1.0 INTRODUCTION
Proper pre-commissioning of new electrical equipment is important to prove that new equipment has
been properly shipped and correctly erected and installed. This Procedure highlights the necessary steps
related to proper pre-commissioning of new electrical equipment.
As a general practice, all equipment is tested in the factory before delivery to the site. Pre-commissioning
testing at site is done to prove that:
1.1 Purpose
1.2 Procedure
This Procedure is divided to two parts: the first part describes organizing the work at site before,
during and after pre-commissioning tests.
The second part concerns the mechanical checks, inspections and electrical tests to be
performed on the equipment before commissioning the equipment into service.
Table of Contents
Title Page
ORGANIZATION OF THE WORK SITE FOR PRE-COMMISSIONING 5
1.0 INTRODUCTION 5
2.0 PROCEDURES 5
3.0 WITNESSING COMMENCEMENT 7
4.0 ISSUING SITE INSTRUCTIONS/RECORDS 10
5.0 SAFETY & COORDINATION MEETING 14
6.0 TECHNICAL PROBLEM REPORT 14
6.0 TIME AND QUALITY MANAGEMENT 15
7.0 UNCONTROLLABLE PROJECT DELAY FORM 16
8.0 ENTITY HAND OVER FORM 17
9.0 FINAL PRE COMMISSIONING REPORT AND CONTRACTOR’S EVALUATION 17
10.0 IMPLEMENTATION & IMPROVEMENT 18
MECHANICAL TESTS, VISUAL INSPECTIONS AND ELECTRICAL TESTS 20
1.0 INTRODUCTION 20
2.0 PURPOSE 20
3.0 PROCEDURE FOR TESTING OF MAIN EQUIPMENT 20
3.1 Oil Filled Power Transformer 22
3.2 Shunt Reactors 26
3.3 Bushings Inspection and Testing 29
3.4 Surge Arrestors 30
3.5 Station Service Transformers (less than 2 MVA) 31
3.6 Neutral Earthing Resistors. 33
3.7 Current Transformers 34
3.8 Potential Transformers 35
3.9 Capacitive Voltage Transformers 36
3.10 Coupling Capacitor Voltage Transformer 37
3.11 Gas Insulated Switchgear (GIS) 38
3.12 Metal Clad Switchgear 44
3.13 Metal Enclosed Bus Duct 48
3.14 Indoor and Outdoor Bus Structures 49
3.15 Indoor Circuit Breakers 50
3.16 Outdoor Circuit Breakers 53
3.17 Disconnect & Grounding Switches 56
3.18 Circuit Switchers 58
3.19 LV Switchgear (110/220 V) 59
3.20 230kV and 380kV XLPE Cables 60
3.21 230 kV and 380kV LPOF Cables 62
3.22 110kV and 115kV and 132kV XLPE cables 64
3.23 110kV and 115kV and 132kV LPOF Cables 65
3.24 69 kV XLPE power Cables 67
3.25 13.8 kV and 33 kV XLPE Power Cables 69
3.26 LV Cables 70
3.27 Control Cable 71
3.28 Pilot Cables 72
3.29 Overhead Lines 74
3.30 Protection and Control 76
3.31 Station Batteries 85
3.32 Battery Charger 87
3.33 AC Distribution Panels 89
3.34 DC Distribution Panels 90
3.35 LV AC Auto-Transfer Schemes/Switches 91
3.36 GROUNDING SYSTEM 92
3.37 Switchgear Air Compressor Systems 93
3.38 HVAC Systems 95
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Part I
Title: INDEX NO.
1.0 INTRODUCTION
Pre-commissioning tests for a new or reinforcement project are to be checked thoroughly and witnessed
by an SEC Commissioning engineer or technician. During the course of the commissioning it has been
observed that at many stages the contractors are not ready and consequently the Commissioning
personnel have to wait with the result that some tests may be missed or ignored. A procedure is required
to check the complete readiness of the contractor before the pre-commissioning tests and prepare the
commissioning engineer/technician for applying commissioning tests as per SEC commissioning
Procedure. This document briefly outlines the necessary steps to be followed to ensure that contractors
are ready to start the pre -commissioning in order to reduce or maintain the approved project milestones
and control the quality of the commissioning tests.
The main purpose of this procedure is to provide necessary guidelines to ensure the readiness of the
contractors to start the pre-commissioning testing of new or reinforcement projects and how to apply and
perform the pre-commissioning tests ensuring that:
2.0 PROCEDURES
Project Management shall confirm the readiness of the contractor from all aspects. A joint
inspection shall be conducted with commissioning personnel and the contractor to ensure the
contractor‟s readiness to start the project after written confirmation is received from Project
Management.
Equipment is installed and has been inspected by the SEC Project Quality Unit.
Availability of contractor‟s qualified manpower and testing engineers.
Availability of tools and test equipment with one-year valid calibration certificate.
Insulation Resistance test and pre check of all wiring.
Stable power supply for testing
The site is safe for testing.
Approved relay settings and drawings.
Site office as per SEC requirements.
Over-all approved schedule along with approved outages.
Substation HVAC system is in service; required for protection/control testing.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Part I
Title: INDEX NO.
The contractor, Project Engineer and commissioning personnel shall visit the substation
jointly two weeks prior to the start of the pre commissioning testing and the following
points shall be confirmed.
During the joint site visit, the contractor shall demonstrate the availability of his
qualified man-power and testing engineers as had been indicated in the confirmation
letter. These engineers should demonstrate proper engineering practice throughout
the project and adhere to proper safety procedures. During commissioning the
commissioning engineer withholds the right to dismiss contractor engineers that are
unqualified or unsafe in their work for the sake of project progress or personnel
safety. The contractor‟s staff shall also include a Qualified Coordination Engineer with
commissioning experience preferably in the SEC network. The coordinator‟s
responsibilities shall include but are not limited to the following:
After confirmation of all the items of Section 2.1.2, witnessing can begin after two weeks.
The Commissioning engineer/technician shall have a Commissioning File for each substation; the
File shall include at minimum:
Commissioning personnel are responsible for witnessing the pre-commissioning tests for
reinforcement and new substations. During the course of witnessing, the necessary Site
Instructions (S.I.) are issued which indicate the deficiencies in fulfilling SEC relevant Standards,
SOW, workmanship, safety and common operation and maintenance problems.
Sometimes differences have been noted in the S.I.s issued by different engineers on a particular
point. Therefore guidelines are required for issuing S.I.s. This document briefly describes the
guidelines to be followed by all Commissioning personnel to issue S.I.s in order to achieve
uniformity and consistency. It should be kept in mind that this is a guideline only and it will not
supercede any SEC relevant Specification in any manner.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Part I
Title: INDEX NO.
Any items contrary to SEC Standards, SOW, workmanship and safety will be reflected in
the deficiency section of the Register File, see Attachment No. 2.
The Register File has two sections, one section belongs to the activities (Attachment No.
3) along with the single line diagram to help an engineer to visualize the project and the
other section for the deficiencies.
After one week from the registration of a deficiency in the book, all outstanding items will
be sent to the Project Engineer via Site Instructions/Records (Attachment No. 4).
Any Item that needs to be followed up in multiple worksites will require a technical
problem report. Attachment No.
Weekly, there is a Safety & Coordination meeting where the commissioning engineer and
the commissioning contractor will review their safety performance and coordinate next
week‟s activities. Attachment No.
Bi-weekly, the status of the punch list has to be issued by the contractor on the SEC
format, Attachment No. 5.
If the commissioning activities are halted for an uncontrollable reason, the Uncontrollable
Delay Form will be used to document the start, duration, and reason for the halt in
commissioning. Attachment No.
One month prior to the scheduled energizing of the equipment, the categorized deficiency
list shall be issued by the commissioning personnel to identify the items which must be
corrected prior to energization. Attachment No. 6
Once all the work is complete on the equipment, and the equipment is ready for
energization, the commissioning engineer will clear the equipment for energization using
the Entity Hand Over Form. Attachment No.
ATTACHMENT
DESCRIPTION REMARKS
NO.
The contractor, Project Engineer and commissioning
Joint Site Visit
1. personnel shall visit the substation jointly to confirm the
Checklist
readiness of the worksite for precommissioning.
2. Register The Commissioning engineer/technician shall record all the
Book/Deficiency items contravening safety, SEC Standards, Scope of Work and
Record workmanship on the Deficiency Record.
3. Register Book/Activity The Commissioning engineer/technician is responsible to daily
Record update site activities to help any engineer to familiarize him
with the status of the project.
4. Site Instructions After one week from recording in the Deficiency Record,
incomplete items will conveyed to the Project Engineer via the
Site Instructions Form.
5. Safety & Coordination Purpose of this form is to set norms to assure safe work
Meeting environment and a proper coordination between the entire
parties.
6. Status of the Punch Bi-weekly the status of the punch list shall be updated by the
List contractor.
7. Categorization of the One month prior to energizing the equipment, the categorized
Punch List deficiency list shall be issued by the commissioning personnel
to identify the items to be done before energization.
8. Pre-Commissioning The commissioning engineer/technician shall fill in this sheet on
Time Utilization a daily basis.
Statistic Sheet
9. Uncontrollable Project Purpose of this form is to set norms so that uncontrollable
Delay Form delay in project energization will be documented, monitored
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Part I
Title: INDEX NO.
14. Sample Check In order to reduce the pre-Commissioning time the “sample
(Optional check” procedure may be exercised based on the contractor‟s
Agreement) previous performance and the last time utilizations status
sheet. This shall be based on agreement between the
contractor and SEC Transmission.
15. Check List The check list is intended to provide information to the
commissioning engineer/technician who are assigned to
inspect the contractor‟s work and witness commissioning
testing on behalf of SEC.
16. Contractor‟s The commissioning engineer/technician shall fill this form at the
Performance Report end of the project to evaluate the performance of the
contractor.
17. Commissioning Details the overall commissioning process and the
Process Flow Chart responsibilities within.
18. Procedure To be used to formally request an update or an improvement to
Improvement Form the existing procedure.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Part I
Title: INDEX NO.
The contents of the S.I. can be categorized under various headings as noted below. The common
Snags/Punch list mentioned will be issued once in one S.I. for the whole substation and repetition of the
same for different bays shall be avoided.
This consists of the following deficiencies relating to protection, metering and control equipment.
Missing equipment.
Physical damage to the equipment.
Rating is not matching with relevant specifications.
Equipment with internal fault causing incorrect test results.
The equipment is not on the SEC Approved Manufacturer‟s List.
Protection or a part of it is not in line with SEC relevant Specifications and/or Protection
requirements.
Work has not been executed in line with general requirements or has had approval during
the design stage.
Design comments have not been implemented for the protection scheme and other
equipment.
Segregation of protection CT and VT cables is not maintained and color coded cables are
not used.
Poor ferrule printing quality which will fade over time.
Cables are directly terminated on terminal blocks without providing adequate clearances
for access during troubleshooting or maintenance.
Equipment or terminals are not sufficiently accessible to allow maintenance.
Ferruling method does not meet relevant specifications.
Apparatus is not properly labeled.
Wiring has either wrong ferrules or no ferrules.
Improper use of terminal lugs.
Control cables do not carry proper number tags.
Proper wiring dressing has not been done in panels.
Labels with incorrect spelling, uneven engraved letters, improperly aligned, letters too
small, badly cut edges, etc.
Alarm annunciator labels/text with letters too small to read from a distance, and
acknowledge/reset/test push buttons at difficult to reach locations.
Congested wiring obstructs other terminals on a terminal block.
Very loose plug/socket arrangement. These should always be locking type.
Improper locking of panel doors has caused frequent breaking of the panel door locking
mechanism.
Adequate illumination does not reach all working places, terminals, in the panel, in front
of relays, etc.
Terminals, auxiliary relays, flag relays mounted at very low level or very high level.
Wiring not supported properly causing undue termination tension, which may result
eventually slipping of wire/breaking off from crimp.
Bad crimping of wires. For CT circuit this is most dangerous as this may lead to open
circuiting of energized circuits. Open circuited energized CT circuits may cause fires and
serious electrical hazards.
Inadequately rated relays used for continuously energized relays in fail safe, scheme, etc.
A protection scheme may not operate properly in spite of implementation of the relevant
specification. Examples are listed as follows:
The following Punch list/ snags are found repeatedly in substation construction. Most of them are
clearly mentioned in the SEC Specifications/General Requirements. Irrespective of this fact, they
are usually repeatedly discovered. When these types of points are raised at site, the contractor
generally tries to avoid implementation. Every effort should be made to have the contractor
promptly correct the inadequacies. Some examples are listed as follows:
Color-coded cables shall be used for control and/or alarm functions and black ones shall
be used for CT, PT or AC circuits.
Quality of printing and the placement of ferrules is poor in many cases.
While terminating cables, the contractor does not leave any margin inside/outside the
panel for re-terminating the cables in another location in the same panel, in case it is
required.
While laying cables, segregation is not maintained section-wise, so that in case of fire in
one section the other sections will also be affected.
Paralleling of alarms is done with software, whereas it is necessary to do this with help of
wiring for system reliability.
Equipment lists do not correlate with the installed equipment and details such as ordering
number and the numbers of NO/NC contacts, etc., are not correct.
More than one earth point has been made for the CT‟s feeding the unit protection, e.g.,
Restricted Earth fault, Differential, Breaker Failure and Bus bar protection.
From the maintenance point of view the access to relay terminal blocks is very important;
some contractors do not pay enough attention to this.
Positive (+), Negative (-) and trip marked in red are not provided on the relevant wires.
Contractors do not allocate fault recorder channels as per SEC specifications.
Site modifications are not properly reflected in the drawings.
CT shorting and isolating arrangement is not in line with SEC standard arrangements
including shorting/isolating, instruction and caution notices.
Lack of proper labeling to the protection and control equipment in different location, e.g.,
relay panels, control panels, LCC and AVC panels, AC/DC distribution boards, power
transformer marshalling kiosks, CB isolators and earth switches, etc. This equipment
includes main relays, auxiliary relays, contactors, trip relays, MCB‟s terminal blocks,
points on the test switch (MMLG or ABB type), trip links and other links used for other
specific functions.
CT and VT protection cables are not segregated.
Terminal block wiring is too low for convenient access, especially CT shorting and
isolating switches. These shall be at working height level.
Crimping of terminal lugs is not done properly, particularly for CT and VT wires.
Length of the metallic part of CT and VT lugs is not enough to provide proper grip when
they are tightened in the terminal blocks.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Part I
Title: INDEX NO.
Plug in type miniature relays are used in tripping and interlock circuits. After a period of
time, these relays do not function properly, due to displacement from their original
position.
Normal earth switch was used on the line instead of high-speed type.
In one substation, the backup main protection was found not working when the DC
supply to the first main protection was switched off since the isolator image was
controlled by the first main DC supply.
Power cables for the fans from the AC distribution board to the transformer marshalling
kiosk were found underrated.
Protection coordination of MCB‟s installed in the DC distribution board was not
maintained, so the contacts of an ON/OFF switch were burnt due to a short circuit in the
DC wiring.
During on-load checks 12 volts were observed across the CT terminals of feeder cable
protection.
The manual mode status of the Halon was found not annunciated.
As per SEC specifications it is necessary to install an independent synchrocheck relay for
manual and auto re-closing for each CB rated 110 kV and above.
The bus-bar protection trip logic for double bus-bar substations does not conform with
SEC specifications.
The annunciator output contacts did not follow the initiation when the input was reset as
per SEC specifications.
Remote end breakers also trip in case the HV E/F relay of transformer operates. It
should only trip the local breaker.
The A/R did not close the breaker when the D.E.F. tripped the breaker. It was due to the
tripping of the breaker in advance before the initiation of the A/R.)
The phases R and B were found interchanged for the reactors.
Two phases of earth switch were on one side of the CT‟s whereas the third one was on
the other side of CT‟s.
CT polarity if it was left reversed on one of the spare feeders and the loading of the spare
feeder led to operation of BBP.
The anti pumping circuit is not operational for CBs. This deficiency will lead to re-closing
of the CB on to fault when a long duration closing pulse is initiated.
The pilot wire protection 87PW is commissioned with reverse pilot; this will lead to
indiscriminate tripping.
The DEF relay for one circuit is commissioned with wrong direction this will lead to
indiscriminate tripping of the circuit.
Labeling of relays, pressure relief devices, oil temperature gauges and winding
temperature gauges, etc.
Blocking of spare plugs.
Avoiding use of plug in connections and plug-in type auxiliary relays.
It is very important to clear the Punch List/Snag items as soon as possible after confirming their
implementation. Sometimes it is very difficult to confirm their implementation once the substation
is energized, if they are not cleared during the pre-commissioning stage. It is very useful that the
witnessing engineer/technician keeps the site instruction records updated by putting his signature
with date without any delay after inspecting and approving the relevant snag.
5.1 DEFINITION
It is a site meeting between the concerned parties who will discuss a selected safety subject
as well as revision of three weeks schedule and any other project related issue.
5.2 SCOPE
This Policy shall be applicable in Commissioning Services Department (CSD).
.
5.3 PURPOSE
Purpose of this form is to set norms to assure safe work environment and a proper
coordination between the entire parties.
5.4 POLICY
Safety and loss prevention plan must be given top priority over all other activities during
project so that no loss should occur to manpower and equipment. So its constant revision and
updating is necessary. Also progress of work schedule and clearance of deficiencies/punch
list should be regularly monitored so that project may complete in due time.
Some problems that arise during testing and commissioning are not limited to a single
substation.
In these situations, the procedural use of a deficiency record and possibly a site
instruction will rectify the situation in that specific substation. However, to prevent this
problem from occurring in future installations, the commissioning engineer / technician is
required to issue a Technical Problem Report.
o The technical problem report will be issued on a standard format, see Attachment 3.
o The technical problem report does not eliminate the need to follow up the problem with a
snag and site instruction at the incident substation/ project.
o The report shall include a clear description of the problem.
o The report shall include a history of occurrences in other projects and associated
documentation (snags / SI).
o All relevant materials (manuals, manufacturer letters of clarification, formal
communication with the contractor, fault records and analysis reports …etc) to be
attached with the report as supporting documents.
o The report shall be sent to the technical support and coordination division to inform them
of the problem.
o The technical support and coordination division is responsible for archival, circulation and
follow up the report with the relevant departments in SEC.
The following sections listed below elaborate the techniques to ensure that all equipment tests are done
with optimal use of the time available.
The Check List is intended to provide information to commissioning personnel who are assigned
to inspect the contractor‟s work and witness commissioning testing on behalf of SEC to verify that
substation and transmission line equipment and system are acceptable as per SEC- Standards
and Specifications. The listing of commissioning checks and tests are based on the SEC-
Commissioning Procedure T-PreCom-1000-01.
A time utilization statistics sheet is being included in this Procedure. This sheet must be filled in
daily. The contents of this sheet will be used for planning future projects by using the total time
consumed. Moreover this sheet will also allow corrective measures to be taken to reduce the pre-
commissioning time. The number of hours lost should be filled correctly, see Attachment No. 6.
In order to start witnessing after two weeks from confirmation, the contractor shall submit to SEC
the testing schedule, giving details for each test of the time and the commissioning personnel
required. SEC commissioning engineer / technician shall review the schedule and give comments to
the contractor on the schedule in the interest of maintaining the quality of the work or improving the
performance of the commissioning period. Every week, the contractor shall submit a three-week
testing program giving details of the previous week‟s completed jobs and the current and following
week‟s proposed jobs. If in the previous week, some job was not completed, a reason for the deferral
and its effect on the overall schedule should also be mentioned. SEC commissioning engineer /
technician may also review this three week schedule before it is sent to the project manager and
advise the contractor accordingly.
The contractor is responsible to provide enough qualified manpower to prepare three sets of marked-
up drawings during the pre-commissioning testing period in order to expeditiously finalize the as-built
drawings without using the substation marked-up drawing. The three copies of the marked up
drawing shall be distributed as the following:
Contractor copy to prepare the as-built drawing, this copy may be used by the contractor
during the 100% pre-check of the equipment in the presence of a time reduction agreement.
Commissioning Copy to be used by SEC commissioning engineer / technician during pre-
commissioning and will remain in the substation for maintenance purposes till the completion
of final As-Built Drawings.
A third copy for the Commissioning Services Department library to be handed over at the end
of commissioning. This copy will be used for review and verification of the As-Built drawings
before issuing the Final As-Built.
The contractor may want to keep one copy of substation schematics without mark-up for emergency use or
replacement of lost drawings.
In order to reduce the pre-Commissioning time, “sample checks” could be exercised based on the
following criteria, see Attachment No. 8.
If the overall rating of the contractor performance in his immediately previous contract
was GOOD.
If the hours lost due to the contractor is less than 5% of the work, for the last time
utilization statistic sheet.
7.1 DEFINITION
Any delay which is out of CSD control and leads to stop the project commissioning activities or delay
in equipment energization and ultimately cause a significant delay in project commissioning planed
completion date is called an uncontrollable project delay form.
7.2 SCOPE
This Policy shall be applicable in Commissioning Services Department (CSD).
7.3 PURPOSE
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Part I
Title: INDEX NO.
Purpose of this form is to set norms so that uncontrollable delay in project energization will be
documented, monitored and coordinate with the concern department in order to avoid it. .
7.4 POLICY
CSD is committed to the timely completion of commissioning of transmission projects with
high quality standards. In view the above; any uncontrollable project delay as delay of
energization or outage shall be documented. Uncontrollable delay event period shall be
calculated and the cause of the event shall be investigated and accordingly the required
action to overcome such event shall be taken.
It is essential that no entity in the Transmission project enter the Transmission network without formal
handover. The handover procedure is set to prevent accidental or rush energization without the
equipment being 100% ready for energization. Rush energization of unprepared entities can cause a
series of problems ranging from the minor – requiring a shutdown to do some modification or
corrective work – to the major – the possibility of a fault or a failure of protection and the complete
loss of the power equipment or loss of life.
The entity desired to handover must conform to the following mandatory requirements to assure a
safe, and hassle-free handover:
Commissioning Representative: to ensure that all tests and activities have been completed
with satisfactory results and that the equipment is ready to energize.
Project Management Representative: for contractual purposes and follow up and
enforcement of the contract.
Operation & Maintenance Representative: to ensure that all the documents have been
received and that the entity can be operated & maintained successfully post energization.
CSD Division Manager: for department approval.
This form can be filled on an entity by entity basis (ex. feeder bay, transformer bay, High voltage
switchgear) or for the complete substation/project depending on the project schedule and energization
schedule.
Project completion depends on the pre commissioning report, which has to be issued by the
commissioning engineer/technician (Attachment No. 7). In case of separate contractors working on the
same substation (lines and substation), the line-commissioning engineer/technician shall provide a copy
of the final reports to the substation-commissioning engineer/technician and vise versa. Each
commissioning engineer/technician shall evaluate the contractor at the end of the project, see Attachment
No. 10.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Part I
Title: INDEX NO.
The commissioning engineer/technician shall issue the Report based on but not limited to the
following.
The status of the Punch List (A, B) for which “A” refers to any deficiency requiring an
outage to clear it or equipment damage or a safety requirements. “B” is any deficiency
other than “A”.
Marked up drawing are available at site in good condition.
One copy of marked up drawings is complete and handed over to Maintenance
Department library for as-built drawing verifications
Emergency contact list provided.
Operation spare parts are available.
Operation and Maintenance Manuals are available.
Test results provided.
All final settings applied as per the original copy of the issued final settings documents
and the commissioning engineer / technician has filled out the necessary final setting
confirmation formats.
All site tests completed.
Test completion and energization of station service transformer.
Test completion and energization of HVAC.
The commissioning engineer/technician shall use SEC format to evaluate the contractor using the
following criteria:
The commissioning process is under continuous pressure to complete the testing and commissioning of
electrical projects in the shortest duration and at the highest quality possible. The safe energization of the
company‟s assets is key to the success of this process and so the commissioning team is continuously finding
ways to improve their work, increase the quality of their output, and reduce the time required to achieve the
commissioning goals.
To achieve these goals, proper implementation of this procedure is essential. The following steps need to
be given special consideration, for implementation of this procedure:
The contractor/Project Management Engineer shall return all the dismantled material to SEC
store.
It is recommended to store a Project Commissioning File, which includes critical Punch
List/Snags, contractor evaluation, final commissioning report, single line diagram, Minutes of
Meeting and Relay Setting Sheet in the substation.
Within the context of continuous process improvement, the Pre-commissioning Test Procedure itself may
require a revision or an update from time to time. This will mainly be due to:
We have supplied a Procedure Improvement Form (Attachment No. ) in this procedure for the purpose of
documenting and then implementing the improvement requests. This form is to be filled out indicating the
portion of the procedure to be revised, the comments on the existing procedure, the type of improvement
desired (correction, elaboration, addition). Any related documents (standards, designs, test formats,
manuals) that are the basis of this request are to be attached with the form and sent to the Technical
Support & Coordination Division in the Commissioning Services Department for their information and
action.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
1.0 INTRODUCTION
This Procedure describes the tests and checks to be performed during the pre-commissioning stage of
SEC Transmission projects. It deals primarily with the pre-commissioning tests to be followed for
protection schemes and main equipment such as cables, transformers and switchgear, etc., keeping in
view the SEC standard practices for various types of tests. Further, this listing of tests and checks is
based on the requirements and recommendations of international standards such as IEC, ANSI, etc.
They are the minimum tests and checks to be performed during pre-commissioning.
2.0 PURPOSE
The main purpose of this Procedure is to present a list of checks and tests to be performed on
transmission equipment. They shall be performed by the substation contractor and witnessed by SEC
Precommissioning personnel.
Check all pipes – hoses and fan protection (not rubber or plastic).
14.
21. Check Oil leakage by applying 0.35kpa over pressure for 24 hrs.
22. Check that the sampling devices are reachable.
Check oil level in main tank, conservator, tap changer tank and bushing etc.
23.
test the oil level gauges and their alarms.
24. Bleed trapped air at the bushing turrets and tank top.
Check flow of oil in flow meter in correct direction and proper rate (if applicable
25.
)
26. Check all external wiring for correctness and tightness.
Check on line insulating oil dissolved gas and ,moisture monitoring system (if
27.
installed )
28. Check pocket of temperature sensors have oil inside
Internal inspection of the transformer before installation of the high side bushing of
29. new transformer in order to inspect the upper yoke for any bents on the core and paint
particles found.
4. and from secondary side when energized from secondary terminals keeping
primary side open or winding excitation current measurement test at 10 kV.
Check for current and voltage ratings of all motors for tap changer and fans
11. match to SEC standard supply. MCBs for protection are set at proper over load
settings
Fan motors current shall be measured and checked against rating .check wiring
12.
size suitable to carry the current.
Check fan running direction to get air flow towards radiator. Phase sequence of
13.
supply voltage to fan motors circuits is correct.
MCBs in cooler control cubicle to be checked by current injection for alarm and
14.
trip.
A main tank insulation oil sample for dissolved gas analysis shall be
taken immediately prior to first energizing a power transformer and
19.
another sample three days after continuous energization.
TABLE 1
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
AC HV tests on main circuit of GIS are performed with all CB’s and disconnect switches in the closed position at 80% of
the factory routine test voltage for one minute. Partial discharge measurements (If applicable and possible to be
performed) are performed at 1.2 X Un (Un = phase to neutral voltage).
Check and confirm following points and condition to be met before high voltage tests.
i. The Switchgear shall be erected completely and filled with gas at rated pressure.
ii. Some part may be disconnected before test, such as:
High Voltage cables and overhead lines.
Power transformer and most voltage transformers.
Surge arrestors and protective spark gaps.
Current transformer secondary windings should be shorted and grounded.
iii. Every newly erected part of GIS shall be tested with high voltage.
iv. The test should be performed at rated frequency (60 Hz.). If such arrangement is not possible, then the
frequency should be limited to the range of 30 to 300 Hz.
v. AC voltage tests are sensitive in detecting contamination and abnormal field configuration.
vi. Tests with switching impulse voltages are useful especially for high rated voltage to detect the presence
of contamination as well as abnormal field configuration
Contractor can adopt one of the two procedures A or B to perform high voltage test on GIS after erection at
site
i. Procedure A
Site AC test voltage level shall be equal to the 80% of the factory routine test voltage.
This test may be performed through series resonance method
Or by a test transformer with sufficient capacity. PD measurements are possible to be measured in this case at
test voltage level = 1.2 Un (Un = phase to neutral rated voltage) during the HV Test process.
Electrical conditioning at voltage equal to U/3 for longer period such as 30 minutes may be
performed to move and trap the contamination in areas where they become harmless.
Partial discharge measurements may be helpful in detecting some kind of faults.
Site AC test voltage level equal to 1.2 Un for 5 minutes followed by Impulse Voltage test at a
test level equal to 64% of the rated lightening impulse withstand level specified in IEC-517.
Three positive and three negative polarity impulses shall be applied.
In case the GIS VTs are not suitable to be used as test transformer; a special voltage
transformer shall be used to perform such tests. GIS VT can only be used as a test
transformer if the manufacturer guarantees its safety and capability to perform such tests
otherwise it shall not be used as a test source.
V. Assessment of Tests
i. Test is considered passed if no disruptive discharge occurs during the test period.
ii. If disruptive discharge occurs in solid insulation, the compartment should be opened and
repaired. After fault repair, again, test with full site test voltage.
iii. If disruptive discharge occurs in gas, the test may be repeated and if discharge again takes
place, then compartment should be opened to clean out the compartment.
iv. If the discharge occurs and second time it disappears, it should be considered acceptable
after repeating one test more at full site test voltage mentioned in Table 1.
Test may be repeated several times to listen and locate the location of fault point subject to the agreement
between SEC and Contractor.
Table-1 on the next page describes the exact test voltage levels, time and kind of tests to be applied after
erection of GIS at site.
i. For 132 kV GIS the test voltage shall be 220 kV AC 60 Hz for one minute as per Procedure A clause
7.107.1.5 of IEC 517- 1990
ii. For 380 kV GIS and GIBs shall be 416 kV AC 60 Hz for one minute as per procedure A clause
7.107.1.5 of IEC 517-1990.
iii. In case of procedure B as per clause 7.107.1.5 of IEC 517-1990 the test voltage for 132 kV rated GIS
shall be 84 kV AC for 5 minutes and followed by 416 kV Impulses of three positive and three negative
polarities.
iv. In case of procedure B to be applied for high voltage tests on 132 kV GIS special VT should
be used as Test voltage source. GIS VTs shall not be used as HV test voltage source.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
Table 1. Test Voltage Levels for Metal-Enclosed Gas Filled Switchgear (GIS)
System Rated
Impulse level
Conditioning
REMARKS
Switching.
Discharge
Electrical
Impulses
Measure
Swing or
AC Test
AC Test
Time Of
Voltage
Voltage
Voltage
Voltage
Method
Of Test
No. Of
Partial
Freq.
No.
KV
kV
Leakage
10 kV for 10 current
A 13.8 30 60 Hz 1 min. - - -
min. < 1000
mA
Leakage
22 kV for 15 current
A 33 56 60 Hz 1 min. - - -
min. < 0.86
mA
Electrical
60 Hz. At 48 kV conditioni
44 kV for 30 ng is a
A 69 128 or 10- 1 min. - - less than cleaning
min.
300 Hz. 10 pC process
only.
3
positive
B 69 - 44 60 Hz. 5 min. 248 kV
3
negative
Electrical
60 Hz. At 92 kV conditioni
84 kV for 30 ng is a
A 110 220 or 10- 1 min. - - less than cleaning
min.
300 Hz. 10 pC process
only.
3
positive
B 110 - 84 60 Hz. 5 min. 416 kV
3
negative
Electrical
60 Hz. At 92 kV conditioni
84 kV for 30 ng is a
A 115 220 or 10- 1 min. - - less than cleaning
min.
300 Hz. 10 pC process
only.
3
positive
B 115 - 84 60 Hz. 5 min. 416 kV
3
negative
Electrical
60 Hz. At 92 kV conditioni
84 kV for 30 ng is a
A 132 220 or 10- 1 min. - - less than cleaning
min.
300 Hz. 10 pC process
only.
3
positive
B 132 - 84 60 Hz. 5 min. 416 kV
3
negative
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
20. For SF6 breakers, check the correct gas pressure. Quality and leakage.
For SF6 breakers, check the operation of the gas density switch (alarm and
21.
lockout functions).
Perform all specific checks on the breaker and spring operating mechanism
22.
according to the manufacture‟s instructions.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
19. For SF6 breakers, verify electrically the low gas pressure alarm
and lockout functions.
20. For minimum oil breakers, test insulating oil for dielectric
strength. ASTM D-877 (with 2.5 mm gap)
21. Check correct operation of all auxiliary “a” and “b” contacts (for
breaker open/closed position).
22. Calibrate the metering devices such as ammeter, voltmeter…
For vacuum breakers, test across open contact and live parts to ground. Precautions should be taken against
emission of X-rays.
For all other breakers. Test in conjunction with breaker racked in the switchgear and in the closed position.
The new switchgear not connected yet to cables should be tested as a whole unit with all circuit breaker in close
position.
All back shutters must be closed.
Gas Pressure indication for the circuit breaker should be checked under permissible limits.
VTS, cables or any other voltage indication should be in out position and VTS secondary side fuses should be
taken out.
CTS secondary terminals should be short-circuited and earthed.
Test voltage should be applied on each phase to ground with other phases in earthed position. The test should be
repeated on other phases similarly.
The test period should not be more than one minute at full test level and the test voltage frequency should be
kept at 60 Hz.
Charging current for each test is noted and recorded.
HV Test is considered successful if no breakdown occurs during test period.
HV Test levels and time for pre-commissioning testing of switchgear are given in Table 2.
TABLE-2
TEST VOLTAGE LEVEL FOR MEDIUM VOLTAGE METAL CLAD SWITCHGEAR
56 kV 60 Hz 60 Sec
33 & 34.5 kV
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
Test
Test Description REMARKS
No.
1 Phase checking for conductor & sheath bonding in every link box
Test
Test Description REMARKS
No.
1 Inspect for physical damage or defects
2 Check tightness of all bolted connections (torque wrench method)
3 Check for proper cable bolted connections
Check cable bends to ensure that bending radius is equal to or greater than the minimum
4
bending radius specified
5 Check for proper cable support, clamping, trays, Blocking.
6 Verify that shields are terminated as specified (through link box or directly grounded)
Verification of exact route length as per approved drawings from termination to
7
termination.
8 Check that all grounding points are securely connected to ground grid as specified
9 Pressure test of all associated oil piping
10 Check that phases are identified and color coded
11 Single Core Cable connected between Power Transformer and Switchgear shall be
single point earthed at Switchgear side and at floating side SVL(sheath voltage limiter)
should be installed
12 Availability of oil sampling facility valve arrangement.
13 Check Single point or both ends, via voltage limiter as per approved design
14 Check cable entry path trench as ducts are to be properly sealed.
15 Oil flow test
16 Impregnation test
17 RGP test / DGA test
For accessories (sealing terminations, pressure tank, gauges, instrument panels and link
boxes), check the following as applicable:
a. Nameplates installed and data is correct.
b. All valve positions according to design (open/closed).
18 c. Calibrate pressure gauges and pressure switches.
d. Oil pressure.
e. No oil leaks.
f. Condition of paint work
g. All bolted connections
(Standard Reference is. IEC 60141-1 and relevant SEC Transmission. Specifications)
Test
Test Description REMARKS
No.
1 Check Phasing for conductor & sheath bonding in every link box
2 Conductor resistance, Capacitance and inductance measurement test
Sheath DC high voltage test (10kV DC for 1 min.) and 5 kV DC insulation tester
3
before and after high voltage/24 hour soaking test
4 SVL (Sheath voltage Limiter)test by2.5kV DC insulation tester
5 Anti corrosion sheath test
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
Test
Test Description REMARKS
No.
Test
Test Description REMARKS
No.
Check Phasing for conductor & sheath bonding in every link
1
box
Sheath DC high voltage test (10kV DC for 1 min.) and 5 kV DC
2 insulation tester before and after high voltage/24 hour soaking
test
3 Conductor resistance, Capacitance and inductance measurement
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
Test REMAR
Test Description
No. KS
1 Inspect for physical damage or defects
Check tightness of all bolted connections (torque wrench
2
method)
3 Check for proper cable bolted connections
Check cable bends to ensure that bending radius is equal to or
4
greater than the minimum bending radius specified
5 Check for proper cable support ,clamping ,trays, blocking
6 Link box tightness check
Verify that shields are terminated as specified (through link
7
box or directly grounded)
Verification of exact route length as per approved drawings
8
from termination to termination.
Check that all grounding points are securely connected to
9
ground grid as specified
10 Check that phases are identified and color coded
11 Single Core Cable connected between Power Transformer and
Switchgear shall be single point earthed at Switchgear side and
at floating side SVL(sheath voltage limiter) should be installed
12 Check Single point or both ends, via voltage limiter as per
approved design
13 Check cable entry path trench as ducts are to be properly sealed
14 Check irregularities of outer jacket formed by non uniform
shield wire distribution.
15 For accessories (sealing terminations, instrument panels and
link boxes), check the following as applicable.
a. Nameplates installed and data is correct.
b. Condition of paint work
c. All bolted connections
Test
Test Description REMARKS
No.
3.26 LV Cables
(Standard Reference is IEC 60227-2 and relevant SEC Transmission Specifications)
REFERENCES
Test Voltage levels for LV Cables, Control Cable and Pilot Cables
27 Check solar unit for tower lighting with cable (if applicable).
For terminal compound, check the following, if available, as per
contract:
Outdoor equipment such as surge arresters, CVT‟s, etc.
Equipment structure
Foundation
28
Bonding of equipment / structures
Gravelling inside terminal compound
Circuit identification
Conductor dropper and connectors
Fence and gate are complete and grounded.
Ensure that the site has been properly cleaned up and all
29
earthwork profiles are correct before acceptance.
Cable testing requires at least two personnel with a means of communication between
the cable/wiring ends. Spare cores shall be clearly identified and of sufficient length to be
terminated at the farthest terminal in the panel.
CAUTION: Before conducting any external wiring or cable tests, ensure that all sources
of supply to the circuits involved have been de-energized or disconnected.
3.30.6 Energization
Loss Prevention Department is responsible for fire detection and suppression systems, but
transmission witnessing personnel shall check the alarms and trip signals (if applicable) which
affect the main equipment such as power transformer, GIS, etc.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
Witnessing of civil work is the responsibility of the Civil Department to witness the work of the civil
contractor. Transmission witnessing personnel shall check the accesses and ventilation that
affects the main equipment.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
The reliability of air-conditioning is very important for the SVC controller, so this part of the equipment
should be tested thoroughly. For details of its pre-commissioning please refer to Section 3.38, HVAC
Systems.
The reliability of fire detection and suppression systems is very important for the SVC System, like any
other substation component. This equipment should be thoroughly tested. For details of its pre-
commissioning please refer to Section 3.40, Fire Detection and Suppression Systems
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
The following is an example of a Test Record Form submitted by the contractor for the Substation
9000 SVC pre-energization checks:
1. General
2. Pre-Energization Checklist
With bus bar energized voltage response to VAR Control was checked.
For each phase it was checked that the signals were as below: ----------------------- □
5. Energization of Filters
6. Energization of TCR
-------------------------------------------------------------------------------------------------------------
Voltage Current
Sec
Prim
Voltage Current
Sec
Prim
Max inductive is: ___________ MVAR Max capacitive is: ______________ MVAR
Time
Time
Test with Max load on cooling system, SVC operated at __________ MVAR.
Time
Increase and decrease ramp of control signals for all phases checked: ------------------- □
_____________ ______________
Measurement of load-sharing:
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
_____________ ________________
Current limit
ILIMGAIN: ____________
Parameters corresponds to _______ A primary TCR current and __________ sec time constant
Prim. Values Bus Voltage (kV) Delta Current (A) Impedance (Ω)
Q-tot Ph. a-b b-c c-a a-b b-c c-a a-b b-c c-a
Prim. Values Bus Voltage (kV) Delta Current (A) Impedance (Ω)
Q-tot Ph. a-b b-c c-a a-b b-c c-a a-b b-c c-a
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
Parameter
Switch-
U (kV) I (A) B (mS) B (p. u.)
Point
Name Value
Parameter
Switch-
U (kV) I (A) B (ms) B (p. u.)
Point
Name Name
____________ _____________
____________ _____________
____________ _____________
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
Switching from MAN to AUTO and from AUTO to MAN works correctly
SLOPE: ____________
Measurement of slope:
MLOSST: ____________
It was checked that the SVC operates correct during the following change-overs to redundant functions.
Checked
___________________________: ------------------- □
________________________: --------------------- □
___________________________: ------------------
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title: INDEX NO.
ANSI
ITEM
EQUIPMENT REFERENCE
NUMBER
NO.
4.1 Auxiliary relays
4.2 Supervision relays (under-voltage) 27
4.3 Supervision relays (over-voltage) 95
4.4 Trip Lockout relays 84
4.5 Trip Auto reset relays 94
4.6 Timers 62
4.7 Definite Time Over-current protection 50
4.8 Inverse Definite Minimum Time (IDMT) Over-current 51
4.9 Circuit Breaker Fail protection 50 / 62
4.10 Bus Bar Differential Protection 87B
4.11 Metrosils and non linear resistors
4.12 Synchronism check 25
4.13 Distance / Impedance protection 21
4.14 Directional Over-current and Directional Earth Fault 67 / 67N
Protection
4.15 Line / Cable Differential Protection 87L / 87C
4.16 Auto re-closer function
4.17 Transformer Differential Protection 87T
4.18 Restricted Earth Fault Protection 64NS / 64NP
4.19 Temperature Rise Protection 49 W
4.20 Under-frequency protection and Rate of frequency 81 / 81R
change protection
4.21 Automatic Voltage Controller 90
4.22 Disturbance and Fault Recorder
4.23 Sequence of Events Recorder
4.24 Annunciators
4.25 Transducers
4.26 Automated Bus Transfer System (ABTS)
4.27 Auto Changeover Switching Equipment (ACSE)
4.28 Guidelines for Testing Digital Protection Relays and
IED‟s
4.29
4.30
4.31
4.32
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
Check that rating of the relay agree with the Auxiliary Supply to
1.
which it is connected.
2. Check that DC Supplies are wired with the correct Polarity.
Check that the frequency of the relay supply is compatible with
3.
the system‟s rated frequency.
Verify that the secondary current for current operated relays
4.
matches the used CT secondary current
Verify proper phase shorting for CT field test switches and test
5.
plugs used with current operated relays.
Check that the relay nominal input voltage matches the
6.
VT voltage.
Verify proper case shorting facility for current operated draw
7.
out type relays.
Make sure that all trip circuits are using high burden trip
8.
contacts from the protection relays.
Make sure that the low burden annunciation contacts are used
9.
only in low burden circuits such as annunciation and indication.
Verify that the number of contacts and the contact
10. configuration (NC NO CO) is the same in the drawing as
it is in the relay
Voltage operated relays to have a pickup voltage less
than 80% of the rated substation voltage to allow for
11.
proper operation of the relay even during substation DC
under-voltage condition.
12. Check Annunciation LEDs and flags.
13. Check Annunciation contacts
14. Check Binary inputs.
15. Check output contacts.
16. Check Watchdog or Internal Relay Fail contacts
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
On Units fitted with hand reset flag indicators, check that the
flag is free to fall before, or just, any contacts closes. Make
2. sure that the reset mechanism in the cover is correctly located
with respect to the relay element and the flag (or mechanism)
can be reset.
Check condition of any connectors, contacts alignment and
3.
travel.
Check armature gap.
4.
Check Lockout mechanism.
5.
4.4.2.2Electrical tests
Check Drop off voltage and current of operate Coil and Reset
5.
Coil.
6. Check Change-Over time for contacts which makes/breaks.
7. Check power consumption of operate and Reset Coil.
500 V insulation tests shall be conducted between:
8. a) all electrically isolated circuits.
b) all circuits and earth..
Verify the functional test of the relay for which functions it is
9.
being used.
10. Check operation indication/Flag/LED function.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
2. Check measurements
3. Check over voltage pick-up and drop-off
4. Check under voltage pick-up and drop-off
5. Check voltage-timing
6. Check low voltage blocking
7. Check binary input contacts
8. Check output contacts for proper operation
9. Check indication LEDs
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
If we are checking trip and closing test (although I think this is part of function test) then shouldn‟t
it be “check trip and close blocking test” or trip and anti pumping ? that the trip is continuous from
the lockout relay, but the CB aux contact should disconnect the trip coil
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
On Units fitted with hand reset flag indicators, check that the
flag is free to fall before, or just, any contacts closes. Make
2. sure that the reset mechanism in the cover is correctly located
with respect to the relay element and the flag (or mechanism)
can be reset.
Check condition of any connectors, contacts alignment and
3.
travel.
On Units fitted with hand reset flag indicators, check that the
flag is free to fall before, or just, any contacts closes. Make
2. sure that the reset mechanism in the cover is correctly located
with respect to the relay element and the flag (or mechanism)
can be reset.
Check condition of any connectors, contacts alignment and
3.
travel.
4. Check armature gap.
How many points? How many Current Samples? How many time settings?
DESCRIPTION
ITEM REMARKS
Check for the correct color coding for trip / non-trip alarms.
Electrical tests
Check that ten percent (10%) spare alarm windows are available
for future modifications
General Electrical Tests for Protection Relays As per 4.2 & 4.3
General Function Tests As per 5.1
Trip circuit supervision
Verify integrity of individual trip circuit supervision,
including pre-closing and closed CB supervision.
Make sure wiring is made point to point with no
branched connections to make sure that all trip supplies
are supervised
Disable Trip circuits individually and verify that the other
circuit is healthy and operable
Trip circuit supervision should have indication on both
the control panel and in the alarm scheme
Verify tripping arrangement as per approved schematic
drawings, example:
First main protection to trip on circuit 1
As per approved scheme
Second main to trip on circuit 2
Busbar protection or breaker fail or Transformer
differential protection to trip on both TC1 and TC2
Check wiring for bus bar protection loop and CBF relay, check
CBF supply is ok, check CBF initiation from all trip relays, and
that all trips (even mechanical trips) initiate trip relays, which
then initiate the CBF.
When specified, the relay panel should incorporate proper In/out
facility:
Locally or remotely operated (SCADA)
Indication and or Alarm of the status of the protection (in
or out)
Disconnecting alarm and trip contacts when in out
position
Bus-bar zone out of service will still trip depending on
check zone (for discrimination zone out), or depending
on discrimination zone (for check zone out of service)
Verify the use of close blocking lockout relays and auto resetting
trip relays is as per scheme depending on the type of protection
operated.
Mimic & Indication
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
A General checks
1. General Function Tests As per 5.1
2. Relay & Control Panel Function Tests As per 5.3
B Protection Panel Check
Verify the distribution of main and backup protections on the
3.
protection supplies R1,R2,R3,R4)
Mechanical protection tripping by simulation from the source
contact for EVERY mechanical protection from the source (from
4.
the protection device itself, not from the GTMK panel and not
from the TX panel).
C Control Panel Check
Mimic has to be ok, color coding for HV, MV, and tertiary if
5.
applicable for single line should be correct.
Check interlocking between isolators and breakers and between
6.
HV and MV breakers (test / service conditions)
D Fire Protection Panel Check
DC supply and supervision for supplies shared between the
7.
relay panel and the fire protection control panel.
Verify proper interfacing between fire protection scheme and
transformer protection scheme:
8. Trip both sides of the transformer
Disconnect Transformer cooling fan motors
Initiate water spray system in the Transformer Room
Assure the connection fire protection alarm scheme to the
substation alarm scheme for fire protection ready, healthy,
9. operated, water low …etc
Ensure that alarms are received at the Transformer control
panel annunciator and reaching to SCADA.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
Electrical tests
Electrical tests
Electrical tests
Visual Inspection
1.
General Function Tests As per 5.1 & 5.2
2. Study the different schemes for automatic closing of the spare
or the parallel running Transformer incomer Breakers or Bus
Couplers in case of tripping of any transformer available in the
Schematic diagram,
3. Check the Schemes by tripping of the different transformers
one by one and changeover of the switchgears are according to
the Scheme.
4. Check the blocking of Changeover for the Blocking Conditions
of Auto Changeover of Switchgears.
5. Check the Scheme opening of Bus Couplers or Incomers in
case of energization of tripped Transformer.
6. Check all interlocking functions before closing the Bus Couplers
or incomers.
7. Check panel indication for:
ACSE/ABTS ready
ACSE/ABTS close command failed
TOP scheme selected
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
Visual Inspection
DESCRIPTION REMARKS
11. Ensure that every protection trips through it's desired trip circuit
independently by disabling the other trip circuit before secondary
injection.
12. Ensure that both trip circuits are normalized at the end of the trip
test.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
Close bus bar disconnector Q1 for two feeders one feeder will
be reference and another will be test feeder .Apply primary
2 Injection (inject 25% from primary current) to the red phase for
reference and test feeders.
6 Repeat the above steps for the yellow and blue phases
A B C
P1
I1
Id
Temporarily
I2 short circuit
P1
- It is known that the restricted earth fault protection aims to protect the star windings (primary or
secondary windings or both) of the power transformers used in transmission networks and this type
of relay is used to protect the transformer windings against internal earth faults.
- As shown, the protective circuit consists of 4 CTS (a CT for each phase and one for the neutral
point); the four CTS are connected in parallel with the REF relay as in the figure.
High impedance relay should be tested as trip/no trip with short duration of current
injection
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
DESCRIPTION REMARKS
DESCRIPTION REMARKS
DESCRIPTION REMARKS
Inject appropriate primary current to cable ( for example 1. Repeat all these check at every
1
200A) phase
Check the current in the two ends 2. Calculate Idiff and Irest and
Check the reading of the current value in both ends (should compare them with the
2 be same) measured value. And calculate
Check Idiff and Irest in both ends ( should be same in both the errors
ends)
3 Reverse the polarity of one end CT and inject current
Check the current in the two ends
Check the reading of the current value in both ends
4
Check Idiff and Irest in both ends
Check if Idiff and Irest exceed the limit the relay will trip
Ensure that the new Feeder was energized without any load for one
1
hour at least before on load Test.
Ensure to decrease the tripping time of over current protection to
2
less than 0.5 sec (if DMT O\C).
3 Ensure that the tripping of Line or Cable differential Relay is
ISOLATED to prevent false operation of relay.
4 Ensure that the Feeder is loaded by 25% at least form its rated
current.
5 Read phases currents and phases angles must be balance and
measure the differential current must be Zero in stable case.
6 Check the relay performance (Trip Action) at unstable condition by
reversing the current direction by one of the following methods :
1- Reverse the current direction from relay software.
2- Reverse two Current phases by reversing current wire (must
prevent opening of CT circuit by making short circuit for
current pass).
3- By short one current phase with neutral to make current
unbalance
7 Ensure that all hardware connections are ok as per drawing and
tightness and ferules are ok.
8 Ensure that the tripping of differential relay is in services after
finished the test.
9 Ensure that the tripping time of over current protection as final
setting after finished the test (if DMT O\C).
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
Ensure that the new Feeder was energized without any load for one
1
hour at least before on load Test.
Ensure to decrease the tripping time of over current protection to
2
less than 0.5 sec (if DMT O\C).
3 Ensure that the tripping of Directional Relay is ISOLATED to prevent
false operation of relay.
4 Ensure that VT fail function of directional Relay is switched off to
prevent relay block.
5 Ensure that the Feeder is loaded by 25% at least form its rated
current.
6 Check the Power direction by checking the current direction, if the
feeder export in this case the active power will be forward (+ive),
and wise versa the power will be reverse (– ive).
7 By removing phase (R) voltage signal, Ensure that the relay will trip
or pick up at forward active power and wise versa the relay will not
Trip or pick up if the active power was reversed by reversing the
current direction by :
4- Reverse the current direction from relay software.
5- Reverse two voltage phases by reversing voltage wire.
8 Repeat Step (6) for (S) and (T) voltage phases, and check relay
performance.
9 Ensure that all hardware connections are ok as per drawing and
tieness and ferules are ok.
10 Ensure that the tripping of Directional relay is in services after
finished the test.
11 Ensure that the tripping time of over current protection as final
setting after finished the test (if DMT O\C).
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title: INDEX NO.
Electrical Tests
Electrical tests
Close bus bar disconnector Q1 for two feeders one feeder will
be reference and another will be test feeder .Apply primary
2 Injection (inject 25% from primary current) to the red phase for
reference and test feeders.
6 Repeat the above steps for the yellow and blue phases
ATTACHMENTS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Attachments
Title: INDEX NO.
In order to reduce pre-commissioning time for __________Project, the following agreement is being
made between SEC and the contractor.
1. Site Conditions
All the tools and equipment with valid calibration certificate shall be available at site.
3. Documents
The following documents shall be available at site before start of SEC witnessing:
a. Approved drawings bearing very clear name and signature of the approving authority with
approval stamp on each sheet along with complete approval correspondence.
b. The manuals giving detailed test procedure of each equipment, technical data of all
electrical equipment, factory test records of all equipment, cable schedules, equipment
interconnection wiring schedule and wiring tables/diagrams.
c. SEC approved test procedure and test formats carrying approval stamp with name and
signature of the approving authority.
d. The project specifications and protection requirements.
e. List of deviations from SEC specs and SEC approval letters for the same.
4. Relay Settings
a. The contractor shall submit his proposed relay settings for all settable relays one month
before starting of pre-commissioning witnessing.
b. SEC-Engineering Protection Division shall provide final approved settings before pre-
commissioning witnessing is started.
c. Pre-commissioning witnessing will not be started in the absence of approved relay settings,
in order to avoid re-setting.
d. Commissioning Program.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Attachments
Title: INDEX NO.
f. A three-week testing program based on the approved overall program shall be submitted
every Tuesday indicating the proposed activities for the following two weeks and this
program will indicate activities completed in the current week and the reasons for not
completing any planned activity and its impact on the overall program with proposed
remedial measures.
5. Pre-commissioning Procedures
Pre-commissioning of all equipment shall be carried out in line with SEC Pre-commissioning Procedure and
in line with this agreement.
The contractor shall demonstrate a sample test for each equipment mentioned under (I-V) according to the
approved test procedure in presence of SEC-Commissioning Personnel and record the results on the
approved test format. If the SEC Commissioning personnel are satisfied with test procedures and results,
the contractor can complete the tests of the remaining equipment under (I-V) accordingly without SEC
present.
I. Secondary injection of all the aux. Relays, MCBs, Timers and O/C or E/F relay.
II. CT‟s magnetic curves.
III. AC/DC Distribution boards.
IV. All VTs.
V. The contractor shall prepare the detailed test procedure and format to perform the functional
tests.
The contractor shall carry out on his own 100% functional tests for all relay panels, control panels, LCCs,
AVC panels and transformer-marshalling kiosk etc. The tests shall ensure the following:
k. All DC functional checks and the test results for the same shall be tabulated in special
formats and this format shall include the following items:
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Attachments
Title: INDEX NO.
a. The SEC witnessing personnel will select 20% of the equipment covered under I-IV and the
contractor will test all this equipment under SEC witnessing. SEC commissioning personnel
will sign only those test results which will be done under his presence.
b. SEC witnessing engineer/technician will do sample test by 20% of each type of panels with
minimum of 1 of each type. The contractor will carry out all the functional tests as
mentioned under V for these sample-selected panels under witnessing of SEC
commissioning personnel. SEC engineer will sign only those test results, which will be done
under his presence. SEC engineer has the right to witness complete bay in respect of all
panels, i.e., LCC, relay and control panels, etc.
a. Secondary injection of all main protection relays except O/C and E/F relays.
b. Auxiliary or lockout relays used as trip relays.
c. Final settings of all substation timers.
d. All indicating and recording meters.
e. All transducers.
f. Primary injection and stability and sensitivity test of all unit protections, i.e., BBP,
transformer differential and REF protection and underground cable protection, etc.
g. Final trip tests, closing tests, SCADA alarm tests. End to end tests, operation and interlock
checks and on-load tests, etc.
h. All tests relating to the fault recorder.
i. RCT, CT insulation, Lead resistance, CT polarity and Single Point Grounding.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Attachments
Title: INDEX NO.
a. The test record formats will be duly signed by the contractor‟s testing engineer and SEC
Commissioning personnel simultaneously at the completion of formats for any test. No
formats shall be left unsigned for signing next day for quite obvious reasons.
b. SEC Commissioning personnel shall clear the snags after confirming satisfactory
completion and such clearance shall not be deferred to a later date in any case.
11. The contractor will submit complete test record to SEC. This test record will include all the tests
conducted by the contractor on his own and all those tests conducted by him under SEC witnessing.
12. This agreement can also be applied by the contractor to other substations under the same contract.
13. This agreement will be considered null and void at the end of Contract No. _________ and the
contractor will have to make a fresh agreement for any other contract/substation in the future.
For SEC
For Contractor
Names Signature Names Signature
PMD
CSD
Contract No.
Project Title.
Date:
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Attachments
Title: INDEX NO.
Contract No.
Project Title /
Substation Number
Date of visit
COMMETS:
Project Title:
o Facility Name/Number :
We have checked the subject project related activities and verified status of conformance to the mandatory
requirements that are shown below and list below our findings and comments.
Comments:
Conclusion:
Agree to Energize
Do Not Agree to Energize unless the following tasks are completed
Division Signature:
S/S NAME/NUMBER
The following items have to be confirmed at the end of the pre commissioning tests:
Further Remarks:
Signature:
Name:
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Attachments
Title: INDEX NO.
Project Time:
Comments:
Project Title:
Problem Description :
FILLED BY FIELD STAFF
Problem Consequences :
Previous History :
Attachment :
Detail Report Drawing Others
d
ACCEDED BY :
Commissioning Signature : ACCEDED DATE :
Division Manager
Problem Classification:
Design
Material specifications
Implementation
FILLED BY TSCD
OTHERS
Recommendation & Solution :
Substation Report #
Test Results
Approved Setting Details Setting
Relay & Serial No. Panel / Circuit Final Remarks
SL Applied? Final Trip
Issue no. Date Setting
:التوقيع
SIGNATURE:
NAME : :االسم
DATE : :التاريخ
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Attachments
Title: INDEX NO.
Substation Circuit
Contract No رقم المشروع
Project Title اسم المشروع
Contractor Name اسم المقاول
Attention Mr.. لعنلية السيد
FORM:
SAFETY SUBJECT:
SAFETY
FILLED ON WEEKLY
& BI-WEEKLY BASIS
Snag/ Confirmed By
S.I. Expected Time of
Punch Description of the Deficiency Issued Date Issued By Commissioning Remark
# Completion by
list No. Personnel
* To be filled by SEC Commissioning engineer/technician. Legend: CSD: Comm. Services Department PMD: Project Management SOD: System Operation
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Attachments
Title: INDEX NO.
COMMISSIONING PROCESS FLOW CHART
ATTACHMENT NO. 15 PAGE NUMBER
PAGE 224 OF 227
CONTRACT #:
PROJECT TITLE:
DATE:
S/S NAME/NUMBER :
Type of
Snag/ Date to be
Deficiency Issued
S.I. # Punch Description of the Deficiency Issued By Completed by the Remarks
Date
list No. Contractor
“A” or ”B”
N
N
C S D E ng . S ubmittal
C omments c omplies w/
T C S -P -105 ?
N Y
Are there any
s nag s or
P rog res s of S tart P re-C ommis s ioning C S D C oordination E ng .
c omments ?
C ommis s ioning reported tes ts within two weeks of prepares planned
by C S D eng . joint s ite vis it ac tivities
N
P erform O n-load F inal Ac c eptanc e
S tability & of E nerg iz ed
Direc tionality tes ts C irc uits
C P M
M
P repare report of
pre-c ommis s ioning E nerg iz e P rojec t
P re E nerg iz ation C hec ks : P repare final
tes ts to c lear the by S O C with
F inal S etting Applied, projec t report
Drawing s Marked Up, equipment / projec t
and is s ue (NC )
pres enc e of C S D
E ng .
(P AC ) Is s ued
by P MD E ng .
P unc h-lis t B
c learanc e in order to E nd
T es t R es ults c omplete is s ue (F AC )
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Attachments
Title: INDEX NO.
COMMISSIONING PROCESS FLOW CHART
ATTACHMENT NO. 15 PAGE NUMBER
PAGE 226 OF 227
Responsibilities Legend
CSD PMD SOC SMD Contractor
Participation Icons
CSD C PMD P SOC O SMD M
Acronyms
NC Notice of Clearance
PAC Preliminary Acceptance Certification
FAC Final Acceptance Certification
List A Snags to be cleared before Energization or snags that require shutdowns and outages
List B Snags does not effect Energization and can cleared after Energization
CSD Commissioning Services Department
PMD Project Management Department
SOC System Operations and Control
SMD Substation Maintenance Department
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Attachments
Title: INDEX NO.
PROCEDURE IMPROVEMENT REQUEST
ATTACHMENT NO. 15 PAGE NUMBER
PAGE 227 OF 227
This form to be forwarded to the Technical Support & Coordination Division in the Commissioning Services Department.