Beruflich Dokumente
Kultur Dokumente
CURRENT TRENDS
TOPICS
Legality of Contracts
4. Labour contract
Advantages:
The final price is known, by the owner, before the work commences.
The contractor has more incentive to reduce his cost to increase the
profit.
The contractor hopes to complete the job as quickly as possible, to
minimize overhead, to maximize profit and to move to the next Job.
When level of risks is low and quantifiable, and
When the client does not wish to be involved in the management of his
project.
That can be accurately and completely described at the time of bidding
such as residential and building construction.
When limited variation is needed.
The materials used on the temporary works during construction are
relieved earlier resulting in their effective use in other works also.
Disadvantages:
o The owner tries to get the maximum work out of money he spends,
whereas the contractor tries to get the maximum profit, this causes
conflicting interests.
o It becomes very difficult to adjust the additions and alterations in the
plan and the specifications at a later stage.
o If the plans and specifications are not clear, the contractors will quote
higher rates, resulting in high cost of the work.
o The contractor carries much of the risks. The tendered price may include
high risk contingency.
o Competent contractors may decide not to bid to avoid a high-risk lump
sum contract.
The additions and alterations in the plan and specifications can be easily
made at any stage.
As the contractor gets the payment against the actual quantities of items
done by him, the method is economical. No possibility for excess
payment.
As the rates are item-wise the contractor is not worried regarding the
uncertainties in the plan and specifications.
The work can be started after accepting the tenders without waiting for
all the detailed drawings and specifications.
Disadvantages:
The total cost of the work can only be computed after completion of
entire project. In such case the owner may face financial difficulties if final
cost increases abnormally.
Before preparing the bills for payment of money to the contractor, all
measurements of various items of work have to be carefully taken and
suitably entered in the measurement book.
Great care shall be taken by the department officers to strictly enforce
the specifications during execution of work to avoid the using of
substandard materials by the contractor.
Contractor raises prices on certain items if he apprehends the quantity of
those items is likely to increase during execution and make corresponding
reductions of prices on other items, whose quantity likely to reduce during
execution. This increases total cost of the project.
4. Labour contract
In this type of contract, all materials for the construction are
arranged and supplied at the site of work by the department or owner.
The labour contractor engages the labour and gets the work done
according to specifications. The contract is on item rate basis for labour
portion only.The contractor is paid for the quantities of work done on
measurement of the different items of work at the stipulated rate as in
agreement. Contractor uses his own tools for working. Plants and
machineries are arranged by the department or owner. This system of
contract is not generally adopted in government works but preferable for
private sectors
5. Bill of quantities: Giving quantities and rates of each item of work and
the total cost of the whole work.
9. Drawings: Complete set of drawings like plans, elevations, etc. and site
plan, of fully dimensioned
Conditions of Contract
Both parties of a construction team should be fully
acquainted with their rights and duties. So while preparing the contract
agreement, certain clauses related to the work are laid down and these
will be binding on both parties. The main purpose of the conditions of
contract is to avoid dispute and keep the parties as far as possible out of
the court of law. Therefor it is imperative that all the clauses of conditions
of contract must be precise and definite and there should not be any
room for ambiguity or misconstruction therein.
The conditions of contract mainly depend upon the nature of
the work. For most of the civil engineering construction projects following
clauses are mostly provided in the contract documents:
VALUATION
Definition
Valuation is the technique of determination of fair price of a
property such as land, building, factory or other structures. Valuation
determines present value of the property for sale or renting purpose.
Cost means the original cost of construction minus the loss due to
its age and change in taste or fashion.
Price is the amount calculated adding the cost of the production,
interest on investment and profit to the producer or the owner.
Value is the worth or utility of a property. Value of a property
depends largely on the demand and supply.
For example the cost to draw a painting may be 1,000/-
rupees, but by adding profit for the painter the price may be fixed at
1,500/- rupees. Let us consider the painting is a very famous painting
whose demand is more (like Monalisa by Leonardo da Vinci) then the
value of the painting may be significantly high.
Rent Fixation
To work out the insurance value of a property
To determine the quantum of loan that can be sanctioned against
a property as mortgage or security
For compulsory acquisition of the property by govt. for public
purpose.
To determine the speculative value of a property, i.e. the purchase
of a property with intention to sale at a later date and to make
some profit.
To fix up the betterment charges, i.e. construction of new road,
providing market complex, community hall etc. so that the value of
the property will increase.
Terminology
1. Incomes:
management and collection charges, sinking fund, and loss of rent (for
c) Net income: The amount left after deducting all outgoings from the
gross income.
2. Scrap value
3. Salvage value
Scrap value of an asset is merely sale Salvage value deposition may take the
of scarp and has a limitation. form of a sale of the asset to a
purchaser who will continue to use it
for the function for which it was
originally designed. In this case salvage
value dominate scrap value in the
calculation of depreciation
Scarp value is not counted as a minus There are time when it may be a minus
quantity. quantity
4. Year’s purchase
Rate of interest = 8%
In order to get an annual interest equal to the net annual rent of Rs. 25,000
(8/100) * X = 25000
6. Obsolescence
The value of property decreases if its style and design are outdated
i.e rooms not properly set, thick walls, poor ventilation etc. The reason of this is
fast changing techniques of construction, design, ideas leading to more
comfort etc.
7. Market value
Book value is the amount shown in the account book after allowing
necessary depreciations. The book value of a property at a particularly year is
the original cost minus the amount of depreciation up to the previous year.
Market value is considered for the Book value is considered for the
valuation accounts book of a company
9. Annuity
sinking fund,
Depreciation
It is the loss in value of a building or property due to structural
deterioration, wear and tear, decay and obsolescence. It depends on use, age,
nature of maintenance etc. A certain percentage (per annum) of the total cost
may be allowed as depreciation to determine its present value.
Depreciation Obsolescence
This is the physical loss I the value of the This is the loss in the value of the
property due to wear & tear, decay property due to the change in design,
etc. fashion, in structure of the other,
change of utility and demand.
Depreciation depends on its original Obsolesce depends on normal
condition, quality of maintenance and progress in the arts, inadequacy to
mode of use present or growing needs etc.
This is variable according to age of the This is not dependent on age of the
property. More is the age, more will be building. A new building may suffer in
the amount for depreciation its usual rent due to obsolescence.
There are different methods by which At present there is no method of
the amount of depreciation can be calculation of obsolescence
calculated
Calculation of Depreciation
The amount of depreciation being known, the present value
of the property can be calculated after deducting the total amount of
depreciation from the original cost.
The property is studied in detail and loss in value worked out. Each
step is based on some logical reasoning without any fixed percentage of the
cost of the property. Only an experienced valuator can work out the amount of
depreciation and the present value of the property using this method.
Present day cost may be estimated from the records, Estimates and
Bill of Quantities. If the actual cost of construction is known, this may increase or
decrease according to the percentage rise or fall in the rate obtained from the
PWD Schedule of Rates. Following are the methods to ascertain the present day
cost of a building:
The plinth area of the building is measured and the present day
plinth area rate of similar buildings in the locality is studied, and the cost
calculated. It is necessary to examine thoroughly the different parts of the
building including the foundation, structure, doors & windows, finishes etc.
2. Estimation of present day value of the building
Following methods are available to determine value of a building:
c. Rental method
Introduction
Freedom of Contract
Morality of Promise
Fairness