Abstract Time is one of the factors to assess a worker's performance in utilizing the available resources.
Operator in his work requires efficient time to improve work productivity. One of factory in produce a shrimp
feed in Surabaya has a large production level. In the production process, the packaging department in this
company still uses human resources in their production process and the company define the standard of
production without using standard time. This paper investigates the opportunity a logical analysis in
determining the standard time in this company. The determination of the standard time in the packaging
process requires comprehensive analysis. Objects observed are four operators in the packaging department
that carried out the activities of filling bag the shrimp feed with 40 replication for each data. The work
measurement was conducted by direct method using Stopwatch Time Study (STS) with snap-back method. The
results of this study indicate the standard time value of the four lines packaging is not much different or
almost the same. Sequentially the standard time workers line 1 to line 4 is 7.325 seconds, 7.240 seconds,
7.225 seconds, and 7.065 seconds. Allowance used for workers is 8%. However, the existing production rate
of company is higher than the production rate of work measurement calculation. This is due to the difference
of definition in employee allowance rate and performance rating.
The determination of this standard time is very is within the upper control limits and
important for production especially for lower control limits. The formula used in
production which still uses manual process the calculation of data uniformity is as
(human labor) as main factor. Anything that follows [6].
supports the workforce should be considered 𝑈𝐿𝑆, 𝐿𝑆𝐿 = 𝑥̅ ± 3𝜎 (1)
including performance rating and allowance. Explanation:
Performance rating is an activity used to assess 𝑥̅ : average of processing time
or evaluate the speed of an operator's work [8]. 𝜎 : deviation standard of data
Performance rating is done by comparing the d. Testing adequacy of Data
assessment with the ability of existing standards Testing adequacy of data is done on result
that is the standard of the worker's ability under of a set activity time with the aim whether
normal conditions. While allowance is the data collection has been sufficiently
allocation of time given to the operator for the representative of the population. To
fatigue, personal needs, and other reasons perform this test use 5% accuracy and
beyond the control of the operator [6]. By 95% confidence [9].
setting the standard time, the company can e. Determination of performance rating
realize the target. The determination of the performance
The purpose of this research is to rating is to observe the activities
calculate the standard time on 4 line packaging undertaken by the operator based on the
of shrimp feed product, to determine the Westing House rating system which
allowance that can be given during work, and consists of four elements [6]:
determine the comparative analysis of output 1) Effort
from company with standard output calculation. 2) Ability
This research was conducted by observing the 4 3) Consistency
operators in each line packaging in process of 4) Condition
filling shrimp feeding bag. The data taken in 40 f. Determination of allowance
replication consisting of 3 elements of work. The determination of allowance in this
The timing of work standard is to use direct study is based on four considerations:
measurement which is stopwatch time study 1) Personal needs of the operator
with snap back method. Measurement 2) Fatigue
performance rating using Westing House 3) Avoidable delay
System Rating. Assuming Confidence Level of 4) Unavoidable delay
95% and Degree of Accuracy of 5%, and g. Determination of Standard time
normal distribution of data. Standard time is calculate based on the
normal time that calculated by
2. Research Methods performance rating and allowance. This
This study was conducted by measuring standard time is useful for companies in
working time by sequence such as activity time determining [6]:
measurement, uniformity test, adequacy test, 1) Manpower planning
determination of performance rating,
2) Estimated costs for wages of
allowance, standard time, and standard output.
employees
a. Measurement of activity time
3) Production scheduling and budgeting
b. This measurement is to identify the
4) Planning a bonus reward system and
average time of shrimp feed filling
incentives for outstanding employees
activity. This time measurement is done by
or workers
using stopwatch time study with snap back
5) Identification of output that can be
method. The result will be tested for
produced by a worker.
uniformity and adequacy. When not
meeting the uniformity and adequacy it The standard time is calculated by
will be retrieval data. equation 2[6].
c. Testing Uniformity of data 𝑊𝑠 = 𝑊𝑛 𝑥
100%
(2)
100%−%𝐴𝑙𝑙𝑜𝑤𝑎𝑛𝑐𝑒
A set of data we can call uniform when it
Site this Article As ……….
Paper Accepted : January, 30th 2018
Paper Published : March, 8th 2018 88
JOURNAL OF ENGINEERING AND MANAGEMENT e-ISSN 2477-6025
INDUSTRIAL SYSTEM VOL. 5 NO. 2 YEAR 2017 DOI 10.21776
From the table 10 and 11 shows the Table 15 Cycle Time, Normal Time, and Standard
allowance on each worker by rounding up. The Time at Line 4
result of allowance is used in the next Work Cycle Normal Standard
calculation. Element Time Time Time
A 1,515 1,575 1,713
3.2.4 Calculation of Cycle Time, Normal B 3,473 3,611 3,925
Time, Standard Time, Standard C 1,263 1,313 1,427
Output at Packaging Process Total 6,250 6,500 7,065
Calculating of cycle time, normal time,
and standard time we considering the value of Result of standard time in at line 1-4 use to
the predetermined peformance rating and calculate output standard using equation 3.
allowance. Below is the example. line 1: 1. Output standard for line 1
Element 1: 1
a. Cycle time 𝑂𝑢𝑡𝑝𝑢𝑡 𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 =
𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑇𝑖𝑚𝑒
𝛴𝑋𝑖 1,8+1,2+1,1+1,9+1,3+⋯+1,6 1
𝑊𝐶𝑦𝑐𝑙𝑒 = = = unit/second = 0,137 unit/second
𝑁 40 7,325
= 1,53 second = 8,191 unit/minutes ≈ 9 unit/minutes
Site this Article As ……….
Paper Accepted : January, 30th 2018
Paper Published : March, 8th 2018 91
JOURNAL OF ENGINEERING AND MANAGEMENT e-ISSN 2477-6025
INDUSTRIAL SYSTEM VOL. 5 NO. 2 YEAR 2017 DOI 10.21776