Supports, Part - 1
The subject, "Pipe Supports" is a much more complex subject than the term
suggests.
There are so many situations that a pipe can find itself in and in every case
it will need to be supported.
Pipe supports is a general term that actually is split into two families.
There is what I call the primary pipe support systems, and then there are
the secondary pipe support systems.
The primary pipe supports systems are those supports that are a part of the
infrastructure and fall under the prime responsibility of the structural
department.
The secondary pipe support systems are more a part of the piping systems
and as such fall under the prime responsibility of the piping department.
You notice I used the words 'prime responsibility' with each of these there is
still a cross over responsibility to provide proper, accurate and timely
information and then action.
As noted above the primary pipe supports are a part of the infrastructure.
This is true of most all projects. For simplicity the emphasis here will focus
on "Grass Root" or new construction plants.
These support systems may be major or minor and they may be overhead or
sleeper pipe racks.
It is important to understand that even though they are called pipe racks
they support and carry more than just piping.
These other items may include the cables for electrical and instrumentation
services.
For clarification, overhead pipe racks are elevated to the point where you
can walk and/or drive under the supported piping.
Sleepers or sleeper ways are low to the ground so there is no passage under
the supported piping.
Pipe racks (overhead or sleeper) are normally established and sized early in
the preliminary engineering phase of a project.
This time of the project is normally called the plant development phase or
the plot plan development phase.
Once they are established and sized they are one of the first things the
structural department can work on.
The terms 'establish' and 'size' requires a lot of wisdom and work.
The wisdom and work means thinking one, two or three years into the future
and deciding where (location) the primary pipe support systems will run.
Other critical elements include the configuration, height, width, spacing and
the materials of construction/fabrication method.
Location In order to set the location of the primary pipe support systems the
total plant layout must be established.
This means that all the various disciplines must have a very good idea what
equipment is required and it's size.
The "Plot Plan" must be reviewed by all the key people on the project and
then approved by the client.
Configuration
Each main run, minor run and branch run must be looked at to determine its
configuration.
A second part of the configuration issue effects pipe racks in the process
units themselves.
This is the question of whether or not the pipe rack will support equipment
such as Air Coolers (Fin Fans).
Poor planning on this issue can cause problems later with the piping.
Height
The sleepers are concrete with an imbedded steel plate on the top.
For sleepers, they need to be off the ground to allow for maintenance and
drainage also to prevent corrosion.
For elevated racks you must plan the height and the separation of the whole
system together.
Width This requires a detailed study of the total piping systems for the whole
plant based on pipe rack routing.
In the past, a study (called a "Transposition") was done to, as best you
could, account for each line on each pipe rack.
From this study, a berth sequence was established and the line spacing set.
A percentage was added as an error factor and then the clients "future"
reserve was added.
The final width would be set after all racks were "sized" and then some
might be rounded up in width for consistence based on the materials of
construction/fabrication method.
Spacing
This issue can be addressed after the transposition has been completed.
The transposition identifies all the rack piping from the largest to the
smallest.
From this the average line size for each leg of the rack system can be
established.
With the pipe size information (largest, smallest and average pipe size) the
number and spacing of the pipe support bents can be set.
A cost tradeoff is evaluated and made between more pipe supports spaced
closer together or fewer pipe supports and some sort of intermediate
support system.
Pipe racks can be bare steel, steel w/a concrete encasement (fireproofing),
reinforced concrete or a combination.
The concrete fireproofing can be cast in place onto (or around) the steel
columns and beams or it can be pre-cast onto the columns and beams prior
to installation.
The reinforced concrete pipe supports can also be cast in place or pre-cast
then field erected.
The piping design group on the project (at the company where I came from)
was the lead group in all of the above issues except the last one, materials
of construction/fabrication method.
There is no doubt that economics, the jobsite location, labor and material
availability played a part.
The two branches are defined as (a) "engineered" devices and (b)
"miscellaneous" pipe support devices.
The term "engineered" pipe supports relates to devices that are non-static,
one-of-a-kind, location and condition specific.
They are identified at the time the need is recognized and then designed and
engineered for that specific need.
Constant support spring hangers and snubbers are just two of the devices in
this category.
The piping stress engineer is the party/person who is responsible for the
engineering of these.
However, the piping designer working in the specific area has a shared
responsibility.
All companies have their own operating methods and may not use a different
approach to miscellaneous pipe support devices.
Some may allow each piping designer to pick and choose pieces and parts
from various catalogs to design their own pipe supports.
The term "pre-engineer" means that the various devices are an existing
company standard that may be used on the project.
There is also an "If-then" selection key and criteria established (If you have
"X" support problem, then you can/must use "Y" support device).
The extensive use of computers and plant design software makes this
approach more viable.
Note #1 – This item is normally used only for (a) services subject to heavy
vibration such as at reciprocating compressors or (b) services that contain
highly hazardous or toxic material.
Note #2 – This item is normally only used for the suction and discharge
piping at reciprocating compressors.
Base Anchors – This will occur most often at control valve manifolds (or
stations) situated close to grade or a platform. Base anchors are simply a
stub of pipe (dummy leg) attached to the lower portion of an elbow and
extended to grade (or platform). A square steel plate is welded flat to the
pipe. The plate may have holes in it and be cinch-anchored to the paving or
welded to platform steel. The sizing of the “pipe leg” can be the same as for
Dummy Legs.
Base Guides – This item is constructed of the material and methods as the
base anchor except that the bottom plate is not bolted or welded down. For
this item angle iron strips are installed on two opposite sides (depending on
desired movement) to control the direction.
Base Supports – This is another name for one of the items that sometimes
falls under the name Field Support. This item also has a dummy leg type
pipe extension (or stub) welded down from an elbow. However, the bottom
end if the stub is threaded using a straight (conduit) thread machine. A
straight thread, conduit coupling in then used to make height adjustments to
the support. When this is required for high cost piping materials that require
post weld heat treating the stub is shortened and added in the shop. The
balance of the stub is added in the field from carbon steel. Another variation
of this is restricted to small diameter piping. For this a 3’-0” (1 meter)
length of 3”x3” steel angle is welded to a 6”x6” plate. Holes are drilled in
the angle at the proper elevation and a “U” bolt secures the pipe to the
angle.
Directional Anchor – This item could also be called a Directional Guide and
is most often associated with hot piping. This item is designed to allow for
thermal movement in a specific axis. The design may require longitudinal
movement or it may require side-to-side movement of a line. This item has
two versions, one for longitudinal movement and a second for the
side-to-side movement. Remember this most often occurs in hot piping.
Hot piping also requires shoes to elevate the line and the insulation above
the pipe support. So we have a pipe, a hot pipe, already on a shoe. Now, to
allow for longitudinal movement we simply add (weld) Guides to the top
(steel) surface of the pipe support. To allow for side-to-side movement in
the pipe we DO NOT ADD GUIDES. We add two pieces piece of steel (“T” or
channel) to the bottom of the pipe shoe, one on each side of the pipe
support with a small (1/4”) gap to avoid binding.
Dummy Support Legs – (or Dummy Legs) – This is simply a piece of pipe
extended from an elbow to provide support when a pipe line enters or leaves
a pipe rack short of a support and is left improperly support. A stub or
length of pipe sized to carry the load is welded to the elbow and extended
beyond the support. The length and the wall schedule of the pipe extension
are a rather complex formula based on the parent line size and the total
load. The total load is based on the distance (indirection of flow) from the
last support to the drop, the distance of the drop, the distance from the drop
to the next support, the weight of any insulation plus the weight of the
hydrotest water or commodity which ever is greater.
(The term “Field Support” (or F.S.) is seen on old drawings from existing
plants of years ago. It was used on drawings with only a simple symbol
indicating a location. This may have occurred when the piper got lazy or did
not know enough about pipe supports. The intention was for the installation
contractor “Field” to do what ever they chose to do with whatever material
that was available.)
These are:
Hanger Rods – These devices are one of the most dangerous items used in
the piping field. In many if not most cases they are not properly “designed”.
Hanger Rods, Rod Hangers and Pipe Hangers all terms for the same device.
There are three basic types of Hanger support devices: (type 1)
beam-to-pipe, (type 2) pipe-to-pipe and (type 3) beam-to-beam (or
trapeze). In general they all have three components, a top connection
component, a connector component and a bottom component. For the type
1 Hanger the top component normally connects to a structural beam. The
connector component is normally steel rod. The bottom component is
normally a pipe clamp. For the type 2 Hanger the top component is also a
pipe clamp. Other components are the same as type 1. For the type 3
Hanger there are two top connector components and two connector rods.
The bottom component is a piece of steel angle or channel sized to span the
distance and carry the intended load.
The danger with the design of these items is in the lack of knowledge of the
people doing the design. They do not know how to calculate all the actual
dead and live loading that the Hanger will support. Then they choose the
wrong type or strength of component for the intended load.
Load Distribution Pads – This is simply a 120 degree section of pipe about
18” long. The Pad is cut from the same material as the subject line. The
Pad is opened up a little to fit the pipe O. D. and then welded to the pipe at
the required location.
Shoes – This device is required to raise a hot insulated off the structural
support surface. The reason for this is to prevent damage to the insulation
as the pipe expands as it heats up and shrinks as it cools down. For pipe
sizes 3” thru 10” a simple inverted “T” shoe with a flat bottom plate and one
(single) vertical plate should be used. For pipe sizes 12” thru 18” a shoe
with a flat bottom plate and two (double) vertical plates should be used. For
pipe sizes 20” and larger consideration should be given to the addition of a
Load Distribution Plate (see above) where thin wall pipe may exist. The
material for pipe shoes will normally be carbon steel. However, where the
pipeline is an exotic material this would cause a weld of dissimilar metals to
exist where the shoe is attached to the pipe. For shoes used on exotic
materials only the bottom plate is carbon steel. The (single or double)
vertical plates are made of the same material as the pipe. For piping that
requires post weld heat treating (PWHT) after fabrication the shoes must be
added by the shop. Some company’s (engineering and client) will also
require the use of shoes (with the Load Distribution Pad) for all uninsulated
24” and larger piping where the pipe wall is below a certain limit.
Trunnions – For this device a vertical pipeline will have two (2) stub pipes
attached horizontally to opposite sides of the pipe. One end of these stub
pipes is shaped to fit the O.D. of the vertical pipe the other end is normally
square cut. The shaped end of the stubs are welded to the vertical pipe with
a full penetration (*) fillet weld. When used on a pipe attached to and
supported from a vertical vessel the vessel department supplies the primary
support. Coordination of size, type, elevation, orientation, etc. between the
piping designer and the vessel group is required. When used on a pipe
attached to and supported from a vertical structure the structural
department supplies the primary support. Coordination of size, type,
elevation, location, etc. between the piping designer and the structural
group is required.
(*) This full penetration refers to the wall thickness of only the stub pipes
not the vertical pipe.
The recommended practice for all of these secondary pipe support devices is
to determine what is needed. Start out with items that are found to have
consistent and repetitive use within the company’s past projects. Document
each device complete with parts list and installation instructions.
(Documenting also includes the updates required for any electronic design
system database, AutoCAD, PDS, PDMS or other) Qualify each device by the
specific use criteria based on pipe size, load limitations and application.
Define the selection criteria for each based on the qualification criteria. Then
train all the piping designers, stress engineers, material group and
construction contractors on the responsibility, purpose, use, application and
limitations.
There are of course other opinions on this subject and there are no doubt
questions and more that can be discussed. The other opinions I will warmly
accept. And, as for the questions, please ask. If you don’t ask you will
never give others a chance to offer answers.