SOLUNA GUIDELINES FOR COMMERCIAL CONSTRUCTION AND RULES AND

REGULATIONS

Any proposed construction activity, shall require a Commercial Construction Permit from the
Soluna Home Owners Association, Inc. (SHOAI) and shall strictly comply with this code of
Construction Rules and Regulations. The Commercial Construction Permit (CCP), upon
approval, shall allow the ingress of workers and delivery of materials to the commercial site.

New Construction, renovations, interior fit out, and all other kinds of auxiliary structures are
covered by this code and the Soluna Deed of Restrictions. For technical details, please refer to
the Soluna Deed of Restrictions.

Any violation shall result in the revocation of the Commercial Construction Permit and/or the
imposition of fines and penalties prescribed herein.

1.0 PRE-CONSTRUCTION RULES PURPOSE AND INTENT

To preserve the general character and design intent of SOLUNA, a Commercial Structure
and all improvements thereto must be of a type of architecture that is in harmony with the
character of the entire development. Similar architectural form and details, building
materials and building color palette as the Subdivision clubhouse will greatly help bring
aesthetic harmony to the development. Even as the design of the Commercial Structure
maintains a distinctive façade, the Commercial Structure should maintain a likeness and
similarity with the Housing Structures and other Commercial Structures in the Subdivision.
Colors used for all exterior features, attachments, improvement or expansion of the
Commercial Structure (including roofing, exterior walls, doors, window jambs), shall be in
harmony with the colors of the other Structures in the Subdivision. Roofing components of
any improvement or expansion on the Commercial Structure shall maintain the same pitch
of roof as that of the design of the Commercial Structure as indicated in the original plans for
the Commercial Structure initially approved by the Declarant and the Association. All
improvements and expansions must be made of strong materials.

1.1 PREPARATION OF PLANS – Before the preparation of commercial plans, the Commercial
Lot Owner shall request the SHOAI for a briefing/conference which shall explain all the
aspects of these rules and regulations. This conference shall be held between the
owner (or his/her duly authorized representative) and a representative of the SHOAI.
The owner’s contractor, architect and engineer are required to attend such
conference so that they are properly informed and guided from the very start of
construction.

Preparation of Plans must commence only after proper understanding of the Soluna
Deed Restrictions and Commercial Construction Rules and Regulations. Every lot
owner is furnished with the Deed of Restrictions upon purchase of the lot, while the
Construction Rules and Regulations are given upon turnover of lot.

1.2 LOT PLAN – The COMMERCIAL LOT OWNER shall secure an official lot plan from New
Pacific Resources management Inc. (NPRMI).

1.3 LOT VERIFICATION – For those constructing for the first time, the COMMERCIAL LOT
OWNER shall request from SHOAI the official verification and relocation (if necessary) of
monuments. The owner or his/her representative should be present when the surveyors
from XXXXXXXXXXXXXX verify/relocate the monuments. Survey shall also include
elevation verification. This shall be free of charge for the first lot verification. Any
succeeding verifications shall be for the account of the Commercial Lot Owner. Lot
verification forms are available at the Administration office.

For succeeding construction works, official certification of a Geodetic Engineer must


be submitted together with the plans for the SHOAI file. Soil boring test is
recommended for those constructing for the first time (applicable for lots only).
1.4 SITE INSPECTION/INVESTIGATION – The architect and engineer must conduct site
inspection prior to preparation of house plans. They should acquaint themselves with the
ground features, utility service connections, and other improvements in relation to the lot.

1.5 SUBMISSION OF PLANS – (signed and sealed) The HOMEOWNER shall submit to SHOAI five
(5) sets (Owner’s copy, Contractor’s copy, SHOAI’s copy, Office of the Building
Official/City Engineer’s copy, site copy) of each of the following plans (scale 1:50 m),
which must bear the signatures of the owner and architect on the architectural plan (as
needed for renovation works); of the civil engineer/architect on the structural plan (as
needed for renovation works); of the electrical engineer on the electrical plan; and of
the sanitary engineer/master plumber on the sanitary/ plumbing plan (as needed for
renovation works), cut & fill plan (as needed for renovation works); fence elevation &
plan (all sides, natural ground contour indicated):

1.5.1. Vicinity plan;


1.5.2. Location plan showing bearings & distances;
1.5.3. Plan and sections showing differences in elevation of the four corners and
center point of the lot;
1.5.4. Development plan and elevation showing the proposed fences, driveways, and
landscaping;
1.5.5. Floor plans (showing relation to property lines, all levels);
1.5.6. Elevation plans and section plans;
1.5.7. Utility plans

1.5.7.1 Plumbing plan showing water, drainage, sewer lines. The location, size and
elevation of drainage, sewer, and water service connections must be verified
to ensure proper design of the systems;

1.5.7.1 Complete electrical plan showing proposed service entrance

1.5.8 Property Lines should be indicated on all plans and at all levels.

1.5.8.1 Photocopy of TCT (3 copies); original copy must be presented for verification;
TCT and submitted plans should have the same name of owner. Special
Power of Attorney needed (S.P.A.) for different names.
1.5.8.2 Only plans submitted with complete requirements shall be accepted

Note: No three-phase electrical load is allowed.

2.0 APPROVAL BY THE SHOAI

Upon verification and/or correction of the commercial plans by SHOAI so that they
conform to the building codes and to the Deed Restrictions of SHOAI, and the rules
and regulations of SHOAI, the SHOAI shall issue a Commercial Construction Permit to
the COMMERCIAL LOT OWNER.

The Commercial Construction Permit is granted to the COMMERCIAL LOT OWNER


whose account (assessments, dues, utilities, etc. is up to date).

Thereafter, the approved/corrected commercial plans must be strictly observed and


adhered to by the owner, the architect, the engineer, and the contractor and a copy
must be kept at the construction site at all times for purposes of inspection and
compliance.

Note: No stockpiling or any form of construction works shall be allowed before release
of CCP

3.0 UTILITY SERVICES

The COMMERCIAL LOT OWNER shall apply with entities concerned for utility services:

3.1.1 Water – Maynilad Water System Inc.


3.1.2 Electricity – Meralco
Note: Forms are available at the SHOAI administration office

Tapping of electrical and plumbing utilities should be provided by the Commercial Lot
Owner in coordination with the Village Administration. No tapping of electrical supply in
the common area is allowed.

4.0 PERMITS & CLEARANCES

4.1 BODEGA/STOCKPILING – is authorized only on the commercial unit owner’s lot. Using
another lot requires a signed adjacent lot permit from its owner. Stockpiling materials on
common areas such as sidewalks, easements, alleys, streets, and other open spaces is
prohibited.

4.2 SHOAI COMMERCIAL CONSTRUCTION PERMIT (CCP) – is issued upon compliance with all
pre-construction requirements and approval of construction plans by SHOAI. This will
serve as the official Notice to Proceed.

To acquire the Commercial Work Permit


1. Submit a copy of the Building Permit.
2. Deposit the construction bond with the Village accountant and pay
administrative and plan processing fees, settle all dues, utilities, etc.
3. Submit appointment of contractor.
4. Submit Deed of Undertaking and adjacent lot permit (if necessary).
5. Proof of release of SHOAI approved plans.

4.3 TEMPORARY PERMIT – is issued by SHOAI upon full payment of the fees pertinent to
construction to allow temporary mobilization only. Excavation and construction work
will not be allowed.

4.4 ORIGINAL NOTARIZED DEED OF UNDERTAKING-this form is acquired at the SHOAI


administration and must be signed by the HOMEOWNER to comply with the Soluna
Deed Restrictions and Village Construction Rules and Regulations.

4.5 APPOINTMENT LETTER OF CONTRACTOR-must be submitted to the SHOAI administration.


This must be signed by the COMMERCIAL LOT OWNER.

4.6 BUILDING PERMIT – Upon approval of the Commercial plans by the SHOAI, the
HOMEOWNER shall submit to the City Engineer’s Office of Bacoor the SHOAI-approved
plans for the purpose of securing the Municipal Building Permit.

4.7 COMPREHENSIVE GENERAL LIABILITY INSURANCE

4.7.1 The contractor shall secure Comprehensive General Liability Insurance from
reputable insurance company for bodily injury, property damage to the village
and/ or any third party for the entire duration of the construction. A copy of the
insurance coverage shall be submitted to Village Administration prior to any work.

4.7.2 A Comprehensive General Liability Insurance is necessary for any construction/


repair work which will cost P100,000.

4.8 FIRE SAFETY

4.8.1 One (1) unit -20lbs. ABC type fire extinguisher shall be provided by the
homeowner for every 11.40 m radius of his lot, for the duration of the construction.
4.8.2 An extinguisher shall be provided and a fire watch assigned for any welding and/
or gas cutting operation.

4.8.3 Smoking is strictly prohibited within the construction site.

4.8.4 Fire wood cooking is strictly prohibited within the construction site.

4.8.5 Water supply and distribution facilities for firefighting purposes shall be provided
and maintained in the construction site in accordance with the Local Fire Code.

4.9 CONSTRUCTION WORKERS’ IDs & UNIFORM – Construction workers’ ID Application Forms
are to be secured from the SHOAI office. No worker shall be allowed entry to or exit
from the Commercial Area without the worker’s ID, which must be worn at all times.
The SHOAI reserves the right to refuse, revoke or cancel any worker’s ID at SHOAI’s sole
discretion. NBI clearance is required.

All construction workers must be in proper construction attire with PPE (Personnel
Protective Equipment). Uniform t-shirt bearing the contractors’ logo, long pants and
safety shoes are required. Those in sleeveless, shorts and slippers and the like are not
allowed to enter the commercial premises.

4.10 OPERATIONAL LATRINE/BARRACKS/BUNKHOUSE/BODEGA/BATHHOUSE – To observe


proper hygiene and waste disposal, every builder/contractor must provide an
operational latrine, shower, bathhouse, and barracks within the lot during the
construction period. The said structures are temporary and shall be restricted as
follows:

4.10.1 The structures must be one-story only and made of decent looking materials;

4.10.2 No clothesline shall be within public view;

4.10.3 The latrine and bathhouse must be maintained in sanitary state at all times, well-
covered and kept from public view. Water used must be properly connected
and metered;

4.10.4 The construction area (including the barracks, delivery area, etc.) should be
fenced with decent looking materials (i.e. sawali, painted G.I. sheets, etc.). The
temporary fence should not be less than 2.40 meters in height.

4.11 GUIDELINES FOR CONSTRUCTION BOND

4.11.1 Construction of any house shall be for continuous period of no more than twelve
(12) months.

4.11.2 Commercial Lot Owners shall post a construction bond of P125,000.00. This will
answer for damages or losses to the common area and to the adjacent
lot/establishment during construction/ renovation. Fines and penalties levied on
the COMMERCIAL LOT OWNER for violations of construction rules and regulations
(if any), and all expenses incurred by the SHOAI for the account of the
HOMEOWNER as provided herein, shall be deducted from the construction bond
of the COMMERCIAL LOT OWNER. The balance (if any) shall be refunded to the
COMMERCIAL LOT OWNER.

4.11.3 If construction exceeds twelve months the homeowner will be charged an extra
P 1,000 per month. Non-payment of the above will mean stoppage of the
renovation work and is subject to penalty in them same manner as a regular
village assessment.

4.12 FEE AND CHARGES

The COMMERCIAL LOT OWNER shall pay the following fees and charges:

4.12.1 P 5,000.00 non-refundable plans processing fee;

4.12.2 P10,000.00 non-refundable administrative charges which will cover the


following:

4.12.2.1 Additional security chores


4.12.2.2 Monitoring of construction activities;
4.12.2.3 Assistance for utilities monitoring/ application;
4.12.2.4 Administration works (issuance of permits, notices, I.D.
processing and the like).

4.12.3 Hauling of construction debris is excluded from these charges and is the
responsibility of the COMMERCIAL LOT OWNER.

5 RULES DURING CONSTRUCTION

The intention of these construction rules is to guide the Owner on the basic restrictions for
residential construction. These guidelines were established to maintain order in construction
areas which will help the Owner in managing and maintaining their property.

5.1 TECHNICAL RULES AND SPECIFICATIONS.

The following rules apply to all COMMERCIAL LOTS in all phases, except wherein
indicated in the Soluna Deed of Restrictions.

5.1.1. Deed of Restrictions. All provisions of the Deed of Restrictions on the title of
the lot shall be strictly observed.

5.1.2 Setback Requirements. The required setbacks of the each property/lot


are enumerated on the Soluna Deed of Restrictions.

Note: Measurements starts from the property line to the finished surface of the
wall/column, roof, or any appurtenance or projection of the structure.

5.1.3 Height Restrictions. Prior to start of construction, the Parties (consisting of the
owner of the lot, the contractor or builder, the authorized representatives of
SHOAI and NPRMI) shall meet at the construction site to determine and agree on:

5.1.3.1 The highest point of solid land as originally cleared with NPRMI.

5.1.3.2 The difference in height between the original reference point and
the highest original ground level point shall be ascertained and measured
by use of carpenter’s level; it shall be noted in writing on the official
copies of the approved plans and agree to and signed by all Parties;
5.1.3.3 The height of the completed structure shall not exceed nine (9)
meters measured vertically from the highest corner of the lot (as
determined by NPRMI) to the apex of the roof of such Dwelling Unit.

5.1.4 Construction of Antenna Towers/ Satellite Dish/ Auxiliary Structures– must


be properly designed to withstand strong winds and earthquakes and
must conform to setback requirements. Requires submission of plans
signed and sealed by a structural engineer.

The Association shall not be held responsible or co-liable for any


damages/s of life or lives. Should such structure fall, whether by accident
or fortuitous event, or for any other causes.

5.1.5 Water- No more than 1” diameter pipe may be used before the water
meter. No water booster pumps are allowed BEFORE the water storage
reservoir.

5.1.6 Sewer- Approved design of septic vaults must be acquired prior to


construction.

5.1.7 Drainage-All drainage lines will be tapped to the allotted tapping point
for each lot. In case of the presence of a basement that is lower than the
drainage main line, the owner shall provide a sump pit equipped with a
pump to lift the drainage water.

5.1.8 Bathhouses-These are subject to the setback requirements in the Deed


Restrictions.

5.1.9 Guardhouses- may be constructed inside the front gate area for sentry
duty only, and not as sleeping quarters. The floor area therefore must not
be bigger than 1.2 meters by 1.2 meters, and its roof must not protrude
beyond the property line.

5.1.10 Water tanks- No aerial or elevated water tanks are allowed. Booster
pumps directly connected to the water main are not allowed; however,
booster pumps may be installed to draw water from a ground storage
tank of adequate capacity, supplied by natural pressure from the water
main.

5.1.11 Garbage Depository – It should have proper enclosure and drainage; the
dimension should not exceed one (1) meter long by one (1) meter wide
by one (1) meter high.

5.1.12 Green strip Landscaping – should not encroach the sidewalk and requires
assigned undertaking from the Lot owner.

5.2 SITE ENCLOSURE. All construction sites are required to provide enclosures (sawali, G.I.,
plywood, or tarp) on all sides of the construction site. The enclosure must be stable
and should follow the height and scope of the construction.

5.3 CONSTRUCTION HOURS. Construction work will be allowed from 8 am to 5 pm,


Mondays to Saturdays. Work after 5 pm will be considered as overtime. Overtime
works must acquire an overtime permit from the Association. The association
approval for OT will be dependent on the condition that such activity does not
create noise or disturbance and does not elicit any complaints from neighbors.
Workers are allowed to enter the village by 7 am and should be out by 7pm. NO
CONSTRUCTION WORK PERMITTED ON SUNDAYS AND HOLIDAYS.

5.4 DELIVERY HOURS. Delivery of construction materials are allowed from 8:00 a.m. to
5:00 p.m., Mondays to Saturdays only. No deliveries on Sundays and holidays. No
deliveries shall be allowed from 8:01 pm to & 7:59am.

5.5 CURFEW. No one associated with the construction, except the Owner, may roam
around, stray from or leave the work site between 7pm and 7am the following
morning.

5.6 STAY-IN WORKERS. A maximum of two (2) personnel per construction site may stay
overnight at the job site. The Owner or contractor shall furnish the association office
the names of these workers. These workers should have valid Soluna IDs. The
following conditions are strictly observed:

5.6.1. Not more than two (2) workers per specific construction site to safeguard
own construction materials, equipment and personal belongings.

5.6.2 A specific area with an appropriate bunkhouse has been designated as


cantonment area for other workers within or near the project site.
Construction of the temporary bunkhouse at the designated location shall
be at the sub-contractors’ expense.

5.6.3 Stay-in workers should be back at their bunkhouse by 7 pm. Those not yet
in by the designated time will not be admitted through the gates except when
there is an acceptable work-related reason. Those coming in drunk will not be
admitted. The workers shall at all times stay at the project site. Curfew shall be
from 7pm-7am.

5.6.4 Trafficking or imbibing intoxicating substances and use of prohibited drugs


within the cantonment areas are strictly prohibited. Violation will result in
confiscation of the items, cancellation of IDs and denial of entry to the
project. Confiscated items will be disposed of by security in the presence
of the employer’s representative.

5.6.5 Loud noise and heated arguments/ brawls will not be tolerated.
Implements that could be construed as deadly weapons other than
construction tools will be confiscated for safekeeping by security.

5.6.6 All workers shall maintain cleanliness and observe proper sanitation and
hygiene in the project and cantonment areas.

5.6.7 Only workers actually working in the project will be allowed to stay at the
bunkhouse. Sub-contractors will not use the bunkhouse as a dormitory for
their excess workers or those working in other projects.

5.6.8 Workers’ dependents, friends or relatives are not allowed to stay at the
bunkhouse.

5.7 SANITATION. Construction workers may eat at the job site or in the house but should
provide a covered trash van for waste and leftovers. All waste must be removed
from the house and lot at the end of every working day and dispose of outside the
village. Nothing shall be left in the house, lot or street or in any part of the village
premises.
5.8 SAFETY MATERIALS/ EQUIPMENT
The Commercial Lot Owner’s contractor shall provide safety measures such as
construction net, sheeting, shoring, PPE, etc. whenever necessary.

5.9 INSPECTION.

5.9.1 No materials, equipment or tools may be brought out of the village


without the proper property pass. Workers and their belongings may be
subjected to physical inspection by the guards when leaving the project
site. Vehicles leaving and entering the project gates may be also
inspected for unauthorized cargo. Workers and drivers are encouraged
to cooperate fully with the guards to facilitate inspection.

5.9.2 The Administration Office and their assigned representatives shall conduct
routine inspections of all construction sites frequently and regularly. All
observations and instruction given by the inspectors must be taken note of
and strictly followed. The Homeowner’s Association reserves the right to
issue and demand construction changes on approved plans when
deemed necessary.

5.9.3 The security personnel is given authority to issue violation slip on workers
who violate the House Rules and Regulations and General Construction
Guidelines of the Homeowners’ Association

6 BEHAVIOR AND DISCIPLINE OF WORKERS

The Owner shall be held responsible for the behavior and discipline of all persons working
on his or her construction project, including Architects, Engineers, contractors, suppliers,
foremen, domestic help, construction workers and security guards.

6.1 PERSONAL CONDUCT. Any construction personnel showing disrespect to


Residents, Association personnel including security guards will not be tolerated
and will be immediately removed and permanently banned from the
Construction. Workers shall report guards whom they perceive as abusive or
arrogant to the head of security for the project or directly to their employers. All
reports will be treated with utmost confidentiality.

Swearing and use of cuss words in the presence of others shall be avoided.

6.2 INTOXICATING LIQUOR/ USE OF PROHIBITED DRUGS. Bringing in and drinking of any
alcoholic or intoxicating beverage and prohibited drugs are not permitted.
Intoxicated personnel and workers shall be removed and permanently banned
from the Village.

6.3 GAMBLING. Any form of gambling, or betting with money, is not allowed.

6.4 PUBLIC DISTURANCE. Noise or disturbance, especially during curfew hours is strictly
prohibited. This includes loud singing, loud TV or radio sets, boisterous talk or
laughter, abusive and profane language.

6.5 INDECENT EXPOSURE. Bathing, urinating, defecating or not in proper clothing (half
naked or in undergarments) in public view is prohibited.

6.6 LOITERING, CURFEW Workers and their supervisors are not allowed to loiter within
the construction premises e.g. they should stay only within their work area to
prevent loss or damage, disturbance and inconvenience in any form to other
commercial establishment.

The curfew for the workers shall be from 7pm-7am.

6.7 INAPPROPRIATE USE OF ID. When inside the Commercial premises, the SOLUNA ID
card must be pinned and prominently displayed on the personnel at all times.

6.7.1 The ID must, at the minimum, contain the following identification data:
name and photo of worker taken within the last six months, ID number,
name of employer/ company of sub-contractor, signature of worker,
authenticating signature of Association Representative.

6.7.1.1 Construction Workers: Color Tag-Blue

The contractor of each construction site shall be responsible for acquiring the ID
cards from the Administration office prior to construction in the Commercial Lot. The
NBI clearance shall be a requirement for issuance of Village ID. Validity is only up to 6
months or upon termination of contract/ completion of project, whichever comes
first.
Application Requirements:

a. Completed Application Form


b. 1X1 photos (2 pieces-1 for the application form, 1 for and for the Village ID,
1)
a. Copy of NBI Clearance or Police Clearance
Rules & Regulations:

a. The Employee Identification Card shall only be valid if authorized by the


Owner of the property of the authorized tenant.
b. The Identification Card shall be noted by the Village Administrator first prior to
issuing the card.
c. Curfew for construction workers is between 7pm to 7am
d. When leaving the village and entering the premises, they are subject to
inspection.
e. The ID card shall be returned to the administration upon termination of
contract or completion of project.

Registration Fee:

Cost of IDs is included in the Administrative Fees to be paid by owner prior to


construction. P100 deposit refundable upon return or termination of ID

6.8 TRESPASSING. Any person entering the Village other than the designated entry
points are considered as trespassers. Trespassers shall be apprehended and
brought to the local barangay authorities.

6.9 GRAVE MISCONDUCT. Any construction personnel engaging in grave misconduct


or any other conduct offensive to law or the peace and tranquility of the
residents and commercial establishment shall be removed and permanently
banned from the Commercial Construction Site. This includes but not limited to,
threats, physical injuries, fighting, theft, trespassing, rude behavior and the likes.

6.10 DRUGS. Any person possessing, selling or using prohibited drugs shall be turned
over to the police authorities and shall be permanently banned from the shall be
removed and permanently banned from the Commercial Construction Site.

6.11 DEADLY WEAPONS. Firearms and bladed weapons are prohibited in the
Commercial Construction Site. All dangerous tools and pointed objects must be
securely kept inside the toolbox. Offenders involved in any incident shall be
permanently banned from the Commercial Construction Site.

6.12 ANIMALS. Farm animals, such as goats, pigs, chicken, game fowls and the likes,
are prohibited at the construction sites.

7 MAINTENANCE OF CONSTRUCTION SITE AND VICINITY

The COMMERCIAL LOT OWNER/builder shall maintain the construction site and vicinity in
sanitary and clean condition at all times. Garbage and construction debris must be
properly disposed of and/or dumping of the same in neighboring areas is prohibited.
Upon failure of the Homeowner to comply with this provision, the SHOAI shall clean the
premises and the expense shall be charged to the Commercial Lot owner’s renovation
deposit.

8 RULES AFTER CONSTRUCTION

8.1 CONSTRUCTION DEBRIS AND MATERIALS – There should be no construction debris


and/or excess materials left anywhere in the vicinity of the construction site upon
its completion. Upon failure by the Commercial Lot Owner to clean up, the SHOAI
shall do so and charge the expense against the Commercial Lot Owner’s
guarantee deposit.

8.2 DAMAGED TO COMMON AREAS – Any damage to common areas such as


sidewalks, streets, etc., as a result of construction shall be repaired by the SHOAI
and the expense against the Commercial Lot Owner’s guarantee/ construction
deposit.

8.3 REMOVAL OF AUXILLARY STRUCTURES – The Commercial Lot Owner upon


completion of the house shall remove the following structures: 1) bunkhouse, 2)
warehouse, 3) storage area, 4) field office, 5) temporary latrine and shower. Upon
failure by the Homeowner to do so, the SHOAI shall remove the same and charge
the expense against the Commercial Lot Owner’s construction deposit.

8.4 REMOVAL CONSTRUCTION EQUIPMENT AND VEHICLES – There should be no


construction equipment and vehicles left anywhere in the vicinity of the site upon
the house construction.

8.5 RETRIEVAL OF WORKERS’ ID – IDs issued by SHOAI to construction personnel are for
a fixed period only and for the construction site applied for. It is not valid for use
at other construction sites and must be surrendered to SHOAI upon completion of
the project. A worker who fails to surrender his ID following the completion of the
construction will be prohibited from subsequent work in the Village.

8.6 ABORTED CONSTRUCTION – In case of construction aborted or abandoned by


the COMMERCIAL UNIT OWNER, the SHOAI reserves the right to suspend or revoke
the Commercial Construction Permit (CCP) until further notice.

8.7 FINAL INSPECTION-The owner shall request the SHOAI/ Village Administration (in
written form) at least 3 days in advance to conduct final inspection for the
following critical areas bases on NPMI standards, National Building Code, or any
other existing national standards, whichever is safer in the opinion of the Village
Engineer. The construction bond will be refunded when the SHOAI representative
recommends the refund based on the final inspection.

Electrical Installation testing (meager testing, load limitations per unit, etc.),
plumbing standards, and other critical work that might endanger the village will
be considered in the final inspection.
Any final work which does not conform with the specification of the plan as
originally submitted or which poses a potential hazard may be removed,
demolished by the SHOAI at the expense of the COMMERCIAL UNIT OWNER
concerned.

9 FINES AND PENALTIES

Unless otherwise provided above, the violation of any of the rules and regulation herein
contained shall incur fines and/or penalties on the COMMERCIAL UNIT OWNER and the
construction personnel/workers depending on the gravity of the offense see appendix for
the list of fines and penalties.

The SHOAI reserves the right to impose the maximum fines and penalties in case of failure
and/or refusal by the COMMERCIAL UNIT OWNER to implement corrective measures required
by the SHOAI even if it is the first or second offense only, and in case constructions
personnel/workers fail to abide by the directives of the SHOAI.
In case of a violation of the Deed of Restrictions (i.e. setbacks, height restrictions, etc.),
NPRMI and SHOAI reserves the right to stop construction totally if the violation is not rectified
within the period of time (for rectification) agreed upon with the COMMERCIAL UNIT OWNER.

Any violation, which does not fall within the list, shall be dealt with on a case-to-case basis by
the SHOAI. See Appendix for List of Fines and Penalties according to the Violation.

10 MISCELLANEOUS INFORMATION AND OTHER RULES

10.1 Trucks – Trucks delivering construction materials are required to observe cleanliness
of the premises by clearing the roads of their scattered mud, sand, gravel and
other forms of unsightly littering. Drivers are required to strictly observe traffic rules
and Village rules and regulations particularly the speed limit of 10 kms / hr. Erring
drivers and their trucks shall be banned from the Village.

10.2 Load Limit - The cement roads of the village are built for a maximum load limit of
twenty (20) tons only. These may be seriously damaged and destroyed by the
trucks with loads that are over the limit. Therefore, the following shall not be
allowed entry into the Village.

10.2.1. Trucks weighing over 20 tons, while loaded


10.2.2 Trucks carrying over 400 bags of cement
10.2.3. Trucks with more than ten (10) wheels
10.2.4. Crawler type trucks

In any case, damage to roads and common areas caused by delivery trucks shall
be charged to the account of the COMMERCIAL UNIT OWNER.
It is the COMMERCIAL UNIT OWNER’s responsibility to advise his/her suppliers of the
load limits in Soluna. The SHOAI shall not be liable for construction delays and/or
damages arising from the banning of overloaded delivery trucks. The preservation
of the roads of the Village shall prevail over any inconvenience or loss to any
supplier and/or contractor.

11 COMPLIANCE

11.1 Violations and/ or non-compliance with any or all of the above guidelines and
requirements and deviations from approved plans shall constitute grounds for work
stoppage (especially when previous notices remain not acted upon). The
Commercial Unit Owner shall be responsible for the communication and
implementation of all Construction Guidelines to his assigned contractor.
11.2 Damage made on common areas or other commercial establishment by the
said construction work should be repaired prior to continuation of work.
COMMERCIAL CONSTRUCTION PLANS REVIEW PROCEDURE

1. Any construction, improvement, addition, alteration, modification, expansion,


reconstruction, renovation or repainting of the Unit, including but not limited to
the construction of the Commercial Structure, eaves, carports or extensions, and
the construction of outdoor structures, shall be subject to the prior written
approval of the Declarant and Association. For said purpose, the Owner shall
submit the complete, detailed plans and specifications to the Declarant and
Association for review, evaluation and approval at least thirty (30) business days
prior to the intended date of commencement of works to be conducted.

2. Prior to the submission of any plans for construction within a Commercial Lot to
any public agency for the purpose of obtaining the relevant permits therefor
and within the period specified in Section IV.B.1, an Owner shall submit three (3)
sets of plans in connection with the proposed construction. The documents to
be submitted to the Declarant and Association shall include, but shall not be
limited to, the following:

a. 1:200 meter scale detailed site development plan showing the lot plan,
building footprint with roof outline, driveway, fence location, outdoor
structures, ripraps retaining walls, landscape development, adjacent street
and sidewalk;
b. 1:50 meter scale floor plans showing the lot plan;
c. 1:50 meter scale elevation drawings for all four (4) building sides; and
d. Perspective drawing of the proposed new construction.

3. Within thirty (30) business days from receipt of the foregoing documents and all
other documents that it shall deem fit to require from the Owner, the Declarant
and the Association shall, at their discretion, either approve, approve with
modifications, or deny the plans, and shall forward such decision to the Owner.

The Declarant and the Association shall have the power to approve, approve with
modifications, or deny the plans and proposed works, and shall advise the applicant of
its decision accordingly. Notwithstanding any approval given by the Declarant and the
Association, the Declarant and Association make no representation as to the suitability
of the design or structural integrity of the Commercial Structure in relation to the soil
conditions or the requirements of the Owner. Moreover, it shall be the sole responsibility
of the Owner to ensure that any construction, improvement, alteration, modification,
expansion, reconstruction, renovation, repainting, extension or expansion on the Unit
complies with the provisions and requirements of the National Building Code, Deed of
Restrictions and Design Standards and other applicable laws, ordinances and
regulations.