Beruflich Dokumente
Kultur Dokumente
Percentage: 73.3%
Duration: 00:14:56
Feedback
Thank you for taking the Developer Open assessment of Scrum. Please read the Scrum Guide on Scrum.org and
take this assessment again to improve your score.
Scrum on,
Ken Schwaber
Question 1 of 30
Correct answer: A)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 1/14
1/18/2020 Finished.
Question 2 of 30
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
B) A way for the team to ensure that the system satisfies the user requirements.
Question 3 of 30
Correct answer: B) C) D) E) F)
You chose: B) C) D) E) F)
Note: This question displayed answer options in random order when taking this Test.
A) Exploratory
B) Functional
C) Integration
D) Smoke
E) Performance
F) Unit
Question 4 of 30
While changing software, you find a bug in a previously delivered piece of functionality. What
should you do?
https://www.classmarker.com/online-test/results/ 2/14
1/18/2020 Finished.
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
A) Fix the bug if it is critical or easily fixed. Otherwise, put the new bug into the Product
Backlog to be prioritized and fixed in an upcoming Sprint.
B) Fix the bug.
C) Stub out the code that caused the bug so it no longer occurs.
D) Revise the tests so that the bug no longer appears on the bug report.
Feedback
Unless your company has specific guidance on fixing bugs, they represent work to be done and should be
ordered on the Product Backlog by the PO.
Two exceptions are if the work to fix the bug is less than the work to actually log it, or if the bug is so critical
that it would be negligent to leave it unfixed.
Question 5 of 30
Correct answer: C) D)
You chose: C) D)
Note: This question displayed answer options in random order when taking this Test.
A) The external business analysts that have prepared the functional details.
B) The stakeholders.
C) The Product Owner.
D) The Development Team.
E) Only the most senior people from the Development Team.
F) The integration architects from the release department.
Question 6 of 30
https://www.classmarker.com/online-test/results/ 3/14
1/18/2020 Finished.
Correct answer: A)
You chose: A)
Question 7 of 30
Correct answer: D)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
D) They provide rapid assurance that defects and configuration management issues have not
been introduced.
Feedback
Builds are just an extra level of validation to make sure that you still have a unit of potentially shippable
software. Automating builds makes that process very faster.
Question 8 of 30
Correct answer: B)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 4/14
1/18/2020 Finished.
C) To ensure that "orphan functions" are not created.
Question 9 of 30
True or False: Only technical writers can create documentation during a Sprint.
Correct answer: B)
You chose: B)
A) True
B) False
Question 10 of 30
Correct answer: A) B) C)
You chose: A) B) C)
Note: This question displayed answer options in random order when taking this Test.
Question 11 of 30
Correct answer: A)
You chose: D)
Question 12 of 30
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
B) Two programmers write code separately. A third programmer integrates the work.
C) The Scrum Team is divided into several two-person Development Teams that consolidate
work in a Scrum of Scrums.
D) A developer and a tester work together to write and test code.
Question 13 of 30
Correct answer: B) C) D) E)
You chose: B) C) D) E)
Note: This question displayed answer options in random order when taking this Test.
Question 14 of 30
https://www.classmarker.com/online-test/results/ 6/14
1/18/2020 Finished.
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) Regression Testing
Feedback
Advanced practices of test-driven development can lead to Acceptance Test-driven development (ATDD) where
the criteria specified by the customer are automated into acceptance tests, which then drive the traditional unit
test-driven development (UTDD) process.
Question 15 of 30
When a Continuous Integration build fails, who ideally ensures the build is repaired?
Correct answer: A)
You chose: A)
B) The person assigned to the configuration management role within the team
Question 16 of 30
https://www.classmarker.com/online-test/results/ 7/14
1/18/2020 Finished.
Correct answer: A)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
B) Never. It is the sole responsibility of the Product Owner to refine the Product Backlog.
Question 17 of 30
Correct answer: A) B) D)
You chose: A) B) D)
Note: This question displayed answer options in random order when taking this Test.
Question 18 of 30
Correct answer: A)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
C) Having the tester in the Development Team write the test plans before coding.
https://www.classmarker.com/online-test/results/ 8/14
1/18/2020 Finished.
Question 19 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
C) Throughout the project, as understanding emerges and the Development Team learns more
about the project.
D) In the beginning of the project, during Sprint 0.
Question 20 of 30
You are on a Scrum Team that is enhancing an existing product. Which is the LEAST useful piece
of documentation you want to have at your disposal?
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
C) Acceptance tests.
D) Detailed designs.
Question 21 of 30
https://www.classmarker.com/online-test/results/ 9/14
1/18/2020 Finished.
Correct answer: B)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
A) A software development practice that continuously integrates feedback from users into
software design.
B) A software development practice where members of a development team integrate and
verify their work frequently, often multiple times each day, to detect integration errors as
quickly as possible.
C) A software development practice where members of a development team all work on the
same computer to ensure a common code base.
D) A software development practice used by Integration Teams to create best practice
branching and merging strategies.
Question 22 of 30
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
D) Coders
Question 23 of 30
What are some shortcomings of code coverage as a measurement for how well a system or
product is tested?
Correct answer: C) D) E)
You chose: C) D) E)
Note: This question displayed answer options in random order when taking this Test.
Feedback
Code coverage is a useful metric, but not in isolation. It should not be considered a replacement for effective
test design techniques.
Question 24 of 30
The definition of "Done" describes the work that must be completed for every Product Backlog
item before it can be deemed releasable. What should the Development Team do when, during the
Sprint, it finds out that a problem outside of their control blocks them from doing all this work?
Correct answer: A)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
C) Complete the work that can be done on as much scope as possible and use the Sprint
Review to plan the rest with the stakeholders.
D) Complete the work that can be done on as much scope as possible and complete the rest
during the "hardening" sprints at the end of the release.
E) Stop using Scrum.
Question 25 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
Feedback
The Daily Scrum is for the people transforming the Product Backlog items into an Increment. Only the people
that are building the product should be present at the Daily Scrum.
Question 26 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
D) Whenever the Quality Assurance group becomes uncertain that the system works.
Question 27 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) None.
D) Scrum Development Teams with excellent technical practices will likely be more successful.
https://www.classmarker.com/online-test/results/ 12/14
1/18/2020 Finished.
Feedback
While technical practices aren't specifically included as a part of Scrum, the rapid pace of development using
Scrum often requires that good technical practices are utilized by Development Teams in order to be
successful.
Question 28 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) To have all code in a single file for easy printing and code reviews.
Question 29 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) The average time or money a Scrum Team spends per Sprint on bug fixes.
Question 30 of 30
https://www.classmarker.com/online-test/results/ 13/14
1/18/2020 Finished.
Correct answer: A) B)
You chose: A) B)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 14/14
1/18/2020 Finished.
Percentage: 76.7%
Duration: 00:16:46
Feedback
Thank you for taking the Developer Open assessment of Scrum. Please read the Scrum Guide on Scrum.org and
take this assessment again to improve your score.
Scrum on,
Ken Schwaber
Question 1 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 1/14
1/18/2020 Finished.
D) A software development practice where members of a development team integrate and
verify their work frequently, often multiple times each day, to detect integration errors as
quickly as possible.
Question 2 of 30
Correct answer: A)
You chose: A)
Question 3 of 30
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) Establish base system architecture and design, install version control and continuous
integration setup.
B) There is no such thing as Sprint 0.
D) Overall planning, base system architecture, base design, version control and continuous
integration setup.
E) Requirements gathering, version control setup, and continuous integration setup.
Feedback
Scrum does not include the concept of a Sprint 0. "Sprint 0" has become a phrase misused to describe the
planning that occurs prior to the first sprint.
https://www.classmarker.com/online-test/results/ 2/14
1/18/2020 Finished.
Question 4 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) Regression Testing
Feedback
Advanced practices of test-driven development can lead to Acceptance Test-driven development (ATDD) where
the criteria specified by the customer are automated into acceptance tests, which then drive the traditional unit
test-driven development (UTDD) process.
Question 5 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) None.
D) Scrum Development Teams with excellent technical practices will likely be more successful.
Feedback
While technical practices aren't specifically included as a part of Scrum, the rapid pace of development using
Scrum often requires that good technical practices are utilized by Development Teams in order to be
successful.
https://www.classmarker.com/online-test/results/ 3/14
1/18/2020 Finished.
Question 6 of 30
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
A) The degree to which the system under test has been exercised by tests.
Question 7 of 30
Correct answer: D)
You chose: D)
Question 8 of 30
Correct answer: A) B) C)
You chose: A) B) C)
Note: This question displayed answer options in random order when taking this Test.
Question 9 of 30
Correct answer: A) D)
You chose: A) D)
Note: This question displayed answer options in random order when taking this Test.
Question 10 of 30
Correct answer: A) B) C) D)
You chose: A) B) C) D)
Note: This question displayed answer options in random order when taking this Test.
A) Code in each test is as small as possible while maintaining readability of the code.
B) Each test makes assertions about only one logical concept.
C) The test executes fast.
D) Each test is independent of other unit tests.
E) They exercise the persistence layer of a solution.
Question 11 of 30
https://www.classmarker.com/online-test/results/ 5/14
1/18/2020 Finished.
Correct answer: A) D)
You chose: A) D)
Note: This question displayed answer options in random order when taking this Test.
Question 12 of 30
True or False: Programmers and testers should not be included in refining Product Backlog items.
Correct answer: B)
You chose: A)
A) True
B) False
Question 13 of 30
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
D) The Scrum Team is divided into several two-person Development Teams that consolidate
work in a Scrum of Scrums.
https://www.classmarker.com/online-test/results/ 6/14
1/18/2020 Finished.
E) Two programmers write code separately. A third programmer integrates the work.
Question 14 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
C) They provide rapid assurance that defects and configuration management issues have not
been introduced.
D) Without them you can't tell if your code works.
Feedback
Builds are just an extra level of validation to make sure that you still have a unit of potentially shippable
software. Automating builds makes that process faster.
Question 15 of 30
Correct answer: B) C) E)
You chose: B) C) E)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 7/14
1/18/2020 Finished.
Question 16 of 30
Who is responsible for the system architecture of a product being developed using Scrum?
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
Question 17 of 30
Correct answer: B)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
Question 18 of 30
Correct answer: A) B) C) D) E) F)
You chose: A) B) C) D) E) F)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 8/14
1/18/2020 Finished.
A) Simple and repeatable reproduction steps.
B) Expected results and observed results.
C) Clear title and proper grammar in report.
D) One bug per report.
E) Build/version where bug was found.
F) Screenshots or other pictures of bug in action when user interfaces are involved.
Question 19 of 30
While changing software, you find a bug in a previously delivered piece of functionality. What
should you do?
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) Revise the tests so that the bug no longer appears on the bug report.
B) Fix the bug if it is critical or easily fixed. Otherwise, put the new bug into the Product
Backlog to be prioritized and fixed in an upcoming Sprint.
C) Stub out the code that caused the bug so it no longer occurs.
Feedback
Unless your company has specific guidance on fixing bugs, they represent work to be done and should be
ordered on the Product Backlog by the PO.
Two exceptions are if the work to fix the bug is less than the work to actually log it, or if the bug is so critical
that it would be negligent to leave it unfixed.
Question 20 of 30
Correct answer: C)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 9/14
1/18/2020 Finished.
A) The continuous restructuring of software to retain flexibility.
D) Having the tester in the Development Team write the test plans before coding.
Question 21 of 30
You are on a Scrum Team that is enhancing an existing product. Which is the LEAST useful piece
of documentation you want to have at your disposal?
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
B) Detailed designs.
D) Acceptance tests.
Question 22 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) To have all code in a single file for easy printing and code reviews.
Question 23 of 30
https://www.classmarker.com/online-test/results/ 10/14
1/18/2020 Finished.
Correct answer: D)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
B) The ratio of number of tests to lines of code in the system being tested
Question 24 of 30
What are ways a Development Team can ensure a good application architecture?
Correct answer: D) E)
You chose: D) E)
Note: This question displayed answer options in random order when taking this Test.
A) The Development Team plans a Sprint 0 at the beginning of a project with the objective of
developing an architecture model used during the following Sprints.
B) The Development Team should assign someone to the role of software architect whose job
it is to make sure a consistent architecture is developed.
C) A Development Team doesn't need an architecture model in Scrum and should focus on
adding functionality. The architecture will come into place without fail as the Development
Team adds functionality.
D) The Development Team plans some time each Sprint to discuss the architecture needed for
the features planned in that Sprint.
E) The Development Team should have a set of guiding architecture principles that every
Development Team member understands and follows when writing code.
Feedback
There is no specific "architect" role on a Scrum team, nor is there an architecture planning Sprint. But, a good
architecture doesn't just happen automatically. Guiding principles and frequent conversations on the team help
ensure that the most appropriate architecture is developed as it is needed by features being developed in the
current Sprint.
https://www.classmarker.com/online-test/results/ 11/14
1/18/2020 Finished.
Question 25 of 30
True or False: The Scrum Team should choose at least one high priority process improvement,
identified during the Sprint Retrospective, and place it in the Product Backlog.
Correct answer: B)
You chose: A)
A) True
B) False
Feedback
False, to ensure continuous improvement, the Sprint Backlog rather than the Product Backlog includes at least
one high priority process improvement identified in the previous Sprint Retrospective meeting.
Question 26 of 30
Correct answer: A) D)
You chose: A) D)
Note: This question displayed answer options in random order when taking this Test.
Question 27 of 30
True or False: Only technical writers can create documentation during a Sprint.
Correct answer: B)
You chose: B)
A) True
B) False
https://www.classmarker.com/online-test/results/ 12/14
1/18/2020 Finished.
Question 28 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) The average time or money a Scrum Team spends per Sprint on bug fixes.
Question 29 of 30
Correct answer: B)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
Question 30 of 30
Correct answer: A)
You chose: D)
https://www.classmarker.com/online-test/results/ 14/14
1/19/2020 Finished.
Percentage: 90%
Duration: 00:09:38
Feedback
Congratulations! Your score on the Developer Open assessment demonstrates you know some Scrum developer
basics.
Scrum on,
Ken Schwaber
Question 1 of 30
Correct answer: E)
You chose: E)
Note: This question displayed answer options in random order when taking this Test.
A) The ratio of number of tests to lines of code in the system being tested
https://www.classmarker.com/online-test/results/ 1/14
1/19/2020 Finished.
Question 2 of 30
Correct answer: B) E)
You chose: B) C)
Note: This question displayed answer options in random order when taking this Test.
A) Class coupling
B) Code Coverage
C) Depth of inheritance
D) Cyclomatic complexity
E) Cycle time per feature
Feedback
Note regarding Code Coverage: Code Coverage might be an indicator, but it would not be considered a
metric of Code Quality.
Question 3 of 30
What are some shortcomings of code coverage as a measurement for how well a system or
product is tested?
Correct answer: A) C) D)
You chose: A) C) D)
Note: This question displayed answer options in random order when taking this Test.
Feedback
https://www.classmarker.com/online-test/results/ 2/14
1/19/2020 Finished.
Code coverage is a useful metric, but not in isolation. It should not be considered a replacement for effective
test design techniques.
Question 4 of 30
Correct answer: E)
You chose: E)
Note: This question displayed answer options in random order when taking this Test.
Feedback
The Daily Scrum is for the people transforming the Product Backlog items into an Increment. Only the people
that are building the product should be present at the Daily Scrum.
Question 5 of 30
Correct answer: B) C) D) E)
You chose: B) C) D) E)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 3/14
1/19/2020 Finished.
Question 6 of 30
Correct answer: E)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
A) Two programmers write code separately. A third programmer integrates the work.
C) The Scrum Team is divided into several two-person Development Teams that consolidate
work in a Scrum of Scrums.
D) Managers doing performance reviews by comparing one programmer's code to another's.
Question 7 of 30
While changing software, you find a bug in a previously delivered piece of functionality. What
should you do?
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) Revise the tests so that the bug no longer appears on the bug report.
C) Stub out the code that caused the bug so it no longer occurs.
D) Fix the bug if it is critical or easily fixed. Otherwise, put the new bug into the Product
Backlog to be prioritized and fixed in an upcoming Sprint.
Feedback
Unless your company has specific guidance on fixing bugs, they represent work to be done and should be
ordered on the Product Backlog by the PO.
Two exceptions are if the work to fix the bug is less than the work to actually log it, or if the bug is so critical
that it would be negligent to leave it unfixed.
https://www.classmarker.com/online-test/results/ 4/14
1/19/2020 Finished.
Question 8 of 30
Correct answer: B) C) E)
You chose: B) C) E)
Note: This question displayed answer options in random order when taking this Test.
Question 9 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
B) A way for the team to ensure that the system satisfies the user requirements.
Question 10 of 30
Correct answer: A)
You chose: A)
https://www.classmarker.com/online-test/results/ 5/14
1/19/2020 Finished.
Note: This question displayed answer options in random order when taking this Test.
B) To have all code in a single file for easy printing and code reviews.
Question 11 of 30
True or False: Only technical writers can create documentation during a Sprint.
Correct answer: B)
You chose: B)
A) True
B) False
Question 12 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
C) They provide rapid assurance that defects and configuration management issues have not
been introduced.
D) Without them you can't tell if your code works.
Feedback
Builds are just an extra level of validation to make sure that you still have a unit of potentially shippable
software. Automating builds makes that process faster.
Question 13 of 30
https://www.classmarker.com/online-test/results/ 6/14
1/19/2020 Finished.
Correct answer: A)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
Feedback
Since the test exists before the code that makes it pass, the test acts a requirement of the system under test.
Question 14 of 30
Correct answer: A) B) D)
You chose: A) B) D)
Note: This question displayed answer options in random order when taking this Test.
Question 15 of 30
Correct answer: C)
You chose: C)
https://www.classmarker.com/online-test/results/ 7/14
1/19/2020 Finished.
Note: This question displayed answer options in random order when taking this Test.
C) The degree to which the system under test has been exercised by tests.
Question 16 of 30
Correct answer: A)
You chose: A)
Question 17 of 30
Correct answer: D)
You chose: D)
Question 18 of 30
https://www.classmarker.com/online-test/results/ 8/14
1/19/2020 Finished.
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
B) Never. It is the sole responsibility of the Product Owner to refine the Product Backlog.
Question 19 of 30
Correct answer: A) B) C) D) E)
You chose: A) B) C) D) E)
Note: This question displayed answer options in random order when taking this Test.
A) Performance
B) Smoke
C) Unit
D) Integration
E) Functional
F) Exploratory
Question 20 of 30
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 9/14
1/19/2020 Finished.
B) Once per day.
C) Whenever the Quality Assurance group becomes uncertain that the system works.
Question 21 of 30
When a Continuous Integration build fails, who ideally ensures the build is repaired?
Correct answer: A)
You chose: A)
B) The person assigned to the configuration management role within the team
Question 22 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
C) Throughout the project, as understanding emerges and the Development Team learns more
about the project.
D) Whenever the assigned architect can join the Development Team.
Question 23 of 30
https://www.classmarker.com/online-test/results/ 10/14
1/19/2020 Finished.
Correct answer: A) C)
You chose: A) C)
Note: This question displayed answer options in random order when taking this Test.
Question 24 of 30
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
Question 25 of 30
What are ways a Development Team can ensure a good application architecture?
Correct answer: C) D)
You chose: C) D)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 11/14
1/19/2020 Finished.
A) The Development Team should assign someone to the role of software architect whose job
it is to make sure a consistent architecture is developed.
B) The Development Team plans a Sprint 0 at the beginning of a project with the objective of
developing an architecture model used during the following Sprints.
C) The Development Team should have a set of guiding architecture principles that every
Development Team member understands and follows when writing code.
D) The Development Team plans some time each Sprint to discuss the architecture needed for
the features planned in that Sprint.
E) A Development Team doesn't need an architecture model in Scrum and should focus on
adding functionality. The architecture will come into place without fail as the Development
Team adds functionality.
Feedback
There is no specific "architect" role on a Scrum team, nor is there an architecture planning Sprint. But, a good
architecture doesn't just happen automatically. Guiding principles and frequent conversations on the team help
ensure that the most appropriate architecture is developed as it is needed by features being developed in the
current Sprint.
Question 26 of 30
True or False: The Scrum Team should choose at least one high priority process improvement,
identified during the Sprint Retrospective, and place it in the Product Backlog.
Correct answer: B)
You chose: B)
A) True
B) False
Feedback
False, to ensure continuous improvement, the Sprint Backlog rather than the Product Backlog includes at least
one high priority process improvement identified in the previous Sprint Retrospective meeting.
Question 27 of 30
Correct answer: C) D) E)
You chose: C) D) E)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 12/14
1/19/2020 Finished.
A) They eliminate the need for Build Engineers.
B) They ensure your product remains bug free.
C) The build process is clearly defined and scripted, making it easy consistent and repeatable.
D) They support continuous integration.
E) They allow frequent validation of the unit of software being worked on, ensuring it remains
in a potentially shippable state.
Question 28 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
C) Regression Testing
Feedback
Advanced practices of test-driven development can lead to Acceptance Test-driven development (ATDD) where
the criteria specified by the customer are automated into acceptance tests, which then drive the traditional unit
test-driven development (UTDD) process.
Question 29 of 30
You are on a Scrum Team that is enhancing an existing product. Which is the LEAST useful piece
of documentation you want to have at your disposal?
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) Acceptance tests.
https://www.classmarker.com/online-test/results/ 13/14
1/19/2020 Finished.
C) Detailed designs.
Question 30 of 30
Correct answer: A) B) C) D) E) F)
You chose: A) B) C) D) E) F)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 14/14
1/19/2020 Finished.
Percentage: 90%
Duration: 00:09:54
Feedback
Congratulations! Your score on the Developer Open assessment demonstrates you know some Scrum developer
basics.
Scrum on,
Ken Schwaber
Question 1 of 30
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 1/14
1/19/2020 Finished.
D) A software development practice that continuously integrates feedback from users into
software design.
Question 2 of 30
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
D) The Scrum Team is divided into several two-person Development Teams that consolidate
work in a Scrum of Scrums.
E) Two programmers write code separately. A third programmer integrates the work.
Question 3 of 30
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) Overall planning, base system architecture, base design, version control and continuous
integration setup.
B) There is no such thing as Sprint 0.
C) Establish base system architecture and design, install version control and continuous
integration setup.
D) Requirements gathering, version control setup, and continuous integration setup.
Feedback
https://www.classmarker.com/online-test/results/ 2/14
1/19/2020 Finished.
Scrum does not include the concept of a Sprint 0. "Sprint 0" has become a phrase misused to describe the
planning that occurs prior to the first sprint.
Question 4 of 30
Correct answer: B) C) D) E)
You chose: B) C) D) E)
Note: This question displayed answer options in random order when taking this Test.
Question 5 of 30
While changing software, you find a bug in a previously delivered piece of functionality. What
should you do?
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) Revise the tests so that the bug no longer appears on the bug report.
B) Fix the bug if it is critical or easily fixed. Otherwise, put the new bug into the Product
Backlog to be prioritized and fixed in an upcoming Sprint.
C) Fix the bug.
D) Stub out the code that caused the bug so it no longer occurs.
Feedback
Unless your company has specific guidance on fixing bugs, they represent work to be done and should be
ordered on the Product Backlog by the PO.
https://www.classmarker.com/online-test/results/ 3/14
1/19/2020 Finished.
Two exceptions are if the work to fix the bug is less than the work to actually log it, or if the bug is so critical
that it would be negligent to leave it unfixed.
Question 6 of 30
Correct answer: C) D) E)
You chose: C) D) E)
Note: This question displayed answer options in random order when taking this Test.
Question 7 of 30
True or False: The Scrum Team should choose at least one high priority process improvement,
identified during the Sprint Retrospective, and place it in the Product Backlog.
Correct answer: B)
You chose: B)
A) True
B) False
Feedback
False, to ensure continuous improvement, the Sprint Backlog rather than the Product Backlog includes at least
one high priority process improvement identified in the previous Sprint Retrospective meeting.
Question 8 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
C) They provide rapid assurance that defects and configuration management issues have not
been introduced.
D) You are unable to check-in code without one.
Feedback
Builds are just an extra level of validation to make sure that you still have a unit of potentially shippable
software. Automating builds makes that process faster.
Question 9 of 30
Correct answer: B) E)
You chose: B) E)
Note: This question displayed answer options in random order when taking this Test.
A) Depth of inheritance
B) Cycle time per feature
C) Class coupling
D) Cyclomatic complexity
E) Code Coverage
Question 10 of 30
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) The average time or money a Scrum Team spends per Sprint on bug fixes.
https://www.classmarker.com/online-test/results/ 5/14
1/19/2020 Finished.
Question 11 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) Having the tester in the Development Team write the test plans before coding.
Question 12 of 30
Correct answer: A) B) C) D) E) F)
You chose: A) B) C) D) E) F)
Note: This question displayed answer options in random order when taking this Test.
Question 13 of 30
https://www.classmarker.com/online-test/results/ 6/14
1/19/2020 Finished.
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
D) Whenever the Quality Assurance group becomes uncertain that the system works.
Question 14 of 30
Correct answer: A) D)
You chose: A) D)
Note: This question displayed answer options in random order when taking this Test.
Question 15 of 30
True or False: Only technical writers can create documentation during a Sprint.
Correct answer: B)
You chose: B)
A) True
B) False
https://www.classmarker.com/online-test/results/ 7/14
1/19/2020 Finished.
Question 16 of 30
To refine Product Backlog items, the following activities will occur implicitly or explicitly:
Correct answer: A) B) E)
You chose: A) C) E)
Note: This question displayed answer options in random order when taking this Test.
A) Design
B) Decomposition
C) Testing
D) Programming
E) Analysis
Question 17 of 30
Correct answer: C)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
Question 18 of 30
https://www.classmarker.com/online-test/results/ 8/14
1/19/2020 Finished.
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
D) Coders
Question 19 of 30
Correct answer: C)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
Question 20 of 30
When a Continuous Integration build fails, who ideally ensures the build is repaired?
Correct answer: A)
You chose: A)
B) The person assigned to the configuration management role within the team
https://www.classmarker.com/online-test/results/ 9/14
1/19/2020 Finished.
Question 21 of 30
Who is responsible for the system architecture of a product being developed using Scrum?
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
Question 22 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) The ratio of number of tests to lines of code in the system being tested
Question 23 of 30
Correct answer: A)
You chose: A)
https://www.classmarker.com/online-test/results/ 10/14
1/19/2020 Finished.
A) From the beginning and throughout all Sprints.
Question 24 of 30
Correct answer: A) C)
You chose: A) C)
Note: This question displayed answer options in random order when taking this Test.
Question 25 of 30
What are some shortcomings of code coverage as a measurement for how well a system or
product is tested?
Correct answer: B) C) E)
You chose: B) C) E)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 11/14
1/19/2020 Finished.
Feedback
Code coverage is a useful metric, but not in isolation. It should not be considered a replacement for effective
test design techniques.
Question 26 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
Feedback
Since the test exists before the code that makes it pass, the test acts a requirement of the system under test.
Question 27 of 30
Correct answer: A) B) C)
You chose: A) B) C)
Note: This question displayed answer options in random order when taking this Test.
Question 28 of 30
https://www.classmarker.com/online-test/results/ 12/14
1/19/2020 Finished.
The definition of "Done" describes the work that must be completed for every Product Backlog
item before it can be deemed releasable. What should the Development Team do when, during the
Sprint, it finds out that a problem outside of their control blocks them from doing all this work?
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) Complete the work that can be done on as much scope as possible and complete the rest
during the "hardening" sprints at the end of the release.
B) Immediately raise the issue to the Scrum Master as an impediment.
C) Complete the work that can be done on as much scope as possible and use the Sprint
Review to plan the rest with the stakeholders.
D) Stop using Scrum.
Question 29 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) Always.
B) They must be provided to the Development Team as part of the user specifications
documents.
C) If they are part of the Definition of "done".
D) Never.
Question 30 of 30
True or False: Programmers and testers should not be included in refining Product Backlog items.
https://www.classmarker.com/online-test/results/ 13/14
1/19/2020 Finished.
Correct answer: B)
You chose: B)
A) True
B) False
https://www.classmarker.com/online-test/results/ 14/14
1/20/2020 Finished.
Percentage: 86.7%
Duration: 00:12:14
Feedback
Congratulations! Your score on the Developer Open assessment demonstrates you know some Scrum developer
basics.
Scrum on,
Ken Schwaber
Question 1 of 30
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
B) They provide rapid assurance that defects and configuration management issues have not
been introduced.
C) Without them you can't tell if your code works.
https://www.classmarker.com/online-test/results/ 1/14
1/20/2020 Finished.
Feedback
Builds are just an extra level of validation to make sure that you still have a unit of potentially shippable
software. Automating builds makes that process faster.
Question 2 of 30
Who is responsible for the system architecture of a product being developed using Scrum?
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
Question 3 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) The ratio of number of tests to lines of code in the system being tested
Question 4 of 30
https://www.classmarker.com/online-test/results/ 2/14
1/20/2020 Finished.
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) The Scrum Team is divided into several two-person Development Teams that consolidate
work in a Scrum of Scrums.
B) Managers doing performance reviews by comparing one programmer's code to another's.
D) Two programmers write code separately. A third programmer integrates the work.
Question 5 of 30
True or False: Only technical writers can create documentation during a Sprint.
Correct answer: B)
You chose: B)
A) True
B) False
Question 6 of 30
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
A) The degree to which the system under test has been exercised by tests.
https://www.classmarker.com/online-test/results/ 3/14
1/20/2020 Finished.
Question 7 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
D) Regression Testing
Feedback
Advanced practices of test-driven development can lead to Acceptance Test-driven development (ATDD) where
the criteria specified by the customer are automated into acceptance tests, which then drive the traditional unit
test-driven development (UTDD) process.
Question 8 of 30
Correct answer: C)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
Question 9 of 30
https://www.classmarker.com/online-test/results/ 4/14
1/20/2020 Finished.
Correct answer: A)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
Question 10 of 30
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
B) To have all code in a single file for easy printing and code reviews.
Question 11 of 30
Correct answer: A) B) C) D) E) F)
You chose: A) B) C) D) E) F)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 5/14
1/20/2020 Finished.
E) Screenshots or other pictures of bug in action when user interfaces are involved.
F) Clear title and proper grammar in report.
Question 12 of 30
Correct answer: A)
You chose: D)
Question 13 of 30
What are ways a Development Team can ensure a good application architecture?
Correct answer: C) E)
You chose: C) E)
Note: This question displayed answer options in random order when taking this Test.
A) A Development Team doesn't need an architecture model in Scrum and should focus on
adding functionality. The architecture will come into place without fail as the Development
Team adds functionality.
B) The Development Team should assign someone to the role of software architect whose job
it is to make sure a consistent architecture is developed.
C) The Development Team should have a set of guiding architecture principles that every
Development Team member understands and follows when writing code.
D) The Development Team plans a Sprint 0 at the beginning of a project with the objective of
developing an architecture model used during the following Sprints.
E) The Development Team plans some time each Sprint to discuss the architecture needed for
the features planned in that Sprint.
Feedback
https://www.classmarker.com/online-test/results/ 6/14
1/20/2020 Finished.
There is no specific "architect" role on a Scrum team, nor is there an architecture planning Sprint. But, a good
architecture doesn't just happen automatically. Guiding principles and frequent conversations on the team help
ensure that the most appropriate architecture is developed as it is needed by features being developed in the
current Sprint.
Question 14 of 30
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
B) Coders
Question 15 of 30
You are on a Scrum Team that is enhancing an existing product. Which is the LEAST useful piece
of documentation you want to have at your disposal?
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
B) Acceptance tests.
D) Detailed designs.
Question 16 of 30
https://www.classmarker.com/online-test/results/ 7/14
1/20/2020 Finished.
While changing software, you find a bug in a previously delivered piece of functionality. What
should you do?
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) Revise the tests so that the bug no longer appears on the bug report.
B) Fix the bug if it is critical or easily fixed. Otherwise, put the new bug into the Product
Backlog to be prioritized and fixed in an upcoming Sprint.
C) Fix the bug.
D) Stub out the code that caused the bug so it no longer occurs.
Feedback
Unless your company has specific guidance on fixing bugs, they represent work to be done and should be
ordered on the Product Backlog by the PO.
Two exceptions are if the work to fix the bug is less than the work to actually log it, or if the bug is so critical
that it would be negligent to leave it unfixed.
Question 17 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
B) Whenever the Quality Assurance group becomes uncertain that the system works.
Question 18 of 30
https://www.classmarker.com/online-test/results/ 8/14
1/20/2020 Finished.
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
C) Overall planning, base system architecture, base design, version control and continuous
integration setup.
D) Establish base system architecture and design, install version control and continuous
integration setup.
E) Requirements gathering, version control setup, and continuous integration setup.
Feedback
Scrum does not include the concept of a Sprint 0. "Sprint 0" has become a phrase misused to describe the
planning that occurs prior to the first sprint.
Question 19 of 30
The definition of "Done" describes the work that must be completed for every Product Backlog
item before it can be deemed releasable. What should the Development Team do when, during the
Sprint, it finds out that a problem outside of their control blocks them from doing all this work?
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) Complete the work that can be done on as much scope as possible and complete the rest
during the "hardening" sprints at the end of the release.
B) Immediately raise the issue to the Scrum Master as an impediment.
C) Complete the work that can be done on as much scope as possible and use the Sprint
Review to plan the rest with the stakeholders.
D) Stop using Scrum.
Question 20 of 30
https://www.classmarker.com/online-test/results/ 9/14
1/20/2020 Finished.
Correct answer: D)
You chose: D)
Question 21 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
A) Never. It is the sole responsibility of the Product Owner to refine the Product Backlog.
Question 22 of 30
Correct answer: B) E)
You chose: B) E)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 10/14
1/20/2020 Finished.
D) The external business analysts that have prepared the functional details.
E) The Development Team.
F) The integration architects from the release department.
Question 23 of 30
Correct answer: A) C)
You chose: A) C)
Note: This question displayed answer options in random order when taking this Test.
Question 24 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
Feedback
Since the test exists before the code that makes it pass, the test acts a requirement of the system under test.
Question 25 of 30
https://www.classmarker.com/online-test/results/ 11/14
1/20/2020 Finished.
To refine Product Backlog items, the following activities will occur implicitly or explicitly:
Correct answer: A) B) D)
You chose: A) B) D)
Note: This question displayed answer options in random order when taking this Test.
A) Design
B) Analysis
C) Testing
D) Decomposition
E) Programming
Question 26 of 30
Correct answer: A) B) C) D)
You chose: A) C) D)
Note: This question displayed answer options in random order when taking this Test.
Question 27 of 30
What are some shortcomings of code coverage as a measurement for how well a system or
product is tested?
Correct answer: C) D) E)
You chose: C) D) E)
Note: This question displayed answer options in random order when taking this Test.
Feedback
Code coverage is a useful metric, but not in isolation. It should not be considered a replacement for effective
test design techniques.
Question 28 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
C) None.
D) Scrum Development Teams with excellent technical practices will likely be more successful.
Feedback
While technical practices aren't specifically included as a part of Scrum, the rapid pace of development using
Scrum often requires that good technical practices are utilized by Development Teams in order to be
successful.
Question 29 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 13/14
1/20/2020 Finished.
A) Code that has not been commented or documented.
D) The average time or money a Scrum Team spends per Sprint on bug fixes.
Question 30 of 30
Correct answer: A)
You chose: A)
https://www.classmarker.com/online-test/results/ 14/14
1/20/2020 Finished.
Percentage: 100%
Duration: 00:08:31
Feedback
Congratulations! Your score on the Developer Open assessment demonstrates you know some Scrum developer
basics.
Scrum on,
Ken Schwaber
Question 1 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) A software development practice that continuously integrates feedback from users into
software design.
B) A software development practice used by Integration Teams to create best practice
branching and merging strategies.
C) A software development practice where members of a development team integrate and
verify their work frequently, often multiple times each day, to detect integration errors as
quickly as possible.
https://www.classmarker.com/online-test/results/ 1/14
1/20/2020 Finished.
D) A software development practice where members of a development team all work on the
same computer to ensure a common code base.
Question 2 of 30
To refine Product Backlog items, the following activities will occur implicitly or explicitly:
Correct answer: B) D) E)
You chose: B) D) E)
Note: This question displayed answer options in random order when taking this Test.
A) Testing
B) Analysis
C) Programming
D) Decomposition
E) Design
Question 3 of 30
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
A) They provide rapid assurance that defects and configuration management issues have not
been introduced.
B) They are part of your "done" criteria.
Feedback
Builds are just an extra level of validation to make sure that you still have a unit of potentially shippable
software. Automating builds makes that process faster.
https://www.classmarker.com/online-test/results/ 2/14
1/20/2020 Finished.
Question 4 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) Having the tester in the Development Team write the test plans before coding.
Question 5 of 30
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
C) Always.
D) Never.
E) They must be provided to the Development Team as part of the user specifications
documents.
Question 6 of 30
https://www.classmarker.com/online-test/results/ 3/14
1/20/2020 Finished.
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
D) A way for the team to ensure that the system satisfies the user requirements.
Question 7 of 30
Correct answer: A) C) D) E)
You chose: A) C) D) E)
Note: This question displayed answer options in random order when taking this Test.
Question 8 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) None.
D) Scrum Development Teams with excellent technical practices will likely be more successful.
https://www.classmarker.com/online-test/results/ 4/14
1/20/2020 Finished.
Feedback
While technical practices aren't specifically included as a part of Scrum, the rapid pace of development using
Scrum often requires that good technical practices are utilized by Development Teams in order to be
successful.
Question 9 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) To have all code in a single file for easy printing and code reviews.
Question 10 of 30
Correct answer: A) B) C) D)
You chose: A) B) C) D)
Note: This question displayed answer options in random order when taking this Test.
Question 11 of 30
https://www.classmarker.com/online-test/results/ 5/14
1/20/2020 Finished.
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
B) The ratio of number of tests to lines of code in the system being tested
Question 12 of 30
While changing software, you find a bug in a previously delivered piece of functionality. What
should you do?
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) Revise the tests so that the bug no longer appears on the bug report.
B) Fix the bug if it is critical or easily fixed. Otherwise, put the new bug into the Product
Backlog to be prioritized and fixed in an upcoming Sprint.
C) Stub out the code that caused the bug so it no longer occurs.
Feedback
Unless your company has specific guidance on fixing bugs, they represent work to be done and should be
ordered on the Product Backlog by the PO.
Two exceptions are if the work to fix the bug is less than the work to actually log it, or if the bug is so critical
that it would be negligent to leave it unfixed.
Question 13 of 30
https://www.classmarker.com/online-test/results/ 6/14
1/20/2020 Finished.
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
Question 14 of 30
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) The average time or money a Scrum Team spends per Sprint on bug fixes.
Question 15 of 30
Correct answer: A) C) D) E) F)
You chose: A) C) D) E) F)
Note: This question displayed answer options in random order when taking this Test.
A) Unit
B) Exploratory
C) Performance
https://www.classmarker.com/online-test/results/ 7/14
1/20/2020 Finished.
D) Integration
E) Smoke
F) Functional
Question 16 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) Coders
Question 17 of 30
Correct answer: E)
You chose: E)
Note: This question displayed answer options in random order when taking this Test.
Feedback
The Daily Scrum is for the people transforming the Product Backlog items into an Increment. Only the people
that are building the product should be present at the Daily Scrum.
https://www.classmarker.com/online-test/results/ 8/14
1/20/2020 Finished.
Question 18 of 30
Correct answer: A) C)
You chose: A) C)
Note: This question displayed answer options in random order when taking this Test.
Question 19 of 30
Correct answer: A)
You chose: A)
Question 20 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 9/14
1/20/2020 Finished.
A) Managers doing performance reviews by comparing one programmer's code to another's.
B) Two programmers write code separately. A third programmer integrates the work.
E) The Scrum Team is divided into several two-person Development Teams that consolidate
work in a Scrum of Scrums.
Question 21 of 30
True or False: Programmers and testers should not be included in refining Product Backlog items.
Correct answer: B)
You chose: B)
A) True
B) False
Question 22 of 30
Correct answer: A)
You chose: A)
Question 23 of 30
https://www.classmarker.com/online-test/results/ 10/14
1/20/2020 Finished.
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
C) The degree to which the system under test has been exercised by tests.
Question 24 of 30
True or False: Only technical writers can create documentation during a Sprint.
Correct answer: B)
You chose: B)
A) True
B) False
Question 25 of 30
Correct answer: A) B) C) D) E) F)
You chose: A) B) C) D) E) F)
Note: This question displayed answer options in random order when taking this Test.
Question 26 of 30
https://www.classmarker.com/online-test/results/ 11/14
1/20/2020 Finished.
Correct answer: B) C) D)
You chose: B) C) D)
Note: This question displayed answer options in random order when taking this Test.
Question 27 of 30
Correct answer: B) F)
You chose: B) F)
Note: This question displayed answer options in random order when taking this Test.
Question 28 of 30
Correct answer: B) C) E)
You chose: B) C) E)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 12/14
1/20/2020 Finished.
B) They allow frequent validation of the unit of software being worked on, ensuring it remains
in a potentially shippable state.
C) The build process is clearly defined and scripted, making it easy consistent and repeatable.
D) They ensure your product remains bug free.
E) They support continuous integration.
Question 29 of 30
True or False: The Scrum Team should choose at least one high priority process improvement,
identified during the Sprint Retrospective, and place it in the Product Backlog.
Correct answer: B)
You chose: B)
A) True
B) False
Feedback
False, to ensure continuous improvement, the Sprint Backlog rather than the Product Backlog includes at least
one high priority process improvement identified in the previous Sprint Retrospective meeting.
Question 30 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
D) Regression Testing
Feedback
Advanced practices of test-driven development can lead to Acceptance Test-driven development (ATDD) where
the criteria specified by the customer are automated into acceptance tests, which then drive the traditional unit
https://www.classmarker.com/online-test/results/ 13/14
1/20/2020 Finished.
test-driven development (UTDD) process.
https://www.classmarker.com/online-test/results/ 14/14
1/19/2020 Finished.
Percentage: 46.7%
Duration: 00:13:15
Feedback
Thank you for taking the Open assessment of Scrum. Please review The Scrum Guide on Scrum.org and take this
assessment again to improve your score.
Ken Schwaber
Question 1 of 30
Correct answer: B) C) E)
You chose: B) C) E)
Note: This question displayed answer options in random order when taking this Test.
A) Customers
B) Product Owner
C) Development Team
D) Users
E) Scrum Master
https://www.classmarker.com/online-test/results/ 1/16
1/19/2020 Finished.
Feedback
The Scrum Team consists of a Product Owner, the Development Team, and a Scrum Master.
Question 2 of 30
Correct answer: D)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
B) Size, where small items are at the top and large items are at the bottom.
C) Risk, where safer items are at the top, and riskier items are at the bottom.
Feedback
The Product Owner decides what makes the most sense to optimize the value of the work being done by the
Development Team.
Question 3 of 30
True or False: Scrum does not have a role called "project manager."
Correct answer: A)
You chose: A)
A) True
B) False
Feedback
A Scrum Team has a Scrum Master, a Product Owner and a Development Team. As a whole they have all
controls needed.
Question 4 of 30
https://www.classmarker.com/online-test/results/ 2/16
1/19/2020 Finished.
Correct answer: D)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
Feedback
The Development Team uses the Daily Scrum to inspect progress toward the Sprint Goal and to inspect how
progress is trending toward completing the work in the Sprint Backlog.
Question 5 of 30
Correct answer: C)
You chose: E)
Note: This question displayed answer options in random order when taking this Test.
A) 2 hours.
B) 1 day.
D) As long as needed.
Feedback
Sprint Review is a four-hour time-boxed meeting for one-month Sprints. For shorter Sprints, the event is usually
shorter.
Question 6 of 30
https://www.classmarker.com/online-test/results/ 3/16
1/19/2020 Finished.
True or False: It is mandatory that the product increment be released to production at the end of
each Sprint.
Correct answer: B)
You chose: A)
A) True
B) False
Feedback
The product increment should be usable and releasable at the end of every Sprint, but it does not have to be
released.
Question 7 of 30
Who has the final say on the order of the Product Backlog?
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) The Stakeholders
D) The CEO
Feedback
The Product Owner is the sole person responsible for managing the Product Backlog.
Question 8 of 30
When does a Development Team member become the sole owner of a Sprint Backlog item?
https://www.classmarker.com/online-test/results/ 4/16
1/19/2020 Finished.
Correct answer: D)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
D) Never. All Sprint Backlog Items are "owned" by the entire Development Team, even though
each one may be implemented by an individual development team member.
Feedback
Sprint Backlog and all of its items are collectively owned by the Development Team. No individual team
member can claim ownership over an item as this would block communication and collaboration.
Question 9 of 30
Which two things does the Development Team do during the first Sprint?
Correct answer: B) C)
You chose: A) B)
Note: This question displayed answer options in random order when taking this Test.
Feedback
The heart of Scrum is a Sprint, a time-box of one month or less during which a "Done", useable, and potentially
releasable product Increment is created. This applies to every Sprint.
Question 10 of 30
The Development Team should not be interrupted during the Sprint. The Sprint Goal should remain
intact. These are conditions that foster creativity, quality and productivity.
https://www.classmarker.com/online-test/results/ 5/16
1/19/2020 Finished.
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) The Development Team may work with the Product Owner to remove or add work if it finds
it has more or less capacity than it expected.
B) As a decomposition of the selected Product Backlog Items, the Sprint Backlog changes
and may grow as the work emerges.
C) The Sprint Backlog is fully formulated in the Sprint Planning meeting and does not change
during the Sprint.
D) The Product Owner can help clarify or optimize the Sprint when asked by the Development
Team.
Feedback
The Sprint Backlog makes visible all of the work that the Development Team identifies as necessary to meet the
Sprint Goal. The Development Team modifies the Sprint Backlog throughout the Sprint, and the Sprint Backlog
emerges during the Sprint.
Question 11 of 30
What is the recommended size for a Development Team (within the Scrum Team)?
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
A) 7 plus or minus 2
B) 9
C) Minimal 7
D) 3 to 9
Feedback
Optimal Development Team size is small enough to remain nimble and large enough to complete significant
work. Fewer than three Development Team members decreases interaction and results in smaller productivity
gains. More than nine members simply requires too much coordination.
Question 12 of 30
https://www.classmarker.com/online-test/results/ 6/16
1/19/2020 Finished.
When many Development Teams are working on a single product, what best describes the
definition of "Done?"
Correct answer: A)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) All Development Teams must have a definition of "Done" that makes their combined work
potentially releasable.
B) Each Development Team defines and uses its own. The differences are discussed and
reconciled during a hardening Sprint.
C) Each Development Team uses its own but must make their definition clear to all other
teams so the differences are known.
D) It depends.
Feedback
Scrum requires an Increment to be releasable. This is an Increment of product. Many teams working on a single
product are expected to deliver such an Increment.
Question 13 of 30
Correct answer: B)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
C) Managing the project and ensuring that the work meets the commitments to the
stakeholders.
D) Keep stakeholders from distracting the Development Team.
Feedback
The Product Owner is responsible for maximizing the value of the product and the work of the Development
Team.
https://www.classmarker.com/online-test/results/ 7/16
1/19/2020 Finished.
Question 14 of 30
Correct answer: A)
You chose: A)
A) True
B) False
Feedback
The heart of Scrum is a Sprint, a time-box of one month or less during which a "Done", usable, and potentially
releasable product Increment is created.
Question 15 of 30
Correct answer: D)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
Feedback
Scrum is founded on empirical process control theory, or empiricism. Empiricism asserts that knowledge
comes from experience and making decisions based on what is known.
Three pillars uphold every implementation of empirical process control: transparency, inspection, and
adaptation.
Question 16 of 30
https://www.classmarker.com/online-test/results/ 8/16
1/19/2020 Finished.
Which of the following services are appropriate for a Scrum Master in regard to the Daily Scrum?
Correct answer: B)
You chose: E)
Note: This question displayed answer options in random order when taking this Test.
B) Teach the Development Team to keep the Daily Scrum within the 15 minute time-box.
C) Facilitate in a way that ensures each team member has a chance to speak.
Feedback
The Scrum Master ensures that the Development Team has the meeting, but the Development Team is
responsible for conducting the Daily Scrum. The Scrum Master teaches the Development Team to keep the
Daily Scrum within the 15-minute time-box. The Scrum Master enforces the rule that only Development Team
members participate in the Daily Scrum.
Question 17 of 30
Why is the Daily Scrum held at the same time and same place?
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
Feedback
The Daily Scrum is held at the same time and place each day to reduce complexity.
Question 18 of 30
https://www.classmarker.com/online-test/results/ 9/16
1/19/2020 Finished.
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
Feedback
Only the people doing the work described on the Sprint Backlog need to inspect and adapt at the Daily Scrum.
If the Scrum Master or Product Owner is also on the Development Team, they will need to be at the Daily
Scrum. Otherwise, the Scrum Master simply has to make sure the Development Team knows how to conduct a
Daily Scrum and does so.
Question 19 of 30
True or False: The Scrum Team should choose at least one high priority process improvement,
identified during the Sprint Retrospective, and place it in the Product Backlog.
Correct answer: B)
You chose: B)
A) True
B) False
Feedback
False, to ensure continuous improvement, the Sprint Backlog rather than the Product Backlog includes at least
one high priority process improvement identified in the previous Sprint Retrospective meeting.
Question 20 of 30
https://www.classmarker.com/online-test/results/ 10/16
1/19/2020 Finished.
Correct answer: A)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
C) When the Development Team feels that the work is too hard.
D) When it becomes clear that not everything will be finished by the end of the Sprint.
Feedback
A Sprint can be cancelled before the Sprint time-box is over. A Sprint would be cancelled if the Sprint Goal
becomes obsolete. This might occur if the company changes direction or if market or technology conditions
change.
Question 21 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
A) Whenever it is done.
B) Monthly.
C) 4 hours.
Feedback
Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the
event is usually shorter.
Question 22 of 30
https://www.classmarker.com/online-test/results/ 11/16
1/19/2020 Finished.
Correct answer: A)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
Feedback
Teams typically go through some steps before achieving a state of increased performance. Changing
membership typically reduces cohesion, affecting performance and productivity in the short term.
Question 23 of 30
Correct answer: C) E) F)
You chose: B) C) F)
Note: This question displayed answer options in random order when taking this Test.
A) Release Testing.
B) Release Retrospective.
C) Sprint Review.
D) Sprint Testing.
E) The Sprint.
F) Daily Scrum.
G) Design Sprint.
Feedback
The Scrum Guide states that all Scrum Events are time-boxed. The Sprint - 1 month or less, Sprint Planning -
maximum 8 hours for a one-month sprint, Daily Scrum - 15-minutes, Sprint Review - maximum 4 hours for a
one-month sprint, and the Sprint Retrospective - maximum 3 hours for a one-month sprint.
Question 24 of 30
https://www.classmarker.com/online-test/results/ 12/16
1/19/2020 Finished.
What is the main reason for the Scrum Master to be at the Daily Scrum?
Correct answer: B)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) He or she does not have to be there; he or she only has to ensure the Development Team
has a Daily Scrum.
C) To write down any changes to the Sprint Backlog, including adding new items, and tracking
progress on the burn-down.
D) To make sure every team member answers the three questions.
Feedback
The Scrum Master enforces the rule that only Development Team members participate in the Daily Scrum.
Question 25 of 30
Correct answer: D)
You chose: D)
A) Short enough to keep the business risk acceptable to the Product Owner.
B) Short enough to be able to synchronize the development work with other business events.
Feedback
All of these choices are appropriate considerations in determining the length of a Sprint.
Question 26 of 30
During a Sprint, a Development Team determines that it will not be able to finish the complete
forecast. Who should be present to review and adjust the Sprint work selected?
https://www.classmarker.com/online-test/results/ 13/16
1/19/2020 Finished.
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
D) The Scrum Master, the project manager and the Development Team.
Feedback
During the Sprint, scope may be clarified and re-negotiated between the Product Owner and Development
Team as more is learned.
Question 27 of 30
Correct answer: B)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) Next Monday.
Feedback
A new Sprint starts immediately after the conclusion of the previous Sprint.
Question 28 of 30
The CEO asks the Development Team to add a "very important" item to a Sprint that is in progress.
What should the Development Team do?
https://www.classmarker.com/online-test/results/ 14/16
1/19/2020 Finished.
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
A) Inform the Product Owner so he/she can work with the CEO.
D) Add the item to the current Sprint and drop an item of equal size.
Feedback
The items selected for a Sprint have been selected as most valuable with the Product Owner. The items serve
the Sprint's goal. No changes should be made that endanger the Sprint Goal. No one external to the Scrum
Team can force changes on the Development Team (Sprint Backlog) and the Product Owner (Product Backlog).
Question 29 of 30
Correct answer: C)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
A) It is a demo at the end of the Sprint for everyone in the organization to check on the work
done.
B) It is a mechanism to control the Development Team's activities during a Sprint.
C) It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out
what to do next.
Feedback
Every event in Scrum, besides the Sprint which is a container for the other events, is an opportunity to Inspect
AND Adapt.
Question 30 of 30
https://www.classmarker.com/online-test/results/ 15/16
1/19/2020 Finished.
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
A) 15 minutes.
C) 4 hours.
Feedback
The length of a daily Scrum is time-boxed at 15 minutes, it does not change with the length of a Sprint.
https://www.classmarker.com/online-test/results/ 16/16
1/20/2020 Finished.
Percentage: 66.7%
Duration: 00:10:51
Feedback
Thank you for taking the Open assessment of Scrum. Please review The Scrum Guide on Scrum.org and take this
assessment again to improve your score.
Ken Schwaber
Question 1 of 30
True or False: The Scrum Team should choose at least one high priority process improvement,
identified during the Sprint Retrospective, and place it in the Product Backlog.
Correct answer: B)
You chose: B)
A) True
B) False
Feedback
False, to ensure continuous improvement, the Sprint Backlog rather than the Product Backlog includes at least
one high priority process improvement identified in the previous Sprint Retrospective meeting.
Question 2 of 30
https://www.classmarker.com/online-test/results/ 1/16
1/20/2020 Finished.
Who should know the most about the progress toward a business objective or a release, and be
able to explain the alternatives most clearly?
Correct answer: B)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
Feedback
The Product Owner is the sole person responsible for managing the Product Backlog, which includes that the
Product Backlog is visible, transparent, and clear to all, and shows what the Scrum Team will work on next.
Question 3 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) 1 day.
D) As long as needed.
E) 2 hours.
Feedback
Sprint Review is a four-hour time-boxed meeting for one-month Sprints. For shorter Sprints, the event is usually
shorter.
https://www.classmarker.com/online-test/results/ 2/16
1/20/2020 Finished.
Question 4 of 30
True or False: When multiple teams work together on the same product, each team should
maintain a separate Product Backlog.
Correct answer: B)
You chose: B)
A) True
B) False
Feedback
Products have one Product Backlog, regardless of how many teams are used. Any other setup makes it difficult
for the Development Team to determine what it should work on.
Question 5 of 30
Correct answer: A)
You chose: A)
A) True
B) False
Feedback
The heart of Scrum is a Sprint, a time-box of one month or less during which a "Done", usable, and potentially
releasable product Increment is created.
Question 6 of 30
During a Sprint, a Development Team determines that it will not be able to finish the complete
forecast. Who should be present to review and adjust the Sprint work selected?
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) The Scrum Master, the project manager and the Development Team.
https://www.classmarker.com/online-test/results/ 3/16
1/20/2020 Finished.
Feedback
During the Sprint, scope may be clarified and re-negotiated between the Product Owner and Development
Team as more is learned.
Question 7 of 30
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
C) Managing the project and ensuring that the work meets the commitments to the
stakeholders.
D) Directing the Development Team.
Feedback
The Product Owner is responsible for maximizing the value of the product and the work of the Development
Team.
Question 8 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 4/16
1/20/2020 Finished.
B) The event must happen at a set time.
Feedback
Time-boxed events are events that have a maximum duration.
Question 9 of 30
When does a Development Team member become the sole owner of a Sprint Backlog item?
Correct answer: C)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
C) Never. All Sprint Backlog Items are "owned" by the entire Development Team, even though
each one may be implemented by an individual development team member.
D) At the Sprint planning meeting.
Feedback
Sprint Backlog and all of its items are collectively owned by the Development Team. No individual team
member can claim ownership over an item as this would block communication and collaboration.
Question 10 of 30
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 5/16
1/20/2020 Finished.
C) When all Product Backlog items meet their definition of done.
Feedback
The duration of a Sprint is fixed and cannot be shortened or lengthened.
Question 11 of 30
What are the two primary ways a Scrum Master keeps a Development Team working at its highest
level of productivity?
Correct answer: B) C)
You chose: B) D)
Note: This question displayed answer options in random order when taking this Test.
Feedback
A Scrum Master is a servant-leader for the Development Team. Facilitation and removing impediments serves a
team in achieving the best productivity possible.
Question 12 of 30
Correct answer: C) E) F)
You chose: B) C) F)
Note: This question displayed answer options in random order when taking this Test.
A) Release Testing.
B) Release Retrospective.
C) Sprint Review.
https://www.classmarker.com/online-test/results/ 6/16
1/20/2020 Finished.
D) Sprint Testing.
E) The Sprint.
F) Daily Scrum.
G) Design Sprint.
Feedback
The Scrum Guide states that all Scrum Events are time-boxed. The Sprint - 1 month or less, Sprint Planning -
maximum 8 hours for a one-month sprint, Daily Scrum - 15-minutes, Sprint Review - maximum 4 hours for a
one-month sprint, and the Sprint Retrospective - maximum 3 hours for a one-month sprint.
Question 13 of 30
Correct answer: A) B) C)
You chose: A) B) C)
Feedback
The Scrum Team consists of the Scrum Master (manages the process), the Product Owner (decides what to do)
and the Development Team (does the work).
Question 14 of 30
Correct answer: E)
You chose: E)
Note: This question displayed answer options in random order when taking this Test.
A) Size, where small items are at the top and large items are at the bottom.
https://www.classmarker.com/online-test/results/ 7/16
1/20/2020 Finished.
B) Items are randomly arranged.
C) Risk, where safer items are at the top, and riskier items are at the bottom.
Feedback
The Product Owner decides what makes the most sense to optimize the value of the work being done by the
Development Team.
Question 15 of 30
True or False: It is mandatory that the product increment be released to production at the end of
each Sprint.
Correct answer: B)
You chose: B)
A) True
B) False
Feedback
The product increment should be usable and releasable at the end of every Sprint, but it does not have to be
released.
Question 16 of 30
The CEO asks the Development Team to add a "very important" item to a Sprint that is in progress.
What should the Development Team do?
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
B) Inform the Product Owner so he/she can work with the CEO.
C) Add the item to the current Sprint and drop an item of equal size.
Feedback
The items selected for a Sprint have been selected as most valuable with the Product Owner. The items serve
the Sprint's goal. No changes should be made that endanger the Sprint Goal. No one external to the Scrum
Team can force changes on the Development Team (Sprint Backlog) and the Product Owner (Product Backlog).
Question 17 of 30
Correct answer: C)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
Feedback
Teams typically go through some steps before achieving a state of increased performance. Changing
membership typically reduces cohesion, affecting performance and productivity in the short term.
Question 18 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
B) Next Monday.
https://www.classmarker.com/online-test/results/ 9/16
1/20/2020 Finished.
Feedback
A new Sprint starts immediately after the conclusion of the previous Sprint.
Question 19 of 30
What is the recommended size for a Development Team (within the Scrum Team)?
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) 9
B) 7 plus or minus 2
C) 3 to 9
D) Minimal 7
Feedback
Optimal Development Team size is small enough to remain nimble and large enough to complete significant
work. Fewer than three Development Team members decreases interaction and results in smaller productivity
gains. More than nine members simply requires too much coordination.
Question 20 of 30
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
B) A defined and predictive process that conforms to the principles of Scientific Management.
Feedback
https://www.classmarker.com/online-test/results/ 10/16
1/20/2020 Finished.
Scrum is not a process or a technique for building products; rather, it is a framework within which you can
employ various processes and techniques.
Question 21 of 30
Which of the following services are appropriate for a Scrum Master in regard to the Daily Scrum?
Correct answer: E)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
A) Facilitate in a way that ensures each team member has a chance to speak.
E) Teach the Development Team to keep the Daily Scrum within the 15 minute time-box.
Feedback
The Scrum Master ensures that the Development Team has the meeting, but the Development Team is
responsible for conducting the Daily Scrum. The Scrum Master teaches the Development Team to keep the
Daily Scrum within the 15-minute time-box. The Scrum Master enforces the rule that only Development Team
members participate in the Daily Scrum.
Question 22 of 30
Correct answer: B)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
A) The Scrum Team, in a collaborative effort where the result is the common denominator of
all members' definitions
B) The development organization (or Development Team if none is available from the
development organization)
C) The Product Owner as he/she is responsible for the product's success
https://www.classmarker.com/online-test/results/ 11/16
1/20/2020 Finished.
Feedback
If the definition of "done" is part of the conventions, standards or guidelines of the development organization,
all Scrum Teams must follow it as a minimum. The Development Team of the Scrum Team can complement it
with elements specific for the product or context.
If "done" for an increment is not a convention of the development organization, the Development Team of the
Scrum Team must define a definition of "done" appropriate for the product.
Question 23 of 30
Correct answer: D)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
A) Complex
B) Hybrid
C) Defined
D) Empirical
Feedback
Scrum is founded on empirical process control theory, or empiricism. Empiricism asserts that knowledge
comes from experience and making decisions based on what is known.
Question 24 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) 4 hours.
B) Monthly.
D) Whenever it is done.
https://www.classmarker.com/online-test/results/ 12/16
1/20/2020 Finished.
Feedback
Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the
event is usually shorter.
Question 25 of 30
An organization has decided to adopt Scrum, but management wants to change the terminology to
fit with terminology already used. What will likely happen if this is done?
Correct answer: D)
You chose: B)
A) Without a new vocabulary as a reminder of the change, very little change may actually
happen.
B) The organization may not understand what has changed with Scrum and the benefits of
Scrum may be lost.
C) Management may feel less anxious.
Question 26 of 30
Why is the Daily Scrum held at the same time and same place?
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
Feedback
The Daily Scrum is held at the same time and place each day to reduce complexity.
https://www.classmarker.com/online-test/results/ 13/16
1/20/2020 Finished.
Question 27 of 30
The Development Team should not be interrupted during the Sprint. The Sprint Goal should remain
intact. These are conditions that foster creativity, quality and productivity.
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
A) The Development Team may work with the Product Owner to remove or add work if it finds
it has more or less capacity than it expected.
B) The Product Owner can help clarify or optimize the Sprint when asked by the Development
Team.
C) As a decomposition of the selected Product Backlog Items, the Sprint Backlog changes
and may grow as the work emerges.
D) The Sprint Backlog is fully formulated in the Sprint Planning meeting and does not change
during the Sprint.
Feedback
The Sprint Backlog makes visible all of the work that the Development Team identifies as necessary to meet the
Sprint Goal. The Development Team modifies the Sprint Backlog throughout the Sprint, and the Sprint Backlog
emerges during the Sprint.
Question 28 of 30
Correct answer: C)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
A) It is a demo at the end of the Sprint for everyone in the organization to check on the work
done.
B) It is a mechanism to control the Development Team's activities during a Sprint.
C) It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out
what to do next.
https://www.classmarker.com/online-test/results/ 14/16
1/20/2020 Finished.
Feedback
Every event in Scrum, besides the Sprint which is a container for the other events, is an opportunity to Inspect
AND Adapt.
Question 29 of 30
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
C) When the Development Team feels that the work is too hard.
D) When it becomes clear that not everything will be finished by the end of the Sprint.
Feedback
A Sprint can be cancelled before the Sprint time-box is over. A Sprint would be cancelled if the Sprint Goal
becomes obsolete. This might occur if the company changes direction or if market or technology conditions
change.
Question 30 of 30
What is the main reason for the Scrum Master to be at the Daily Scrum?
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
A) To write down any changes to the Sprint Backlog, including adding new items, and tracking
progress on the burn-down.
B) To gather status and progress information to report to management.
D) He or she does not have to be there; he or she only has to ensure the Development Team
has a Daily Scrum.
https://www.classmarker.com/online-test/results/ 15/16
1/20/2020 Finished.
Feedback
The Scrum Master enforces the rule that only Development Team members participate in the Daily Scrum.
https://www.classmarker.com/online-test/results/ 16/16
1/20/2020 Finished.
Percentage: 83.3%
Duration: 00:11:56
Feedback
Thank you for taking the Open assessment of Scrum. Please review The Scrum Guide on Scrum.org and take this
assessment again to improve your score.
Ken Schwaber
Question 1 of 30
The Development Team should not be interrupted during the Sprint. The Sprint Goal should remain
intact. These are conditions that foster creativity, quality and productivity.
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) The Development Team may work with the Product Owner to remove or add work if it finds
it has more or less capacity than it expected.
B) As a decomposition of the selected Product Backlog Items, the Sprint Backlog changes
and may grow as the work emerges.
C) The Sprint Backlog is fully formulated in the Sprint Planning meeting and does not change
during the Sprint.
https://www.classmarker.com/online-test/results/ 1/16
1/20/2020 Finished.
D) The Product Owner can help clarify or optimize the Sprint when asked by the Development
Team.
Feedback
The Sprint Backlog makes visible all of the work that the Development Team identifies as necessary to meet the
Sprint Goal. The Development Team modifies the Sprint Backlog throughout the Sprint, and the Sprint Backlog
emerges during the Sprint.
Question 2 of 30
Correct answer: A) C) D)
You chose: B) E) F)
Note: This question displayed answer options in random order when taking this Test.
Feedback
1. Scrum is meant to be implemented as prescribed in the Scrum Guide. For example, the five events
in the Scrum Guide are mandatory, each event has a specific purpose.
2. Scrum does not eliminate the complexity that is inherent in delivering a product in today’s world,
instead it offers a framework for dealing with complexity. By regularly delivering increments of
value teams gain the ability to inspect and rapidly adapt based on the feedback received.
3. Project Managers are not simply replaced by self-organizing teams. Scrum is a framework for
optimizing decision making based on the knowledge and experience of the entire team.
Question 3 of 30
https://www.classmarker.com/online-test/results/ 2/16
1/20/2020 Finished.
Correct answer: E)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
A) 4 hours.
E) 15 minutes.
Feedback
The length of a daily Scrum is time-boxed at 15 minutes, it does not change with the length of a Sprint.
Question 4 of 30
Which of the following services are appropriate for a Scrum Master in regard to the Daily Scrum?
Correct answer: E)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
D) Facilitate in a way that ensures each team member has a chance to speak.
E) Teach the Development Team to keep the Daily Scrum within the 15 minute time-box.
Feedback
The Scrum Master ensures that the Development Team has the meeting, but the Development Team is
responsible for conducting the Daily Scrum. The Scrum Master teaches the Development Team to keep the
Daily Scrum within the 15-minute time-box. The Scrum Master enforces the rule that only Development Team
members participate in the Daily Scrum.
Question 5 of 30
https://www.classmarker.com/online-test/results/ 3/16
1/20/2020 Finished.
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
C) Support the Product Owner with insights and information into high value product and
system capabilities. Support the Scrum Master to cause organizational change that fosters
empiricism, self-organization, bottom-up intelligence, and intelligent release of software.
D) Continually monitor staffing levels of the Development Team.
Feedback
Management has no active role in the actual product development through Scrum. However, management
external to the Scrum team is incredibly important in setting the vision and strategy to guide the overall
direction of the organization.
Question 6 of 30
An organization has decided to adopt Scrum, but management wants to change the terminology to
fit with terminology already used. What will likely happen if this is done?
Correct answer: D)
You chose: D)
A) Without a new vocabulary as a reminder of the change, very little change may actually
happen.
B) The organization may not understand what has changed with Scrum and the benefits of
Scrum may be lost.
C) Management may feel less anxious.
Question 7 of 30
https://www.classmarker.com/online-test/results/ 4/16
1/20/2020 Finished.
Correct answer: D)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
Feedback
The Development Team uses the Daily Scrum to inspect progress toward the Sprint Goal and to inspect how
progress is trending toward completing the work in the Sprint Backlog.
Question 8 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) A defined and predictive process that conforms to the principles of Scientific Management.
Feedback
Scrum is not a process or a technique for building products; rather, it is a framework within which you can
employ various processes and techniques.
Question 9 of 30
Correct answer: B)
You chose: B)
https://www.classmarker.com/online-test/results/ 5/16
1/20/2020 Finished.
Note: This question displayed answer options in random order when taking this Test.
A) Complex
B) Empirical
C) Defined
D) Hybrid
Feedback
Scrum is founded on empirical process control theory, or empiricism. Empiricism asserts that knowledge
comes from experience and making decisions based on what is known.
Question 10 of 30
Correct answer: D)
You chose: D)
A) Short enough to keep the business risk acceptable to the Product Owner.
B) Short enough to be able to synchronize the development work with other business events.
Feedback
All of these choices are appropriate considerations in determining the length of a Sprint.
Question 11 of 30
Correct answer: A) B) C)
You chose: A) B) C)
https://www.classmarker.com/online-test/results/ 6/16
1/20/2020 Finished.
C) The Development Team
D) Project Manager
E) None of the above
Feedback
The Scrum Team consists of the Scrum Master (manages the process), the Product Owner (decides what to do)
and the Development Team (does the work).
Question 12 of 30
Why is the Daily Scrum held at the same time and same place?
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
Feedback
The Daily Scrum is held at the same time and place each day to reduce complexity.
Question 13 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) Whenever it is done.
B) 4 hours.
https://www.classmarker.com/online-test/results/ 7/16
1/20/2020 Finished.
D) Monthly.
Feedback
Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the
event is usually shorter.
Question 14 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) Next Monday.
Feedback
A new Sprint starts immediately after the conclusion of the previous Sprint.
Question 15 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 8/16
1/20/2020 Finished.
Feedback
Teams typically go through some steps before achieving a state of increased performance. Changing
membership typically reduces cohesion, affecting performance and productivity in the short term.
Question 16 of 30
Correct answer: A)
You chose: A)
A) True
B) False
Feedback
The heart of Scrum is a Sprint, a time-box of one month or less during which a "Done", usable, and potentially
releasable product Increment is created.
Question 17 of 30
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
Feedback
Time-boxed events are events that have a maximum duration.
Question 18 of 30
https://www.classmarker.com/online-test/results/ 9/16
1/20/2020 Finished.
Who should know the most about the progress toward a business objective or a release, and be
able to explain the alternatives most clearly?
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
Feedback
The Product Owner is the sole person responsible for managing the Product Backlog, which includes that the
Product Backlog is visible, transparent, and clear to all, and shows what the Scrum Team will work on next.
Question 19 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) Size, where small items are at the top and large items are at the bottom.
E) Risk, where safer items are at the top, and riskier items are at the bottom.
Feedback
The Product Owner decides what makes the most sense to optimize the value of the work being done by the
Development Team.
Question 20 of 30
https://www.classmarker.com/online-test/results/ 10/16
1/20/2020 Finished.
During a Sprint, a Development Team determines that it will not be able to finish the complete
forecast. Who should be present to review and adjust the Sprint work selected?
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) The Scrum Master, the project manager and the Development Team.
Feedback
During the Sprint, scope may be clarified and re-negotiated between the Product Owner and Development
Team as more is learned.
Question 21 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) Managing the project and ensuring that the work meets the commitments to the
stakeholders.
C) Directing the Development Team.
Feedback
The Product Owner is responsible for maximizing the value of the product and the work of the Development
Team.
Question 22 of 30
https://www.classmarker.com/online-test/results/ 11/16
1/20/2020 Finished.
The Development Team should have all the skills needed to:
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
A) Turn the Product Backlog items it selects into an increment of potentially releasable
product functionality.
B) Complete the project as estimated when the date and cost are committed to the Product
Owner.
C) Do all of the development work, except for specialized testing that requires additional tools
and environments.
Feedback
The Development Team consists of professionals who do the work of delivering a potentially releasable
Increment of "Done" product at the end of each Sprint. Development Teams are cross-functional, with all of the
skills as a team necessary to create a product Increment.
Question 23 of 30
True or False: The Scrum Team should choose at least one high priority process improvement,
identified during the Sprint Retrospective, and place it in the Product Backlog.
Correct answer: B)
You chose: B)
A) True
B) False
Feedback
False, to ensure continuous improvement, the Sprint Backlog rather than the Product Backlog includes at least
one high priority process improvement identified in the previous Sprint Retrospective meeting.
Question 24 of 30
What is the main reason for the Scrum Master to be at the Daily Scrum?
https://www.classmarker.com/online-test/results/ 12/16
1/20/2020 Finished.
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
A) He or she does not have to be there; he or she only has to ensure the Development Team
has a Daily Scrum.
B) To make sure every team member answers the three questions.
C) To write down any changes to the Sprint Backlog, including adding new items, and tracking
progress on the burn-down.
D) To gather status and progress information to report to management.
Feedback
The Scrum Master enforces the rule that only Development Team members participate in the Daily Scrum.
Question 25 of 30
How much work must a Development Team do to a Product Backlog item it selects for a Sprint?
Correct answer: D)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
D) As much as it has told the Product Owner will be done for every Product Backlog item it
selects in conformance with the definition of "Done".
Feedback
The purpose of each Sprint is to deliver Increments of potentially releasable functionality that adhere to the
Scrum Team's current definition of "Done".
Question 26 of 30
https://www.classmarker.com/online-test/results/ 13/16
1/20/2020 Finished.
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) When it becomes clear that not everything will be finished by the end of the Sprint.
C) When the Development Team feels that the work is too hard.
Feedback
A Sprint can be cancelled before the Sprint time-box is over. A Sprint would be cancelled if the Sprint Goal
becomes obsolete. This might occur if the company changes direction or if market or technology conditions
change.
Question 27 of 30
What is the recommended size for a Development Team (within the Scrum Team)?
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
A) 3 to 9
B) 9
C) 7 plus or minus 2
D) Minimal 7
Feedback
Optimal Development Team size is small enough to remain nimble and large enough to complete significant
work. Fewer than three Development Team members decreases interaction and results in smaller productivity
gains. More than nine members simply requires too much coordination.
Question 28 of 30
Which two things does the Development Team do during the first Sprint?
https://www.classmarker.com/online-test/results/ 14/16
1/20/2020 Finished.
Correct answer: A) E)
You chose: A) E)
Note: This question displayed answer options in random order when taking this Test.
Feedback
The heart of Scrum is a Sprint, a time-box of one month or less during which a "Done", useable, and potentially
releasable product Increment is created. This applies to every Sprint.
Question 29 of 30
True or False: It is mandatory that the product increment be released to production at the end of
each Sprint.
Correct answer: B)
You chose: B)
A) True
B) False
Feedback
The product increment should be usable and releasable at the end of every Sprint, but it does not have to be
released.
Question 30 of 30
The CEO asks the Development Team to add a "very important" item to a Sprint that is in progress.
What should the Development Team do?
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 15/16
1/20/2020 Finished.
B) Add the item to the current Sprint without any adjustments.
C) Inform the Product Owner so he/she can work with the CEO.
D) Add the item to the current Sprint and drop an item of equal size.
Feedback
The items selected for a Sprint have been selected as most valuable with the Product Owner. The items serve
the Sprint's goal. No changes should be made that endanger the Sprint Goal. No one external to the Scrum
Team can force changes on the Development Team (Sprint Backlog) and the Product Owner (Product Backlog).
https://www.classmarker.com/online-test/results/ 16/16
1/21/2020 Finished.
Percentage: 90%
Duration: 00:10:02
Feedback
Congratulations! Your score on the Open assessment demonstrates you know some Scrum basics.
Scrum on,
Ken Schwaber
Question 1 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 1/16
1/21/2020 Finished.
Feedback
Only the people doing the work described on the Sprint Backlog need to inspect and adapt at the Daily Scrum.
If the Scrum Master or Product Owner is also on the Development Team, they will need to be at the Daily
Scrum. Otherwise, the Scrum Master simply has to make sure the Development Team knows how to conduct a
Daily Scrum and does so.
Question 2 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) As long as needed.
B) 2 hours.
E) 1 day.
Feedback
Sprint Review is a four-hour time-boxed meeting for one-month Sprints. For shorter Sprints, the event is usually
shorter.
Question 3 of 30
When many Development Teams are working on a single product, what best describes the
definition of "Done?"
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) Each Development Team uses its own but must make their definition clear to all other
teams so the differences are known.
B) Each Development Team defines and uses its own. The differences are discussed and
reconciled during a hardening Sprint.
https://www.classmarker.com/online-test/results/ 2/16
1/21/2020 Finished.
C) All Development Teams must have a definition of "Done" that makes their combined work
potentially releasable.
D) It depends.
Feedback
Scrum requires an Increment to be releasable. This is an Increment of product. Many teams working on a single
product are expected to deliver such an Increment.
Question 4 of 30
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
Feedback
Time-boxed events are events that have a maximum duration.
Question 5 of 30
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
https://www.classmarker.com/online-test/results/ 3/16
1/21/2020 Finished.
D) Managing the project and ensuring that the work meets the commitments to the
stakeholders.
Feedback
The Product Owner is responsible for maximizing the value of the product and the work of the Development
Team.
Question 6 of 30
The CEO asks the Development Team to add a "very important" item to a Sprint that is in progress.
What should the Development Team do?
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) Add the item to the current Sprint and drop an item of equal size.
B) Inform the Product Owner so he/she can work with the CEO.
Feedback
The items selected for a Sprint have been selected as most valuable with the Product Owner. The items serve
the Sprint's goal. No changes should be made that endanger the Sprint Goal. No one external to the Scrum
Team can force changes on the Development Team (Sprint Backlog) and the Product Owner (Product Backlog).
Question 7 of 30
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
B) 15 minutes.
https://www.classmarker.com/online-test/results/ 4/16
1/21/2020 Finished.
C) Two minutes per person.
E) 4 hours.
Feedback
The length of a daily Scrum is time-boxed at 15 minutes, it does not change with the length of a Sprint.
Question 8 of 30
An organization has decided to adopt Scrum, but management wants to change the terminology to
fit with terminology already used. What will likely happen if this is done?
Correct answer: D)
You chose: D)
A) Without a new vocabulary as a reminder of the change, very little change may actually
happen.
B) The organization may not understand what has changed with Scrum and the benefits of
Scrum may be lost.
C) Management may feel less anxious.
Question 9 of 30
Who has the final say on the order of the Product Backlog?
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
A) The CEO
C) The Stakeholders
https://www.classmarker.com/online-test/results/ 5/16
1/21/2020 Finished.
E) The Development Team
Feedback
The Product Owner is the sole person responsible for managing the Product Backlog.
Question 10 of 30
How much work must a Development Team do to a Product Backlog item it selects for a Sprint?
Correct answer: D)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
D) As much as it has told the Product Owner will be done for every Product Backlog item it
selects in conformance with the definition of "Done".
Feedback
The purpose of each Sprint is to deliver Increments of potentially releasable functionality that adhere to the
Scrum Team's current definition of "Done".
Question 11 of 30
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
C) Next Monday.
https://www.classmarker.com/online-test/results/ 6/16
1/21/2020 Finished.
Feedback
A new Sprint starts immediately after the conclusion of the previous Sprint.
Question 12 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) It is a demo at the end of the Sprint for everyone in the organization to check on the work
done.
B) It is a mechanism to control the Development Team's activities during a Sprint.
C) It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out
what to do next.
Feedback
Every event in Scrum, besides the Sprint which is a container for the other events, is an opportunity to Inspect
AND Adapt.
Question 13 of 30
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) The Scrum Team, in a collaborative effort where the result is the common denominator of
all members' definitions
B) The development organization (or Development Team if none is available from the
development organization)
C) The Product Owner as he/she is responsible for the product's success
https://www.classmarker.com/online-test/results/ 7/16
1/21/2020 Finished.
Feedback
If the definition of "done" is part of the conventions, standards or guidelines of the development organization,
all Scrum Teams must follow it as a minimum. The Development Team of the Scrum Team can complement it
with elements specific for the product or context.
If "done" for an increment is not a convention of the development organization, the Development Team of the
Scrum Team must define a definition of "done" appropriate for the product.
Question 14 of 30
When does a Development Team member become the sole owner of a Sprint Backlog item?
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
B) Never. All Sprint Backlog Items are "owned" by the entire Development Team, even though
each one may be implemented by an individual development team member.
C) Whenever a team member can accommodate more work.
Feedback
Sprint Backlog and all of its items are collectively owned by the Development Team. No individual team
member can claim ownership over an item as this would block communication and collaboration.
Question 15 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
Feedback
Scrum is founded on empirical process control theory, or empiricism. Empiricism asserts that knowledge
comes from experience and making decisions based on what is known.
Three pillars uphold every implementation of empirical process control: transparency, inspection, and
adaptation.
Question 16 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
B) A defined and predictive process that conforms to the principles of Scientific Management.
Feedback
Scrum is not a process or a technique for building products; rather, it is a framework within which you can
employ various processes and techniques.
Question 17 of 30
True or False: It is mandatory that the product increment be released to production at the end of
each Sprint.
Correct answer: B)
You chose: B)
A) True
B) False
Feedback
https://www.classmarker.com/online-test/results/ 9/16
1/21/2020 Finished.
The product increment should be usable and releasable at the end of every Sprint, but it does not have to be
released.
Question 18 of 30
During a Sprint, a Development Team determines that it will not be able to finish the complete
forecast. Who should be present to review and adjust the Sprint work selected?
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) The Scrum Master, the project manager and the Development Team.
Feedback
During the Sprint, scope may be clarified and re-negotiated between the Product Owner and Development
Team as more is learned.
Question 19 of 30
The Development Team should not be interrupted during the Sprint. The Sprint Goal should remain
intact. These are conditions that foster creativity, quality and productivity.
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
A) As a decomposition of the selected Product Backlog Items, the Sprint Backlog changes
and may grow as the work emerges.
B) The Product Owner can help clarify or optimize the Sprint when asked by the Development
Team.
C) The Development Team may work with the Product Owner to remove or add work if it finds
it has more or less capacity than it expected.
https://www.classmarker.com/online-test/results/ 10/16
1/21/2020 Finished.
D) The Sprint Backlog is fully formulated in the Sprint Planning meeting and does not change
during the Sprint.
Feedback
The Sprint Backlog makes visible all of the work that the Development Team identifies as necessary to meet the
Sprint Goal. The Development Team modifies the Sprint Backlog throughout the Sprint, and the Sprint Backlog
emerges during the Sprint.
Question 20 of 30
Correct answer: A)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
Feedback
The duration of a Sprint is fixed and cannot be shortened or lengthened.
Question 21 of 30
Which of the following services are appropriate for a Scrum Master in regard to the Daily Scrum?
Correct answer: B)
You chose: E)
Note: This question displayed answer options in random order when taking this Test.
A) Facilitate in a way that ensures each team member has a chance to speak.
B) Teach the Development Team to keep the Daily Scrum within the 15 minute time-box.
Feedback
The Scrum Master ensures that the Development Team has the meeting, but the Development Team is
responsible for conducting the Daily Scrum. The Scrum Master teaches the Development Team to keep the
Daily Scrum within the 15-minute time-box. The Scrum Master enforces the rule that only Development Team
members participate in the Daily Scrum.
Question 22 of 30
What are the two primary ways a Scrum Master keeps a Development Team working at its highest
level of productivity?
Correct answer: B) C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
Feedback
A Scrum Master is a servant-leader for the Development Team. Facilitation and removing impediments serves a
team in achieving the best productivity possible.
Question 23 of 30
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) Risk, where safer items are at the top, and riskier items are at the bottom.
C) Size, where small items are at the top and large items are at the bottom.
https://www.classmarker.com/online-test/results/ 12/16
1/21/2020 Finished.
Feedback
The Product Owner decides what makes the most sense to optimize the value of the work being done by the
Development Team.
Question 24 of 30
Correct answer: C) E) F)
You chose: C) E) F)
Note: This question displayed answer options in random order when taking this Test.
A) Design Sprint.
B) Release Retrospective.
C) Sprint Review.
D) Release Testing.
E) Daily Scrum.
F) The Sprint.
G) Sprint Testing.
Feedback
The Scrum Guide states that all Scrum Events are time-boxed. The Sprint - 1 month or less, Sprint Planning -
maximum 8 hours for a one-month sprint, Daily Scrum - 15-minutes, Sprint Review - maximum 4 hours for a
one-month sprint, and the Sprint Retrospective - maximum 3 hours for a one-month sprint.
Question 25 of 30
True or False: Scrum does not have a role called "project manager."
Correct answer: A)
You chose: A)
A) True
https://www.classmarker.com/online-test/results/ 13/16
1/21/2020 Finished.
B) False
Feedback
A Scrum Team has a Scrum Master, a Product Owner and a Development Team. As a whole they have all
controls needed.
Question 26 of 30
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
C) Support the Product Owner with insights and information into high value product and
system capabilities. Support the Scrum Master to cause organizational change that fosters
empiricism, self-organization, bottom-up intelligence, and intelligent release of software.
D) Continually monitor staffing levels of the Development Team.
Feedback
Management has no active role in the actual product development through Scrum. However, management
external to the Scrum team is incredibly important in setting the vision and strategy to guide the overall
direction of the organization.
Question 27 of 30
True or False: When multiple teams work together on the same product, each team should
maintain a separate Product Backlog.
Correct answer: B)
You chose: B)
A) True
B) False
Feedback
https://www.classmarker.com/online-test/results/ 14/16
1/21/2020 Finished.
Products have one Product Backlog, regardless of how many teams are used. Any other setup makes it difficult
for the Development Team to determine what it should work on.
Question 28 of 30
The Development Team should have all the skills needed to:
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) Complete the project as estimated when the date and cost are committed to the Product
Owner.
B) Turn the Product Backlog items it selects into an increment of potentially releasable
product functionality.
C) Do all of the development work, except for specialized testing that requires additional tools
and environments.
Feedback
The Development Team consists of professionals who do the work of delivering a potentially releasable
Increment of "Done" product at the end of each Sprint. Development Teams are cross-functional, with all of the
skills as a team necessary to create a product Increment.
Question 29 of 30
True or False: The Scrum Team should choose at least one high priority process improvement,
identified during the Sprint Retrospective, and place it in the Product Backlog.
Correct answer: B)
You chose: B)
A) True
B) False
Feedback
False, to ensure continuous improvement, the Sprint Backlog rather than the Product Backlog includes at least
one high priority process improvement identified in the previous Sprint Retrospective meeting.
https://www.classmarker.com/online-test/results/ 15/16
1/21/2020 Finished.
Question 30 of 30
Correct answer: D)
You chose: D)
A) Short enough to keep the business risk acceptable to the Product Owner.
B) Short enough to be able to synchronize the development work with other business events.
Feedback
All of these choices are appropriate considerations in determining the length of a Sprint.
https://www.classmarker.com/online-test/results/ 16/16