Beruflich Dokumente
Kultur Dokumente
This AGREEMENT, made and entered into this ____ day of __________, YEAR, by
and between:
-and-
WITNESSETH: That
NOW, THEREFORE, the OWNER and the ARCHITECT, for and in consideration of the
foregoing premises and of the other covenants hereinafter named, agree as follows:
1.02 Designing of the whole building structures and details, including plumbing,
electrical, mechanical, and storm drainage system.
1
c. He shall submit to the Owner a Statement of Probable Project
Construction Cost based on current cost parameters.
c. He shall furnish not more than five (5) complete sets of contract
drawings, specifications and general conditions for purposes of
bidding.
c. To the extent provided by the contract between the Owner and the
Contractor, he shall make decisions on all claims of the Owner and
Contractor and on all other matters relating to the execution and progress
of the work or the interpretation of the Contract Documents. He shall
check and approve samples, schedules, shop drawings and other
submissions only for conformance with the information given by the
Contract Documents, prepare change orders and assemble written
guarantees required of the Contractors for submission to the Owner.
2
d. He will make periodic visits to the site to familiarize himself generally with
the progress and quality of the work and to determine in general if the
work is proceeding in accordance with the Contract Documents. He will
not be required to make exhaustive or continuous on-site inspection to
check the quality of the work and he will not be responsible for the
Contractor’s failure to carry out the construction work in accordance with
the Contract Documents. During such visits and on the basis of his
observations while at the site, he will keep the Owner informed of the
progress of the work, will endeavor to guard the Owner against defects
and deficiencies in the work of Contractors, and he may condemn work as
failing to conform to the Contract Documents.
3.01 That the Owner agrees to pay the Architect for professional services, a fee
of five percent (5%) of the Project Construction Cost, with other payments
and reimbursements as hereinafter provided, the said percentage being
hereinafter called the Basic Rate.
3.02 That payments to the Architect on account of his fee shall be made by the
Owner as follows:
b. Upon the completion of the Schematic Design Services, not more than
15 days after submission of the Schematic Design to the Owner, a sum
equal to fifteen (15%) percent of the Basic Fee, computed upon
reasonable estimated construction cost of the structure.
3
eighty-five (85%) percent of the Basic Fee computed upon reasonable
estimated construction cost of the structure as in b.
e. Within 15 days after the awards to the winning bidder or bidders the
payment to the Architect shall be adjusted so that it will amount to a
sum equivalent to eighty-five (85%) percent of the Basic Fee ,
computed upon the lowest Bonafide Bid or Bids or upon the winning
Bid Price.
g. There will be separate charges for each housing model type designed
by the Architect.
3.03 That the Owner agrees to make partial payments during each of the
various stages of the Architect’s work, upon request of the Architect,
provided that such payments are within the framework of the manner of
payment outlined above.
From two to ten units…………… Fee of 1 unit plus 60% of Basic Fee
for each additional unit
Eleven units and above………… Fee for 10 unit plus 30% of Basic Fee
for each additional unit
4.01 The Owner shall provide full information as to his requirements for the
project.
4.03 He shall furnish or direct the Architect to obtain at the Owner’s expense, a
certified survey of the site, giving, as required, grades and lines of streets,
alleys, pavements, and adjoining property; rights of way, restriction,
boundaries, and contours of the building site; locations, dimensions and
complete data pertaining to existing buildings, other improvements and
trees, full information as to available service and utility lines both public
and private and test borings and pits necessary for determining sub-soil
conditions.
4
4.04 He shall pay for structural, chemical, mechanical, soil mechanics or other
tests and reports as may be required for the project.
4.05 He shall pay for the design and consultancy services on acoustic,
communication, electronic and other specialty systems as may be
required by the Project.
4.06 He shall arrange and pay for such legal, auditing, and insurance
counseling services and taxes as may be required for the Project or by the
government.
4.07 He shall pay all reimbursable expenses incurred in the project as called for
in Article 7 and all taxes (not including income tax) that the government
may impose on the Architect, as a result of the services rendered by the
Architect on the project whether the services were performed as an
individual practitioner, as a partnership or as a corporation.
4.08 If the Owner observes or otherwise becomes aware of any defect in the
project, he shall give prompt written notice thereof to the Architect.
5.01 That the cost of the work or Project Construction Cost as herein referred
to, means the cost of the completed structure to the Owner including
plumbing and electrical fixtures, mechanical and air conditioning facilities,
emergency generators, and pumps attached to the building and all items
indicated in the drawings, specified or designed by the Architect but needs
consultants like interior designers, landscaping and other items of similar
nature are to be paid separately by the Owner to the Architect as
stipulated in Art. 7.02. The Project Construction Cost, however, does not
include any Architect’s fee or engineer’s fee or the salaries of the
construction inspectors. When labor or materials are furnished by the
Owner below its market cost, the cost of the work shall be computed upon
such current market cost.
5
7.02 Different Periods of Construction: If the portions of the building are
erected at different periods of time, thus increasing the Architect’s
construction phase period and burden of services, charges pertaining to
services rendered during the construction phase shall be doubled. It is
understood that a suspension of construction for a period not exceeding
three (3) months shall not be covered by this provision.
7.03 Separate Services: If the Owner requires, the Architect to design or plan
movable closets, cabinets, pieces of furniture, covered walks, grottos,
landscaping, revisions and other items of similar nature, the Owner shall
pay the Architect additional compensation in the amount of Fifteen
Percent (15%) of the construction cost of the above work.
7.05 Miniature Models: The Architect may make and include miniature models
as part of his preliminary sketches if he so deems it to be necessary. If the
Owner desires to have miniature models of the final approved preliminary
drawings for exhibitive and display purposes, the Owner shall pay for the
cost of said miniature models.
7.06 Per Diems and Traveling Expenses: A per diem of not less than One
Thousand Pesos (PhP1,000) plus traveling and living expenses shall be
chargeable to the Owner on any occasion where the Architect or his duly
authorized representative shall be required to perform services at a
locality beyond the radius of 50 kilometers from his established office.
7.07 Extra Sets of Contract Documents: The Architect is to furnish the Owner
five (5) sets of Drawings, Specifications and other Contract Documents.
Cost for printing or reproduction of extra sets of Contract Documents when
required by the Owner or his representatives is to be paid by the Owner.
6
FIVE PERCENT (5%) for the Architect’s liability under the Civil Code
–and-
TWO PERCENT (2%) for the construction phase service which includes
preparation of contract document forms and periodic
visits during the construction.
When the Owner therefore fails to implement the plans and document for
construction as prepared by the Architect, the Architect is entitled to
receive as compensation the sum corresponding to EIGHTY-FIVE (85%)
Percent of his fee.
ARTICLE 9 ESTIMATES
Since the Architect has no control over the cost of labor and materials, or
competitive bidding, he does not guarantee the accuracy of any
Statements of Probable Construction Cost, or any Semi-Detailed or
detailed Cost Estimates.
During the progress of work, the Owner shall furnish the Architect two (2)
copies of records of expenses being incurred for the construction. Every
end of the month and upon completion of the project, the Owner shall
furnish the Architect two (2) copies of the summary of all cost of labor,
services, materials, equipment, fixtures and all items used at and for the
completion of the construction.
7
ARTICLE 12 OWNERSHIP OF DOCUMENTS
The Owner and the Architect each binds himself, his partners, successors,
legal representative and assigns to the other party to this Agreement, and
to the partners, successors, legal representatives and assigns of such
other party in respect of all covenants of this Agreement. Except, as
above, neither the Owner nor the Architect shall assign, sublet or transfer
his interest in this Agreement without the written consent of the other.
ARTICLE 14 ARBITRATION
By:
_________________________ ________________________
Print name & sign above Print name & sign above
Address: _________________ Address: ________________
_________________________ ________________________
8
ACKNOWLEDGEMENT
Before me, a Notary Public for and in the City of _________________ this
________________________, personally appeared:
Notary Public