NODE ACTIVITY NAME OF DURATION EARLY EARLY LATE LATE FLOAT

ACTIVITY START FINISH START FINISH


0-1 A MOBILIZATION 2 0 2 0 2 0

1-2 B LAY OUT 1 2 3 2 3 0

2-3 C EXCAVATION 5 3 8 3 8 0

3-4 D FOUNDATION 15 8 23 8 23 0

3-5 E WALL 10 8 18 19 29 11
FOOTING
4-8 F 1ST FLOOR 7 23 30 23 30 0
COLUMN
5-6 G BACKFILLING 1 18 19 29 30 11

8-10 H 2ND FLOOR 7 30 37 30 37 0


BEAM
8-11 I 2ND FLOOR 3 30 33 32 35 2
SLAB
11-15 J STAIRS 2 33 35 35 37 2

8-9 K 1ST FLOOR 8 30 38 34 42 5


MASONRY
10-12 L 2ND FLOOR 5 37 42 37 42 0
COLUMN
12-14 M ROOF BEAM 5 42 47 42 47 0

12-13 N 2ND FLOOR 4 42 46 43 47 1


MASONRY
14-17 O ROOF 6 47 53 47 53 0
FRAMING
14-21 P PLASTERING 5 47 52 48 53 1

17-18 Q ROOFING 6 53 59 53 59 0

17-16 R GROUND 4 53 57 55 59 2
FLOOR SLAB
8-23 S ELECTRICAL 28 30 58 36 64 6
WORKS
8-20 T PLUMBING 30 30 60 34 64 4
WORKS
18-23 U CARPENRTY 5 59 64 59 64 0
WORKS
18-22 V CEILING 4 59 63 60 64 1

23-24 W PAINTING 15 64 79 64 79 0

24-25 X TILEWORKS 15 79 94 79 94 0

3-25 Y FALSE WORK 75 8 83 19 94 11

25-26 Z CLEARING 1 94 95 94 95 0