMAT
ITEM 1 Earthfilling
Est. Qty.
I. Others
253.00 cu.m Madrigal Sand
SUMMARY OF ESTIMAT
1 Earthfilling
2 Sign Board
NOLASCO ERNESTO P. CASTILLO
OWNER
NOLCAST CONST. AND SUPPLY
006519-0000-00
MATERIALS AND COST ESTIMATES OF THE
Proposed Earthfilling
ng Silang (Poro), San Felipe, Naga City
DETAILED ESTIMATES
253.00 cu.m
@ 675.00
cost:
@ 1,272.00
RY OF ESTIMATES
170,775.00
30,613.00
201,388.00
796.00
1,272.00
1,272.00
228.00
1,500.00
1,500.00
TOTAL
201,388.00
1,500.00
202,888.00
006519-0000-00
BILL OF MATERIALS AND COST EST
Proposed Earthfillin
Bagong Silang (Poro), San Felip
DETAILED ESTIMATE
ITEM 1 Earthfilling
Est. Qty.
I. Others
253.00 cu.m Madrigal Sand
SUMMARY OF ESTIMATES
1 Earthfilling
2 Sign Board
AIDA C. DUMAWAL
OWNER
A.D. CONSTRUCTION
006519-0000-00
OF MATERIALS AND COST ESTIMATES OF THE
Proposed Earthfilling
agong Silang (Poro), San Felipe, Naga City
DETAILED ESTIMATES
253.00 cu.m
@ 677.00
cost:
@ 1,372.00
MARY OF ESTIMATES
171,281.00
30,711.67
201,992.67
798.39
1,372.00
1,372.00
228.00
1,600.00
1,600.00
TOTAL
201,992.67
1,600.00
203,592.67
006519-0000-00
BILL OF MATERIALS AND COST ES
Proposed Earthfillin
Bagong Silang (Poro), San Feli
DETAILED ESTIMAT
ITEM 1 Earthfilling
Est. Qty.
I. Others
253.00 cu.m Madrigal Sand
1 Earthfilling
2 Sign Board
RENATO S. DELOVINO
OWNER
R.S. DELOVINO BUILDERS AND SUPPLIES
006519-0000-00
MATERIALS AND COST ESTIMATES OF THE
Proposed Earthfilling
ong Silang (Poro), San Felipe, Naga City
DETAILED ESTIMATES
253.00 cu.m
@ 679.00
cost:
@ 1,372.00
171,787.00
30,800.22
202,587.22
800.74
1,372.00
1,372.00
228.00
1,600.00
1,600.00
TOTAL
202,587.22
1,600.00
204,187.22
006682-2019-01
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Drainage
Temporo Dy St., Dayangdang, Naga City
DETAILED ESTIMATES
ITEM 1 Clearing and Grubbing
Est. Qty. 198.80 sq.m
I. Others
198.80 sq.m Clearing and Grubbing @ 35.00 6,958.00
ITEM 2 Excavation
Est. Qty. 133.06 cu.m
ITEM 4 Drainage
Est. Qty. 106.00 ln.m
I. Materials
659.00 bags Portland Cement @ 240.00 158,160.00
### pcs CHB 6" @ 16.00 31,168.00
31.00 kgs Tie Wire #16 @ 70.00 2,170.00
20.00 cu.m Crushed Gravel 3/4 @ 1,200.00 24,000.00
38.00 cu.m Albay Sand @ 600.00 22,800.00
13.00 pcs Hacksaw Blade @ 60.00 780.00
603.00 pcs 12mm dia. X 6.0 RSB @ 200.00 120,600.00
Cost Of Materials: 359,678.00
Labor: 100,709.84
ITEM 5 Drainage
Est. Qty. 61.00 ln.m
I. Materials
328.00 bags Portland Cement @ 240.00 78,720.00
961.00 pcs CHB 6" @ 16.00 15,376.00
17.00 kgs Tie Wire #16 @ 70.00 1,190.00
10.00 cu.m Crushed Gravel 3/4 @ 1,200.00 12,000.00
20.00 cu.m Albay Sand @ 600.00 12,000.00
7.00 pcs Hacksaw Blade @ 60.00 420.00
334.00 pcs 12mm RSB x 6.0m @ 200.00 66,800.00
3.00 pcs PVC Pipe 2" @ 200.00 600.00
Cost Of Materials: 187,106.00
Labor: 52,389.68
ITEM 6 Formworks
Est. Qty. 167.00 ln.m
I. Materials
14.00 kls Asst. CW Nails @ 60.00 840.00
438.00 bdft Formworks Coco Lumber @ 18.00 7,884.00
58.00 pcs Plywood 1/4" @ 350.00 20,300.00
Cost Of Materials: 29,024.00
Labor: 8,126.72
SUMMARY OF ESTIMATES
DETAILED ESTIMATES
ITEM 1 Construction Safety and Health
Est. Qty. 1.00 ls
I. Others
3.00 mo. Construction Safety and Health @ 1,600.00 4,800.00
ITEM 2 Demolition
Est. Qty. 290.00 sq.m
ITEM 3 Forms
Est. Qty. 1.00 lot
ITEM 4 Excavation
Est. Qty. 171.00 cu.m
I. Materials
171.00 cu.m Cost of Excavation @ 178.00 30,438.00
SUMMARY OF ESTIMATES
DETAILED ESTIMATES
ITEM 1 Construction Safety and Health
Est. Qty. 1.00 ls
I. Others
1.00 ls Construction Safety and Health @ 10,100.00 10,100.00
ITEM 3 Excavation
Est. Qty. 1,188.00 cu.m
ITEM 5 Formworks
Est. Qty. 1.00 lot
I. Materials
60.00 kgs CW Nails @ 84.00 5,040.00
213.00 pcs Marine Plywood 1/4" @ 480.00 102,240.00
### bd.ft Formworks Coco lumber @ 25.00 66,250.00
Cost Of Materials: 173,530.00
Labor: 52,059.00
SUMMARY OF ESTIMATES
DETAILED ESTIMATES
Item 1 Demolition/Chipping Owrks/Removal of Obstruction
Est. Qty. 3.20 cu.m
ITEM 2 Excavation
Est. Qty. 12.64 cu.m
ITEM 11 Railing
Est. Qty. 13.50 ln.m
I. Materials
0.50 gal Body Filler @ 475.00 237.50
23.00 pcs Square Bar 12mm @ 255.00 5,865.00
2.00 pcs GI Pipe s40 40mm dia @ 1,206.00 2,412.00
1.00 gal Epoxy Primer Paint w/ Catalyst @ 890.00 890.00
6.00 kls Welding Rod @ 165.00 990.00
2.00 pcs Paint Brush @ 124.00 248.00
3.00 bottle Lacquer Thinner @ 30.00 90.00
4.00 pcs GI Pipe 2 s40 @ 2,150.00 8,600.00
2.00 pcs Grinding Disk @ 175.00 350.00
1.00 pcs Cutting Disk 14" @ 840.00 840.00
Cost Of Materials: 20,522.50
Labor: 7,182.88
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Welding Machine @ 1,000.00/ day 3,000.00
for 3 days
SUMMARY OF ESTIMATES
ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL
DETAILED ESTIMATES
ITEM 1 Excavation
Est. Qty. 130.00 cu.m
S U M MAR Y O F E S T I MAT E S
DETAILED ESTIMATES
ITEM 1 Construction Safety and Health
Est. Qty. 1.00 ls
ITEM 2 Formworks
Est. Qty. 1.00 lot
SUMMARY OF ESTIMATES
DETAILED ESTIMATES
ITEM 1 Construction Safety and Health
Est. Qty. 1.00 ls
SUMMARY OF ESTIMATES
DETAILED ESTIMATES
ITEM 1 Construction Safety and Health
Est. Qty. 1.00 ls
ITEM 2 Formworks
Est. Qty. 1.00 lot
SUMMARY OF ESTIMATES