Activity ID Activity Name Original Duration Start Finish Qtr 1, 2020 Qtr 2, 2020
Jan Feb Mar Apr
783 30-Dec-19 29-Dec-22
DC04 DMRC_DC04- Construction Schedule
DC04.1 Contract Award 0 30-Dec-19 30-Dec-19 30-Dec-19, DC04.1 ContractAward
DC04.KD.1 Key Dates For Complete Viaduct including Viaduct in Station portion as per Appendix-2B 1067 27-Jan-20 29-Dec-22
V-KD-8 (i) (i) Partial Access of the Viaduct including in stations area 0 14-Dec-20
V-KD-8 (ii) (ii) Partial Access of the Viaduct including in stations area for next 2.0 Km (min.) 0 31-May-21
V-KD-8 (iii) (iii) Full Access of the Viaduct including in stations area to Track contractor for laying track. 0 29-Nov-21
V-KD-2 Commissioning of 1st Batching Plant (production of 1st batch of concrete) 0 10-Feb-20 Commissioning of 1st Batching Plant (production of 1st batch of concrete),
V-KD-5 Commissioning of 2nd Batching Plant 0 23-Mar-20 Commissioning of 2nd Batching Plant,
V-KD-6 Completion of 1st working pile 0 13-Apr-20
V-KD-4 Completion of 1st Formwork for precast U – girder element of production line for Engineer’s approval 0 23-Mar-20 Completion of 1st Formwork for precast U – girder element of production line for Engineer’s approval,
V-KD-910 Completion of entire works as per the Contract 0 29-Dec-22
V-KD-7 Erection of 1st U-Girder 0 13-Jul-20
V-KD-9 Full Access to system contractors including G.I Hangers for laying of ables 0 18-Apr-22
V-KD-1 Submission of construction programme 0 27-Jan-20 Submission of construction programme,
V-KD-3 Submission of Definitive Design 0 09-Mar-20 Submission of Definitive Design,
DC04.KD.2 Key Dates For Stations as per Appendix-2B-1 1053 10-Feb-20 29-Dec-22
S-KD-4.1 Access to lift shaft & Escalator pits For first Twostation 0 22-Feb-21
S-KD-4.2 Access to lift shaft & Escalator pits For next Two stations 0 29-Nov-21
S-KD-6.1 Access to PEB contractor for erection of roof structure For first station 0 22-Mar-21
S-KD-7 Access to PEB contractor for erection of roof structure For last station 0 29-Dec-22
S-KD-6.2 Access to PEB contractor for erection of roof structure For next Two stations 0 18-Oct-21
S-KD-2 Completion of 1st Formwork for precast elements i.e. Cross arm, π Girder, Cross beam for Engineer’s approval 0 23-Mar-20 Completion of 1st Formwork for precast elements i.e. Cross arm, π Girder, Cross beam for Engineer’s approval,
S-KD-5.1 Completion of structure works of one Entry/Exit For first Two station 0 07-Jun-21
S-KD-5.2 Completion of structure works of one Entry/Exit For nextTwo stations 0 20-Sep-21
S-KD-3.1 Partial access to finishing contractor in operational rooms For first station 0 20-Sep-21
S-KD-3.3 Partial access to finishing contractor in operational rooms For last station 0 18-Apr-22
S-KD-3.2 Partial access to finishing contractor in operational rooms For next Two stations 0 07-Feb-22
S-KD-1 Submission of Definitive Design 0 10-Feb-20 Submission of Definitive Design,
DC04.KD.3 Key Dates For Integrated Elevated Viaduct and Underpass: as per Appendix-2B-1 1053 10-Feb-20 29-Dec-22
IEV-KD-8 (i) (i) Completion of structural work of the flyover (minimum 1.0 Km in one stretch) 0 10-Aug-20
IEV-KD-8 (ii) (ii) Completion of structural work of the flyover (minimum 2.0 Km in one stretch) 0 12-Jul-21
IEV-KD-8 (iii) (iii) Full completion of structural work of the flyover including approaches 0 29-Nov-21
IEV-KD-9 Complete work of Flyover including Bituminous Carpeting/wearing coat 0 27-Jun-22
IEV-KD-910 Completion of entire works as per the Contract. 0 29-Dec-22
IEV-KD-4 Completion of 1st Formwork for precast I – girder element of production line for Engineer’s approval 0 20-Apr-20
IEV-KD-5 Erection of 1st I-Girder 0 10-Aug-20
IEV-KD-1 Submission of construction programme 0 10-Feb-20 Submission of construction programme,
IEV-KD-3 Submission of Definitive Design 0 23-Mar-20 Submission of Definitive Design,
IEV-KD-2 Submission of preliminary Design 0 24-Feb-20 Submission of preliminary Design,
DC04.EMP.LHO Employer's Obligation- Land Handing Over 7 30-Dec-19 06-Jan-20 06-Jan-20, DC04.EMP.LHO Employer's Obligation- Land Handing Over
A1070 Land Handing over for Integrated Flyover Viauduct 7 30-Dec-19 06-Jan-20 Land Handing over for Integrated Flyover Viauduct
A1060 Land Handing over for Stations 7 30-Dec-19 06-Jan-20 Land Handing over for Stations
A1050 Land Handing over for Viaduct 7 30-Dec-19 06-Jan-20 Land Handing over for Viaduct
DC04.EMP.DRW Employer's Obligation- Issuing of Super Structure Drawing for Viaduct 10 30-Dec-19 09-Jan-20 09-Jan-20, DC04.EMP.DRW Employer's Obligation- Issuing of Super Structure Drawing for Viaduct
EMP.DRW.4 Issuing GFC drawing of Bearing GA & Reinfocement 10 30-Dec-19 09-Jan-20 Issuing GFC drawing of Bearing GA & Reinfocement
EMP.DRW.3 Issuing GFC drawing of Crash barrier GA & Reinfocement 10 30-Dec-19 09-Jan-20 Issuing GFC drawing of Crash barrier GA & Reinfocement
EMP.DRW.1 Issuing GFC drawing of Pier Cap GA & Reinfocement 10 30-Dec-19 09-Jan-20 Issuing GFC drawing of Pier Cap GA & Reinfocement
EMP.DRW.2 Issuing GFC drawing of U Girder GA & Reinfocement 10 30-Dec-19 09-Jan-20 Issuing GFC drawing of U Girder GA & Reinfocement
DC04.EMP.UTI Employer's Obligation-Permission for diversion of utilities 15 01-Jan-20 16-Jan-20 16-Jan-20, DC04.EMP.UTI Employer's Obligation-Permission for diversion of utilities
UTI10 Permission for diversion of Civil utilties 15 01-Jan-20 16-Jan-20 Permission for diversion of Civil utilties
UTI Permission for diversion of Electric utilties 15 01-Jan-20 16-Jan-20 Permission for diversion of Electric utilties
UTI20 Permission for diversion of Uncharted utilties 15 01-Jan-20 16-Jan-20 Permission for diversion of Uncharted utilties
DC04.EMP.DIV Employer's Obligation- Diversion of Utlities 30 10-Jan-20 09-Feb-20 09-Feb-20, DC04.EMP.DIV Employer's Obligation- Diversion of Utliti es
A1010 Diversion of Other uncharted Utilities 30 10-Jan-20 09-Feb-20 Diversion of Other uncharted Utilities
A1000 Diversion of Overhead HT Line 30 10-Jan-20 09-Feb-20 Diversion of Overhead HT Line
DC04.EMP.TC Employer's Obligation- Permission for Tree cutting 10 01-Jan-20 11-Jan-20 11-Jan-20, DC04.EMP.TC Employer's Obligation- Permission for Tree cutting
A1040 Permission for tree cutting in Integrated Flyover Viaduct 10 01-Jan-20 11-Jan-20 Permission for tree cutting in Integrated Flyover Viaduct
A1030 Permission for tree cutting in Station 10 01-Jan-20 11-Jan-20 Permission for tree cutting in Station
A1020 Permission for tree cutting in Viaduct including th tation viduct 10 01-Jan-20 11-Jan-20 Permission for tree cutting in Viaduct including th tation viduct
Actual Level of Effort Remaining Work Milestone Page 1 of 5 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
DMRC_DC04- Construction Schedule THREE MONTH ROLLING PROGRAMME
Activity ID Activity Name Original Duration Start Finish Qtr 1, 2020 Qtr 2, 2020
Jan Feb Mar Apr
INST-94 Installation of STeel Yard 60 28-Jan-20 28-Mar-20 Installation of STeel Yard
DC04.PL.1.4 CastingYard Setup 89 20-Jan-20 18-Apr-20
DC04.PL.1.4.1 Bay 1 73 20-Jan-20 02-Apr-20 02-Apr-20, DC04.PL.1.4.1 Bay 1
B1-05 Area Marking for Bay 12 1 20-Jan-20 21-Jan-20 Area Marking for Bay 12
B1-50 Concreting Work for Gantry foundation 55 02-Feb-20 28-Mar-20 Concreting Work for Gantry foundation
B1-70 EOT Gantry Installation 10 19-Feb-20 29-Feb-20 EOT Gantr y Installation
B1-10 Excavation for Gantry foundation 10 23-Jan-20 02-Feb-20 Excavation for Gantry foundation
B1-40 Formwork for Gantry foundation 55 31-Jan-20 26-Mar-20 Formwork for Gantry foundation
B1-80 Laying GSB at casting Bed 35 09-Feb-20 15-Mar-20 Laying GSB at casting Bed
B1-90 Laying RMC at Casting Bed 35 11-Feb-20 17-Mar-20 Laying RMC at Casting Bed
B1-20 PCC for Gantry foundation 15 25-Jan-20 09-Feb-20 PCC for Gantry foundation
B1-60 Rail FIxing Work for Gantry foundation 50 12-Feb-20 02-Apr-20 Rail FIxing Work for Gantry foundation
B1-30 Reinforcement work for Gantry foundation 55 27-Jan-20 22-Mar-20 Reinforcement work for Gantry foundation
DC04.PL.1.4.2 Bay -2 73 20-Jan-20 02-Apr-20 02-Apr-20, DC04.PL.1.4.2 Bay -2
B2-100 Area Marking for Bay 12 1 20-Jan-20 21-Jan-20 Area Marking for Bay 12
B2-150 Concreting Work for Gantry foundation 55 02-Feb-20 28-Mar-20 Concreting Work for Gantry foundation
B2-170 EOT Gantry Installation 10 19-Feb-20 29-Feb-20 EOT Gantr y Installation
B2-110 Excavation for Gantry foundation 10 23-Jan-20 02-Feb-20 Excavation for Gantry foundation
B2-140 Formwork for Gantry foundation 55 31-Jan-20 26-Mar-20 Formwork for Gantry foundation
B2-180 Laying GSB at casting Bed 35 09-Feb-20 15-Mar-20 Laying GSB at casting Bed
B2-190 Laying RMC at Casting Bed 35 11-Feb-20 17-Mar-20 Laying RMC at Casting Bed
B2-120 PCC for Gantry foundation 15 25-Jan-20 09-Feb-20 PCC for Gantry foundation
B2-160 Rail FIxing Work for Gantry foundation 50 12-Feb-20 02-Apr-20 Rail FIxing Work for Gantry foundation
B2-130 Reinforcement work for Gantry foundation 55 27-Jan-20 22-Mar-20 Reinforcement work for Gantry foundation
Actual Level of Effort Remaining Work Milestone Page 2 of 5 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
DMRC_DC04- Construction Schedule THREE MONTH ROLLING PROGRAMME
Activity ID Activity Name Original Duration Start Finish Qtr 1, 2020 Qtr 2, 2020
Jan Feb Mar Apr
A1130 Installation of Bed 90 04-Mar-20 02-Jun-20
DC04.PL.1.5.7 Mould Bed for Precast Cross Arm and Beam 52 06-Mar-20 27-Apr-20
A1180 Casting of Bed 30 06-Mar-20 05-Apr-20
A1170 Fabrication of Shutter 45 06-Mar-20 20-Apr-20
A1190 Installation of Bed 7 20-Apr-20 27-Apr-20
DC04.PL.1.5.8 Mould Bed for Precast Flyover Pier cap 45 06-Mar-20 20-Apr-20
A1150 Casting of Bed 30 06-Mar-20 05-Apr-20
A1140 Fabrication of Shutter 45 06-Mar-20 20-Apr-20
A1160 Installation of Bed 7 05-Apr-20 12-Apr-20
DC04.5 Submission of Method Statement 5 30-Dec-19 06-Jan-20 06-Jan-20, DC04.5 Submission of Method Statement
DC04.5.1 Submission of Method Statement 5 30-Dec-19 06-Jan-20 06-Jan-20, DC04.5.1 Submission of Method Statement
A1220 Submission of MS for Flyover 5 30-Dec-19 06-Jan-20 Submission of MS for Flyover
A1210 Submission of MS for Station 5 30-Dec-19 06-Jan-20 Submission of MS for Station
A1200 Submission of MS for Viaduct 5 30-Dec-19 06-Jan-20 Submission of MS for Viaduct
DC04.5.2 Approval of Method Statement 5 30-Dec-19 06-Jan-20 06-Jan-20, DC04.5.2 Approval of Method Statement
A1240 Approval of MS for Station 5 30-Dec-19 06-Jan-20 Approval of MS for Station
A1250 Approval of MS for Flyover 5 30-Dec-19 06-Jan-20 Approval of MS for Flyover
A1230 Approval of MS for Viaduct 5 30-Dec-19 06-Jan-20 Approval of MS for Viaduct
Actual Level of Effort Remaining Work Milestone Page 3 of 5 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
DMRC_DC04- Construction Schedule THREE MONTH ROLLING PROGRAMME
Activity ID Activity Name Original Duration Start Finish Qtr 1, 2020 Qtr 2, 2020
Jan Feb Mar Apr
DC04.7.8.2.2.3.5 Clearing and Grabbing work 0
DC04.7.8.2.2.3.8 Installation of working piles 0
DC04.7.8.2.2.3.9 Construction of Pile Caps 0
DC04.7.8.2.2.3.22 Construction of Pier 0
DC04.7.8.2.2.3.23 Construction of Pier - 1st lift in Station and Flyover Portion 0
DC04.7.8.2.2.3.24 Construction of Cast in Situ Pier Cap 0
DC04.7.8.2.2.3.25 Construction of Pier 2 nd Lift at Station and FLyover Portion 0
DC04.7.8.2.2.3.11 Production of Precast Pier Cap 0
DC04.7.8.2.2.3.12 Erection of Precast Pier Cap 0
DC04.7.8.2.2.3.13 Bearing fixing work 0
DC04.7.8.2.2.3.14 Production of U Girder (Precast U Girder) 0
DC04.7.8.2.2.3.15 Erection U Girder (Precast U Girder) 0
DC04.7.8.2.2.3.16 Cable tray & OHE Insert 0
DC04.7.8.2.2.3.17 Expansion Joint 0
DC04.7.8.2.2.3.18 Restoration of Median 0
DC04.7.8.2.2.3.19 Rain Water Harvesting Work 0
DC04.7.8.2.2.3.20 Anti Carbonation paint 0
DC04.7.8.2.3 Emergency Sliding Line 0
DC04.7.8.2.3.2 Stabling Line 0
DC04.7.8.2.3.3 Sick Line 0
DC04.7.8.2.1 Elevated Ramp 0
DC04.7.8.2.1.2 Elevated Ramp - 1 0
DC04.7.8.2.1.2.6 Shoring Work 0
DC04.7.8.2.1.2.1 Excavation 0
DC04.7.8.2.1.2.2 PCC Work 0
DC04.7.8.2.1.2.7 Footing Work 0
DC04.7.8.2.1.2.3 Base Slab 0
DC04.7.8.2.1.2.4 Wallup to Track SLab 0
DC04.7.8.2.1.2.8 Backfilling 0
DC04.7.8.2.1.2.5 Track Slab 0
DC04.7.8.2.1.2.9 Parapet Wall 0
DC04.7.8.2.1.2.10 Railing & Fencing Work 0
DC04.7.8.2.1.5 Elevated Ramp - 2 0
DC04.7.8.2.1.5.6 Shoring Work 0
DC04.7.8.2.1.5.1 Excavation 0
DC04.7.8.2.1.5.2 PCC Work 0
DC04.7.8.2.1.5.7 Footing Work 0
DC04.7.8.2.1.5.3 Base Slab 0
DC04.7.8.2.1.5.4 Wallup to Track SLab 0
DC04.7.8.2.1.5.8 Backfilling 0
DC04.7.8.2.1.5.5 Track Slab 0
DC04.7.8.2.1.5.9 Parapet Wall 0
DC04.7.8.2.1.5.10 Railing & Fencing Work 0
DC04.7.8.2.4 Special Spans ( Steel Structure) 0
DC04.7.8.2.4.1 Special Span Near PP 12 Location 0
DC04.7.8.2.4.1.1 Fabrication Work 0
DC04.7.8.2.4.1.2 Assembly WORK 0
DC04.7.8.2.4.1.3 Erection Work 0
DC04.7.8.2.4.1.4 Paint Work 0
DC04.7.8.2.4.1.5 Railing Work 0
DC04.7.8.2.4.1.6 Cable Tray,OHE Mast 0
DC04.7.8.2.4.2 Special Span Near P64 Location 0
DC04.7.8.2.4.2.1 Fabrication Work 0
DC04.7.8.2.4.2.2 Assembly WORK 0
DC04.7.8.2.4.2.3 Erection Work 0
DC04.7.8.2.4.2.4 Paint Work 0
DC04.7.8.2.4.2.5 Railing Work 0
DC04.7.8.2.4.2.6 Cable Tray,OHE Mast 0
DC04.7.8.1 CONSTRUCTION WORK FOR INTEGRATED ELEVATED VIADUCTAND UNDERPASS 0
DC04.7.8.1.1 Section 1 0
DC04.7.8.1.2 Section 2 0
DC04.7.8.3 CONSTRUCTION WORK FOR STATIONS 0
DC04.7.8.3.1 Station Sangam Vihar 0
DC04.7.8.3.1.1 Hindrance free Area handing over by DMRC 0
DC04.7.8.3.1.6 Barricading Work 0
DC04.7.8.3.1.2 Utilities Identification Work 0
DC04.7.8.3.1.3 Utility Diversion Work ifany byYFC 0
DC04.7.8.3.1.7 Utility Diversion Work ifany by DMRC 0
DC04.7.8.3.1.4 Dismantling Work i.e.Light Poles, Road Median,Railing etc. 0
DC04.7.8.3.1.5 Clearing and Grabbing work 0
DC04.7.8.3.1.8 Installation of working piles 0
DC04.7.8.3.1.9 Construction of Pile Caps 0
DC04.7.8.3.1.22 Construction of Pier 0
DC04.7.8.3.1.23 Construction of Pier - 1st lift up to Concourse 0
DC04.7.8.3.1.24 Precast work of Cross Arm Beam @ Concourse Level 0
DC04.7.8.3.1.25 Erection of Cross ArmBeam@ Concourse Level 0
DC04.7.8.3.1.11 Precast work of Π Girder@ Concourse Level 0
DC04.7.8.3.1.12 Erection of Π Girder @ Concourse Level 0
DC04.7.8.3.1.10 Construction of Pier - 2nd lift up to Platform Level 0
DC04.7.8.3.1.28 Precast work of Π Girder@ Platform Level 0
DC04.7.8.3.1.27 Erection of Cross ArmBeam@ Platform Level 0
DC04.7.8.3.1.26 Precast work of Cross Arm Beam @ Platform Level 0
DC04.7.8.3.1.29 Erection of Π Girder @ Platform Level 0
DC04.7.8.3.1.18 Misc cast in situ concrete work 0
DC04.7.8.3.1.21 Lift Shaft @Concourse to Platform 0
DC04.7.8.3.1.13 Escalator Pit @Concourse to Platform 0
DC04.7.8.3.1.14 Entry Structure 1 0
DC04.7.8.3.1.15 Entry Structure 2 0
DC04.7.8.3.1.16 Cable tray & OHE Insert 0
DC04.7.8.3.1.17 Expansion Joint 0
DC04.7.8.3.1.20 Anti Carbonation paint 0
DC04.7.8.3.1.19 Misc & Other Work 0
DC04.7.8.3.3 Station Khanpur 0
DC04.7.8.3.3.1 Hindrance free Area handing over by DMRC 0
DC04.7.8.3.3.6 Barricading Work 0
DC04.7.8.3.3.2 Utilities Identification Work 0
DC04.7.8.3.3.3 Utility Diversion Work ifany byYFC 0
DC04.7.8.3.3.7 Utility Diversion Work ifany by DMRC 0
DC04.7.8.3.3.4 Dismantling Work i.e.Light Poles, Road Median,Railing etc. 0
DC04.7.8.3.3.5 Clearing and Grabbing work 0
DC04.7.8.3.3.8 Installation of working piles 0
DC04.7.8.3.3.9 Construction of Pile Caps 0
DC04.7.8.3.3.22 Construction of Pier 0
DC04.7.8.3.3.23 Construction of Pier - 1st lift up to Concourse 0
DC04.7.8.3.3.24 Precast work of Cross Arm Beam @ Concourse Level 0
DC04.7.8.3.3.25 Erection of Cross ArmBeam@ Concourse Level 0
DC04.7.8.3.3.11 Precast work of Π Girder@ Concourse Level 0
DC04.7.8.3.3.12 Erection of Π Girder @ Concourse Level 0
DC04.7.8.3.3.10 Construction of Pier - 2nd lift up to Platform Level 0
DC04.7.8.3.3.28 Precast work of Π Girder@ Platform Level 0
DC04.7.8.3.3.27 Erection of Cross ArmBeam@ Platform Level 0
DC04.7.8.3.3.26 Precast work of Cross Arm Beam @ Platform Level 0
DC04.7.8.3.3.29 Erection of Π Girder @ Platform Level 0
DC04.7.8.3.3.18 Misc cast in situ concrete work 0
DC04.7.8.3.3.21 Lift Shaft @Concourse to Platform 0
DC04.7.8.3.3.13 Escalator Pit @Concourse to Platform 0
DC04.7.8.3.3.14 Entry Structure 1 0
DC04.7.8.3.3.15 Entry Structure 2 0
DC04.7.8.3.3.16 Cable tray & OHE Insert 0
DC04.7.8.3.3.17 Expansion Joint 0
DC04.7.8.3.3.20 Anti Carbonation paint 0
DC04.7.8.3.3.19 Misc & Other Work 0
DC04.7.8.3.4 Station AMbedkar Nagar 0
DC04.7.8.3.4.1 Hindrance free Area handing over by DMRC 0
DC04.7.8.3.4.6 Barricading Work 0
DC04.7.8.3.4.2 Utilities Identification Work 0
DC04.7.8.3.4.3 Utility Diversion Work ifany byYFC 0
DC04.7.8.3.4.7 Utility Diversion Work ifany by DMRC 0
DC04.7.8.3.4.4 Dismantling Work i.e.Light Poles, Road Median,Railing etc. 0
DC04.7.8.3.4.5 Clearing and Grabbing work 0
Actual Level of Effort Remaining Work Milestone Page 4 of 5 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
DMRC_DC04- Construction Schedule THREE MONTH ROLLING PROGRAMME
Activity ID Activity Name Original Duration Start Finish Qtr 1, 2020 Qtr 2, 2020
Jan Feb Mar Apr
DC04.7.8.3.4.8 Installation of working piles 0
DC04.7.8.3.4.9 Construction of Pile Caps 0
DC04.7.8.3.4.22 Construction of Pier 0
DC04.7.8.3.4.23 Construction of Pier - 1st lift up to Concourse 0
DC04.7.8.3.4.24 Precast work of Cross Arm Beam @ Concourse Level 0
DC04.7.8.3.4.25 Erection of Cross ArmBeam@ Concourse Level 0
DC04.7.8.3.4.11 Precast work of Π Girder@ Concourse Level 0
DC04.7.8.3.4.12 Erection of Π Girder @ Concourse Level 0
DC04.7.8.3.4.10 Construction of Pier - 2nd lift up to Platform Level 0
DC04.7.8.3.4.28 Precast work of Π Girder@ Platform Level 0
DC04.7.8.3.4.27 Erection of Cross ArmBeam@ Platform Level 0
DC04.7.8.3.4.26 Precast work of Cross Arm Beam @ Platform Level 0
DC04.7.8.3.4.29 Erection of Π Girder @ Platform Level 0
DC04.7.8.3.4.18 Misc cast in situ concrete work 0
DC04.7.8.3.4.21 Lift Shaft @Concourse to Platform 0
DC04.7.8.3.4.13 Escalator Pit @Concourse to Platform 0
DC04.7.8.3.4.14 Entry Structure 1 0
DC04.7.8.3.4.15 Entry Structure 2 0
DC04.7.8.3.4.16 Cable tray & OHE Insert 0
DC04.7.8.3.4.17 Expansion Joint 0
DC04.7.8.3.4.20 Anti Carbonation paint 0
DC04.7.8.3.4.19 Misc & Other Work 0
DC04.7.8.3.2 Station Saket G 0
DC04.7.8.3.2.1 Hindrance free Area handing over by DMRC 0
DC04.7.8.3.2.6 Barricading Work 0
DC04.7.8.3.2.2 Utilities Identification Work 0
DC04.7.8.3.2.3 Utility Diversion Work ifany byYFC 0
DC04.7.8.3.2.7 Utility Diversion Work ifany by DMRC 0
DC04.7.8.3.2.4 Dismantling Work i.e.Light Poles, Road Median,Railing etc. 0
DC04.7.8.3.2.5 Clearing and Grabbing work 0
DC04.7.8.3.2.8 Installation of working piles 0
DC04.7.8.3.2.9 Construction of Pile Caps 0
DC04.7.8.3.2.22 Construction of Pier 0
DC04.7.8.3.2.23 Construction of Pier - 1st lift up to Concourse 0
DC04.7.8.3.2.24 Precast work of Cross Arm Beam @ Concourse Level 0
DC04.7.8.3.2.25 Erection of Cross ArmBeam@ Concourse Level 0
DC04.7.8.3.2.11 Precast work of Π Girder@ Concourse Level 0
DC04.7.8.3.2.12 Erection of Π Girder @ Concourse Level 0
DC04.7.8.3.2.10 Construction of Pier - 2nd lift up to Platform Level 0
DC04.7.8.3.2.28 Precast work of Π Girder@ Platform Level 0
DC04.7.8.3.2.27 Erection of Cross ArmBeam@ Platform Level 0
DC04.7.8.3.2.26 Precast work of Cross Arm Beam @ Platform Level 0
DC04.7.8.3.2.29 Erection of Π Girder @ Platform Level 0
DC04.7.8.3.2.18 Misc cast in situ concrete work 0
DC04.7.8.3.2.21 Lift Shaft @Concourse to Platform 0
DC04.7.8.3.2.13 Escalator Pit @Concourse to Platform 0
DC04.7.8.3.2.14 Entry Structure 1 0
DC04.7.8.3.2.15 Entry Structure 2 0
DC04.7.8.3.2.16 Cable tray & OHE Insert 0
DC04.7.8.3.2.17 Expansion Joint 0
DC04.7.8.3.2.19 Misc & Other Work 0
DC04.7.8.3.2.20 Anti Carbonation paint 0
DC04.2 Completion and Handing Over 0
Actual Level of Effort Remaining Work Milestone Page 5 of 5 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation