Beruflich Dokumente
Kultur Dokumente
Prepared by
Dr. Shubhajit Sadhukhan
Assistant Professor
Department of Architecture and Planning
Indian Institute of Technology Roorkee
Causes of Dampness
• Defective Building Materials
• Faulty Design
• Bad Workmanship
• Capillary Action
• Moisture
Sources of Dampness
• Rising Damp through Foundation
Walling
• Splash Water
• Penetration of Rain Water through
Unprotected Walls
• Penetration of Rain Water through
Defective Roof Covers
• Condensation of Water
• Inadequate Roof Slop (Flat Roof)
• Leakage in Wet Areas (Bathroom,
Kitchens, Water Closet, etc.)
Rising Damp
Methods of Damp-Proofing
➢ Membrane Damp-proofing
➢ Integral Damp-Proofing
➢ Surface Treatment
➢ Guniting
➢ Cavity Wall Construction
Membrane Damp-proofing
• Proving layer or membrane of water repellent material between the source
of dampness and the part of structure adjacent to it
• Also known as Damp proof Course (D.P.C.)
Integral Damp-Proofing
• Adding water-proofing compounds with the concrete mix to increase
impermeability
• Alkaline silicates, Aluminium Sulphates, Calcium Chlorides
• Puldlo, Sica, Impermo, etc.
Surface Treatment
• Filling up the pores of the surfaces subjected to dampness
• Bituminous solution, cement coating, transparent coatings to wall surface
Guniting
• Depositing an impervious layer of rich cement mortar (1:3 or 1:4) over the
surface to be waterproofed.
✓ Treatment to Floors
✓ Treatment to Walls
Treatment to Foundations
Treatment to Floors
• In place where the water table low and rainfall is not much,
• A 75 mm to 100 mm thick layer of coarse sand is first over the entire
area of the flooring over the rammed earth
• A 75 mm to 100 mm thick layer of lean cement concrete (1:3:6) or (1:4:8)
mix or lime concrete is placed over the sand soiling
Treatment to Floors
Treatment to Walls
• Pointing
• Painting
• Plastering
• Surface treatment with damp-proof chemicals
2. Lay bitumen felt in single layer over the hot bonding material laid in step 1, the end
and side laps for felt being not less than 100 and 75 mm respectively
3. Apply hot bitumen at the rate of 1.2 kg/m2 over the bitumen felt laid in step 2
4. Spread pea-sized gravel or grit at the rate of 0.008 m3 per square meter over the layer
2. Lay bitumen felt in single layer over the hot bonding material laid in step 1, the end
and side laps for felt being not less than 100 and 75 mm respectively
3. Apply hot bitumen at the rate of 1.2 kg/m2 over the bitumen felt laid in step 2
4. Lay bitumen felt in single layer over the hot bonding material laid in step 3, the end
and side laps for felt being not less than 100 and 75 mm respectively
5. Apply hot bitumen at the rate of 1.2 kg/m2 over the bitumen felt laid in step 4
6. Spread pea-sized gravel or grit at the rate of 0.008 m3 per square meter over the layer
1. Lay 100 mm thick (average) lime concrete over the roof slab (with proper slope)
2. Apply hot bitumen solution over lime concrete as a primer coat
3. Lay bitumen felt over the primer coat
1. Apply hot bitumen at the rate of 1.7 kg/m2 over the roof surface
2. Spread immediately, coarse sand at the rate of 0.6 m3 of sand per 100 m2 roof surface
3. Lay 100 mm thick (average) lime concrete over the layer (with proper slope)
4. Lay two course of flat brick tiles over the compacted layer of concrete in cement
mortar (1:3), joints are pointed with cement mortar
Department of Architecture and Planning Building Construction-II (ARN203)
Indian Institute of Technology Roorkee
Damp-Proofing and Water-Proofing of Buildings
1. Apply hot bitumen at the rate of 1.7 kg/m2 over the roof surface
2. Spread immediately, coarse sand at the rate of 0.6 m3 of sand per 100 m2 roof surface
3. Lay 100 mm thick (average) mud phuska (@ 8.1 kg bhusa / m3 clay)with proper slope)
4. Plaster the consolidated layer of mud phuska with 13 mm thick coat of mud gobri mortar
(3:1)
5. Lay two course of flat brick tiles over the compacted layer of concrete in cement mortar
(1:3), joints are pointed with cement mortar
Department of Architecture and Planning Building Construction-II (ARN203)
Indian Institute of Technology Roorkee
Damp-Proofing and Water-Proofing of Buildings
1. Lay 15 mm thick coat of slurry made up of neat cement mortar (1:4) mixed with acrylic
based chemical
2. Provide a layer of broken brick bats in cement mortar (1:4) with proper slope
3. Layer of terracing in step 2 is cured for 2 days and lay a thick coat of cement mortar (1:4)
4. Lay 20 mm thick layer of cement mortar admixed with acrylic. Top layer is marked with
300 mm x 300 mm false square
5. Cure the terracing for a period of 2 weeks
Department of Architecture and Planning Building Construction-II (ARN203)
Indian Institute of Technology Roorkee
Damp-Proofing and Water-Proofing of Buildings
Further Readings
Books
• Building Constriction by Sushil Kumar
• Construction Waterproofing Handbook by Michael T. Kubal
• Building Construction by B.C. Punmia, Ashok Kumar Jain, Arun Kumar Jain