PURPOSE :
FOR APPROVAL
Page 1
TANJUNG UNCANG 120MW CCPP PROJECT
HIGH POTENTIAL TEST PROCEDURE FOR SWITCHYARD
TABLE OF CONTENT
1. PURPOSE ..................................................................................................................................... 3
2. SCOPE .......................................................................................................................................... 3
3. PREREQUISITES AND LIST OF TEST ................................................................................... 3
4. TESTING EQUIPMENT LIST .................................................................................................... 3
5. SAFETY PRECAUTION ............................................................................................................. 3
6. REFERENCE DRAWING ........................................................................................................... 4
7. TEST PROCEDURE .................................................................................................................... 4
8. TESR RECORD FORMAT.......................................................................................................... 5
Page 2
TANJUNG UNCANG 120MW CCPP PROJECT
HIGH POTENTIAL TEST PROCEDURE FOR SWITCHYARD
1. PURPOSE
This procedure is established the method to carried out the Hi Potential test of switchyard over head conductor before
energize by normal power at the project Tanjung Uncang 120MW CCPP.
2. SCOPE
This Procedure only used for testing of over head conductor 2 Line Bus Bar and 3 Bay Line at switchyard Tanjung
Uncang 120MW CCPP project.
Prior to tested, testing engineer should make sure that construction work was done and all report was sign by the owner
and no punch list item remaining.
All CT secondary connection should be shorted and connect to ground.
All CVT secondary should be disconnect with the protection system/another system.
All CB and DS shoud be in closed position in order that equipment included at the testing.
All connection HV cable to power transfoermer should be disconnected and isolated.
All connection over head cabe to Exixting switchyard should be disconnected and hanging in safe position and correct
clearence.
The following item tested below for switchyard system 150kV before put in normal operation are:
1. Over head cable Insulation reasistanece
2. Over head cable Hi Potential test
HV Tester
5. SAFETY PRECAUTION
All personal shall be worn Personal Protection Equipment minimum such as uniform, safety helmet, safety shoes ,safety
glasses and safety gove electrical. Before start the activity, make sure all worker and supervisor conducting safety in-
duction and toolbox meeting to make sure the activity planning is clear and make sure work permit was applied to
Commissioning Manager and CC to safety department. All area should be enough lighting for working at night shift.
All personal shall wear safety full body harness if they work at height level more than 2 meters and make sure the scaf-
folding install properly and inspected by scaffolding inspector.
Cable power for testing shall using ELCB to protect human during testing activity from electrical shock. All testing
equipment should have calibration certificate.
All testing activity shall carried out by competence person to avoid equipment damage and make that equipment prop-
erly function.
Page 3
TANJUNG UNCANG 120MW CCPP PROJECT
HIGH POTENTIAL TEST PROCEDURE FOR SWITCHYARD
6. REFERENCE DRAWING
This test procedure should be refer to factory test recommendation, project standard and code and comply with contract
agreement, but no limited to:
150kV switchyard plan view(1HID1-1-4011-702)
Standard for Hi Potential tes HV system(IEC 62271-100/IEC60840/IEC-62067)
150kV Switchyard section-A(1HID1-1-4011-703)
150kV Switchyard section-B(1HID1-1-4011-704)
7. TEST PROCEDURE
Page 4
TANJUNG UNCANG 120MW CCPP PROJECT
HIGH POTENTIAL TEST PROCEDURE FOR SWITCHYARD
System : _______________________________
Cable TAG : _______________________________
Cable from/to : _______________________________
Page 5
TANJUNG UNCANG 120MW CCPP PROJECT
HIGH POTENTIAL TEST PROCEDURE FOR SWITCHYARD
System : _______________________________
Cable TAG : _______________________________
Cable from/to : _______________________________
Page 6