Sie sind auf Seite 1von 138

006328-0000-00

BILL OF MATERIALS AND COST ESTIMATES OF THE


Proposed Drainage
Garnet St. Calauag, Naga City

DETAILED ESTIMATES
ITEM 1 Excavation
Est. Qty. 57.60 cu.m
I. Others
96.00 sq.m Clearing and Grubbing @ 40.00 3,840.00
57.60 cu.m Cost of Excavation @ 245.00 14,112.00
57.60 cu.m Disppossal of Excavated Materials @ 205.00 11,808.00
cost: 29,760.00

TOTAL DIRECT COST 29,760.00


PLUS MARK-UPS 5,376.00
TOTAL ITEM COST 35,136.00
UNIT COST 610.00

ITEM 2 CHB Covered Drainage


Est. Qty. 89.00 mtrs
I. Materials
387.00 bags Portland Cement @ 246.00 95,202.00
1,402.00 pcs CHB 6" @ 17.50 24,535.00
22.00 kgs Tie wire #16 @ 80.00 1,760.00
23.00 cu.m Gravel Crushed 3/4 @ 1,195.00 27,485.00
24.00 cu.m Albay Sand @ 575.00 13,800.00
11.00 pcs Hacksaw Blade @ 72.00 792.00
434.00 pcs RSB 12mm x 6.0m @ 218.00 94,612.00
Cost Of Materials: 258,186.00
Labor: 77,455.80
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ hr 3,000.00
for 3 day

TOTAL DIRECT COST 338,641.80


PLUS MARK-UPS 60,701.20
TOTAL ITEM COST 399,343.00
UNIT COST 4,487.00

ITEM 3 Cross Drainage


Est. Qty. 7.00 mtrs
I. Materials
28.00 bags Portland Cement @ 245.00 6,860.00
4.00 kgs Tie wire #16 @ 85.00 340.00
3.00 cu.m Gravel Crushed 3/4 @ 1,195.00 3,585.00
2.00 cu.m Albay Sand @ 575.00 1,150.00
2.00 pcs Hacksaw Blade @ 70.00 140.00
72.00 pcs RSB 12mm x 6.0m @ 218.00 15,696.00
Cost Of Materials: 27,771.00
Labor: 8,331.30
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ hr 1,000.00
for 1 day
1.00 unit Jack Hammer with Compressor @ 5,000.00/ hr 5,000.00
for 1 day
1.00 unit Concrete Cutter @ 4,000.00/ hr 4,000.00
for 1 day

TOTAL DIRECT COST 46,102.30


PLUS MARK-UPS 8,259.70
TOTAL ITEM COST 54,362.00
UNIT COST 7,766.00

ITEM 4 Formworks and Scaffoldings


Est. Qty. 1.00 ls
I. Materials
16.00 pcs Marine Plywood 1/4 @ 478.00 7,648.00
5.00 kl Asst. CW Nails @ 75.00 375.00
48.00 bdf Formworks Coco Lumber @ 21.00 1,008.00
Labor: 9,031.00
TOTAL DIRECT COST 9,031.00
PLUS MARK-UPS 1,619.00
TOTAL ITEM COST 10,650.00
UNIT COST 10,650.00

ITEM 5 Gutter
Est. Qty. 5.34 cu.m
I. Materials
49.00 bag Portland Cement @ 245.00 12,005.00
6.00 cu.m Gravel Crushed 3/4 @ 1,195.00 7,170.00
3.00 cu.m Albay Sand @ 575.00 1,725.00
Cost Of Materials: 20,900.00
Labor: 6,270.00

TOTAL DIRECT COST 27,170.00


PLUS MARK-UPS 4,870.00
TOTAL ITEM COST 32,040.00
UNIT COST 6,000.00

ITEM 6 Gutter
Est. Qty. 19.00 units
I. Materials
4.00 pcs Paint Brush 2" @ 35.00 140.00
3.00 kls Welding Rod @ 120.00 360.00
5.00 pcs Angle Bar 2x2x1/4 @ 1,495.00 7,475.00
5.00 pcs Flat Bar @ 345.00 1,725.00
1.00 gal Albay Sand @ 495.00 495.00
Cost Of Materials: 10,195.00
Labor: 3,058.50

TOTAL DIRECT COST 13,253.50


PLUS MARK-UPS 2,364.50
TOTAL ITEM COST 15,618.00
UNIT COST 822.00

ITEM 7 Sign Board

1.00 pc. Sign Board @ 1,272.00 1,272.00

TOTAL DIRECT COST 1,272.00


PLUS MARK-UPS 228.00
TOTAL ITEM COST 1,500.00
UNIT COST 1,500.00

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Excavation 57.60 cu.m 610.00 35,136.00


2 CHB Covered Drainage 89.00 mtrs 4,487.00 399,343.00
3 Cross Drainage 7.00 mtrs 7,766.00 54,362.00
4 Formworks and Scaffoldings 1.00 ls 10,650.00 10,650.00
5 Gutter 5.34 cu.m 6,000.00 32,040.00
6 Gutter 19.00 units 822.00 15,618.00
7 Sign Board 1.00 pc. 1,500.00 1,500.00
grand total: 548,649.00

AIDA .C DUMAWAL
OWNER
A.D. CONSTRUCTION
006328-0000-00
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Drainage
Garnet St. Calauag, Naga City

DETAILED ESTIMATES
ITEM 1 Excavation
Est. Qty. 57.60 cu.m
I. Others
96.00 sq.m Clearing and Grubbing @ 44.50 4,272.00
57.60 cu.m Cost of Excavation @ 249.80 14,388.48
57.60 cu.m Disppossal of Excavated Materials @ 209.80 12,084.48
cost: 30,744.96

TOTAL DIRECT COST 30,744.96


PLUS MARK-UPS 5,512.51
TOTAL ITEM COST 36,257.47
UNIT COST 629.47

ITEM 2 CHB Covered Drainage


Est. Qty. 89.00 mtrs
I. Materials
387.00 bags Portland Cement @ 248.00 95,976.00
1,402.00 pcs CHB 6" @ 18.00 25,236.00
22.00 kgs Tie wire #16 @ 84.00 1,848.00
23.00 cu.m Gravel Crushed 3/4 @ 1,199.00 27,577.00
24.00 cu.m Albay Sand @ 579.00 13,896.00
11.00 pcs Hacksaw Blade @ 73.00 803.00
434.00 pcs RSB 12mm x 6.0m @ 219.90 95,436.60
Cost Of Materials: 260,772.60
Labor: 78,231.78
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ hr 3,000.00
for 3 day

TOTAL DIRECT COST 342,004.38


PLUS MARK-UPS 61,321.37
TOTAL ITEM COST 403,325.75
UNIT COST 4,531.75

ITEM 3 Cross Drainage


Est. Qty. 7.00 mtrs
I. Materials
28.00 bags Portland Cement @ 248.00 6,944.00
4.00 kgs Tie wire #16 @ 84.00 336.00
3.00 cu.m Gravel Crushed 3/4 @ 1,198.00 3,594.00
2.00 cu.m Albay Sand @ 579.00 1,158.00
2.00 pcs Hacksaw Blade @ 73.00 146.00
72.00 pcs RSB 12mm x 6.0m @ 219.90 15,832.80
Cost Of Materials: 28,010.80
Labor: 8,403.24
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ hr 1,000.00
for 1 day
1.00 unit Jack Hammer with Compressor @ 5,000.00/ hr 5,000.00
for 1 day
1.00 unit Concrete Cutter @ 4,000.00/ hr 4,000.00
for 1 day

TOTAL DIRECT COST 46,414.04


PLUS MARK-UPS 8,322.04
TOTAL ITEM COST 54,736.08
UNIT COST 7,819.44

ITEM 4 Formworks and Scaffoldings


Est. Qty. 1.00 ls
I. Materials
16.00 pcs Marine Plywood 1/4 @ 479.00 7,664.00
5.00 kl Asst. CW Nails @ 79.00 395.00
48.00 bdft Formworks Coco Lumber @ 22.00 1,056.00
Labor: 9,115.00

TOTAL DIRECT COST 9,115.00


PLUS MARK-UPS 1,634.32
TOTAL ITEM COST 10,749.32
UNIT COST 10,749.32

ITEM 5 Gutter
Est. Qty. 5.34 cu.m
I. Materials
49.00 bag Portland Cement @ 248.00 12,152.00
6.00 cu.m Gravel Crushed 3/4 @ 1,198.00 7,188.00
3.00 cu.m Albay Sand @ 578.00 1,734.00
Cost Of Materials: 21,074.00
Labor: 6,322.20

TOTAL DIRECT COST 27,396.20


PLUS MARK-UPS 4,912.14
TOTAL ITEM COST 32,308.34
UNIT COST 6,050.25

ITEM 6 Gutter
Est. Qty. 19.00 units
I. Materials
4.00 pcs Paint Brush 2" @ 38.00 152.00
3.00 kls Welding Rod @ 124.00 372.00
5.00 pcs Angle Bar 2x2x1/4 @ 1,498.00 7,490.00
5.00 pcs Flat Bar @ 348.00 1,740.00
1.00 gal Albay Sand @ 498.00 498.00
Cost Of Materials: 10,252.00
Labor: 3,075.60

TOTAL DIRECT COST 13,327.60


PLUS MARK-UPS 2,389.58
TOTAL ITEM COST 15,717.18
UNIT COST 827.22

ITEM 7 Sign Board

1.00 pc. Sign Board @ 1,372.00 1,372.00

TOTAL DIRECT COST 1,372.00


PLUS MARK-UPS 228.00
TOTAL ITEM COST 1,600.00
UNIT COST 1,600.00

S U M MARY O F E S T I MAT E S

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Excavation 57.60 cu.m 629.47 36,257.47


2 CHB Covered Drainage 89.00 mtrs 4,531.75 403,325.75
3 Cross Drainage 7.00 mtrs 7,819.44 54,736.08
4 Formworks and Scaffoldings 1.00 ls 10,749.32 10,749.32
5 Gutter 5.34 cu.m 6,050.25 32,308.34
6 Gutter 19.00 units 827.22 15,717.18
7 Sign Board 1.00 pc. 1,600.00 1,600.00
grand total: 554,694.14

RENATO S. DELOVINO
OWNER
R.S. DELOVINO BUILDERS AND SUPPLIES
006328-0000-00
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Drainage
Garnet St. Calauag, Naga City

DETAILED ESTIMATES
ITEM 1 Excavation
Est. Qty. 57.60 cu.m
I. Others
96.00 sq.m Clearing and Grubbing @ 42.00 4,032.00
57.60 cu.m Cost of Excavation @ 247.00 14,227.20
57.60 cu.m Disppossal of Excavated Materials @ 206.00 11,865.60
cost: 30,124.80

TOTAL DIRECT COST 30,124.80


PLUS MARK-UPS 5,401.15
TOTAL ITEM COST 35,525.95
UNIT COST 616.77

ITEM 2 CHB Covered Drainage


Est. Qty. 89.00 mtrs
I. Materials
387.00 bags Portland Cement @ 247.00 95,589.00
1,402.00 pcs CHB 6" @ 18.00 25,236.00
22.00 kgs Tie wire #16 @ 83.00 1,826.00
23.00 cu.m Gravel Crushed 3/4 @ 1,196.00 27,508.00
24.00 cu.m Albay Sand @ 576.00 13,824.00
11.00 pcs Hacksaw Blade @ 73.00 803.00
434.00 pcs RSB 12mm x 6.0m @ 219.00 95,046.00
Cost Of Materials: 259,832.00
Labor: 77,949.60
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ hr 3,000.00
for 3 day

TOTAL DIRECT COST 340,781.60


PLUS MARK-UPS 61,102.35
TOTAL ITEM COST 401,883.95
UNIT COST 4,515.55

ITEM 3 Cross Drainage


Est. Qty. 7.00 mtrs
I. Materials
28.00 bags Portland Cement @ 247.00 6,916.00
4.00 kgs Tie wire #16 @ 86.00 344.00
3.00 cu.m Gravel Crushed 3/4 @ 1,196.00 3,588.00
2.00 cu.m Albay Sand @ 576.00 1,152.00
2.00 pcs Hacksaw Blade @ 72.00 144.00
72.00 pcs RSB 12mm x 6.0m @ 219.00 15,768.00
Cost Of Materials: 27,912.00
Labor: 8,373.60
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ hr 1,000.00
for 1 day
1.00 unit Jack Hammer with Compressor @ 5,000.00/ hr 5,000.00
for 1 day
1.00 unit Concrete Cutter @ 4,000.00/ hr 4,000.00
for 1 day
TOTAL DIRECT COST 46,285.60
PLUS MARK-UPS 8,299.00
TOTAL ITEM COST 54,584.60
UNIT COST 7,797.80

ITEM 4 Formworks and Scaffoldings


Est. Qty. 1.00 ls
I. Materials
16.00 pcs Marine Plywood 1/4 @ 479.00 7,664.00
5.00 kl Asst. CW Nails @ 76.00 380.00
48.00 bdft Formworks Coco Lumber @ 22.00 1,056.00
Labor: 9,100.00

TOTAL DIRECT COST 9,100.00


PLUS MARK-UPS 1,631.63
TOTAL ITEM COST 10,731.63
UNIT COST 10,731.63

ITEM 5 Gutter
Est. Qty. 5.34 cu.m
I. Materials
49.00 bag Portland Cement @ 247.00 12,103.00
6.00 cu.m Gravel Crushed 3/4 @ 1,197.00 7,182.00
3.00 cu.m Albay Sand @ 576.00 1,728.00
Cost Of Materials: 21,013.00
Labor: 6,303.90

TOTAL DIRECT COST 27,316.90


PLUS MARK-UPS 4,897.93
TOTAL ITEM COST 32,214.83
UNIT COST 6,032.74

ITEM 6 Gutter
Est. Qty. 19.00 units
I. Materials
4.00 pcs Paint Brush 2" @ 37.00 148.00
3.00 kls Welding Rod @ 122.00 366.00
5.00 pcs Angle Bar 2x2x1/4 @ 1,496.00 7,480.00
5.00 pcs Flat Bar @ 346.00 1,730.00
1.00 gal Albay Sand @ 500.00 500.00
Cost Of Materials: 10,224.00
Labor: 3,067.20

TOTAL DIRECT COST 13,291.20


PLUS MARK-UPS 2,383.04
TOTAL ITEM COST 15,674.24
UNIT COST 824.96

ITEM 7 Sign Board

1.00 pc. Sign Board @ 1,472.00 1,472.00

TOTAL DIRECT COST 1,472.00


PLUS MARK-UPS 228.00
TOTAL ITEM COST 1,700.00
UNIT COST 1,700.00

SUMMARY OF ESTIMATES
ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Excavation 57.60 cu.m 616.77 35,525.95


2 CHB Covered Drainage 89.00 mtrs 4,515.55 401,883.95
3 Cross Drainage 7.00 mtrs 7,797.80 54,584.60
4 Formworks and Scaffoldings 1.00 ls 10,731.63 10,731.63
5 Gutter 5.34 cu.m 6,032.74 32,214.83
6 Gutter 19.00 units 824.96 15,674.24
7 Sign Board 1.00 pc. 1,700.00 1,700.00
grand total: 552,315.20

NOLASCO ERNESTO P. CASTILLO


OWNER
NOLCAST CONST. AND SUPPLY
006457-0000-00
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Drainage and Road Widening
Temporo Dy St., Dayangdang, Naga City

DETAILED ESTIMATES
ITEM 1 Drainage
Est. Qty. 68.00 cu.m
I. Materials
5.00 kls CWN 3" @ 65.00 325.00
51.00 kls Tie Wire #16 @ 58.00 2,958.00
290.00 bags Portland Cement @ 248.00 71,920.00
3.00 cu.m Gravel 1" @ 1,058.00 3,174.00
14.00 cu.m Gravel 3/4 @ 1,078.00 15,092.00
### pcs ChB 4" @ 11.00 18,700.00
17.00 pcs Plywood 1/4 @ 430.00 7,310.00
17.00 cum Albay Sand @ 678.00 11,526.00
282.00 pcs RSB 12mm @ 245.00 69,090.00
120.00 Pcs Covo Lumber 2x3x12 @ 174.00 20,880.00
Cost Of Materials: 220,975.00
Labor: 66,292.50

TOTAL DIRECT COST 287,267.50


PLUS MARK-UPS 51,372.50
TOTAL ITEM COST 338,640.00
UNIT COST 4,980.00

ITEM 2 Excavation
Est. Qty. 26.04 cu.m

26.00 cu.m Cost of excavation @ 245.00 6,370.00


26.00 cu.m Dispossal and Hauling of Excavated Materilas @ 205.00 5,330.00

TOTAL DIRECT COST 11,700.00


PLUS MARK-UPS 2,075.16
TOTAL ITEM COST 13,775.16
UNIT COST 529.00

Item 3 Aggregate Base Course


Est. Qty. 13.02 cu.m

13.00 cum Item 201 @ 440.00 5,720.00


Labor: 1,716.00
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Plate Compactor @ 2,400.00/ hr 2,400.00
for 1 day
TOTAL DIRECT COST 9,836.00
PLUS MARK-UPS 1,751.80
TOTAL ITEM COST 11,587.80
UNIT COST 890.00

ITEM 4 Portland Cement Concrete Pavement


Est. Qty. 19.53 cu.m
I. Materials
2.00 kgs CWN 3" @ 60.00 120.00
1.00 pcs Hacksaw Blade @ 55.00 55.00
176.00 bags Portland Cement @ 248.00 43,648.00
20.00 cum Gravel 1" @ 1,058.00 21,160.00
15.00 pcs RSb 16mm x 6.0m @ 350.00 5,250.00
26.00 pcs Coco Lumber 2x6x12 @ 24.00 624.00
10.00 cum Albay Sand @ 678.00 6,780.00
Cost of Materials: 77,637.00
Labor: 23,291.10
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ hr 4,000.00
for 4 day

TOTAL DIRECT COST 104,928.10


PLUS MARK-UPS 18,794.45
TOTAL ITEM COST 123,722.55
UNIT COST 6,335.00

ITEM 5 Sign Board

1.00 pc. Sign Board @ 1,272.00 1,272.00

TOTAL DIRECT COST 1,272.00


PLUS MARK-UPS 228.00
TOTAL ITEM COST 1,500.00
UNIT COST 1,500.00

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Drainage 68.00 cu.m 4,980.00 338,640.00


2 Excavation 26.04 cu.m 529.00 13,775.16
3 Aggregate Base Course 13.02 cu.m 890.00 11,587.80
4 Portland Cement Concrete Pavement 19.53 cu.m 6,335.00 123,722.55
5 Sign Board 1.00 pc. 1,500.00 1,500.00
grand total: 489,225.51

RENATO S. DELOVINO
OWNER/PROPRIETOR
R.S. DELOVINO BUILDERS AND SUPPLIES
006457-0000-00
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Drainage and Road Widening
Temporo Dy St., Dayangdang, Naga City

DETAILED ESTIMATES
ITEM 1 Drainage
Est. Qty. 68.00 cu.m
I. Materials
5.00 kls CWN 3" @ 66.00 330.00
51.00 kls Tie Wire #16 @ 59.00 3,009.00
290.00 bags Portland Cement @ 249.00 72,210.00
3.00 cu.m Gravel 1" @ 1,059.00 3,177.00
14.00 cu.m Gravel 3/4 @ 1,079.00 15,106.00
1,700.00 pcs ChB 4" @ 11.00 18,700.00
17.00 pcs Plywood 1/4 @ 431.00 7,327.00
17.00 cum Albay Sand @ 679.00 11,543.00
282.00 pcs RSB 12mm @ 246.00 69,372.00
120.00 Pcs Covo Lumber 2x3x12 @ 175.00 21,000.00
Cost Of Materials: 221,774.00
Labor: 66,532.20

TOTAL DIRECT COST 288,306.20


PLUS MARK-UPS 51,693.12
TOTAL ITEM COST 339,999.32
UNIT COST 4,999.99

ITEM 2 Excavation
Est. Qty. 26.04 cu.m

26.00 cu.m Cost of excavation @ 246.00 6,396.00


26.00 cu.m Dispossal and Hauling of Excavated Materilas @ 206.00 5,356.00

TOTAL DIRECT COST 11,752.00


PLUS MARK-UPS 2,107.00
TOTAL ITEM COST 13,859.00
UNIT COST 532.22

Item 3 Aggregate Base Course


Est. Qty. 13.02 cu.m

13.00 cum Item 201 @ 445.00 5,785.00


Labor: 1,735.50
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Plate Compactor @ 2,400.00/ hr 2,400.00
for 1 day
TOTAL DIRECT COST 9,920.50
PLUS MARK-UPS 1,778.75
TOTAL ITEM COST 11,699.25
UNIT COST 898.56

ITEM 4 Portland Cement Concrete Pavement


Est. Qty. 19.53 cu.m
I. Materials
2.00 kgs CWN 3" @ 61.00 122.00
1.00 pcs Hacksaw Blade @ 56.00 56.00
176.00 bags Portland Cement @ 249.00 43,824.00
20.00 cum Gravel 1" @ 1,059.00 21,180.00
15.00 pcs RSb 16mm x 6.0m @ 352.00 5,280.00
26.00 pcs Coco Lumber 2x6x12 @ 25.00 650.00
10.00 cum Albay Sand @ 679.00 6,790.00
Cost of Materials: 77,902.00
Labor: 23,370.60
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ hr 4,000.00
for 4 day
TOTAL DIRECT COST 105,272.60
PLUS MARK-UPS 18,875.31
TOTAL ITEM COST 124,147.91
UNIT COST 6,356.78

ITEM 5 Sign Board

1.00 pc. Sign Board @ 1,372.00 1,372.00

TOTAL DIRECT COST 1,372.00


PLUS MARK-UPS 228.00
TOTAL ITEM COST 1,600.00
UNIT COST 1,600.00

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Drainage 68.00 cu.m 4,999.99 339,999.32


2 Excavation 26.04 cu.m 532.22 13,859.00
3 Aggregate Base Course 13.02 cu.m 898.56 11,699.25
4 Portland Cement Concrete Pavement 19.53 cu.m 6,356.78 124,147.91
5 Sign Board 1.00 pc. 1,600.00 1,600.00
grand total: 491,305.48

AIDA C. DUMAWAL
OWNER/PROPRIETOR
A.D. CONSTRUCTION
006457-0000-00
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Drainage and Road Widening
Temporo Dy St., Dayangdang, Naga City

DETAILED ESTIMATES
ITEM 1 Drainage
Est. Qty. 68.00 cu.m
I. Materials
5.00 kls CWN 3" @ 67.00 335.00
51.00 kls Tie Wire #16 @ 60.00 3,060.00
290.00 bags Portland Cement @ 248.00 71,920.00
3.00 cu.m Gravel 1" @ 1,060.00 3,180.00
14.00 cu.m Gravel 3/4 @ 1,079.00 15,106.00
1,700.00 pcs ChB 4" @ 11.00 18,700.00
17.00 pcs Plywood 1/4 @ 430.00 7,310.00
17.00 cum Albay Sand @ 679.50 11,551.50
282.00 pcs RSB 12mm @ 247.00 69,654.00
120.00 Pcs Covo Lumber 2x3x12 @ 177.00 21,240.00
Cost Of Materials: 222,056.50
Labor: 66,616.95

TOTAL DIRECT COST 288,673.45


PLUS MARK-UPS 51,759.03
TOTAL ITEM COST 340,432.48
UNIT COST 5,006.36

ITEM 2 Excavation
Est. Qty. 26.04 cu.m

26.00 cu.m Cost of excavation @ 247.00 6,422.00


26.00 cu.m Dispossal and Hauling of Excavated Materilas @ 208.00 5,408.00

TOTAL DIRECT COST 11,830.00


PLUS MARK-UPS 2,120.93
TOTAL ITEM COST 13,950.93
UNIT COST 535.75

Item 3 Aggregate Base Course


Est. Qty. 13.02 cu.m

13.00 cum Item 201 @ 445.00 5,785.00


Labor: 1,735.50
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Plate Compactor @ 2,400.00/ hr 2,400.00
for 1 day
TOTAL DIRECT COST 9,920.50
PLUS MARK-UPS 1,778.75
TOTAL ITEM COST 11,699.25
UNIT COST 898.56

ITEM 4 Portland Cement Concrete Pavement


Est. Qty. 19.53 cu.m
I. Materials
2.00 kgs CWN 3" @ 63.00 126.00
1.00 pcs Hacksaw Blade @ 57.00 57.00
176.00 bags Portland Cement @ 250.00 44,000.00
20.00 cum Gravel 1" @ 1,059.00 21,180.00
15.00 pcs RSb 16mm x 6.0m @ 352.00 5,280.00
26.00 pcs Coco Lumber 2x6x12 @ 26.00 676.00
10.00 cum Albay Sand @ 678.00 6,780.00
Cost of Materials: 78,099.00
Labor: 23,429.70
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ hr 4,000.00
for 4 day

TOTAL DIRECT COST 105,528.70


PLUS MARK-UPS 18,921.34
TOTAL ITEM COST 124,450.04
UNIT COST 6,372.25

ITEM 5 Sign Board

1.00 pc. Sign Board @ 1,472.00 1,472.00

TOTAL DIRECT COST 1,472.00


PLUS MARK-UPS 228.00
TOTAL ITEM COST 1,700.00
UNIT COST 1,700.00

S U M MARY O F E ST I MAT E S

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Drainage 68.00 cu.m 5,006.36 340,432.48


2 Excavation 26.04 cu.m 535.75 13,950.93
3 Aggregate Base Course 13.02 cu.m 898.56 11,699.25
4 Portland Cement Concrete Pavement 19.53 cu.m 6,372.25 124,450.04
5 Sign Board 1.00 pc. 1,700.00 1,700.00
grand total: 492,232.70

NOLASCO ERNESTO P. CASTILLO


OWNER/PROPRIETOR
NOLCAST CONSTRUCTION AND SUPPLY
006495-2019-01
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Mini-Dam
Zone 3, Sitio Almeda, Pacol, Naga City

DETAILED ESTIMATES
Item 1 Excavation
Est. Qty. 28.80 cu.m

29.00 cu.m Cost of Excavation @ 245.00 7,105.00

TOTAL DIRECT COST 7,105.00


PLUS MARK-UPS 1,247.00
TOTAL ITEM COST 8,352.00
UNIT COST 290.00

ITEM 2 Boulder Fill


Est. Qty. 34.50 cu.m
I. Materials
34.50 cu.m Boulder Type A @ 845.00 29,152.50
45.00 bags Portland Cement @ 248.00 11,160.00
2.50 cu.m Albay Sand @ 678.00 1,695.00
Cost of Materials: 42,007.50
Labor: 12,602.25
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ day 7,000.00
for 7 days
TOTAL DIRECT COST 61,609.75
PLUS MARK-UPS 11,012.75
TOTAL ITEM COST 72,622.50
UNIT COST 2,105.00

ITEM 3 Footing Tie Beam


Est. Qty. 4.32 cu.m
I. Materials
5.00 pcs Hacksaw Blade @ 55.00 275.00
4.50 kl Tie Wire @ 55.00 247.50
39.00 bags Portland Cement @ 248.00 9,672.00
37.00 pcs 10mm x 6m @ 125.00 4,625.00
4.50 cu.m Gravel 3/4 @ 1,070.00 4,815.00
2.25 cu.m Albay Sand @ 675.00 1,518.75
16.00 pcs 16mm x7.5m RSB @ 540.00 8,640.00
Cost Of Materials: 29,793.25
Labor: 8,937.98
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ day 2,000.00
for 2 days

TOTAL DIRECT COST 40,731.23


PLUS MARK-UPS 7,307.18
TOTAL ITEM COST 48,038.40
UNIT COST 11,120.00

ITEM 4 Concrete Perimeter Cover


Est. Qty. 27.40 cu.m
I. Materials
0.50 box CWN 3" @ 1,430.00 715.00
1.00 box CWN 4 1,340.00 1,340.00
0.25 box CWN 1 1/2 1,450.00 362.50
15.00 pcs Hacksaw Blade 55.00 825.00
27.50 kl Tie Wire 57.00 1,567.50
247.00 bags Portland Cement 248.00 61,256.00
27.50 cum Gravel 3/4 1,078.00 29,645.00
146.00 pcs RSB 16mm x 6m @ 354.50 51,757.00
40.00 pc. Plywood 1/4 @ 430.00 17,200.00
14.00 cum Albay Sand @ 675.00 9,450.00
300.00 pcs Coco Lumber 2x3x 12 @ 175.00 52,500.00
100.00 pcs RSB 16mm x 7.5m @ 543.00 54,300.00
Cost Of Materials: 280,918.00
Labor: 84,275.40
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ day 7,000.00
for 7 days

TOTAL DIRECT COST 372,193.40


PLUS MARK-UPS 66,754.60
TOTAL ITEM COST 438,948.00
UNIT COST 16,020.00

ITEM 5 Start and End Concrete Cover


Est. Qty. 1.00 cu.m
I. Materials
3.00 kls CWN 3 @ 65.00 195.00
1.00 pcs Hacksaw Blade @ 55.00 55.00
1.00 kl Tie Wire @ 50.00 50.00
9.00 bag Portland Cement @ 248.00 2,232.00
1.00 cum Gravel 3/4 @ 1,070.00 1,070.00
10.00 pcs RSB 16mm x 6m @ 350.00 3,500.00
5.00 kls CWN 4" @ 55.00 275.00
0.50 kl CWN 1 1/2 @ 38.00 19.00
2.00 pc Plywood 1/4 @ 425.00 850.00
0.50 cum Albay Sand @ 675.00 337.50
21.00 pc Coco Lumber 2x3x 12 175.00 3,675.00
Cost Of Materials: 12,258.50
Labor: 3,677.55
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ day 1,000.00
for 1 days

TOTAL DIRECT COST 16,936.05


PLUS MARK-UPS 3,035.95
TOTAL ITEM COST 19,972.00
UNIT COST 19,972.00

Item 6 Hauling
Est. Qty. 1.00 lot

1.00 lot Hauling Cost @ 29,500.00 29,500.00

TOTAL DIRECT COST 29,500.00


PLUS MARK-UPS 5,290.00
TOTAL ITEM COST 34,790.00
UNIT COST 34,790.00

Item 7 Construction Safety and Health


Est. Qty. 1.00 lot

1.00 lot Construction Safety and Health @ 9,500.00 9,500.00

TOTAL DIRECT COST 9,500.00


PLUS MARK-UPS 1,700.00
TOTAL ITEM COST 11,200.00
UNIT COST 11,200.00
ITEM 8 Sign Board

1.00 pc. Sign Board @ 1,272.00 1,272.00

TOTAL DIRECT COST 1,272.00


PLUS MARK-UPS 228.00
TOTAL ITEM COST 1,500.00
UNIT COST 1,500.00

S U M MAR Y O F E ST I MAT E S

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Excavation 28.80 cu.m 290.00 8,352.00


2 Boulder Fill 34.50 cu.m 2,105.00 72,622.50
3 Footing Tie Beam 4.32 cu.m 11,120.00 48,038.40
4 Concrete Perimeter Cover 27.40 cu.m 16,020.00 438,948.00
5 Start and End Concrete Cover 1.00 lot 19,972.00 19,972.00
6 Hauling 1.00 lot 34,790.00 34,790.00
7 Construction Safety and Health 1.00 lot 11,200.00 11,200.00
8 Sign Board 1.00 pc. 1,500.00 1,500.00
grand total: 635,422.90

RENATO S. DELOVINO
OWNER/PROPRIETOR
R.S. DELOVINO BUILDERS AND SUPPLIES
006495-2019-01
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Mini-Dam
Zone 3, Sitio Almeda, Pacol, Naga City

DETAILED ESTIMATES
Item 1 Excavation
Est. Qty. 28.80 cu.m

29.00 cu.m Cost of Excavation @ 247.00 7,163.00

TOTAL DIRECT COST 7,163.00


PLUS MARK-UPS 1,284.33
TOTAL ITEM COST 8,447.33
UNIT COST 293.31

ITEM 2 Boulder Fill


Est. Qty. 34.50 cu.m
I. Materials
34.50 cu.m Boulder Type A @ 850.00 29,325.00
45.00 bags Portland Cement @ 248.00 11,160.00
2.50 cu.m Albay Sand @ 679.00 1,697.50
Cost of Materials: 42,182.50
Labor: 12,654.75
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ day 7,000.00
for 7 days
TOTAL DIRECT COST 61,837.25
PLUS MARK-UPS 11,087.47
TOTAL ITEM COST 72,924.72
UNIT COST 2,113.76

ITEM 3 Footing Tie Beam


Est. Qty. 4.32 cu.m
I. Materials
5.00 pcs Hacksaw Blade @ 56.00 280.00
4.50 kl Tie Wire @ 56.00 252.00
39.00 bags Portland Cement @ 249.00 9,711.00
37.00 pcs 10mm x 6m @ 126.00 4,662.00
4.50 cu.m Gravel 3/4 @ 1,070.00 4,815.00
2.25 cu.m Albay Sand @ 676.00 1,521.00
16.00 pcs 16mm x7.5m RSB @ 543.00 8,688.00
Cost Of Materials: 29,929.00
Labor: 8,978.70
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ day 2,000.00
for 2 days

TOTAL DIRECT COST 40,907.70


PLUS MARK-UPS 7,334.73
TOTAL ITEM COST 48,242.43
UNIT COST 11,167.23

ITEM 4 Concrete Perimeter Cover


Est. Qty. 27.40 cu.m
I. Materials
0.50 box CWN 3" @ 1,432.00 716.00
1.00 box CWN 4 1,342.00 1,342.00
0.25 box CWN 1 1/2 1,450.00 362.50
15.00 pcs Hacksaw Blade 56.00 840.00
27.50 kl Tie Wire 58.00 1,595.00
247.00 bags Portland Cement 248.00 61,256.00
27.50 cum Gravel 3/4 1,079.00 29,672.50
146.00 pcs RSB 16mm x 6m @ 355.00 51,830.00
40.00 pc. Plywood 1/4 @ 432.00 17,280.00
14.00 cum Albay Sand @ 677.00 9,478.00
300.00 pcs Coco Lumber 2x3x 12 @ 177.00 53,100.00
100.00 pcs RSB 16mm x 7.5m @ 543.00 54,300.00
Cost Of Materials: 281,772.00
Labor: 84,531.60
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ day 7,000.00
for 7 days

TOTAL DIRECT COST 373,303.60


PLUS MARK-UPS 66,933.30
TOTAL ITEM COST 440,236.90
UNIT COST 16,067.04

ITEM 5 Start and End Concrete Cover


Est. Qty. 1.00 cu.m
I. Materials
3.00 kls CWN 3 @ 66.00 198.00
1.00 pcs Hacksaw Blade @ 56.00 56.00
1.00 kl Tie Wire @ 51.00 51.00
9.00 bag Portland Cement @ 249.00 2,241.00
1.00 cum Gravel 3/4 @ 1,070.00 1,070.00
10.00 pcs RSB 16mm x 6m @ 355.00 3,550.00
5.00 kls CWN 4" @ 56.00 280.00
0.50 kl CWN 1 1/2 @ 39.00 19.50
2.00 pc Plywood 1/4 @ 425.00 850.00
0.50 cum Albay Sand @ 680.00 340.00
21.00 pc Coco Lumber 2x3x 12 178.00 3,738.00
Cost Of Materials: 12,393.50
Labor: 3,718.05
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ day 1,000.00
for 1 days

TOTAL DIRECT COST 17,111.55


PLUS MARK-UPS 3,068.10
TOTAL ITEM COST 20,179.65
UNIT COST 20,179.65

Item 6 Hauling
Est. Qty. 1.00 lot

1.00 lot Hauling Cost @ 29,600.00 29,600.00

TOTAL DIRECT COST 29,600.00


PLUS MARK-UPS 5,307.28
TOTAL ITEM COST 34,907.28
UNIT COST 34,907.28

Item 7 Construction Safety and Health


Est. Qty. 1.00 lot

1.00 lot Construction Safety and Health @ 9,800.00 9,800.00

TOTAL DIRECT COST 9,800.00


PLUS MARK-UPS 1,757.14
TOTAL ITEM COST 11,557.14
UNIT COST 11,557.14

ITEM 8 Sign Board

1.00 pc. Sign Board @ 1,372.00 1,372.00

TOTAL DIRECT COST 1,372.00


PLUS MARK-UPS 228.00
TOTAL ITEM COST 1,600.00
UNIT COST 1,600.00

SUMMARY OF ESTIMATES
ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Excavation 28.80 cu.m 293.31 8,447.33


2 Boulder Fill 34.50 cu.m 2,113.76 72,924.72
3 Footing Tie Beam 4.32 cu.m 11,167.23 48,242.43
4 Concrete Perimeter Cover 27.40 cu.m 16,067.04 440,236.90
5 Start and End Concrete Cover 1.00 lot 20,179.65 20,179.65
6 Hauling 1.00 lot 34,907.28 34,907.28
7 Construction Safety and Health 1.00 lot 11,557.14 11,557.14
8 Sign Board 1.00 pc. 1,600.00 1,600.00
grand total: 638,095.45

AIDA C. DUMAWAL
OWNER/PROPRIETOR
A.D. CONSTRUCTION
006495-2019-01
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Mini-Dam
Zone 3, Sitio Almeda, Pacol, Naga City

DETAILED ESTIMATES
Item 1 Excavation
Est. Qty. 28.80 cu.m

29.00 cu.m Cost of Excavation @ 249.00 7,221.00

TOTAL DIRECT COST 7,221.00


PLUS MARK-UPS 1,226.33
TOTAL ITEM COST 8,447.33
UNIT COST 293.31

ITEM 2 Boulder Fill


Est. Qty. 34.50 cu.m
I. Materials
34.50 cu.m Boulder Type A @ 851.00 29,359.50
45.00 bags Portland Cement @ 249.00 11,205.00
2.50 cu.m Albay Sand @ 680.00 1,700.00
Cost of Materials: 42,264.50
Labor: 12,679.35
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ day 7,000.00
for 7 days
TOTAL DIRECT COST 61,943.85
PLUS MARK-UPS 11,106.45
TOTAL ITEM COST 73,050.30
UNIT COST 2,117.40

ITEM 3 Footing Tie Beam


Est. Qty. 4.32 cu.m
I. Materials
5.00 pcs Hacksaw Blade @ 57.00 285.00
4.50 kl Tie Wire @ 57.00 256.50
39.00 bags Portland Cement @ 250.00 9,750.00
37.00 pcs 10mm x 6m @ 127.00 4,699.00
4.50 cu.m Gravel 3/4 @ 1,079.00 4,855.50
2.25 cu.m Albay Sand @ 677.00 1,523.25
16.00 pcs 16mm x7.5m RSB @ 543.00 8,688.00
Cost Of Materials: 30,057.25
Labor: 9,017.18
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ day 2,000.00
for 2 days

TOTAL DIRECT COST 41,074.43


PLUS MARK-UPS 7,364.66
TOTAL ITEM COST 48,439.08
UNIT COST 11,212.75

ITEM 4 Concrete Perimeter Cover


Est. Qty. 27.40 cu.m
I. Materials
0.50 box CWN 3" @ 1,433.00 716.50
1.00 box CWN 4 1,345.00 1,345.00
0.25 box CWN 1 1/2 1,453.00 363.25
15.00 pcs Hacksaw Blade 57.00 855.00
27.50 kl Tie Wire 59.00 1,622.50
247.00 bags Portland Cement 248.00 61,256.00
27.50 cum Gravel 3/4 1,079.00 29,672.50
146.00 pcs RSB 16mm x 6m @ 356.00 51,976.00
40.00 pc. Plywood 1/4 @ 433.00 17,320.00
14.00 cum Albay Sand @ 678.00 9,492.00
300.00 pcs Coco Lumber 2x3x 12 @ 178.00 53,400.00
100.00 pcs RSB 16mm x 7.5m @ 544.00 54,400.00
Cost Of Materials: 282,418.75
Labor: 84,725.63
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ day 7,000.00
for 7 days

TOTAL DIRECT COST 374,144.38


PLUS MARK-UPS 67,084.13
TOTAL ITEM COST 441,228.50
UNIT COST 16,103.23

ITEM 5 Start and End Concrete Cover


Est. Qty. 1.00 cu.m
I. Materials
3.00 kls CWN 3 @ 67.00 201.00
1.00 pcs Hacksaw Blade @ 57.00 57.00
1.00 kl Tie Wire @ 52.00 52.00
9.00 bag Portland Cement @ 250.00 2,250.00
1.00 cum Gravel 3/4 @ 1,070.00 1,070.00
10.00 pcs RSB 16mm x 6m @ 356.00 3,560.00
5.00 kls CWN 4" @ 57.00 285.00
0.50 kl CWN 1 1/2 @ 40.00 20.00
2.00 pc Plywood 1/4 @ 430.00 860.00
0.50 cum Albay Sand @ 683.00 341.50
21.00 pc Coco Lumber 2x3x 12 179.00 3,759.00
Cost Of Materials: 12,455.50
Labor: 3,736.65
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ day 1,000.00
for 1 days

TOTAL DIRECT COST 17,192.15


PLUS MARK-UPS 3,082.55
TOTAL ITEM COST 20,274.70
UNIT COST 20,274.70

Item 6 Hauling
Est. Qty. 1.00 lot

1.00 lot Hauling Cost @ 29,800.00 29,800.00

TOTAL DIRECT COST 29,800.00


PLUS MARK-UPS 5,343.14
TOTAL ITEM COST 35,143.14
UNIT COST 35,143.14

Item 7 Construction Safety and Health


Est. Qty. 1.00 lot

1.00 lot Construction Safety and Health @ 9,900.00 9,900.00

TOTAL DIRECT COST 9,900.00


PLUS MARK-UPS 1,775.07
TOTAL ITEM COST 11,675.07
UNIT COST 11,675.07

ITEM 8 Sign Board

1.00 pc. Sign Board @ 1,472.00 1,472.00

TOTAL DIRECT COST 1,472.00


PLUS MARK-UPS 228.00
TOTAL ITEM COST 1,700.00
UNIT COST 1,700.00

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Excavation 28.80 cu.m 293.31 8,447.33


2 Boulder Fill 34.50 cu.m 2,117.40 73,050.30
3 Footing Tie Beam 4.32 cu.m 11,212.75 48,439.08
4 Concrete Perimeter Cover 27.40 cu.m 16,103.23 441,228.50
5 Start and End Concrete Cover 1.00 lot 20,274.70 20,274.70
6 Hauling 1.00 lot 35,143.14 35,143.14
7 Construction Safety and Health 1.00 lot 11,675.07 11,675.07
8 Sign Board 1.00 pc. 1,700.00 1,700.00
grand total: 639,958.12

NOLASCO ERNESTO P. CASTILLO


OWNER/PROPRIETOR
NOLCAST CONSTRUCTION AND SUPPLY
006326-2018-03
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Improvement of Multi-Purpose Building
Vilmar Homes, Calauag, Naga City

DETAILED ESTIMATES
Item 1 Construction Safety and Health
Est. Qty. 1.00 ls

1.00 ls Construction Safety and Health @ 3,350.00 3,350.00

TOTAL DIRECT COST 3,350.00


PLUS MARK-UPS 600.00 5
TOTAL ITEM COST 3,950.00
UNIT COST 3,950.00

ITEM 2 Formworks and Scaffoldings


Est. Qty. 1.00 lot
I. Materials
2.00 kgs CW Nails @ 78.00 156.00
3.00 pcs Plywood Marine 1/4 @ 470.00 1,410.00
200.00 bdf Coco Lumber Formworks @ 24.50 4,900.00
Cost of Materials: 6,466.00
Labor: 1,939.80

TOTAL DIRECT COST 8,405.80


PLUS MARK-UPS 1,506.20
TOTAL ITEM COST 9,912.00
UNIT COST 9,912.00

ITEM 3 Concrete Works


Est. Qty. 7.81 cu.m
I. Materials
71.00 bags Pozzolan Cement @ 244.00 17,324.00
4.00 kgs Tie Wire #16 @ 80.00 320.00
8.00 cu.m Gi Crushed Gravel @ 975.00 7,800.00
4.00 cu.m Albay Sand @ 575.00 2,300.00
2.00 pcs Hacksaw Blade @ 70.00 140.00
67.00 pcs RSB 10mm x 6m @ 175.00 11,725.00
25.00 pcs RSB 16mm x 6m @ 360.00 9,000.00
Cost Of Materials: 48,609.00
Labor: 14,582.70
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 2,500.00/ day 5,000.00
for 2 days
III. Others
5.86 cum Cost of Excavation @ 180.00 1,054.80

TOTAL DIRECT COST 69,246.50


PLUS MARK-UPS 12,415.88
TOTAL ITEM COST 81,662.38
UNIT COST 10,456.13

ITEM 4 Masonry Works


Est. Qty. 31.44 sq.m
I. Materials
37.00 bags Pozzolan Cement @ 244.00 9,028.00
393.00 pcs chB 4" @ 11.50 4,519.50
1.00 kgs Tie Wire #16 @ 80.00 80.00
2.00 cum Albay Sand @ 575.00 1,150.00
1.00 pcs Hacksaw Blade @ 65.00 65.00
23.00 pcs RSB 10mm x 6m @ 175.00 4,025.00
Cost Of Materials: 18,867.50
Labor: 5,660.25
III. Others
5.86 cum Cost of Excavation @ 180.00 1,054.80

TOTAL DIRECT COST 24,527.75


PLUS MARK-UPS 4,397.05
TOTAL ITEM COST 28,924.80
UNIT COST 920.00

ITEM 5 Steel Works


Est. Qty. 1.00 lot
I. Materials
15.00 kl Welding rod @ 82.00 1,230.00
40.00 pcs Angle bar @ 972.00 38,880.00
73.00 pcs Square bar @ 144.00 10,512.00
2.00 unit Acetylene @ 595.00 1,190.00
2.00 pcs Grinding disk @ 160.00 320.00
96.00 pcs Expansion Bolt @ 25.00 2,400.00
15.00 pcs Angle Bar 3/16 x 1 @ 240.00 3,600.00
3.00 pcs 2x6x2mm C-Purlins @ 990.00 2,970.00
12.00 pcs Fabricated Hinges @ 128.00 1,536.00
9.00 pcs C Purlins 2 x 4 x 1.3 mm @ 635.00 5,715.00
6.00 pcs Pillow Block 1 1/2 @ 985.00 5,910.00
Cost Of Materials: 74,263.00
Labor: 22,278.90
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Welding Machine @ 750.00/ day 3,750.00
for 5 days
TOTAL DIRECT COST 100,291.90
PLUS MARK-UPS 17,981.10
TOTAL ITEM COST 118,273.00
UNIT COST 118,273.00

ITEM 6 Roofing Works


Est. Qty. 70.00 sq.m
I. Materials
1.00 box Blind Rivets @ 640.00 640.00
2.00 tbs Rubber Sealant Silicone @ 390.00 780.00
500.00 pcs Tekscrew Steel 12 x 65mm w/ neo @ 2.00 1,000.00
2.00 pcs Pre Painted Gi Ridge roll @ 410.00 820.00
3.00 pcs Pre Painted End Flashing @ 410.00 1,230.00
14.00 pcs Hardi fascia Board 12mm x 10 x 8 @ 320.00 4,480.00
12.00 pcs GI Roofing Sheet, corrugated GA #26 x 12 @ 615.00 7,380.00
Cost Of Materials: 16,330.00
Labor: 4,899.00

TOTAL DIRECT COST 21,229.00


PLUS MARK-UPS 3,831.00
TOTAL ITEM COST 25,060.00
UNIT COST 358.00

Item 7 Ceiling Works


Est. Qty. 38.72 lot

1.00 kgs Concrete Nails @ 85.00 85.00


2.00 kgs CW Nails @ 75.00 150.00
15.00 pcs Marine Plywwod 1/4 @ 475.00 7,125.00
160.00 bdf Good lumber @ 53.00 8,480.00
Cost Of Materials: 15,840.00
Labor: 4,752.00

TOTAL DIRECT COST 20,592.00


PLUS MARK-UPS 3,685.44
TOTAL ITEM COST 24,277.44
UNIT COST 627.00

Item 8 Down spout/ Catch Basin


Est. Qty. 4.00 units

7.00 bags Pozzolan Cement @ 244.00 1,708.00


45.00 pcs CHB 4" @ 11.00 495.00
1.00 kgs Tie Wire#16 @ 80.00 80.00
0.50 cum GI Crushed Gravel @ 974.00 487.00
0.50 cum Albay Sand @ 576.00 288.00
8.00 pcs PCV Pipes 4Ø x 10 @ 515.00 4,120.00
6.00 pcs PVC Pipes 3Ø x 10 @ 445.00 2,670.00
4.00 pcs PVC 4Ø x 90 deg. Elbow @ 50.00 200.00
8.00 pcs PVC 3Ø x 90 deg. Elbow @ 50.00 400.00
4.00 pcs PVC Coupling 4Ø @ 60.00 240.00
4.00 pcs PVC Coupling 3Ø @ 30.00 120.00
2.00 pcs Solvent Cement @ 175.00 350.00
12.00 pcs PVC Clamp @ 24.00 288.00
Cost Of Materials: 11,446.00
Labor: 3,433.80
II. Others
1.00 cum Cost of Excavation @ 180.00 180.00

TOTAL DIRECT COST 15,059.80


PLUS MARK-UPS 2,700.20
TOTAL ITEM COST 17,760.00
UNIT COST 4,440.00

Item 9 Electrical Works


Est. Qty. 25.00 outlet

3.00 pcs RSC Pipes 32mm @ 890.00 2,670.00


13.00 pcs Utility Box @ 28.00 364.00
1.00 pcs Plate & Switch 1 gang @ 118.00 118.00
2.00 pcs Plate & Switch 3 gang @ 185.00 370.00
16.00 pcs Junction Box @ 25.00 400.00
1.00 pcs Panel Board @ 1,190.00 1,190.00
1.00 pcs Entrance Cap @ 65.00 65.00
3.00 pcs Ceiling fan @ 1,480.00 4,440.00
12.00 pcs 20mm Adaptor @ 15.00 180.00
1.00 pair 30A, CB, 2P, Bolt-on @ 385.00 385.00
54.00 pcs PVC Pipe 20mmØ @ 75.00 4,050.00
4.00 pcs PVC Pipe 25mmØ @ 115.00 460.00
18.00 pcs UPVC Long Sweep Elbow 20mmØ @ 15.00 270.00
7.00 set Duplex Convenient Outlet Universal @ 175.00 1,225.00
2.00 can Solvent Cement @ 175.00 350.00
8.00 pcs Electrical Tape @ 30.00 240.00
20.00 m THHN/THWN Wire 5.50mm sqr @ 50.00 1,000.00
9.00 pcs 8 watts Pinlight @ 435.00 3,915.00
2.00 box THHN/THWN Wire 2.0 mm sqr @ 2,390.00 4,780.00
1.00 box THHN/THWN Wire 3.5 mm sqr @ 3,590.00 3,590.00
1.00 pair 20A Circuit Breaker @ 340.00 340.00
1.00 pair 15A Circuit Breaker @ 340.00 340.00
1.00 pcs Secondary Bracket w/ Insulator @ 460.00 460.00
3.00 pcs PVC Clamp @ 20.00 60.00
1.00 pcs Grounding Rod 5/8 @ 1,590.00 1,590.00
1.00 set Circuit Breaker 2P 60A @ 960.00 960.00
30.00 m 22.00 sq.m THHN/THWN @ 128.00 3,840.00
Cost Of Materials: 37,652.00
Labor: 11,295.60

TOTAL DIRECT COST 48,947.60


PLUS MARK-UPS 8,752.40
TOTAL ITEM COST 57,700.00
UNIT COST 2,308.00

ITEM 10 Painting Works


Est. Qty. 317.14 sq.m
I. Materials
4.00 pcs Paint Brush @ 70.00 280.00
1.00 pcs Paint Roller with tray @ 145.00 145.00
4.00 gal Paint Remover @ 370.00 1,480.00
2.00 pcs Steel Brush @ 60.00 120.00
1.00 ltr Acry color @ 145.00 145.00
1.00 ltr Tinting Color @ 145.00 145.00
1.00 gals Rust Converter @ 425.00 425.00
4.00 gals Epoxy Primer w/ catalyst @ 1,195.00 4,780.00
4.00 gals Latex Semi Gloss @ 615.00 2,460.00
2.00 gals Paint Thinner @ 315.00 630.00
8.00 gals BS Flat latex @ 600.00 4,800.00
5.00 gals BS Flat wall Enamel @ 675.00 3,375.00
4.00 gals Roof Paint @ 845.00 3,380.00
1.00 qrts Polituff Hardener @ 185.00 185.00
1.00 gal Polituff Body Filler @ 645.00 645.00
12.00 pcs Sand Paper @ 15.00 180.00
4.00 gal Quick Dry Enamel @ 640.00 2,560.00
4.00 pcs Spatula @ 30.00 120.00
Cost Of Materials: 25,855.00
Labor: 7,756.50

TOTAL DIRECT COST 33,611.50


PLUS MARK-UPS 6,030.75
TOTAL ITEM COST 39,642.25
UNIT COST 125.00

Item 11 Demolition
Est. Qty. 1.00 lot

4.00 ls Add'l labor cost for demolition @ 2,400.00 9,600.00

TOTAL DIRECT COST 9,600.00


PLUS MARK-UPS 1,720.00
TOTAL ITEM COST 11,320.00
UNIT COST 11,320.00

ITEM 12 Sign Board

1.00 pc. Sign Board @ 1,272.00 1,272.00

TOTAL DIRECT COST 1,272.00


PLUS MARK-UPS 228.00
TOTAL ITEM COST 1,500.00
UNIT COST 1,500.00

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Construction Safety and Health 1.00 ls 3,950.00 3,950.00


2 Formworks and Scaffoldings 1.00 lot 9,912.00 9,912.00
3 Concrete Works 7.81 cu.m 10,456.13 81,662.38
4 Masonry Works 31.44 sq.m 920.00 28,924.80
5 Steel Works 1.00 lot 118,273.00 118,273.00
6 Roofing Works 70.00 lot 358.00 25,060.00
7 Ceiling Works 38.72 units 627.00 24,277.44
8 Down spout/ Catch Basin 4.00 units 4,440.00 17,760.00
9 Electrical Works 25.00 outlet 2,308.00 57,700.00
10 Painting Works 317.14 sq.m 125.00 39,642.25
11 Demolition 1.00 lot 11,320.00 11,320.00
12 Sign Board 1.00 pc. 1,500.00 1,500.00
grand total: 419,981.87

AIDA C. DUMAWAL
OWNER/PROPRIETOR
A.D. CONSTRUCTION
006326-2018-03
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Improvement of Multi-Purpose Building
Vilmar Homes, Calauag, Naga City

DETAILED ESTIMATES
Item 1 Construction Safety and Health
Est. Qty. 1.00 ls

1.00 ls Construction Safety and Health @ 3,390.00 3,390.00

TOTAL DIRECT COST 3,390.00


PLUS MARK-UPS 607.00
TOTAL ITEM COST 3,997.00
UNIT COST 3,997.00

ITEM 2 Formworks and Scaffoldings


Est. Qty. 1.00 lot
I. Materials
2.00 kgs CW Nails @ 80.00 160.00
3.00 pcs Plywood Marine 1/4 @ 475.00 1,425.00
200.00 bdft Coco Lumber Formworks @ 25.00 5,000.00
Cost of Materials: 6,585.00
Labor: 1,975.50

TOTAL DIRECT COST 8,560.50


PLUS MARK-UPS 1,534.90
TOTAL ITEM COST 10,095.40
UNIT COST 10,095.40

ITEM 3 Concrete Works


Est. Qty. 7.81 cu.m
I. Materials
71.00 bags Pozzolan Cement @ 245.00 17,395.00
4.00 kgs Tie Wire #16 @ 83.00 332.00
8.00 cu.m Gi Crushed Gravel @ 978.00 7,824.00
4.00 cu.m Albay Sand @ 578.00 2,312.00
2.00 pcs Hacksaw Blade @ 73.00 146.00
67.00 pcs RSB 10mm x 6m @ 178.00 11,926.00
25.00 pcs RSB 16mm x 6m @ 363.00 9,075.00
Cost Of Materials: 49,010.00
Labor: 14,703.00
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 2,500.00/ day 5,000.00
for 2 days
III. Others
5.86 cum Cost of Excavation @ 180.00 1,054.80

TOTAL DIRECT COST 69,767.80


PLUS MARK-UPS 12,509.38
TOTAL ITEM COST 82,277.18
UNIT COST 10,534.85

ITEM 4 Masonry Works


Est. Qty. 31.44 sq.m
I. Materials
37.00 bags Pozzolan Cement @ 245.00 9,065.00
393.00 pcs chB 4" @ 12.00 4,716.00
1.00 kgs Tie Wire #16 @ 84.00 84.00
2.00 cum Albay Sand @ 578.00 1,156.00
1.00 pcs Hacksaw Blade @ 70.00 70.00
23.00 pcs RSB 10mm x 6m @ 178.00 4,094.00
Cost Of Materials: 19,185.00
Labor: 5,755.50
III. Others
5.86 cum Cost of Excavation @ 180.00 1,054.80

TOTAL DIRECT COST 24,940.50


PLUS MARK-UPS 4,465.65
TOTAL ITEM COST 29,406.15
UNIT COST 935.31

ITEM 5 Steel Works


Est. Qty. 1.00 lot
I. Materials
15.00 kl Welding rod @ 84.00 1,260.00
40.00 pcs Angle bar @ 978.00 39,120.00
73.00 pcs Square bar @ 145.00 10,585.00
2.00 unit Acetylene @ 598.00 1,196.00
2.00 pcs Grinding disk @ 164.00 328.00
96.00 pcs Expansion Bolt @ 27.00 2,592.00
15.00 pcs Angle Bar 3/16 x 1 @ 243.00 3,645.00
3.00 pcs 2x6x2mm C-Purlins @ 995.00 2,985.00
12.00 pcs Fabricated Hinges @ 130.00 1,560.00
9.00 pcs C Purlins 2 x 4 x 1.3 mm @ 640.00 5,760.00
6.00 pcs Pillow Block 1 1/2 @ 990.00 5,940.00
Cost Of Materials: 74,971.00
Labor: 22,491.30
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Welding Machine @ 750.00/ day 3,750.00
for 5 days
TOTAL DIRECT COST 101,212.30
PLUS MARK-UPS 18,147.37
TOTAL ITEM COST 119,359.67
UNIT COST 119,359.67

ITEM 6 Roofing Works


Est. Qty. 70.00 sq.m
I. Materials
1.00 box Blind Rivets @ 645.00 645.00
2.00 tbs Rubber Sealant Silicone @ 395.00 790.00
500.00 pcs Tekscrew Steel 12 x 65mm w/ neo @ 2.50 1,250.00
2.00 pcs Pre Painted Gi Ridge roll @ 415.00 830.00
3.00 pcs Pre Painted End Flashing @ 415.00 1,245.00
14.00 pcs Hardi fascia Board 12mm x 10 x 8 @ 325.00 4,550.00
12.00 pcs GI Roofing Sheet, corrugated GA #26 x 12 @ 617.00 7,404.00
Cost Of Materials: 16,714.00
Labor: 5,014.20

TOTAL DIRECT COST 21,728.20


PLUS MARK-UPS 3,896.00
TOTAL ITEM COST 25,624.20
UNIT COST 366.06

Item 7 Ceiling Works


Est. Qty. 38.72 lot

1.00 kgs Concrete Nails @ 90.00 90.00


2.00 kgs CW Nails @ 80.00 160.00
15.00 pcs Marine Plywwod 1/4 @ 478.00 7,170.00
160.00 bdft Good lumber @ 55.00 8,800.00
Cost Of Materials: 16,220.00
Labor: 4,866.00
TOTAL DIRECT COST 21,086.00
PLUS MARK-UPS 3,780.76
TOTAL ITEM COST 24,866.76
UNIT COST 642.22

Item 8 Down spout/ Catch Basin


Est. Qty. 4.00 units

7.00 bags Pozzolan Cement @ 245.00 1,715.00


45.00 pcs CHB 4" @ 12.00 540.00
1.00 kgs Tie Wire#16 @ 84.00 84.00
0.50 cum GI Crushed Gravel @ 978.00 489.00
0.50 cum Albay Sand @ 578.00 289.00
8.00 pcs PCV Pipes 4Ø x 10 @ 519.00 4,152.00
6.00 pcs PVC Pipes 3Ø x 10 @ 447.00 2,682.00
4.00 pcs PVC 4Ø x 90 deg. Elbow @ 52.00 208.00
8.00 pcs PVC 3Ø x 90 deg. Elbow @ 50.00 400.00
4.00 pcs PVC Coupling 4Ø @ 60.00 240.00
4.00 pcs PVC Coupling 3Ø @ 34.00 136.00
2.00 pcs Solvent Cement @ 178.00 356.00
12.00 pcs PVC Clamp @ 25.00 300.00
Cost Of Materials: 11,591.00
Labor: 3,477.30
II. Others
1.00 cum Cost of Excavation @ 180.00 180.00

TOTAL DIRECT COST 15,248.30


PLUS MARK-UPS 2,734.02
TOTAL ITEM COST 17,982.32
UNIT COST 4,495.58

Item 9 Electrical Works


Est. Qty. 25.00 outlet

3.00 pcs RSC Pipes 32mm @ 900.00 2,700.00


13.00 pcs Utility Box @ 29.00 377.00
1.00 pcs Plate & Switch 1 gang @ 119.00 119.00
2.00 pcs Plate & Switch 3 gang @ 190.00 380.00
16.00 pcs Junction Box @ 29.00 464.00
1.00 pcs Panel Board @ 1,195.00 1,195.00
1.00 pcs Entrance Cap @ 68.00 68.00
3.00 pcs Ceiling fan @ 1,490.00 4,470.00
12.00 pcs 20mm Adaptor @ 16.00 192.00
1.00 pair 30A, CB, 2P, Bolt-on @ 390.00 390.00
54.00 pcs PVC Pipe 20mmØ @ 78.00 4,212.00
4.00 pcs PVC Pipe 25mmØ @ 118.00 472.00
18.00 pcs UPVC Long Sweep Elbow 20mmØ @ 18.00 324.00
7.00 set Duplex Convenient Outlet Universal @ 178.00 1,246.00
2.00 can Solvent Cement @ 178.00 356.00
8.00 pcs Electrical Tape @ 33.00 264.00
20.00 m THHN/THWN Wire 5.50mm sqr @ 55.00 1,100.00
9.00 pcs 8 watts Pinlight @ 440.00 3,960.00
2.00 box THHN/THWN Wire 2.0 mm sqr @ 2,398.00 4,796.00
1.00 box THHN/THWN Wire 3.5 mm sqr @ 3,598.00 3,598.00
1.00 pair 20A Circuit Breaker @ 348.00 348.00
1.00 pair 15A Circuit Breaker @ 348.00 348.00
1.00 pcs Secondary Bracket w/ Insulator @ 463.00 463.00
3.00 pcs PVC Clamp @ 23.00 69.00
1.00 pcs Grounding Rod 5/8 @ 1,598.00 1,598.00
1.00 set Circuit Breaker 2P 60A @ 964.00 964.00
30.00 m 22.00 sq.m THHN/THWN @ 129.00 3,870.00
Cost Of Materials: 38,343.00
Labor: 11,502.90

TOTAL DIRECT COST 49,845.90


PLUS MARK-UPS 9,533.35
TOTAL ITEM COST 59,379.25
UNIT COST 2,375.17

ITEM 10 Painting Works


Est. Qty. 317.14 sq.m
I. Materials
4.00 pcs Paint Brush @ 74.00 296.00
1.00 pcs Paint Roller with tray @ 149.00 149.00
4.00 gal Paint Remover @ 371.00 1,484.00
2.00 pcs Steel Brush @ 64.00 128.00
1.00 ltr Acry color @ 149.00 149.00
1.00 ltr Tinting Color @ 148.00 148.00
1.00 gals Rust Converter @ 428.00 428.00
4.00 gals Epoxy Primer w/ catalyst @ 1,198.00 4,792.00
4.00 gals Latex Semi Gloss @ 618.00 2,472.00
2.00 gals Paint Thinner @ 318.00 636.00
8.00 gals BS Flat latex @ 605.00 4,840.00
5.00 gals BS Flat wall Enamel @ 680.00 3,400.00
4.00 gals Roof Paint @ 848.00 3,392.00
1.00 qrts Polituff Hardener @ 188.00 188.00
1.00 gal Polituff Body Filler @ 650.00 650.00
12.00 pcs Sand Paper @ 17.00 204.00
4.00 gal Quick Dry Enamel @ 645.00 2,580.00
4.00 pcs Spatula @ 30.00 120.00
Cost Of Materials: 26,056.00
Labor: 7,816.80

TOTAL DIRECT COST 33,872.80


PLUS MARK-UPS 6,074.15
TOTAL ITEM COST 39,946.95
UNIT COST 125.96

Item 11 Demolition
Est. Qty. 1.00 lot

4.00 ls Add'l labor cost for demolition @ 2,490.00 9,960.00

TOTAL DIRECT COST 9,960.00


PLUS MARK-UPS 1,785.83
TOTAL ITEM COST 11,745.83
UNIT COST 11,745.83

ITEM 12 Sign Board

1.00 pc. Sign Board @ 1,372.00 1,372.00

TOTAL DIRECT COST 1,372.00


PLUS MARK-UPS 228.00
TOTAL ITEM COST 1,600.00
UNIT COST 1,600.00

S U M MAR Y O F E ST I MAT E S

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Construction Safety and Health 1.00 ls 3,997.00 3,997.00


2 Formworks and Scaffoldings 1.00 lot 10,095.40 10,095.40
3 Concrete Works 7.81 cu.m 10,534.85 82,277.18
4 Masonry Works 31.44 sq.m 935.31 29,406.15
5 Steel Works 1.00 lot 119,359.67 119,359.67
6 Roofing Works 70.00 lot 366.06 25,624.20
7 Ceiling Works 38.72 units 642.22 24,866.76
8 Down spout/ Catch Basin 4.00 units 4,495.58 17,982.32
9 Electrical Works 25.00 outlet 2,375.17 59,379.25
10 Painting Works 317.14 sq.m 125.96 39,946.95
11 Demolition 1.00 lot 11,745.83 11,745.83
12 Sign Board 1.00 pc. 1,600.00 1,600.00
grand total: 426,280.71

RENATO S. DELOVINO
OWNER/PROPRIETOR
R.S. DELOVINO BUILDERS AND SUPPLIES
006326-2018-03
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Improvement of Multi-Purpose Building
Vilmar Homes, Calauag, Naga City

DETAILED ESTIMATES
Item 1 Construction Safety and Health
Est. Qty. 1.00 ls

1.00 ls Construction Safety and Health @ 3,360.00 3,360.00

TOTAL DIRECT COST 3,360.00


PLUS MARK-UPS 602.45
TOTAL ITEM COST 3,962.45
UNIT COST 3,962.45

ITEM 2 Formworks and Scaffoldings


Est. Qty. 1.00 lot
I. Materials
2.00 kgs CW Nails @ 79.00 158.00
3.00 pcs Plywood Marine 1/4 @ 472.00 1,416.00
200.00 bdft Coco Lumber Formworks @ 25.00 5,000.00
Cost of Materials: 6,574.00
Labor: 1,972.20

TOTAL DIRECT COST 8,546.20


PLUS MARK-UPS 1,532.33
TOTAL ITEM COST 10,078.53
UNIT COST 10,078.53

ITEM 3 Concrete Works


Est. Qty. 7.81 cu.m
I. Materials
71.00 bags Pozzolan Cement @ 245.00 17,395.00
4.00 kgs Tie Wire #16 @ 82.00 328.00
8.00 cu.m Gi Crushed Gravel @ 977.00 7,816.00
4.00 cu.m Albay Sand @ 577.00 2,308.00
2.00 pcs Hacksaw Blade @ 72.00 144.00
67.00 pcs RSB 10mm x 6m @ 177.00 11,859.00
25.00 pcs RSB 16mm x 6m @ 362.00 9,050.00
Cost Of Materials: 48,900.00
Labor: 14,670.00
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 2,500.00/ day 5,000.00
for 2 days
III. Others
5.86 cum Cost of Excavation @ 180.00 1,054.80

TOTAL DIRECT COST 69,624.80


PLUS MARK-UPS 12,483.76
TOTAL ITEM COST 82,108.56
UNIT COST 10,513.26

ITEM 4 Masonry Works


Est. Qty. 31.44 sq.m
I. Materials
37.00 bags Pozzolan Cement @ 245.00 9,065.00
393.00 pcs chB 4" @ 12.00 4,716.00
1.00 kgs Tie Wire #16 @ 82.00 82.00
2.00 cum Albay Sand @ 577.00 1,154.00
1.00 pcs Hacksaw Blade @ 687.00 687.00
23.00 pcs RSB 10mm x 6m @ 177.00 4,071.00
Cost Of Materials: 19,775.00
Labor: 5,932.50
III. Others
5.86 cum Cost of Excavation @ 180.00 1,054.80

TOTAL DIRECT COST 25,707.50


PLUS MARK-UPS 4,609.46
TOTAL ITEM COST 30,316.96
UNIT COST 964.28

ITEM 5 Steel Works


Est. Qty. 1.00 lot
I. Materials
15.00 kl Welding rod @ 84.00 1,260.00
40.00 pcs Angle bar @ 974.00 38,960.00
73.00 pcs Square bar @ 145.00 10,585.00
2.00 unit Acetylene @ 597.00 1,194.00
2.00 pcs Grinding disk @ 162.00 324.00
96.00 pcs Expansion Bolt @ 27.00 2,592.00
15.00 pcs Angle Bar 3/16 x 1 @ 242.00 3,630.00
3.00 pcs 2x6x2mm C-Purlins @ 992.00 2,976.00
12.00 pcs Fabricated Hinges @ 130.00 1,560.00
9.00 pcs C Purlins 2 x 4 x 1.3 mm @ 637.00 5,733.00
6.00 pcs Pillow Block 1 1/2 @ 987.00 5,922.00
Cost Of Materials: 74,736.00
Labor: 22,420.80
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Welding Machine @ 750.00/ day 3,750.00
for 5 days
TOTAL DIRECT COST 100,906.80
PLUS MARK-UPS 18,093.20
TOTAL ITEM COST 119,000.00
UNIT COST 119,000.00

ITEM 6 Roofing Works


Est. Qty. 70.00 sq.m
I. Materials
1.00 box Blind Rivets @ 642.00 642.00
2.00 tbs Rubber Sealant Silicone @ 392.00 784.00
500.00 pcs Tekscrew Steel 12 x 65mm w/ neo @ 2.75 1,375.00
2.00 pcs Pre Painted Gi Ridge roll @ 412.00 824.00
3.00 pcs Pre Painted End Flashing @ 412.00 1,236.00
14.00 pcs Hardi fascia Board 12mm x 10 x 8 @ 322.00 4,508.00
12.00 pcs GI Roofing Sheet, corrugated GA #26 x 12 @ 617.00 7,404.00
Cost Of Materials: 16,773.00
Labor: 5,031.90

TOTAL DIRECT COST 21,804.90


PLUS MARK-UPS 3,909.60
TOTAL ITEM COST 25,714.50
UNIT COST 367.35

Item 7 Ceiling Works


Est. Qty. 38.72 lot

1.00 kgs Concrete Nails @ 87.00 87.00


2.00 kgs CW Nails @ 77.00 154.00
15.00 pcs Marine Plywwod 1/4 @ 477.00 7,155.00
160.00 bdft Good lumber @ 55.00 8,800.00
Cost Of Materials: 16,196.00
Labor: 4,858.80

TOTAL DIRECT COST 21,054.80


PLUS MARK-UPS 3,775.17
TOTAL ITEM COST 24,829.97
UNIT COST 641.27

Item 8 Down spout/ Catch Basin


Est. Qty. 4.00 units

7.00 bags Pozzolan Cement @ 245.00 1,715.00


45.00 pcs CHB 4" @ 12.00 540.00
1.00 kgs Tie Wire#16 @ 82.00 82.00
0.50 cum GI Crushed Gravel @ 974.00 487.00
0.50 cum Albay Sand @ 576.00 288.00
8.00 pcs PCV Pipes 4Ø x 10 @ 515.00 4,120.00
6.00 pcs PVC Pipes 3Ø x 10 @ 446.00 2,676.00
4.00 pcs PVC 4Ø x 90 deg. Elbow @ 52.00 208.00
8.00 pcs PVC 3Ø x 90 deg. Elbow @ 52.00 416.00
4.00 pcs PVC Coupling 4Ø @ 65.00 260.00
4.00 pcs PVC Coupling 3Ø @ 32.00 128.00
2.00 pcs Solvent Cement @ 177.00 354.00
12.00 pcs PVC Clamp @ 26.00 312.00
Cost Of Materials: 11,586.00
Labor: 3,475.80
II. Others
1.00 cum Cost of Excavation @ 180.00 180.00

TOTAL DIRECT COST 15,241.80


PLUS MARK-UPS 2,732.84
TOTAL ITEM COST 17,974.64
UNIT COST 4,493.66

Item 9 Electrical Works


Est. Qty. 25.00 outlet

3.00 pcs RSC Pipes 32mm @ 892.00 2,676.00


13.00 pcs Utility Box @ 30.00 390.00
1.00 pcs Plate & Switch 1 gang @ 120.00 120.00
2.00 pcs Plate & Switch 3 gang @ 187.00 374.00
16.00 pcs Junction Box @ 27.00 432.00
1.00 pcs Panel Board @ 1,192.00 1,192.00
1.00 pcs Entrance Cap @ 67.00 67.00
3.00 pcs Ceiling fan @ 1,482.00 4,446.00
12.00 pcs 20mm Adaptor @ 17.00 204.00
1.00 pair 30A, CB, 2P, Bolt-on @ 387.00 387.00
54.00 pcs PVC Pipe 20mmØ @ 77.00 4,158.00
4.00 pcs PVC Pipe 25mmØ @ 117.00 468.00
18.00 pcs UPVC Long Sweep Elbow 20mmØ @ 17.00 306.00
7.00 set Duplex Convenient Outlet Universal @ 176.00 1,232.00
2.00 can Solvent Cement @ 176.00 352.00
8.00 pcs Electrical Tape @ 32.00 256.00
20.00 m THHN/THWN Wire 5.50mm sqr @ 52.00 1,040.00
9.00 pcs 8 watts Pinlight @ 437.00 3,933.00
2.00 box THHN/THWN Wire 2.0 mm sqr @ 2,395.00 4,790.00
1.00 box THHN/THWN Wire 3.5 mm sqr @ 3,595.00 3,595.00
1.00 pair 20A Circuit Breaker @ 348.00 348.00
1.00 pair 15A Circuit Breaker @ 348.00 348.00
1.00 pcs Secondary Bracket w/ Insulator @ 465.00 465.00
3.00 pcs PVC Clamp @ 23.00 69.00
1.00 pcs Grounding Rod 5/8 @ 1,600.00 1,600.00
1.00 set Circuit Breaker 2P 60A @ 970.00 970.00
30.00 m 22.00 sq.m THHN/THWN @ 130.00 3,900.00
Cost Of Materials: 38,118.00
Labor: 11,435.40

TOTAL DIRECT COST 49,553.40


PLUS MARK-UPS 8,884.85
TOTAL ITEM COST 58,438.25
UNIT COST 2,337.53

ITEM 10 Painting Works


Est. Qty. 317.14 sq.m
I. Materials
4.00 pcs Paint Brush @ 72.00 288.00
1.00 pcs Paint Roller with tray @ 147.00 147.00
4.00 gal Paint Remover @ 372.00 1,488.00
2.00 pcs Steel Brush @ 62.00 124.00
1.00 ltr Acry color @ 147.00 147.00
1.00 ltr Tinting Color @ 147.00 147.00
1.00 gals Rust Converter @ 430.00 430.00
4.00 gals Epoxy Primer w/ catalyst @ 1,197.00 4,788.00
4.00 gals Latex Semi Gloss @ 617.00 2,468.00
2.00 gals Paint Thinner @ 317.00 634.00
8.00 gals BS Flat latex @ 605.00 4,840.00
5.00 gals BS Flat wall Enamel @ 680.00 3,400.00
4.00 gals Roof Paint @ 850.00 3,400.00
1.00 qrts Polituff Hardener @ 190.00 190.00
1.00 gal Polituff Body Filler @ 650.00 650.00
12.00 pcs Sand Paper @ 15.00 180.00
4.00 gal Quick Dry Enamel @ 645.00 2,580.00
4.00 pcs Spatula @ 32.00 128.00
Cost Of Materials: 26,029.00
Labor: 7,808.70

TOTAL DIRECT COST 33,837.70


PLUS MARK-UPS 6,068.03
TOTAL ITEM COST 39,905.73
UNIT COST 125.83

Item 11 Demolition
Est. Qty. 1.00 lot

4.00 ls Add'l labor cost for demolition @ 2,480.00 9,920.00

TOTAL DIRECT COST 9,920.00


PLUS MARK-UPS 1,778.66
TOTAL ITEM COST 11,698.66
UNIT COST 11,698.66

ITEM 12 Sign Board

1.00 pc. Sign Board @ 1,472.00 1,472.00

TOTAL DIRECT COST 1,472.00


PLUS MARK-UPS 228.00
TOTAL ITEM COST 1,700.00
UNIT COST 1,700.00

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Construction Safety and Health 1.00 ls 3,962.45 3,962.45


2 Formworks and Scaffoldings 1.00 lot 10,078.53 10,078.53
3 Concrete Works 7.81 cu.m 10,513.26 82,108.56
4 Masonry Works 31.44 sq.m 964.28 30,316.96
5 Steel Works 1.00 lot 119,000.00 119,000.00
6 Roofing Works 70.00 lot 367.35 25,714.50
7 Ceiling Works 38.72 units 641.27 24,829.97
8 Down spout/ Catch Basin 4.00 units 4,493.66 17,974.64
9 Electrical Works 25.00 outlet 2,337.53 58,438.25
10 Painting Works 317.14 sq.m 125.83 39,905.73
11 Demolition 1.00 lot 11,698.66 11,698.66
12 Sign Board 1.00 pc. 1,700.00 1,700.00
grand total: 425,728.25

NOLASCO ERNESTO P. CASTILLO


OWNER/PROPRIETOR
NOLCAST CONSTRUCTION AND SUPPLY
006537-2019-01
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Fencing
San Rafael ES, Cararayan, Naga City

DETAILED ESTIMATES
Item 1 Clearing and Grubbing
Est. Qty. 96.00 sq.m

96.00 sqm Clearing and Grubbing @ 40.00 3,840.00

TOTAL DIRECT COST 3,840.00


PLUS MARK-UPS 688.32
TOTAL ITEM COST 4,528.32
UNIT COST 47.17

ITEM 2 Earthworks
Est. Qty. 60.00 cu.m

60.00 cu.m Cost of Excavation @ 243.00 14,580.00

TOTAL DIRECT COST 14,580.00


PLUS MARK-UPS 2,614.20
TOTAL ITEM COST 17,194.20
UNIT COST 286.57

ITEM 3 Concrete Works


Est. Qty. 45.00 cu.m
I. Materials
402.00 bags Portland Cement @ 248.00 99,696.00
53.00 kgs Tie Wire #16 @ 83.00 4,399.00
45.00 cu.m Crushed Gravel GI @ 1,148.00 51,660.00
23.00 cu.m Albay Sand @ 645 14,835.00
175.00 pcs RSB 10mm x 6m @ 178.00 31,150.00
291.00 pcs RSB 12mm x 6m @ 218.00 63,438.00
62.00 pcs RSB 16mm x 6m @ 378.00 23,436.00
48.00 pcs Bamboo poles Guhi @ 118.00 5,664.00
Cost Of Materials: 294,278.00
Labor: 102,997.30

TOTAL DIRECT COST 397,275.30


PLUS MARK-UPS 71,231.40
TOTAL ITEM COST 468,506.70
UNIT COST 10,411.26

ITEM 4 Masonry Works


Est. Qty. 115.20 sq.m
I. Materials
196.00 bag Portland Cement @ 248.00 48,608.00
1,512.00 pcs CHB 4" @ 14.00 21,168.00
9.00 kgs Tie Wire #16 @ 80.00 720.00
11.00 cum Albay Sand @ 645.00 7,095.00
87.00 pcs RSB 12mm x 6.0m @ 219.00 19,053.00
9.00 pcs RC Pipes 12" or 300m @ 548.00 4,932.00
Cost Of Materials: 101,576.00
Labor: 35,551.60

TOTAL DIRECT COST 137,127.60


PLUS MARK-UPS 24,586.44
TOTAL ITEM COST 161,714.04
UNIT COST 1,403.77

ITEM 5 Construction Safety and Health


Est. Qty. 48.00 ln.m
I. Materials
1.00 ls Construction Safety and Health @ 1,680.00 1,680.00
48.00 ln.n Fabrication of Safety Protectors @ 80.00 3,840.00
and warning signs

TOTAL DIRECT COST 5,520.00


PLUS MARK-UPS 989.76
TOTAL ITEM COST 6,509.76
UNIT COST 135.62

ITEM 6 Sign Board

1.00 pc. Sign Board @ 1,372.00 1,372.00

TOTAL DIRECT COST 1,372.00


PLUS MARK-UPS 228.00
TOTAL ITEM COST 1,600.00
UNIT COST 1,600.00

S U M MARY O F E STI MATE S

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Clearing and Grubbing 96.00 sq.m 47.17 4,528.32


2 Earthworks 60.00 cu.m 286.57 17,194.20
3 Concrete Works 45.00 cu.m 10,411.26 468,506.70
4 Masonry Works 115.20 sq.m 1,403.77 161,714.04
5 Construction Safety and Health 48.00 ln.m 135.62 6,509.76
6 Sign Board 1.00 pc. 1,600.00 1,600.00
grand total: 660,053.02

RENATO S. DELOVINO
OWNER/PROPRIETOR
R.S. DELOVINO BUILDERS AND SUPPLIES
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Fencing
San Rafael ES, Cararayan, Naga City

DETAILED ESTIMATES
Item 1 Clearing and Grubbing
Est. Qty. 96.00 sq.m

96.00 sqm Clearing and Grubbing @ 38.00 3,648.00

TOTAL DIRECT COST 3,648.00


PLUS MARK-UPS 672.00
TOTAL ITEM COST 4,320.00
UNIT COST 45.00

ITEM 2 Earthworks
Est. Qty. 60.00 cu.m

60.00 cu.m Cost of Excavation @ 240.00 14,400.00

TOTAL DIRECT COST 14,400.00


PLUS MARK-UPS 2,580.00
TOTAL ITEM COST 16,980.00
UNIT COST 283.00

ITEM 3 Concrete Works


Est. Qty. 45.00 cu.m
I. Materials
402.00 bags Portland Cement @ 246.00 98,892.00
53.00 kgs Tie Wire #16 @ 82.00 4,346.00
45.00 cu.m Crushed Gravel GI @ 1,147.00 51,615.00
23.00 cu.m Albay Sand @ 643.00 14,789.00
175.00 pcs RSB 10mm x 6m @ 177.00 30,975.00
291.00 pcs RSB 12mm x 6m @ 216.00 62,856.00
62.00 pcs RSB 16mm x 6m @ 377.00 23,374.00
48.00 pcs Bamboo poles Guhi @ 117.00 5,616.00
Cost Of Materials: 292,463.00
Labor: 102,362.05

TOTAL DIRECT COST 394,825.05


PLUS MARK-UPS 70,789.95
TOTAL ITEM COST 465,615.00
UNIT COST 10,347.00

ITEM 4 Masonry Works


Est. Qty. 115.20 sq.m
I. Materials
196.00 bag Portland Cement @ 247.00 48,412.00
1,512.00 pcs CHB 4" @ 13.50 20,412.00
9.00 kgs Tie Wire #16 @ 78.00 702.00
11.00 cum Albay Sand @ 640.00 7,040.00
87.00 pcs RSB 12mm x 6.0m @ 218.00 18,966.00
9.00 pcs RC Pipes 12" or 300m @ 545.00 4,905.00
Cost Of Materials: 100,437.00
Labor: 35,152.95

TOTAL DIRECT COST 135,589.95


PLUS MARK-UPS 24,307.65
TOTAL ITEM COST 159,897.60
UNIT COST 1,388.00

ITEM 5 Construction Safety and Health


Est. Qty. 48.00 ln.m
I. Materials
1.00 ls Construction Safety and Health @ 1,670.00 1,670.00
48.00 ln.n Fabrication of Safety Protectors @ 80.00 3,840.00
and warning signs

TOTAL DIRECT COST 5,510.00


PLUS MARK-UPS 970.00
TOTAL ITEM COST 6,480.00
UNIT COST 135.00

ITEM 6 Sign Board

1.00 pc. Sign Board @ 1,272.00 1,272.00

TOTAL DIRECT COST 1,272.00


PLUS MARK-UPS 228.00
TOTAL ITEM COST 1,500.00
UNIT COST 1,500.00

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Clearing and Grubbing 96.00 sq.m 45.00 4,320.00


2 Earthworks 60.00 cu.m 283.00 16,980.00
3 Concrete Works 45.00 cu.m 10,347.00 465,615.00
4 Masonry Works 115.20 sq.m 1,388.00 159,897.60
5 Construction Safety and Health 48.00 ln.m 135.00 6,480.00
6 Sign Board 1.00 pc. 1,500.00 1,500.00
grand total: 654,792.60

AIDA C. DUMAWAL
OWNER/PROPRIETOR
A.D. CONSTRUCTION
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Fencing
San Rafael ES, Cararayan, Naga City

DETAILED ESTIMATES
Item 1 Clearing and Grubbing
Est. Qty. 96.00 sq.m

96.00 sqm Clearing and Grubbing @ 43.00 4,128.00

TOTAL DIRECT COST 4,128.00


PLUS MARK-UPS 740.16
TOTAL ITEM COST 4,868.16
UNIT COST 50.71

ITEM 2 Earthworks
Est. Qty. 60.00 cu.m

60.00 cu.m Cost of Excavation @ 245.00 14,700.00

TOTAL DIRECT COST 14,700.00


PLUS MARK-UPS 2,635.80
TOTAL ITEM COST 17,335.80
UNIT COST 288.93

ITEM 3 Concrete Works


Est. Qty. 45.00 cu.m
I. Materials
402.00 bags Portland Cement @ 248.00 99,696.00
53.00 kgs Tie Wire #16 @ 85.00 4,505.00
45.00 cu.m Crushed Gravel GI @ 1,150.00 51,750.00
23.00 cu.m Albay Sand @ 645.00 14,835.00
175.00 pcs RSB 10mm x 6m @ 178.00 31,150.00
291.00 pcs RSB 12mm x 6m @ 217.00 63,147.00
62.00 pcs RSB 16mm x 6m @ 379.00 23,498.00
48.00 pcs Bamboo poles Guhi @ 120.00 5,760.00
Cost Of Materials: 294,341.00
Labor: 103,019.35

TOTAL DIRECT COST 397,360.35


PLUS MARK-UPS 71,246.70
TOTAL ITEM COST 468,607.05
UNIT COST 10,413.49

ITEM 4 Masonry Works


Est. Qty. 115.20 sq.m
I. Materials
196.00 bag Portland Cement @ 248.00 48,608.00
1,512.00 pcs CHB 4" @ 14.00 21,168.00
9.00 kgs Tie Wire #16 @ 80.00 720.00
11.00 cum Albay Sand @ 643.00 7,073.00
87.00 pcs RSB 12mm x 6.0m @ 220.00 19,140.00
9.00 pcs RC Pipes 12" or 300m @ 550.00 4,950.00
Cost Of Materials: 101,659.00
Labor: 35,580.65

TOTAL DIRECT COST 137,239.65


PLUS MARK-UPS 24,607.13
TOTAL ITEM COST 161,846.78
UNIT COST 1,404.92

ITEM 5 Construction Safety and Health


Est. Qty. 48.00 ln.m
I. Materials
1.00 ls Construction Safety and Health @ 1,675.00 1,675.00
48.00 ln.n Fabrication of Safety Protectors @ 85.00 4,080.00
and warning signs

TOTAL DIRECT COST 5,755.00


PLUS MARK-UPS 1,031.72
TOTAL ITEM COST 6,786.72
UNIT COST 141.39

ITEM 6 Sign Board

1.00 pc. Sign Board @ 1,472.00 1,472.00

TOTAL DIRECT COST 1,472.00


PLUS MARK-UPS 228.00
TOTAL ITEM COST 1,700.00
UNIT COST 1,700.00

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Clearing and Grubbing 96.00 sq.m 50.71 4,868.16


2 Earthworks 60.00 cu.m 288.93 17,335.80
3 Concrete Works 45.00 cu.m 10,413.49 468,607.05
4 Masonry Works 115.20 sq.m 1,404.92 161,846.78
5 Construction Safety and Health 48.00 ln.m 141.39 6,786.72
6 Sign Board 1.00 pc. 1,700.00 1,700.00
grand total: 661,144.51

NOLASCO ERNESTO P. CASTILLO


OWNER/PROPRIETOR
NOLCAST CONSTRUCTION AND SUPPLY
006329-0000-00
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Drainage
Emerald St. Calauag, Naga City

DETAILED ESTIMATES
ITEM 1 Excavation
Est. Qty. 150.50 cu.m
I. Others
215.00 sq.m Clearing and Grubbing @ 43.00 9,245.00
150.50 cu.m Cost of Excavation @ 248.00 37,324.00
150.50 cu.m Dispossal of Excavated Materials @ 208.00 31,304.00
cost: 77,873.00

TOTAL DIRECT COST 77,873.00


PLUS MARK-UPS 13,932.00
TOTAL ITEM COST 91,805.00
UNIT COST 610.00

ITEM 2 CHB Covered Drainage


Est. Qty. 215.00 mtrs
I. Materials
1,009.00 bags Portland Cement @ 247.50 249,727.50
3,951.00 pcs CHB 6" @ 18.00 71,118.00
53.00 kgs Tie wire #16 @ 80.00 4,240.00
54.00 cu.m Gravel Crushed 3/4 @ 1,195.00 64,530.00
57.00 cu.m Albay Sand @ 575.00 32,775.00
27.00 pcs Hacksaw Blade @ 72.00 1,944.00
1,045.00 pcs RSB 12mm x 6.0m @ 219.50 229,377.50
Cost Of Materials: 653,712.00
Labor: 196,113.60
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ day 7,000.00
for 7 days

TOTAL DIRECT COST 856,825.60


PLUS MARK-UPS 153,674.40
TOTAL ITEM COST 1,010,500.00
UNIT COST 4,700.00

ITEM 3 Formworks and Scaffoldings


Est. Qty. 1.00 ls
I. Materials
30.00 pcs Marine Plywood 1/4 @ 478.00 14,340.00
10.00 kl Asst. CW Nails @ 75.00 750.00
190.00 bdf Formworks Coco Lumber @ 21.00 3,990.00
Cost of materials: 19,080.00
Labor: 5,724.00

TOTAL DIRECT COST 24,804.00


PLUS MARK-UPS 4,447.00
TOTAL ITEM COST 29,251.00
UNIT COST 29,251.00

ITEM 4 Gutter
Est. Qty. 12.90 cu.m
I. Materials
117.00 bag Portland Cement @ 246.00 28,782.00
7.00 cu.m Gravel Crushed 3/4 @ 1,190.00 8,330.00
13.00 cu.m Albay Sand @ 570.00 7,410.00
Cost Of Materials: 44,522.00
Labor: 13,356.60
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,000.00/ day 1,000.00
for 1 day

TOTAL DIRECT COST 58,878.60


PLUS MARK-UPS 10,523.40
TOTAL ITEM COST 69,402.00
UNIT COST 5,380.00
ITEM 5 Fabrication And Installation of Inlets
Est. Qty. 44.00 units
I. Materials
4.00 pcs Paint Brush 2" @ 36.00 144.00
5.00 kls Welding Rod @ 123.00 615.00
11.00 pcs Angle Bar 2x2x1/4 @ 1,495.00 16,445.00
11.00 pcs Flat Bar 1x3/16 @ 330.00 3,630.00
1.00 gal Red Oxide @ 490.00 490.00
Cost Of Materials: 21,324.00
Labor: 6,397.20

TOTAL DIRECT COST 27,721.20


PLUS MARK-UPS 4,970.80
TOTAL ITEM COST 32,692.00
UNIT COST 743.00

ITEM 6 Sign Board

1.00 pc. Sign Board @ 1,122.00 1,122.00

TOTAL DIRECT COST 1,122.00


PLUS MARK-UPS 228.00
TOTAL ITEM COST 1,350.00
UNIT COST 1,350.00

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Excavation 150.50 cu.m 610.00 91,805.00


2 CHB Covered Drainage 215.00 m 4,700.00 1,010,500.00
3 Formworks and Scaffoldings 1.00 ls 29,251.00 29,251.00
4 Gutter 12.90 cu.m 5,380.00 69,402.00
5 Fabrication And Installation of Inlets 44.00 units 743.00 32,692.00
6 Sign Board 1.00 pc. 1,350.00 1,350.00
grand total: 1,235,000.00

AIDA .C DUMAWAL
OWNER
A.D. CONSTRUCTION
006329-0000-00
BILL OF MATERIALS AND COST EST
Proposed Drainage
Emerald St. Calauag, Nag

DETAILED ESTIMATE
ITEM 1 Excavation
Est. Qty.
I. Others
215.00 sq.m Clearing and Grubbing
150.50 cu.m Cost of Excavation
150.50 cu.m Dispossal of Excavated Materials

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 2 CHB Covered Drainage


Est. Qty.
I. Materials
1,009.00 bags Portland Cement
3,951.00 pcs CHB 6"
53.00 kgs Tie wire #16
54.00 cu.m Gravel Crushed 3/4
57.00 cu.m Albay Sand
27.00 pcs Hacksaw Blade
1,045.00 pcs RSB 12mm x 6.0m

II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)


1.00 unit Concrete Mixer

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 3 Formworks and Scaffoldings


Est. Qty.
I. Materials
30.00 pcs Marine Plywood 1/4
10.00 kl Asst. CW Nails
190.00 bdf Formworks Coco Lumber

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 4 Gutter
Est. Qty.
I. Materials
117.00 bag Portland Cement
7.00 cu.m Gravel Crushed 3/4
13.00 cu.m Albay Sand

II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)


1.00 unit Concrete Mixer
TOTAL DIRECT COST
PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 5 Fabrication And Installation of Inlets


Est. Qty.
I. Materials
4.00 pcs Paint Brush 2"
5.00 kls Welding Rod
11.00 pcs Angle Bar 2x2x1/4
11.00 pcs Flat Bar 1x3/16
1.00 gal Red Oxide

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 6 Sign Board

1.00 pc. Sign Board

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST
SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION

1 Excavation
2 CHB Covered Drainage
3 Formworks and Scaffoldings
4 Gutter
5 Fabrication And Installation of Inlets
6 Sign Board

AIDA .C DUMAWAL
OWNER
A.D. CONSTRUCTION
006329-0000-00
OF MATERIALS AND COST ESTIMATES OF THE
Proposed Drainage
Emerald St. Calauag, Naga City

DETAILED ESTIMATES

150.50 cu.m

@ 25.00
@ 200.00
@ 180.00
cost:

215.00 mtrs

@ 230.00
@ 13.00
@ 68.00
@ 1,150.00
@ 545.00
@ 50.00
@ 210.00
Cost Of Materials:
Labor:
el, oil & lubricants:)
@ 800.00/ day
for 7 days

1.00 ls

@ 420.00
@ 60.00
@ 15.00
Cost of materials:
Labor:

12.90 cu.m

@ 230.00
@ 1,150.00
@ 550.00
Cost Of Materials:
Labor:
el, oil & lubricants:)
@ 800.00/ day
for 1 day

44.00 units

@ 23.00
@ 100.00
@ 1,330.00
@ 300.00
@ 410.00
Cost Of Materials:
Labor:

@ 772.00
MARY OF ESTIMATES

QTY. UNIT UNIT COST

150.50 cu.m 490.00


215.00 m 4,151.42
1.00 ls 23,659.00
12.90 cu.m 4,885.18
44.00 units 634.27
1.00 pc. 1,000.00
grand total:
5,375.00
30,100.00
27,090.00
62,565.00

62,565.00
11,180.00
73,745.00
490.00

232,070.00
51,363.00
3,604.00
62,100.00
31,065.00
1,350.00
219,450.00
601,002.00
150,250.50
5,600.00

756,852.50
135,703.50
892,556.00
4,151.42

12,600.00
600.00
2,850.00
16,050.00
4,012.50

20,062.50
3,596.50
23,659.00
23,659.00

26,910.00
8,050.00
7,150.00
42,110.00
10,527.50

800.00
53,437.50
9,581.34
63,018.84
4,885.18

92.00
500.00
14,630.00
3,300.00
410.00
18,932.00
4,733.00

23,665.00
4,243.00
27,908.00
634.27

772.00

772.00
228.00
1,000.00
1,000.00
TOTAL

73,745.00
892,556.00
23,659.00
63,018.84
27,908.00
1,000.00
1,081,886.84
006341-2018-02
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Drainage and Road Widening
Side of NPS, Ateneo Avenue, Bagumbayan Sur, Naga City

DETAILED ESTIMATES
ITEM 1 Demolition
Est. Qty. 197.00 cu.m

197.00 cu.m Cost of Demolition @ 3,450.00 679,650.00

TOTAL DIRECT COST 679,650.00


PLUS MARK-UPS 121,746.00
TOTAL ITEM COST 801,396.00
UNIT COST 4,068.00

ITEM 2 Excavation
Est. Qty. 400.00 cu.m

400.00 cu.m Cost of excavation @ 170.00 68,000.00

TOTAL DIRECT COST 68,000.00


PLUS MARK-UPS 12,000.00
TOTAL ITEM COST 80,000.00
UNIT COST 200.00

ITEM 3 Dispossal of Excess Materials


Est. Qty. 400.00 cu.m

400.00 cu.m Dispossal of Excess Materials @ 140.00 56,000.00

TOTAL DIRECT COST 56,000.00


PLUS MARK-UPS 10,000.00
TOTAL ITEM COST 66,000.00
UNIT COST 165.00

ITEM 4 Cross Drainage


Est. Qty. 26.00 ln.m
I. Materials
248.00 bags Portland Cement @ 240.00 59,520.00
240.00 pcs RSB 12mmØ x 6.0m @ 210.00 50,400.00
195.00 pcs RSB 16mmØ x 6.0m @ 350.00 68,250.00
16.00 pcs Marine Plywood 1/4 @ 580.00 9,280.00
14.00 cu.m Albay Sand @ 550.00 7,700.00
800.00 bd.f Coco Lumber @ 13.00 10,400.00
35.00 kls Tie Wire @ 60.00 2,100.00
28.00 cu.m Crushed Gravel 3/4 @ 1,130.00 31,640.00
Cost Of Materials: 239,290.00
Labor: 71,787.00
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 800.00/day 3,200.00
for 4 days

TOTAL DIRECT COST 314,277.00


PLUS MARK-UPS 56,327.00
TOTAL ITEM COST 370,604.00
UNIT COST 14,254.00

ITEM 5 Drainage Box Type


Est. Qty. 238.00 ln.m
I. Materials
1,069.00 bags Portland Cement @ 240.00 256,560.00
30.00 kls Welding Rod @ 80.00 2,400.00
61.00 pcs RSB 10mmØ x 6.0m @ 160.00 9,760.00
1,135.00 pcs RSB 12mmØ x 6.0m @ 200.00 227,000.00
31.00 pc. Angle Bar 1 1/2x 1 1/2 x 6mm @ 1,030.00 31,930.00
28.00 pcs Marine Plywood 1/4 @ 550.00 15,400.00
69.00 cu.m Albay Sand @ 550.00 37,950.00
1,600.00 bd.f Coco Lumber @ 13.00 20,800.00
95.00 kls Tie Wire @ 70.00 6,650.00
3,960.00 pcs Chb 6" @ 15.00 59,400.00
58.00 cu.m Crushed Gravel 3/4 @ 1,130.00 65,540.00
12.00 pcs Flat Bar 1/4 x 1 x 6m @ 600.00 7,200.00
106.00 pcs Angle Bar (2x2x6mm) @ 1,200.00 127,200.00
Cost Of Materials: 867,790.00
Labor: 260,337.00
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 800.00/day 9,600.00
for 12 days
1.00 unit Welding Machine @ 800.00/day 9,600.00
for 12 days
TOTAL DIRECT COST 1,147,327.00
PLUS MARK-UPS 205,703.00
TOTAL ITEM COST 1,353,030.00
UNIT COST 5,685.00

Item 6 Road Widening


Est. Qty. 82.56 cu.m

743.00 bags Portland Cement @ 240.00 178,320.00


40.00 gal Gloss Latex Boysen @ 460.00 18,400.00
20.00 pcs RSB 12mmØ x 6.0m @ 210.00 4,200.00
1.00 drums Hot Asphalt @ 5,700.00 5,700.00
42.00 cu.m Albay Sand @ 560.00 23,520.00
480.00 bd.f Coco Lumber @ 13.00 6,240.00
83.00 cu.m G-1 Crushed Gravel @ 980.00 81,340.00
Cost of Materials: 317,720.00
Labor: 53,496.00
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 800.00/day 8,000.00
for 10 days
1.00 unit Plate Compactor @ 2,400.00/ day 36,000.00
for 15 day
TOTAL DIRECT COST 415,216.00
PLUS MARK-UPS 74,447.36
TOTAL ITEM COST 489,663.36
UNIT COST 5,931.00

ITEM 7 Reblocking
Est. Qty. 13.50 cu.m
I. Materials
122.00 bags Portland Cement @ 240.00 29,280.00
5.00 gal Gloss Latex Boysen @ 460.00 2,300.00
5.00 pcs RSB (12mmØ x 6.0m) @ 200.00 1,000.00
7.00 cum Albay Sand @ 550.00 3,850.00
256.00 bd.f Coco Lumber @ 13.00 3,328.00
14.00 cum G-1 Crushed Gravel @ 950.00 13,300.00
Cost of Materials: 53,058.00
Labor: 15,917.40
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 800.00/day 1,600.00
for 2 days
1.00 unit Plate Compactor @ 2,400.00/ day 4,800.00
for 2 days
TOTAL DIRECT COST 75,375.40
PLUS MARK-UPS 13,508.60
TOTAL ITEM COST 88,884.00
UNIT COST 6,584.00

ITEM 8 Road Gutter


Est. Qty. 6.00 cu.m

51.00 bags Pozzolan Cement @ 240.00 12,240.00


3.00 cu.m Albay Sand @ 560.00 1,680.00
6.00 cu.m Crushed Gravel 3/4 @ 1,140.00 6,840.00
Cost of Materials: 20,760.00
Labor: 6,228.00

TOTAL DIRECT COST 26,988.00


PLUS MARK-UPS 4,836.00
TOTAL ITEM COST 31,824.00
UNIT COST 5,304.00

ITEM 9 Cutting Uprooting of Trees


Est. Qty. 15.00 units

15.00 pcs Uprooting/Cutting of Small Trees @ 800.00 12,000.00

TOTAL DIRECT COST 12,000.00


PLUS MARK-UPS 2,145.00
TOTAL ITEM COST 14,145.00
UNIT COST 943.00

ITEM 10 Construction Safety and Health


Est. Qty. 6.00 mo.

6.00 mo. Const. Safety and Health @ 1,600.00 9,600.00

TOTAL DIRECT COST 9,600.00


PLUS MARK-UPS 1,716.00
TOTAL ITEM COST 11,316.00
UNIT COST 1,886.00

ITEM 11 Sign Board

1.00 pc. Sign Board @ 1,272.00 1,272.00

TOTAL DIRECT COST 1,272.00


PLUS MARK-UPS 215.64
TOTAL ITEM COST 1,487.64
UNIT COST 1,487.64

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Demolition 197.00 cu.m 4,068.00 801,396.00


2 Excavation 400.00 cu.m 200.00 80,000.00
3 Dispossal of Excess Materials 400.00 cu.m 165.00 66,000.00
4 Cross Drainage 26.00 ln.m 14,254.00 370,604.00
5 Drainage Box Type 238.00 ln.m 5,685.00 1,353,030.00
6 Road Widening 82.56 cu.m 5,931.00 489,663.36
7 Reblocking 13.50 cu.m 6,584.00 88,884.00
8 Road Gutter 6.00 cu.m 5,304.00 31,824.00
9 Cutting Uprooting of Trees 15.00 units 943.00 14,145.00
10 Construction Safety and Health 6.00 mo. 1,886.00 11,316.00
11 Sign Board 1.00 pc. 1,487.64 1,487.64
grand total: 3,308,350.00

AIDA C. DUMAWAL
OWNER/PROPRIETOR
A.D. CONSTRUCTION
006274-2018-13
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Rehabilitation of Drainage
Jacob Putol Site 1, Bagumbayan Sur, Naga City

DETAILED ESTIMATES
ITEM 1 Demolition
Est. Qty. 25.83 cu.m
I. Others
25.83 cu.m Cost of Demolition @ 2,800.00 72,324.00

TOTAL DIRECT COST 72,324.00


PLUS MARK-UPS 12,966.66
TOTAL ITEM COST 85,290.66
UNIT COST 3,302.00

ITEM 2 Excavation
Est. Qty. 160.20 cu.m
I. Others
160.20 cu.m Cost of Excavation @ 200.00 32,040.00

TOTAL DIRECT COST 32,040.00


PLUS MARK-UPS 5,607.00
TOTAL ITEM COST 37,647.00
UNIT COST 235.00

ITEM 3 Cross Drainage


Est. Qty. 8.00 ln.m
I. Materials
51.00 bags Portland Cement @ 220.00 11,220.00
8.00 kgs Tie wire #16 @ 60.00 480.00
6.00 cu.m Crushed Gravel 3/4 @ 1,120.00 6,720.00
3.00 cu.m Albay Sand @ 530.00 1,590.00
8.00 pcs Hacksaw Blade @ 65.00 520.00
155.00 pcs RSB 12mmØ x 6.0m @ 180.00 27,900.00
2.00 pcs RSB 16mmØ x 6.0m @ 300.00 600.00
Cost Of Materials: 49,030.00
Labor: 14,709.00

TOTAL DIRECT COST 63,739.00


PLUS MARK-UPS 11,421.00
TOTAL ITEM COST 75,160.00
UNIT COST 9,395.00

ITEM 4 Drainage
Est. Qty. 170.00 ln.m
I. Materials
988.00 bags Portland Cement @ 220.00 217,360.00
4,017.00 pcs CHB 6" @ 11.00 44,187.00
39.00 kgs Tie wire #16 @ 60.00 2,340.00
43.00 cum Crushed Gravel 3/4 @ 1,120.00 48,160.00
56.00 cum Albay Sand @ 530.00 29,680.00
39.00 pcs Hacksaw Blade @ 60.00 2,340.00
764.00 pcs RSB 12mmØ x 6.0m @ 200.00 152,800.00
7.00 pcs PVC Pipe 2" @ 210.00 1,470.00
Cost Of Materials: 498,337.00
Labor: 149,501.10
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,800.00/ day 25,200.00
for 14 day

TOTAL DIRECT COST 673,038.10


PLUS MARK-UPS 120,521.90
TOTAL ITEM COST 793,560.00
UNIT COST 4,668.00

ITEM 5 Formworks and Scaffoldings


Est. Qty. 1.00 ls
I. Materials
8.00 pcs Marine Plywood 1/4 @ 430.00 3,440.00
736.00 bdft Formworks Coco Lumber @ 15.00 11,040.00
5.00 kls Asst. CW Nails @ 65.00 325.00
Cost of materials: 14,805.00
Labor: 4,441.50

TOTAL DIRECT COST 19,246.50


PLUS MARK-UPS 3,450.50
TOTAL ITEM COST 22,697.00
UNIT COST 22,697.00

ITEM 6 Construction Safety and Health


Est. Qty. 1.00 ls

1.00 ls Construction Safety and Health Program @ 1,400.00 1,400.00


178.00 ln.n Fabrication of Safety Protectors and Warning Signs @ 65.00 11,570.00
Cost Of Materials: 12,970.00

TOTAL DIRECT COST 12,970.00


PLUS MARK-UPS 2,325.00
TOTAL ITEM COST 15,295.00
UNIT COST 15,295.00

ITEM 7 Dispossal of Excess Materials


Est. Qty. 160.20 cu.m

160.20 cu.m Dispossal of Excess Materials @ 100.00 16,020.00

TOTAL DIRECT COST 16,020.00


PLUS MARK-UPS 2,723.40
TOTAL ITEM COST 18,743.40
UNIT COST 117.00

ITEM 8 Sign Board

1.00 pc. Sign Board @ 913.00 913.00

TOTAL DIRECT COST 913.00


PLUS MARK-UPS 228.59
TOTAL ITEM COST 1,141.59
UNIT COST 1,141.59

S U M MARY O F E S T I MAT E S

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Demolition 25.83 cu.m 3,302.00 85,290.66


2 Excavation 160.20 cu.m 235.00 37,647.00
3 Cross Drainage 8.00 ln.m 9,395.00 75,160.00
4 Drainage 170.00 ln.m 4,668.00 793,560.00
5 Formworks and Scaffoldings 1.00 ls 22,697.00 22,697.00
6 Construction Safety and Health 1.00 ls 15,295.00 15,295.00
7 Dispossal of Excess Materials 160.20 cu.m 117.00 18,743.40
8 Sign Board 1.00 pc. 1,141.59 1,141.59
grand total: 1,049,534.65

NOLASCO ERNESTO P. CASTILLO


OWNER
NOLCAST CONSTRUCTION AND SUPPLY
006550-2019-01
BILL OF MATERIALS AND COST ESTI
Proposed Pathwalk Topp
Zone 5, Tabuco, Naga C

DETAILED ESTIMATES

ITEM 1 Concrete Works


Est. Qty. 53.87
I. Materials
485.00 bags Portland Cement
54.00 cu.m Crushed Gravel 3/4
27.00 cu.m Albay Sand

II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)


1.00 unit Concrete Mixer

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 2 Aggregate Base Course


Est. Qty. 84.50
I. Materials
84.50 cum Item 201

II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)


1.00 unit Plate Compactor

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

Item 3 Hauling
Est. Qty. 1.00

1.00 ls Additional Labor for Hauling of Const. Material

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 4 Forms
Est. Qty. 1.00
I. Materials
18.00 pcs Plywood 1/4
1,344.00 bdft Cocolumber Formworks
15.00 kls Asst. CW Nails

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 5 Construction Safety and Health


Est. Qty. 2.00

2.00 mo Safety and Health

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 6 Sign Board

1.00 pc. Sign Board

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

S U M MARY O F E STI MATE S

ITEM NO. DESCRIPTION QTY.

1 Concrete Works 53.87


2 Aggregate Base Course 84.50
3 Hauling 1.00
4 Forms 1.00
5 Construction Safety and Health 2.00
6 Sign Board 1.00

RENATO S. DELOVINO
OWNER/PROPRIETOR
R.S. DELOVINO BUILDERS AND SUPPLIES
06550-2019-01
AND COST ESTIMATES OF THE
ed Pathwalk Topping
, Tabuco, Naga City

ILED ESTIMATES

cu.m

@ 245.00 118,825.00
@ 1,145.00 61,830.00
@ 590.00 15,930.00
Cost Of Materials: 196,585.00
Labor: 58,975.50
il & lubricants:)
@ 1,400.00/day 8,400.00
for 6 days

263,960.50
47,300.36
311,260.86
5,778.00

cu.m

@ 445.00 37,602.50
Cost Of Materials: 37,602.50
Labor: 11,280.75
il & lubricants:)
@ 2,300.00/day 4,600.00
for 2 days
53,483.25
9,553.75
63,037.00
746.00

ls

@ 13,000.00 13,000.00
Cost of Materials: 13,000.00

13,000.00
2,330.00
15,330.00
15,330.00

ls

@ 375.00 6,750.00
@ 20.00 26,880.00
@ 60.00 900.00
Cost of Materials: 34,530.00
Labor: 10,359.00

44,889.00
8,048.00
52,937.00
52,937.00

mo

@ 1,500.00 3,000.00
Cost of Materials: 3,000.00

3,000.00
537.00
3,537.00
1,768.50

@ 1,272.00 1,272.00

1,272.00
228.00
1,500.00
1,500.00

E STI MATE S

UNIT UNIT COST TOTAL

cu.m 5,778.00 311,260.86


cu.m 746.00 63,037.00
ls 15,330.00 15,330.00
ls 52,937.00 52,937.00
mo 1,768.50 3,537.00
pc. 1,500.00 1,500.00
grand total: 447,601.86
006550-2019-01
BILL OF MATERIALS AND COST ESTIMAT
Proposed Pathwalk Topping
Zone 5, Tabuco, Naga City

DETAILED ESTIMATES

ITEM 1 Concrete Works


Est. Qty. 53.87
I. Materials
485.00 bags Portland Cement
54.00 cu.m Crushed Gravel 3/4
27.00 cu.m Albay Sand

II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)


1.00 unit Concrete Mixer

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 2 Aggregate Base Course


Est. Qty. 84.50
I. Materials
84.50 cum Item 201

II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)


1.00 unit Plate Compactor
TOTAL DIRECT COST
PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

Item 3 Hauling
Est. Qty. 1.00

1.00 ls Additional Labor for Hauling of Const. Material

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 4 Forms
Est. Qty. 1.00
I. Materials
18.00 pcs Plywood 1/4
1,344.00 bdf Cocolumber Formworks
15.00 kls Asst. CW Nails

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 5 Construction Safety and Health


Est. Qty. 2.00

2.00 mo Safety and Health

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 6 Sign Board

1.00 pc. Sign Board

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION QTY.

1 Concrete Works 53.87


2 Aggregate Base Course 84.50
3 Hauling 1.00
4 Forms 1.00
5 Construction Safety and Health 2.00
6 Sign Board 1.00
AIDA C. DUMAWAL
OWNER/PROPRIETOR
A.D. CONSTRUCTION
06550-2019-01
S AND COST ESTIMATES OF THE
ed Pathwalk Topping
5, Tabuco, Naga City

AILED ESTIMATES

cu.m

@ 246.00 119,310.00
@ 1,146.00 61,884.00
@ 593.00 16,011.00
Cost Of Materials: 197,205.00
Labor: 59,161.50
lubricants:)
@ 1,430.00/day 8,580.00
for 6 days

264,946.50
47,504.89
312,451.39
5,800.10

cu.m

@ 446.00 37,687.00
Cost Of Materials: 37,687.00
Labor: 11,306.10
lubricants:)
@ 2,350.00/day 4,700.00
for 2 days
53,693.10
9,626.98
63,320.08
749.35

ls

@ 13,100.00 13,100.00
Cost of Materials: 13,100.00

13,100.00
2,348.83
15,448.83
15,448.83

ls

@ 376.00 6,768.00
@ 21.00 28,224.00
@ 63.00 945.00
Cost of Materials: 35,937.00
Labor: 10,781.10

46,718.10
8,376.55
55,094.65
55,094.65
mo

@ 1,600.00 3,200.00
Cost of Materials: 3,200.00

3,200.00
573.76
3,773.76
1,886.88

@ 1,372.00 1,372.00

1,372.00
228.00
1,600.00
1,600.00

ESTIMATES

UNIT UNIT COST TOTAL

cu.m 5,800.10 312,451.39


cu.m 749.35 63,320.08
ls 15,448.83 15,448.83
ls 55,094.65 55,094.65
mo 1,886.88 3,773.76
pc. 1,600.00 1,600.00
grand total: 451,688.71
006550-2019-01
BILL OF MATERIALS AND COST ESTIM
Proposed Pathwalk Toppin
Zone 5, Tabuco, Naga Cit

DETAILED ESTIMATES

ITEM 1 Concrete Works


Est. Qty. 53.87
I. Materials
485.00 bags Portland Cement
54.00 cu.m Crushed Gravel 3/4
27.00 cu.m Albay Sand

II. Equipments(Inclusive of Operator, fuel, oil & lubricant


1.00 unit Concrete Mixer

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 2 Aggregate Base Course


Est. Qty. 84.50
I. Materials
84.50 cum Item 201

II. Equipments(Inclusive of Operator, fuel, oil & lubricant


1.00 unit Plate Compactor
TOTAL DIRECT COST
PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

Item 3 Hauling
Est. Qty. 1.00

1.00 ls Additional Labor for Hauling of Const. Material

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 4 Forms
Est. Qty. 1.00
I. Materials
18.00 pcs Plywood 1/4
### bdft Cocolumber Formworks
15.00 kls Asst. CW Nails

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 5 Construction Safety and Health


Est. Qty. 2.00
2.00 mo Safety and Health

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 6 Sign Board

1.00 pc. Sign Board

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION QTY.

1 Concrete Works 53.87


2 Aggregate Base Course 84.50
3 Hauling 1.00
4 Forms 1.00
5 Construction Safety and Health 2.00
6 Sign Board 1.00

NOLASCO ERNESTO P. CASTILLO


OWNER/PROPRIETOR
NOLCAST CONSTRUCTION AND SUPPLY
6550-2019-01
AND COST ESTIMATES OF THE
d Pathwalk Topping
Tabuco, Naga City

ILED ESTIMATES

cu.m

@ 248.00 120,280.00
@ 1,148.00 61,992.00
@ 595.00 16,065.00
Cost Of Materials: 198,337.00
Labor: 59,501.10
uel, oil & lubricants:)
@ 1,480.00/day 8,880.00
for 6 days

266,718.10
47,822.36
314,540.46
5,838.88

cu.m

@ 448.00 37,856.00
Cost Of Materials: 37,856.00
Labor: 11,356.80
uel, oil & lubricants:)
@ 2,350.00/day 4,700.00
for 2 days
53,912.80
9,666.69
63,579.49
752.42

ls

t. Material @ 13,000.00 13,000.00


Cost of Materials: 13,000.00

13,000.00
2,330.00
15,330.00
15,330.00

ls

@ 375.00 6,750.00
@ 22.00 29,568.00
@ 60.00 900.00
Cost of Materials: 37,218.00
Labor: 11,165.40

48,383.40
8,675.14
57,058.54
57,058.54

mo
@ 1,650.00 3,300.00
Cost of Materials: 3,300.00

3,300.00
591.70
3,891.70
1,945.85

@ 1,472.00 1,472.00

1,472.00
228.00
1,700.00
1,700.00

ESTIMATES

UNIT UNIT COST TOTAL

cu.m 5,838.88 314,540.46


cu.m 752.42 63,579.49
ls 15,330.00 15,330.00
ls 57,058.54 57,058.54
mo 1,945.85 3,891.70
pc. 1,700.00 1,700.00
grand total: 456,100.19
006554-2019-01
BILL OF MATERIALS AND COST EST
Proposed Rehabilitation of Existi
Cacao and Canda St., Right Side, Clupa

DETAILED ESTIMATE
ITEM 1 Safety and Health Program
Est. Qty.
I. Others
3.00 mo Safety and Health Program

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 2 Demolition
Est. Qty.
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Jack Hammer with Compressor

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 3 Formworks
Est. Qty.
I. Materials
8.00 kgs CW Nails
15.00 pcs Marine Plywood 1/4
600.00 bd.f Formworks Coco Lumber
2.00 rolls Caution Tape

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 4 Excavation
Est. Qty.
188.00 cu.m Cost of excavation

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 5 Reinf. Concrete Box Culvert


Est. Qty.
I. Materials
733.00 bags Portland Cement
58.00 pcs PVC Pipes 3x10
80.00 kls Tie Wire #16
81.00 cu.m Crushed Gravel 3/4
40.00 cu.m Albay Sand
525.00 pcs 12mm dia. RSB
150.00 pcs 16mm RSB x 6.0m
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 6 Sign Board

1.00 pc. Sign Board

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION

1 Safety and Health Program


2 Demolition
3 Formworks
4 Excavation
5 Reinf. Concrete Box Culvert
6 Sign Board
AIDA C. DUMAWAL
OWNER
A.D. CONSTRUCTION
006554-2019-01
OF MATERIALS AND COST ESTIMATES OF THE
oposed Rehabilitation of Existing Drainage
d Canda St., Right Side, Clupa, Calauag, Naga City

DETAILED ESTIMATES

3.00 mo

@ 1,500.00
cost:

52.00 cu.m
el, oil & lubricants:)
@ 4,950.00/ day
for 6 days

1.00 lot

@ 80.00
@ 475.00
@ 24.00
@ 670.00
Cost of materials:
Labor:

26.00 cu.m
@ 175.00
Cost Of Materials:

215.00 ln.m

@ 247.00
@ 445.00
@ 75.00
@ 1,077.00
@ 597.00
@ 208.00
@ 378.00
Cost Of Materials:
Labor:

el, oil & lubricants:)


@ 1,500.00/ day
for 10 days

@ 1,272.00

MARY OF ESTIMATES

QTY. UNIT UNIT COST

3.00 mo 1,768.00
52.00 m 673.00
1.00 ls 36,035.00
26.00 cu.m 1,492.00
215.00 units 3,575.00
1.00 pc. 1,500.00
grand total:
4,500.00
4,500.00

4,500.00
804.00
5,304.00
1,768.00

29,700.00

29,700.00
5,296.00
34,996.00
673.00

640.00
7,125.00
14,400.00
1,340.00
23,505.00
7,051.50

30,556.50
5,478.50
36,035.00
36,035.00

32,900.00
32,900.00

32,900.00
5,892.00
38,792.00
1,492.00

181,051.00
25,810.00
6,000.00
87,237.00
23,880.00
109,200.00
56,700.00
489,878.00
146,963.40

15,000.00

651,841.40
116,783.60
768,625.00
3,575.00

1,272.00

1,272.00
228.00
1,500.00
1,500.00

TOTAL

5,304.00
34,996.00
36,035.00
38,792.00
768,625.00
1,500.00
885,252.00
006554-2019-01
BILL OF MATERIALS AND COST ES
Proposed Rehabilitation of Exis
Cacao and Canda St., Right Side, Clup

DETAILED ESTIMAT
ITEM 1 Safety and Health Program
Est. Qty.
I. Others
3.00 mo Safety and Health Program

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 2 Demolition
Est. Qty.
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Jack Hammer with Compressor

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 3 Formworks
Est. Qty.
I. Materials
8.00 kgs CW Nails
15.00 pcs Marine Plywood 1/4
600.00 bd.ft Formworks Coco Lumber
2.00 rolls Caution Tape

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 4 Excavation
Est. Qty.
188.00 cu.m Cost of excavation

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 5 Reinf. Concrete Box Culvert


Est. Qty.
I. Materials
733.00 bags Portland Cement
58.00 pcs PVC Pipes 3x10
80.00 kls Tie Wire #16
81.00 cu.m Crushed Gravel 3/4
40.00 cu.m Albay Sand
525.00 pcs 12mm dia. RSB
150.00 pcs 16mm RSB x 6.0m
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 6 Sign Board

1.00 pc. Sign Board

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

S U M MARY O F E STI MATE

ITEM NO. DESCRIPTION

1 Safety and Health Program


2 Demolition
3 Formworks
4 Excavation
5 Reinf. Concrete Box Culvert
6 Sign Board

RENATO S. DELOVINO
OWNER
R.S. DELOVINO BUILDERS AND SUPPLY
006554-2019-01
MATERIALS AND COST ESTIMATES OF THE
osed Rehabilitation of Existing Drainage
Canda St., Right Side, Clupa, Calauag, Naga City

DETAILED ESTIMATES

3.00 mo

@ 1,680.00
cost:

52.00 cu.m
fuel, oil & lubricants:)
@ 4,990.00/ day
for 6 days

1.00 lot

@ 84.00
@ 479.00
@ 24.00
@ 674.00
Cost of materials:
Labor:

26.00 cu.m
@ 178.00
Cost Of Materials:

215.00 ln.m

@ 247.00
@ 448.00
@ 78.00
@ 1,079.00
@ 598.00
@ 209.00
@ 379.00
Cost Of Materials:
Labor:
fuel, oil & lubricants:)
@ 1,500.00/ day
for 10 days

@ 1,372.00

ARY O F E STI MATE S

QTY. UNIT UNIT COST

3.00 mo 1,981.22
52.00 m 679.00
1.00 ls 36,188.58
26.00 cu.m 1,517.85
215.00 units 3,584.63
1.00 pc. 1,600.00
grand total:
5,040.00
5,040.00

5,040.00
903.66
5,943.66
1,981.22

29,940.00

29,940.00
5,368.00
35,308.00
679.00

672.00
7,185.00
14,400.00
1,348.00
23,605.00
7,081.50

30,686.50
5,502.08
36,188.58
36,188.58

33,464.00
33,464.00

33,464.00
6,000.10
39,464.10
1,517.85

181,051.00
25,984.00
6,240.00
87,399.00
23,920.00
109,725.00
56,850.00
491,169.00
147,350.70
15,000.00

653,519.70
117,175.75
770,695.45
3,584.63

1,372.00

1,372.00
228.00
1,600.00
1,600.00

TOTAL

5,943.66
35,308.00
36,188.58
39,464.10
770,695.45
1,600.00
889,199.79
006554-2019-01
BILL OF MATERIALS AND COST ES
Proposed Rehabilitation of Exi
Cacao and Canda St., Right Side, Clup

DETAILED ESTIMAT
ITEM 1 Safety and Health Program
Est. Qty.
I. Others
3.00 mo Safety and Health Program

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 2 Demolition
Est. Qty.
II. Equipments(Inclusive of Operator, fuel, oil & lubricant
1.00 unit Jack Hammer with Compressor

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 3 Formworks
Est. Qty.
I. Materials
8.00 kgs CW Nails
15.00 pcs Marine Plywood 1/4
600.00 bd.ft Formworks Coco Lumber
2.00 rolls Caution Tape

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 4 Excavation
Est. Qty.
188.00 cu.m Cost of excavation

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 5 Reinf. Concrete Box Culvert


Est. Qty.
I. Materials
733.00 bags Portland Cement
58.00 pcs PVC Pipes 3x10
80.00 kls Tie Wire #16
81.00 cu.m Crushed Gravel 3/4
40.00 cu.m Albay Sand
525.00 pcs 12mm dia. RSB
150.00 pcs 16mm RSB x 6.0m
II. Equipments(Inclusive of Operator, fuel, oil & lubricant
1.00 unit Concrete Mixer

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 6 Sign Board

1.00 pc. Sign Board

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

SUMMARY OF ESTIMAT

ITEM NO. DESCRIPTION

1 Safety and Health Program


2 Demolition
3 Formworks
4 Excavation
5 Reinf. Concrete Box Culvert
6 Sign Board

NOLASCO ERNESTO P. CASTILLO


OWNER
NOLCAST CONSTRUCTION AND SUPPLY
006554-2019-01
MATERIALS AND COST ESTIMATES OF THE
ed Rehabilitation of Existing Drainage
nda St., Right Side, Clupa, Calauag, Naga City

DETAILED ESTIMATES

3.00 mo

@ 1,690.00
cost:

52.00 cu.m
ator, fuel, oil & lubricants:)
@ 4,980.00/ day
for 6 days

1.00 lot

@ 84.00
@ 479.00
@ 25.00
@ 674.00
Cost of materials:
Labor:

26.00 cu.m
@ 179.00
Cost Of Materials:

215.00 ln.m

@ 248.00
@ 448.00
@ 78.00
@ 1,078.00
@ 598.00
@ 210.00
@ 380.00
Cost Of Materials:
Labor:
ator, fuel, oil & lubricants:)
@ 1,500.00/ day
for 10 days

@ 1,472.00

RY OF ESTIMATES

QTY. UNIT UNIT COST

3.00 mo 1,993.02
52.00 m 677.64
1.00 ls 37,084.85
26.00 cu.m 1,526.38
215.00 units 3,594.09
1.00 pc. 1,700.00
grand total:
5,070.00
5,070.00

5,070.00
909.06
5,979.06
1,993.02

29,880.00

29,880.00
5,357.28
35,237.28
677.64

672.00
7,185.00
15,000.00
1,348.00
24,205.00
7,261.50

31,466.50
5,618.35
37,084.85
37,084.85

33,652.00
33,652.00

33,652.00
6,033.88
39,685.88
1,526.38

181,784.00
25,984.00
6,240.00
87,318.00
23,920.00
110,250.00
57,000.00
492,496.00
147,748.80
15,000.00

655,244.80
117,484.55
772,729.35
3,594.09

1,472.00

1,472.00
228.00
1,700.00
1,700.00

TOTAL

5,979.06
35,237.28
37,084.85
39,685.88
772,729.35
1,700.00
892,416.42
006519-0000-00
BILL OF MATERIALS AND COST ES
Proposed Earthfilli
Bagong Silang (Poro), San Fel

DETAILED ESTIMAT
ITEM 1 Earthfilling
Est. Qty.
I. Others
253.00 cu.m Madrigal Sand

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 6 Sign Board

1.00 pc. Sign Board

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

SUMMARY OF ESTIMAT

ITEM NO. DESCRIPTION

1 Earthfilling
2 Sign Board
NOLASCO ERNESTO P. CASTILLO
OWNER
NOLCAST CONST. AND SUPPLY
006519-0000-00
MATERIALS AND COST ESTIMATES OF THE
Proposed Earthfilling
ng Silang (Poro), San Felipe, Naga City

DETAILED ESTIMATES

253.00 cu.m

@ 675.00
cost:

@ 1,272.00

RY OF ESTIMATES

QTY. UNIT UNIT COST

253.00 cu.m 796.00


1.00 pc. 1,500.00
grand total:
170,775.00
170,775.00

170,775.00
30,613.00
201,388.00
796.00

1,272.00

1,272.00
228.00
1,500.00
1,500.00

TOTAL

201,388.00
1,500.00
202,888.00
006519-0000-00
BILL OF MATERIALS AND COST EST
Proposed Earthfillin
Bagong Silang (Poro), San Felip

DETAILED ESTIMATE
ITEM 1 Earthfilling
Est. Qty.
I. Others
253.00 cu.m Madrigal Sand

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 6 Sign Board

1.00 pc. Sign Board

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION

1 Earthfilling
2 Sign Board
AIDA C. DUMAWAL
OWNER
A.D. CONSTRUCTION
006519-0000-00
OF MATERIALS AND COST ESTIMATES OF THE
Proposed Earthfilling
agong Silang (Poro), San Felipe, Naga City

DETAILED ESTIMATES

253.00 cu.m

@ 677.00
cost:

@ 1,372.00

MARY OF ESTIMATES

QTY. UNIT UNIT COST

253.00 cu.m 798.39


1.00 pc. 1,600.00
grand total:
171,281.00
171,281.00

171,281.00
30,711.67
201,992.67
798.39

1,372.00

1,372.00
228.00
1,600.00
1,600.00

TOTAL

201,992.67
1,600.00
203,592.67
006519-0000-00
BILL OF MATERIALS AND COST ES
Proposed Earthfillin
Bagong Silang (Poro), San Feli

DETAILED ESTIMAT
ITEM 1 Earthfilling
Est. Qty.
I. Others
253.00 cu.m Madrigal Sand

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

ITEM 6 Sign Board

1.00 pc. Sign Board

TOTAL DIRECT COST


PLUS MARK-UPS
TOTAL ITEM COST
UNIT COST

S U M MARY O F E STI MATE

ITEM NO. DESCRIPTION

1 Earthfilling
2 Sign Board
RENATO S. DELOVINO
OWNER
R.S. DELOVINO BUILDERS AND SUPPLIES
006519-0000-00
MATERIALS AND COST ESTIMATES OF THE
Proposed Earthfilling
ong Silang (Poro), San Felipe, Naga City

DETAILED ESTIMATES

253.00 cu.m

@ 679.00
cost:

@ 1,372.00

ARY O F E STI MATE S

QTY. UNIT UNIT COST

253.00 cu.m 800.74


1.00 pc. 1,600.00
grand total:
171,787.00
171,787.00

171,787.00
30,800.22
202,587.22
800.74

1,372.00

1,372.00
228.00
1,600.00
1,600.00

TOTAL

202,587.22
1,600.00
204,187.22
006682-2019-01
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Drainage
Temporo Dy St., Dayangdang, Naga City

DETAILED ESTIMATES
ITEM 1 Clearing and Grubbing
Est. Qty. 198.80 sq.m
I. Others
198.80 sq.m Clearing and Grubbing @ 35.00 6,958.00

TOTAL DIRECT COST 6,958.00


PLUS MARK-UPS 1,391.60
TOTAL ITEM COST 8,349.60
UNIT COST 42.00

ITEM 2 Excavation
Est. Qty. 133.06 cu.m

133.06 cu.m Cost f Excavation @ 200.00 26,612.00

TOTAL DIRECT COST 26,612.00


PLUS MARK-UPS 4,657.10
TOTAL ITEM COST 31,269.10
UNIT COST 235.00

ITEM 3 Demolition Works


Est. Qty. 9.15 cu.m

9.15 cu.m Cost of Demolition @ 2,300.00 21,045.00

TOTAL DIRECT COST 21,045.00


PLUS MARK-UPS 3,769.80
TOTAL ITEM COST 24,814.80
UNIT COST 2,712.00

ITEM 4 Drainage
Est. Qty. 106.00 ln.m
I. Materials
659.00 bags Portland Cement @ 240.00 158,160.00
### pcs CHB 6" @ 16.00 31,168.00
31.00 kgs Tie Wire #16 @ 70.00 2,170.00
20.00 cu.m Crushed Gravel 3/4 @ 1,200.00 24,000.00
38.00 cu.m Albay Sand @ 600.00 22,800.00
13.00 pcs Hacksaw Blade @ 60.00 780.00
603.00 pcs 12mm dia. X 6.0 RSB @ 200.00 120,600.00
Cost Of Materials: 359,678.00
Labor: 100,709.84

TOTAL DIRECT COST 460,387.84


PLUS MARK-UPS 82,544.16
TOTAL ITEM COST 542,932.00
UNIT COST 5,122.00

ITEM 5 Drainage
Est. Qty. 61.00 ln.m
I. Materials
328.00 bags Portland Cement @ 240.00 78,720.00
961.00 pcs CHB 6" @ 16.00 15,376.00
17.00 kgs Tie Wire #16 @ 70.00 1,190.00
10.00 cu.m Crushed Gravel 3/4 @ 1,200.00 12,000.00
20.00 cu.m Albay Sand @ 600.00 12,000.00
7.00 pcs Hacksaw Blade @ 60.00 420.00
334.00 pcs 12mm RSB x 6.0m @ 200.00 66,800.00
3.00 pcs PVC Pipe 2" @ 200.00 600.00
Cost Of Materials: 187,106.00
Labor: 52,389.68

TOTAL DIRECT COST 239,495.68


PLUS MARK-UPS 42,934.32
TOTAL ITEM COST 282,430.00
UNIT COST 4,630.00

ITEM 6 Formworks
Est. Qty. 167.00 ln.m
I. Materials
14.00 kls Asst. CW Nails @ 60.00 840.00
438.00 bdft Formworks Coco Lumber @ 18.00 7,884.00
58.00 pcs Plywood 1/4" @ 350.00 20,300.00
Cost Of Materials: 29,024.00
Labor: 8,126.72

TOTAL DIRECT COST 37,150.72


PLUS MARK-UPS 6,603.28
TOTAL ITEM COST 43,754.00
UNIT COST 262.00

ITEM 7 Dispossal of Excess Materials


Est. Qty. 133.06 cu.m

133.06 cu.m Dispossal of Excavated materials @ 205.00 27,277.30

TOTAL DIRECT COST 27,277.30


PLUS MARK-UPS 4,790.16
TOTAL ITEM COST 32,067.46
UNIT COST 241.00

ITEM 8 Sign Board

1.00 pc. Sign Board @ 1,173.00 1,173.00

TOTAL DIRECT COST 1,173.00


PLUS MARK-UPS 210.04
TOTAL ITEM COST 1,383.04
UNIT COST 1,383.04

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Clearing and Grubbing 198.80 sq.m 42.00 8,349.60


2 Excavation 133.06 cu.m 235.00 31,269.10
3 Demolition Works 9.15 cu.m 2,712.00 24,814.80
4 Drainage 106.00 ln.m 5,122.00 542,932.00
5 Drainage 61.00 ln.m 4,630.00 282,430.00
6 Formworks 167.00 ln.m 262.00 43,754.00
7 Dispossal of Excess Materials 133.06 cu.m 241.00 32,067.46
8 Sign Board 1.00 pc. 1,383.04 1,383.04
grand total: 967,000.00

NOLASCO ERNESTO P. CASTILLO


OWNER
NOLCAST CONSTRUCTION AND SUPPLY
006804-2019-01
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Drainage and Road Concreting
Upville Subdivision, Urban Poor, San Felipe, Naga City

DETAILED ESTIMATES
ITEM 1 Construction Safety and Health
Est. Qty. 1.00 ls
I. Others
3.00 mo. Construction Safety and Health @ 1,600.00 4,800.00

TOTAL DIRECT COST 4,800.00


PLUS MARK-UPS 860.00
TOTAL ITEM COST 5,660.00
UNIT COST 5,660.00

ITEM 2 Demolition
Est. Qty. 290.00 sq.m

290.00 sq.m Add'l labor cost for Demolition/ @ 88.00 25,520.00


Chipping Works

TOTAL DIRECT COST 25,520.00


PLUS MARK-UPS 4,350.00
TOTAL ITEM COST 29,870.00
UNIT COST 103.00

ITEM 3 Forms
Est. Qty. 1.00 lot

10.00 kgs CW Nails @ 82.00 820.00


30.00 pcs Plywood Marine 1/4" @ 475.00 14,250.00
500.00 bd.ft Formworks Coco Lumber @ 24.00 12,000.00
1.00 rolls Caution tape @ 670.00 670.00
Cost Of Materials: 27,740.00
Labor: 8,322.00

TOTAL DIRECT COST 36,062.00


PLUS MARK-UPS 6,479.00
TOTAL ITEM COST 42,541.00
UNIT COST 42,541.00

ITEM 4 Excavation
Est. Qty. 171.00 cu.m
I. Materials
171.00 cu.m Cost of Excavation @ 178.00 30,438.00

TOTAL DIRECT COST 30,438.00


PLUS MARK-UPS 5,472.00
TOTAL ITEM COST 35,910.00
UNIT COST 210.00

ITEM 5 Subgrade Preparation


Est. Qty. 186.00 sq.m
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Compactor @ 830.00/ day 9,960.00
for 12 days

TOTAL DIRECT COST 9,960.00


PLUS MARK-UPS 1,758.00
TOTAL ITEM COST 11,718.00
UNIT COST 63.00

ITEM 6 Aggregate Base Course


Est. Qty. 23.00 cu.m
I. Materials
23.00 cu.m Item 201 @ 470.00 10,810.00
Cost Of Materials: 10,810.00
Labor: 3,243.00
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Compactor @ 800.00/ day 2,400.00
for 3 days

TOTAL DIRECT COST 16,453.00


PLUS MARK-UPS 2,936.00
TOTAL ITEM COST 19,389.00
UNIT COST 843.00

ITEM 7 Portland Cement Concrete Pavement


Est. Qty. 37.12 cu.m
334.00 bags Portland Cement @ 248.00 82,832.00
37.00 cu.m G2 Crushed Gravel @ 1,145.00 42,365.00
19.00 cu.m Albay Sand @ 645.00 12,255.00
13.00 pcs RSB 16mm x 6m @ 375.00 4,875.00
30.00 lit Asphalt Sealant @ 60.00 1,800.00
Cost Of Materials: 144,127.00
Labor: 43,238.10
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,450.00/ day 7,250.00
for 5 days

TOTAL DIRECT COST 194,615.10


PLUS MARK-UPS 34,860.74
TOTAL ITEM COST 229,475.84
UNIT COST 6,182.00

ITEM 8 Drainage with cover


Est. Qty. 116.00 ln.m

564.00 bags Pozzolan Cement @ 241.00 135,924.00


60.00 kgs Tie Wire #16 @ 85.00 5,100.00
63.00 cu.m G1 Crushed Gravel @ 1,145.00 72,135.00
32.00 cu.m Albay SAnd @ 645.00 20,640.00
10.00 pcs Hacksaw Blade @ 70.00 700.00
360.00 pcs RSB 12mm x 6m @ 220.00 79,200.00
390.00 pcs RSB 16mm x 6m @ 380.00 148,200.00
28.00 pcs PVC Pipes 2" x 10 @ 310.00 8,680.00
Cost Of Materials: 470,579.00
Labor: 141,173.70
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,450.00/ day 14,500.00
for 10 days

TOTAL DIRECT COST 626,252.70


PLUS MARK-UPS 112,203.30
TOTAL ITEM COST 738,456.00
UNIT COST 6,366.00

ITEM 9 Sign Board

1.00 pc. Sign Board @ 1,272.00 1,272.00

TOTAL DIRECT COST 1,272.00


PLUS MARK-UPS 228.00
TOTAL ITEM COST 1,500.00
UNIT COST 1,500.00

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Construction Safety and Health 1.00 ls 5,660.00 5,660.00


2 Demolition 290.00 sq.m 103.00 29,870.00
3 Forms 1.00 lot 42,541.00 42,541.00
4 Excavation 171.00 cu.m 210.00 35,910.00
5 Subgrade Preparation 186.00 sq.m 63.00 11,718.00
6 Aggregate Base Course 23.00 cu.m 843.00 19,389.00
7 Portland Cement Concrete Pavement 37.12 cu.m 6,182.00 229,475.84
8 Drainage with cover 116.00 ln.m 6,366.00 738,456.00
9 Sign Board 1.00 pc. 1,500.00 1,500.00
grand total: 1,114,519.84

NOLASCO ERNESTO P. CASTILLO


OWNER
NOLCAST CONSTRUCTION AND SUPPLY
006846-2019-01
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Drainage
Diversion Road to Bicol River, Tabuco, Naga City

DETAILED ESTIMATES
ITEM 1 Construction Safety and Health
Est. Qty. 1.00 ls
I. Others
1.00 ls Construction Safety and Health @ 10,100.00 10,100.00

TOTAL DIRECT COST 10,100.00


PLUS MARK-UPS 1,810.00
TOTAL ITEM COST 11,910.00
UNIT COST 11,910.00

ITEM 2 Demolition/Chipping Works/Removal of Obstruction


Est. Qty. 25.44 cu.m

25.44 cu.m Cost of Demolition @ 3,480.00 88,531.20

TOTAL DIRECT COST 88,531.20


PLUS MARK-UPS 15,849.12
TOTAL ITEM COST 104,380.32
UNIT COST 4,103.00

ITEM 3 Excavation
Est. Qty. 1,188.00 cu.m

### cu.m Cost of Excavation @ 179.00 212,652.00

TOTAL DIRECT COST 212,652.00


PLUS MARK-UPS 38,016.00
TOTAL ITEM COST 250,668.00
UNIT COST 211.00

ITEM 4 Dispossal of Excess Materials


Est. Qty. 970.00 cu.m
I. Materials
970.00 cu.m Dispossal of Excess Materials @ 149.50 145,015.00

TOTAL DIRECT COST 145,015.00


PLUS MARK-UPS 26,190.00
TOTAL ITEM COST 171,205.00
UNIT COST 176.50

ITEM 5 Formworks
Est. Qty. 1.00 lot
I. Materials
60.00 kgs CW Nails @ 84.00 5,040.00
213.00 pcs Marine Plywood 1/4" @ 480.00 102,240.00
### bd.ft Formworks Coco lumber @ 25.00 66,250.00
Cost Of Materials: 173,530.00
Labor: 52,059.00

TOTAL DIRECT COST 225,589.00


PLUS MARK-UPS 40,448.00
TOTAL ITEM COST 266,037.00
UNIT COST 266,037.00

ITEM 6 Drainage With Cover


Est. Qty. 53.00 ln.m

520.00 bags Pozzolan Cement @ 245.00 127,400.00


80.00 kgs Tie Wire #16 @ 84.00 6,720.00
58.00 cu.m Crushed Gravel 3/4" @ 1,298.00 75,284.00
29.00 cu.m Albay Sand @ 654.00 18,966.00
3.00 kls Welding rod @ 84.00 252.00
1.00 pcs Paint brush @ 74.00 74.00
357.00 pcs RSB 12mm x 6m @ 220.00 78,540.00
380.00 pcs RSB 16mm x 6m @ 380.00 144,400.00
12.00 pcs PVC Pipes 2"x 10 @ 310.00 3,720.00
7.00 pcs PVC Pipes PNS 25mm @ 119.00 833.00
31.00 pcs Angle Bar 2x2x1/4 @ 1,265.00 39,215.00
2.00 lit Epoxy Primer w/ Catalyst @ 290.00 580.00
Cost Of Materials: 495,984.00
Labor: 148,795.20
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,500.00/ day 10,500.00
for 7 days
1.00 unit Welding Machine @ 950.00/ day 1,900.00
for 2 days

TOTAL DIRECT COST 657,179.20


PLUS MARK-UPS 117,786.80
TOTAL ITEM COST 774,966.00
UNIT COST 14,622.00

ITEM 7 Open Drainage


Est. Qty. 175.00 ln.m

### bags Pozzolan Cement @ 245.00 586,775.00


295.00 kgs Tie Wire #16 @ 85.00 25,075.00
266.00 cu.m Crushed Gravel @ 1,300.00 345,800.00
134.00 cu.m Albay Sand @ 650.00 87,100.00
110.00 pcs RSB 10mm x 6m @ 179.00 19,690.00
### pcs RSB 12mm x 6m @ 219.50 287,545.00
### pcs RSB 16mm x 6m @ 380.00 469,300.00
Cost Of Materials: 1,821,285.00
Labor: 546,385.50
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,500.00/ day 45,000.00
for 30 days

TOTAL DIRECT COST 2,412,670.50


PLUS MARK-UPS 432,479.50
TOTAL ITEM COST 2,845,150.00
UNIT COST 16,258.00

ITEM 8 Sign Board

1.00 pc. Sign Board @ 1,173.00 1,173.00

TOTAL DIRECT COST 1,173.00


PLUS MARK-UPS 210.04
TOTAL ITEM COST 1,383.04
UNIT COST 1,383.04

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Construction Safety and Health 1.00 ls 11,910.00 11,910.00


2 Demolition/Chipping Works/Removal of Obstr 25.44 cu.m 4,103.00 104,380.32
3 Excavation 1,188.00 cu.m 211.00 250,668.00
4 Dispossal of Excess Materials 970.00 cu.m 176.50 171,205.00
5 Formworks 1.00 lot 266,037.00 266,037.00
6 Drainage With Cover 53.00 ln.m 14,622.00 774,966.00
7 Open Drainage 175.00 ln.m 16,258.00 2,845,150.00
8 Sign Board 1.00 pc. 1,383.04 1,383.04
grand total: 4,425,699.36

NOLASCO ERNESTO P. CASTILLO


OWNER
NOLCAST CONSTRUCTION AND SUPPLY
006745-2019-01
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Children's Center
Brgy. Hall, Compound, Abella, Naga City

DETAILED ESTIMATES
Item 1 Demolition/Chipping Owrks/Removal of Obstruction
Est. Qty. 3.20 cu.m

3.20 cu.m Cost of Demolition @ 3,499.00 11,196.80

TOTAL DIRECT COST 11,196.80


PLUS MARK-UPS 2,007.20
TOTAL ITEM COST 13,204.00
UNIT COST 4,126.25

ITEM 2 Excavation
Est. Qty. 12.64 cu.m

12.64 cu.m Cost of Excavation @ 255.00 3,223.20

TOTAL DIRECT COST 3,223.20


PLUS MARK-UPS 577.91
TOTAL ITEM COST 3,801.11
UNIT COST 300.72

ITEM 3 Concrete Works


Est. Qty. 17.86 cu.m
I. Materials
163.00 bags Portland Cement @ 255.00 41,565.00
1.00 cu.m Boulders type A @ 850.00 850.00
240.00 pcs RSB 10mm x 6m @ 180.00 43,200.00
2.00 cu.m Ordinary Gravel @ 880.00 1,760.00
75.00 bags Add Mix ultra @ 50.00 3,750.00
16.00 cu.m Crushed Gravel 3/4 @ 1,150.00 18,400.00
3.00 rolls Tie Wire #16 @ 2,800.00 8,400.00
10.00 pcs Sandlfex @ 60.00 600.00
216.00 pcs RSB 16mm x 6m @ 245.00 52,920.00
195.00 pcs RSB 12mm x 6m @ 385.00 75,075.00
9.50 cu.m Albay Sand @ 700.00 6,650.00
Cost Of Materials: 253,170.00
Labor: 88,609.50
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Concrete Mixer @ 1,800.00/ day 7,200.00
for 4 days
TOTAL DIRECT COST 348,979.50
PLUS MARK-UPS 62,572.02
TOTAL ITEM COST 411,551.52
UNIT COST 23,043.20

ITEM 4 Masonry Works


Est. Qty. 62.11 sq.m
I. Materials
78.00 pcs RSB 10mm x 6m @ 180.00 14,040.00
700.00 pcs CHB 6" @ 20.00 14,000.00
45.00 bags Add Mix Ultra @ 50.00 2,250.00
140.00 pcs CHB 4" @ 15.00 2,100.00
2.00 pcs Sandflex @ 60.00 120.00
115.00 bags Cement @ 240.00 27,600.00
8.00 kls Tie Wire #16 @ 80.00 640.00
12.00 cu.m Albay Sand @ 700.00 8,400.00
Cost Of Materials: 69,150.00
Labor: 24,202.50

TOTAL DIRECT COST 93,352.50


PLUS MARK-UPS 16,738.10
TOTAL ITEM COST 110,090.60
UNIT COST 1,772.51

ITEM 5 Ceiling Works


Est. Qty. 61.20 sq.m
I. Materials
75.00 pcs Double Furring @ 230.00 17,250.00
25.00 pcs Carrying Channel @ 118.00 2,950.00
2.00 kls Concrete Nails @ 100.00 200.00
2,200.00 pcs Blind Rivets @ 2.00 4,400.00
100.00 pcs Furring Clip @ 6.00 600.00
24.00 pcs Hardilite 4 x 8 x3 @ 460.00 11,040.00
35.00 pcs Wall Angle @ 41.00 1,435.00
200.00 pcs Hardi Screw 3'4" @ 2.00 400.00
Cost Of Materials: 38,275.00
Labor: 13,396.25

TOTAL DIRECT COST 51,671.25


PLUS MARK-UPS 9,264.65
TOTAL ITEM COST 60,935.90
UNIT COST 995.68

ITEM 6 Formworks and Scaffoldings


Est. Qty. 1.00 ls
I. Materials
2,100.00 bd.f Formworks and Coco Lumber @ 25.00 52,500.00
40.00 pcs Marine Plywood @ 450.00 18,000.00
55.00 pcs Assorted CW Nails @ 85.00 4,675.00
Cost Of Materials: 75,175.00
Labor: 26,311.25

TOTAL DIRECT COST 101,486.25


PLUS MARK-UPS 18,196.48
TOTAL ITEM COST 119,682.73
UNIT COST 119,682.73

Item 7 Construction Safety and Health


Est. Qty. 4.00 mo.

4.00 mo. Safety and Health @ 1,800.00 7,200.00

TOTAL DIRECT COST 7,200.00


PLUS MARK-UPS 1,290.00
TOTAL ITEM COST 8,490.00
UNIT COST 2,122.50

Item 8 Electrical Works


Est. Qty. 116.28 sq.m

10.00 pcs 2 Gang Convenience outlet @ 185.00 1,850.00


2.00 pcs 3 Gang switch 2 plate @ 320.00 640.00
2.00 pc. Panel Board @ 1,200.00 2,400.00
1.00 m Wire Gutter @ 400.00 400.00
3.00 pcs 2 gang switch w/ plate @ 180.00 540.00
28.00 m 80mm THHN/THWN Wire @ 520.00 14,560.00
30.00 m THHN-THWN Wire 14.oomm @ 143.00 4,290.00
2.00 set CB 30AT 2 pole @ 340.00 680.00
1.00 set CB bolt on 150 AT 2P @ 3,120.00 3,120.00
35.00 pcs 2omm UPVC Conduit Type @ 85.00 2,975.00
4.00 pcs Ceiling Receptacle @ 45.00 180.00
2.00 set ACU outlet @ 360.00 720.00
1.00 box THHN Wire Allied 5.50mm @ 6,100.00 6,100.00
2.00 pcs CB 2P 40A @ 650.00 1,300.00
15.00 pcs Junction Box @ 40.00 600.00
3.50 box THHN Wire 2.0 sq.m @ 2,100.00 7,350.00
2.00 box THHN Wire 3.5 sq.m @ 3,800.00 7,600.00
2.00 pcs CB 15 amp @ 480.00 960.00
2.00 pcs 20 amp CB @ 480.00 960.00
25.00 pcs 25mm UPVC Rigid @ 115.00 2,875.00
4.00 pcs Led Buld 9w @ 275.00 1,100.00
80.00 m THHN/THWN 8 sqm @ 51.00 4,080.00
1.00 pcs RSC ELbow75mm @ 1,300.00 1,300.00
1.00 pcs RSC Pipes 75mm @ 1,800.00 1,800.00
1.00 pcs Entrance cap 75mm @ 480.00 480.00
13.00 set Pinlight with led bulb 9w @ 450.00 5,850.00
1.00 pcs CB 30A @ 506.00 506.00
1.00 pcs Secondary Bracket @ 250.00 250.00
17.00 pcs Utility Box @ 40.00 680.00
Cost Of Materials: 76,146.00
Labor: 26,651.10
II. Others
1.00 ls Addt'l labor for relocation @ 3,100.00 3,100.00

TOTAL DIRECT COST 105,897.10


PLUS MARK-UPS 18,987.35
TOTAL ITEM COST 124,884.45
UNIT COST 1,074.00

Item 9 Doors and Windows


Est. Qty. 12.90 sq.m
I. Materials
9.44 sq.m Window Grills @ 1,655.00 15,623.20
1.00 set Door Jamb @ 2,125.00 2,125.00
3.00 pcs Door Knob @ 985.00 2,955.00
1.00 set Flush Door .80 x 2.10 @ 3,500.00 3,500.00
2.00 set Panel Board with Jamb @ 9,800.00 19,600.00
6.00 box Loose Pin hinges @ 120.00 720.00
Cost Of Materials: 44,523.20
Labor: 15,583.12
II. Others
1.00 ls Addt'l labor for removal of Existing Door @ 850.00 850.00
3.84 sq.m Amuninum Framed Window @ 3,270.00 12,556.80
1.00 set 1.80 x 2.10 Awning @ 16,200.00 16,200.00
1.00 ls Addt'l Labor for removal of Existing Steel Windows @ 2,600.00 2,600.00

TOTAL DIRECT COST 92,313.12


PLUS MARK-UPS 16,551.74
TOTAL ITEM COST 108,864.86
UNIT COST 8,439.14

ITEM 10 Roofing Works


Est. Qty. 56.40 sq.m
I. Materials
550.00 pcs Teks Screw @ 2.00 1,100.00
4.00 pcs Flat Bar @ 225.00 900.00
6.00 pcs Sagrod 12mm Roofing @ 250.00 1,500.00
6.00 tube Silicon Sealant @ 180.00 1,080.00
4.00 pcs Screw Bolts @ 6.50 26.00
63.00 ln.m Pre painted Long Span Corr GI Sheet @ 350.00 22,050.00
12.00 pcs Pre Painted Wall Flashing @ 420.00 5,040.00
2.00 pcs Cutting disk 14" @ 255.00 510.00
5.00 pcs Tubular Pipe 50x150x2.00mm @ 1,800.00 9,000.00
2.00 pcs Sandflex @ 60.00 120.00
12.00 kls Welding Rod @ 165.00 1,980.00
300.00 pcs Blind Rivets @ 2.00 600.00
4.00 pcs Angle Bar 2x2x1/4 @ 1,500.00 6,000.00
1.00 pcs Sealant Gun @ 148.00 148.00
4.00 pcs Drill Bit 1/8 @ 65.00 260.00
3.00 pcs Tekscrew Socket @ 30.00 90.00
20.00 pcs 12mm x 3 Expansion Bolt @ 69.60 1,392.00
0.50 gal Vulcaseal @ 1,480.00 740.00
18.00 pcs c-Purlins 2 x 4 x 1.2 @ 642.00 11,556.00
1.00 pcs Drill Bit for Cement 3/8 @ 265.00 265.00
Cost Of Materials: 64,357.00
Labor: 22,524.95
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Welding Machine @ 1,500.00/ day 4,500.00
for 3 days
III. Others
1.00 ls Addt'l labor for removal/restoration of Existing Roof @ 5,000.00 5,000.00

TOTAL DIRECT COST 96,381.95


PLUS MARK-UPS 17,281.28
TOTAL ITEM COST 113,663.23
UNIT COST 2,015.31

ITEM 11 Railing
Est. Qty. 13.50 ln.m
I. Materials
0.50 gal Body Filler @ 475.00 237.50
23.00 pcs Square Bar 12mm @ 255.00 5,865.00
2.00 pcs GI Pipe s40 40mm dia @ 1,206.00 2,412.00
1.00 gal Epoxy Primer Paint w/ Catalyst @ 890.00 890.00
6.00 kls Welding Rod @ 165.00 990.00
2.00 pcs Paint Brush @ 124.00 248.00
3.00 bottle Lacquer Thinner @ 30.00 90.00
4.00 pcs GI Pipe 2 s40 @ 2,150.00 8,600.00
2.00 pcs Grinding Disk @ 175.00 350.00
1.00 pcs Cutting Disk 14" @ 840.00 840.00
Cost Of Materials: 20,522.50
Labor: 7,182.88
II. Equipments(Inclusive of Operator, fuel, oil & lubricants:)
1.00 unit Welding Machine @ 1,000.00/ day 3,000.00
for 3 days

TOTAL DIRECT COST 30,705.38


PLUS MARK-UPS 5,505.48
TOTAL ITEM COST 36,210.85
UNIT COST 2,682.29

ITEM 12 Painting Works


Est. Qty. 314.38 sq.m
I. Materials
4.00 gal Powe Mix @ 580.00 2,320.00
10.00 f Sanding Paper #100 @ 65.00 650.00
2.00 gal Epoxy Primer Paint w/ Catalyst @ 890.00 1,780.00
4.00 pcs Baby Roller @ 84.00 336.00
26.00 gal Semi Gloss Latex @ 942.50 24,505.00
8.00 gals Masonry Putty @ 565.00 4,520.00
13.00 gals Flat Latex @ 650.00 8,450.00
1.00 gals Flatwall Enamel @ 683.00 683.00
2.50 gals Quick Drying Enamel @ 755.00 1,887.50
0.50 gal Glazing Putty @ 700.00 350.00
4.00 pcs Paint Roller with tray @ 165.00 660.00
1.00 gal Paint Thinner @ 420.00 420.00
4.00 gals Body Filler @ 655.00 2,620.00
4.00 pcs Paint Brush @ 124.00 496.00
2.00 pcs Spatula @ 58.00 116.00
4.00 pcs Putty Knife @ 40.00 160.00
Cost Of Materials: 49,953.50
Labor: 14,986.05

TOTAL DIRECT COST 64,939.55


PLUS MARK-UPS 11,643.66
TOTAL ITEM COST 76,583.21
UNIT COST 243.60

Item 13 Down Spouts


Est. Qty. 4.00 units

10.00 pcs PVC Pipes 3' x 10 @ 450.00 4,500.00


8.00 pcs PVC Elbow 3x 90 @ 95.00 760.00
1.00 can Neltex 400 cc @ 265.00 265.00
Cost Of Materials: 5,525.00
Labor: 1,933.75

TOTAL DIRECT COST 7,458.75


PLUS MARK-UPS 1,337.35
TOTAL ITEM COST 8,796.10
UNIT COST 2,199.03

ITEM 14 Sign Board

1.00 pc. Sign Board @ 1,055.00 1,055.00

TOTAL DIRECT COST 1,055.00


PLUS MARK-UPS 186.44
TOTAL ITEM COST 1,241.44
UNIT COST 1,241.44

SUMMARY OF ESTIMATES
ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Demolition/Chipping Owrks/Removal of Obstruction 3.20 cu.m 4,126.25 13,204.00


2 Excavation 12.64 cu.m 300.72 3,801.11
3 Concrete Works 17.86 cu.m 23,043.20 411,551.52
4 Masonry Works 62.11 sq.m 1,772.51 110,090.60
5 Ceiling Works 61.20 sq.m 995.68 60,935.90
6 Formworks and Scaffoldings 1.00 mo. 119,682.73 119,682.73
7 Construction Safety and Health 4.00 sq.m 2,122.50 8,490.00
8 Electrical Works 116.28 sq.m 1,074.00 124,884.45
9 Doors and Windows 12.90 sq.m 8,439.14 108,864.86
10 Roofing Works 56.40 sq.m 2,015.31 113,663.23
11 Railing 13.50 ln.m 2,682.29 36,210.85
12 Painting Works 314.38 sq.m 243.60 76,583.21
13 Down Spouts 4.00 units 2,199.03 8,796.10
14 Sign Board 1.00 pc. 1,241.44 1,241.44
grand total: 1,198,000.00

NOLASCO ERNESTO P. CASTILLO


OWNER/PROPRIETOR
NOLCAST CONSTRUCTION AND SUPPLY
006866-0000-00
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Road Concreting
Zone 4, Pacol, Naga City

DETAILED ESTIMATES
ITEM 1 Excavation
Est. Qty. 130.00 cu.m

130.00 cu.m Cost of Excavation @ 250.00 32,500.00


130.00 cu.m Dispossal and Hauling of Excavated Materials @ 210.00 27,300.00

TOTAL DIRECT COST 59,800.00


PLUS MARK-UPS 10,722.00
TOTAL ITEM COST 70,522.00
UNIT COST 542.48

ITEM 2 Aggregate Base Course


Est. Qty. 65.00 cu.m

65.00 cu.m Item 201 @ 450.00 29,250.00


Cost Of Materials: 29,250.00
Labor: 8,190.00
II. Equipments
1.00 unit Road Roller @ 1, 050.00/hour 50,400.00
for 48 hours
TOTAL DIRECT COST 87,840.00
PLUS MARK-UPS 15,705.00
TOTAL ITEM COST 103,545.00
UNIT COST 1,593.00

ITEM 3 Portland Cement Concrete Pavement


Est. Qty. 130.00 cu.m
I. Materials
10.00 pcs Hacksaw Blade @ 60.00 600.00
6.00 kls CWN 3" @ 65.00 390.00
1,170.00 bags Portland Cement @ 249.50 291,915.00
130.00 cu.m Gravel 1" @ 1,065.00 138,450.00
142.00 pcs 2 x 8 x 12 Coco Lumber @ 263.00 37,346.00
28.00 pcs RSB 10mm @ 135.00 3,780.00
65.00 cu.m Albay Sand @ 680.00 44,200.00
Cost Of Materials: 516,681.00
Labor: 155,004.30
II. Equipments
1.00 unit Concrete Mixer @ 1, 000.00/day 24,000.00
for 24 days

TOTAL DIRECT COST 695,685.30


PLUS MARK-UPS 124,735.70
TOTAL ITEM COST 820,421.00
UNIT COST 6,310.93

ITEM 4 Sign Board

2.00 pc. Sign Board @ 1,200.00 2,400.00

TOTAL DIRECT COST 2,400.00


PLUS MARK-UPS 430.00
TOTAL ITEM COST 2,830.00
UNIT COST 1,415.00

S U M MAR Y O F E S T I MAT E S

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Excavation 130.00 cu.m 542.48 70,522.00


2 Aggregate Base Course 65.00 cu.m 1,593.00 103,545.00
3 Portland Cement Concrete Pavement 130.00 cu.m 6,310.93 820,421.00
4 Sign Board 2.00 pc. 1,415.00 2,830.00
grand total: 997,318.00

FRANCISCO A. IMPERIAL JR.


OWNER
TIOFILO CONSTRUCTION
006888-2019-01
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Road Concreting
Sitio Tiripon, Zone 7, Pacol, Naga City

DETAILED ESTIMATES
ITEM 1 Construction Safety and Health
Est. Qty. 1.00 ls

3.00 mo. Construction Safety and Health @ 1,680.00 5,040.00

TOTAL DIRECT COST 5,040.00


PLUS MARK-UPS 903.00
TOTAL ITEM COST 5,943.00
UNIT COST 5,943.00

ITEM 2 Formworks
Est. Qty. 1.00 lot

6.00 kgs Item 201 @ 80.00 480.00


556.00 bd.ft Formworks Coco Lumber @ 24.50 13,622.00
Cost Of Materials: 14,102.00
Labor: 4,230.60

TOTAL DIRECT COST 18,332.60


PLUS MARK-UPS 3,287.40
TOTAL ITEM COST 21,620.00
UNIT COST 21,620.00

ITEM 3 Subgrade Preparation


Est. Qty. 792.00 sq.m
II. Equipments
1.00 unit Compactor @ 830.00/day 11,620.00
for 14 days
III others
47.00 cu.m Construction Safety and Health @ 175.00 8,225.00

TOTAL DIRECT COST 19,845.00


PLUS MARK-UPS 3,915.00
TOTAL ITEM COST 23,760.00
UNIT COST 30.00

ITEM 4 Aggregate Base Course


Est. Qty. 69.00 cu.m
I. Materials
69.00 cu.m Item 201 @ 535.00 36,915.00
Cost Of Materials: 36,915.00
Labor: 9,228.75
II. Equipments
1.00 unit Compactor @ 830.00/day 5,810.00
for 7 days
III others
### bags Cost of Hauling @ 8.00 14,352.00

TOTAL DIRECT COST 66,305.75


PLUS MARK-UPS 11,871.25
TOTAL ITEM COST 78,177.00
UNIT COST 1,133.00

ITEM 5 Concrete Pavement


Est. Qty. 120.12 cu.m
I. Materials
### bags Pozzolan Cement @ 245.00 265,090.00
121.00 cu.m G1 Crushed Gravel @ 1,150.00 139,150.00
61.00 cu.m Albay Sand @ 650.00 39,650.00
1.00 pcs RC Pipe 24" @ 2,000.00 2,000.00
Cost Of Materials: 445,890.00
Labor: 133,767.00
II. Equipments
1.00 unit Concrete Mixer @ 1,480.00/day 22,200.00
for 15 days
III others
### bags Cost of Hauling @ 8.00 46,512.00

TOTAL DIRECT COST 648,369.00


PLUS MARK-UPS 116,435.04
TOTAL ITEM COST 764,804.04
UNIT COST 6,367.00

ITEM 6 Sign Board

1.00 pc. Sign Board @ 1,173.00 1,173.00

TOTAL DIRECT COST 1,173.00


PLUS MARK-UPS 210.00
TOTAL ITEM COST 1,383.00
UNIT COST 1,383.00

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Construction Safety and Health 1.00 ls 5,943.00 5,943.00


2 Formworks 1.00 lot 21,620.00 21,620.00
3 Subgrade Preparation 792.00 sq.m 30.00 23,760.00
4 Aggregate Base Course 69.00 cu.m 1,133.00 78,177.00
5 Concrete Pavement 120.12 cu.m 6,367.00 764,804.04
6 Sign Board 1.00 pc. 1,383.00 1,383.00
grand total: 895,687.04

NOLASCO ERNESTO P. CASTILLO


OWNER
NOLCAST CONSTRUCTION AND SUPPLY
006738-2019-01
BILL OF MATERIALS AND COST ESTIMATES OF THE
PROPOSED EARTHFILLING
Vilmar Homes Subdivision, Calauag, Naga City

DETAILED ESTIMATES
ITEM 1 Construction Safety and Health
Est. Qty. 1.00 ls

1.00 mo. Construction Safety and Health @ 1,500.00 1,500.00

TOTAL DIRECT COST 1,500.00


PLUS MARK-UPS 268.00
TOTAL ITEM COST 1,768.00
UNIT COST 1,768.00

ITEM 2 Earhfilling and Grading


Est. Qty. 218.00 cu.m
I. Materials
218.00 cu.m Item 201 @ 470.00 102,460.00
Cost Of Materials: 102,460.00
Labor: 20,492.00
II. Equipments
1.00 unit Compactor @ 800.00/day 8,000.00
for 10 days

TOTAL DIRECT COST 130,952.00


PLUS MARK-UPS 23,392.00
TOTAL ITEM COST 154,344.00
UNIT COST 708.00

ITEM 3 Sign Board

1.00 pc. Sign Board @ 1,173.00 1,173.00

TOTAL DIRECT COST 1,173.00


PLUS MARK-UPS 210.00
TOTAL ITEM COST 1,383.00
UNIT COST 1,383.00

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Construction Safety and Health 1.00 ls 1,768.00 1,768.00


2 Earhfilling and Grading 218.00 cu.m 708.00 154,344.00
3 Sign Board 1.00 pc. 1,383.00 1,383.00
grand total: 157,495.00

NOLASCO ERNESTO P. CASTILLO


OWNER
NOLCAST CONSTRUCTION AND SUPPLY
006865-2019-01
BILL OF MATERIALS AND COST ESTIMATES OF THE
Proposed Concrete Topping
Mahamis St., Vilmar Homes Subd., Calauag, Naga City

DETAILED ESTIMATES
ITEM 1 Construction Safety and Health
Est. Qty. 1.00 ls

1.00 mo. Construction Safety and Health @ 1,680.00 1,680.00

TOTAL DIRECT COST 1,680.00


PLUS MARK-UPS 300.00
TOTAL ITEM COST 1,980.00
UNIT COST 1,980.00

ITEM 2 Formworks
Est. Qty. 1.00 lot

2.00 kgs CW nails @ 80.00 160.00


205.00 bd.ft Formworks Coco Lumber @ 24.50 5,022.50
Cost Of Materials: 5,182.50
Labor: 1,554.75

TOTAL DIRECT COST 6,737.25


PLUS MARK-UPS 1,207.75
TOTAL ITEM COST 7,945.00
UNIT COST 7,945.00

ITEM 3 Concrete Topping


Est. Qty. 40.00 cu.m
I. Materials
338.00 bags Pozzolan Cement @ 244.50 82,641.00
40.00 cu.m GI Crushed Gravel @ 1,148.00 45,920.00
20.00 cu.m Formworks Coco Lumber @ 645.00 12,900.00
Cost Of Materials: 141,461.00
Labor: 42,438.30
II. Equipments
1.00 unit Concrete Mixer @ 1,500.00/day 7,500.00
for 5 days
TOTAL DIRECT COST 191,399.30
PLUS MARK-UPS 34,280.70
TOTAL ITEM COST 225,680.00
UNIT COST 5,642.00

ITEM 4 Sign Board

1.00 pc. Sign Board @ 1,272.00 1,272.00

TOTAL DIRECT COST 1,272.00


PLUS MARK-UPS 228.00
TOTAL ITEM COST 1,500.00
UNIT COST 1,500.00

SUMMARY OF ESTIMATES

ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL

1 Construction Safety and Health 1.00 ls 1,980.00 1,980.00


2 Formworks 1.00 lot 7,945.00 7,945.00
3 Concrete Topping 40.00 cu.m 5,642.00 225,680.00
4 Sign Board 1.00 pc. 1,500.00 1,500.00
grand total: 237,105.00

NOLASCO ERNESTO P. CASTILLO


OWNER
NOLCAST CONSTRUCTION AND SUPPLY

Das könnte Ihnen auch gefallen