Sie sind auf Seite 1von 4

1.

Philippine Export v Eusebio Baghdad, Iraq, (hereinafter the Project)


to Ajyal Trading and Contracting
PHILIPPINE EXPORT AND FOREIGN Company.
LOAN GUARANTEE CORPORATION,
PETITIONER, VS. V.P. EUSEBIO On 7 March 1981, respondent spouses
CONSTRUCTION, INC.; 3-PLEX Eduardo and Iluminada Santos, in behalf
INTERNATIONAL, INC.; VICENTE P. of respondent 3-Plex International, Inc.
EUSEBIO; SOLEDAD C. EUSEBIO; (hereinafter 3-Plex), a local contractor
EDUARDO E. SANTOS; ILUMINADA engaged in construction business,
SANTOS; AND FIRST INTEGRATED entered into a joint venture agreement
BONDING AND INSURANCE with Ajyal wherein the former undertook
COMPANY, INC., RESPONDENTS. the execution of the entire Project, while
the latter would be entitled to a
Doctrine: No conflicts rule on commission of 4% of the contract price.
essential validity of contracts is Later, or on 8 April 1981, respondent 3-
expressly provided for in our laws. The Plex, not being accredited by or
rule followed by most legal systems, registered with the Philippine Overseas
however, is that the intrinsic validity of Construction Board (POCB), assigned
a contract must be governed by the lex and transferred all its rights and
contractus or “proper law of the interests under the joint venture
contract.” This is the law voluntarily agreement to VPECI, a construction and
agreed upon by the parties (the lex loci engineering firm duly registered with the
voluntatis) or the law intended by them POCB. However, on 2 May 1981, 3-Plex
either expressly or implicitly (the lex and VPECI entered into an agreement
loci intentionis). The law selected may that the execution of the Project would be
be implied from such factors as under their joint management.
substantial connection with the
transaction, or the nationality or To comply with the requirements of SOB,
domicile of the parties. Philippine respondents 3-Plex and VPECI applied
courts would do well to adopt the first for the issuance of a guarantee with
and most basic rule in most legal petitioner Philguarantee who approved
systems, namely, to allow the parties the same.
to select the law applicable to their
contract, subject to the limitation that it Subsequently, letters of guarantee were
is not against the law, morals, or public issued by Philguarantee to the Rafidain
policy of the forum and that the chosen Bank of Baghdad covering 100% of the
law must bear a substantive performance and advance payment
relatonship to the transaction. bonds, but they were not accepted by
SOB. What SOB required was a letter-
guarantee from Rafidain Bank, the
government bank of Iraq. Rafidain Bank
Facts: On 8 November 1980, the State
then issued a performance bond in favor
Organization of Buildings (SOB), Ministry
of SOB on the condition that another
of Housing and Construction, Baghdad,
foreign bank, not Philguarantee, would
Iraq, awarded the construction of the
issue a counter-guarantee to cover its
Institute of Physical Therapy–Medical
exposure. Al Ahli Bank of Kuwait was,
Rehabilitation Center, Phase II, in
therefore, engaged to provide a As of March 1986, the status of the
counter-guarantee to Rafidain Bank, Project was 51% accomplished,
but it required a similar counter- meaning the structures were already
guarantee in its favor from the petitioner. finished. The remaining 47% consisted in
Thus, three layers of guarantees had electro-mechanical works and the 2%,
to be arranged. sanitary works, which both required
importation of equipment and
Upon the application of respondents 3- materials. On 26 October 1986, Al Ahli
Plex and VPECI, petitioner Philguarantee Bank of Kuwait sent a telex call to the
issued in favor of Al Ahli Bank of Kuwait petitioner demanding full payment of its
a performance bond guarantee and performance bond counter-guarantee.
advance payment guarantee. The surety
bond was later amended to increase the Upon receiving a copy of that telex
amount and to change the bank in whose message on 27 October 1986,
favor the petitioner’s guarantee was respondent VPECI requested Iraq Trade
issued, from Rafidain Bank to Al Ahli and Economic Development Minister
Bank of Kuwait. Mohammad Fadhi Hussein to recall the
telex call on the performance guarantee
On 11 June 1981, SOB and the joint for being a drastic action in
venture VPECI and Ajyal executed the contravention of its mutual agreement
service contract for the construction of with the latter that (1) the imposition of
the Institute of Physical Therapy – penalty would be held in abeyance until
Medical Rehabilitation Center, Phase II, the completion of the project; and (2) the
in Baghdad, Iraq, wherein the joint time extension would be open,
venture contractor undertook to depending on the developments on the
complete the Project within a period of negotiations for a foreign loan to finance
547 days or 18 months. Under the the completion of the project. It also wrote
Contract, the Joint Venture would supply SOB protesting the call for lack of factual
manpower and materials, and SOB or legal basis, since the failure to
would refund to the former 25% of the complete the Project was due to (1)
project cost in Iraqi Dinar and the 75% the Iraqi government’s lack of foreign
in US dollars at the exchange rate of 1 exchange with which to pay its
Dinar to 3.37777 US Dollars. (VPECI’s) accomplishments and (2)
SOB’s noncompliance for the past
The project was not completed on several years with the provision in the
schedule due to delays. But in October contract that 75% of the billings would be
1982, upon foreseeing the impossibility paid in US dollars. Subsequently, or on
of meeting the deadline and upon the 19 November 1986, respondent VPECI
request of Al Ahli Bank, the joint venture advised the petitioner not to pay yet Al
contractor worked for the renewal or Ahli Bank because efforts were being
extension of the Performance Bond and exerted for the amicable settlement of the
Advance Payment Guarantee. Project.
Petitioner’s Letters of Guarantee, surety
bond, and performance bond were then On 14 April 1987, the petitioner received
renewed and extended. another telex message from Al Ahli Bank
stating that it had already paid to
Rafidain Bank the sum of US$876,564 respondent contractor has defaulted in
under its letter of guarantee, and the performance of its obligations under
demanding reimbursement by the the service contract?
petitioner of what it paid to the latter
bank plus interest thereon and related Ruling: 1. No, petitioner is not entitled to
expenses. Both petitioner Philguarantee reimbursement.
and respondent VPECI sought the
assistance of some government 2. Philippine law should apply.
agencies of the Philippines. On 10
August 1987, VPECI requested the No conflicts rule on essential validity of
Central Bank to hold in abeyance the contracts is expressly provided for in our
payment by the petitioner. laws. The rule followed by most legal
systems, however, is that the intrinsic
The Central Bank authorized the validity of a contract must be governed by
remittance for its account of an amount to the lex contractus or “proper law of the
Al Ahli Bank representing full payment of contract.” This is the law voluntarily
the performance counter-guarantee for agreed upon by the parties (the lex loci
VPECI’s project in Iraq. Petitioner then voluntatis) or the law intended by them
paid Al Ahli. either expressly or implicitly (the lex loci
intentionis). The law selected may be
Petitioner sent letters of demand to implied from such factors as
respondents. When the latter failed to substantial connection with the
pay, it filed a case before the RTC. transaction, or the nationality or
domicile of the parties. Philippine
After due trial, the trial court ruled against courts would do well to adopt the first and
Philguarantee. The trial court found that most basic rule in most legal systems,
the joint venture contractor incurred no namely, to allow the parties to select the
delay in the execution of the Project. law applicable to their contract, subject to
Considering the Project owner’s the limitation that it is not against the law,
violations of the contract which rendered morals, or public policy of the forum and
impossible the joint venture contractor’s that the chosen law must bear a
performance of its undertaking, no valid substantive relationship to the
call on the guarantee could be made. transaction.
Accordingly, it dismissed the complaint.
The CA affirmed the decision of the RTC. It must be noted that the service contract
between SOB and VPECI contains no
express choice of the law that would
Issue: 1. whether the petitioner is entitled govern it. In the United States and
to reimbursement of what it paid under Europe, the two rules that now seem to
Letter of Guarantee No. 81-194-F it have emerged as “kings of the hill” are
issued to Al Ahli Bank of Kuwait based on (1) the parties may choose the governing
the deed of undertaking and surety bond law; and (2) in the absence of such a
from the respondents. choice, the applicable law is that of the
State that “has the most significant
2. (Corollary issue): What law should be relationship to the transaction and the
applied in determining whether the parties.” Another authority proposed that
all matters relating to the time, place, and materials, which were available from
manner of performance and valid foreign suppliers, thus requiring US
excuses for non-performance are Dollars for their importation. The monthly
determined by the law of the place of billings and payments made by SOB
performance or lex loci solutionis, which reveal that the agreement between the
is useful because it is undoubtedly parties was a periodic payment by the
always connected to the contract in a Project owner to the contractor
significant way. depending on the percentage of
accomplishment within the period. The
In this case, the laws of Iraq bear payments were, in turn, to be used by the
substantial connection to the transaction, contractor to finance the subsequent
since one of the parties is the Iraqi phase of the work. However, as
Government and the place of explained by VPECI in its letter to the
performance is in Iraq. Hence, the issue Department of Foreign Affairs (DFA), the
of whether respondent VPECI defaulted payment by SOB purely in Dinars
in its obligations may be determined by adversely affected the completion of the
the laws of Iraq. However, since that project.
foreign law was not properly pleaded or
proved, the presumption of identity or As found by both the Court of Appeals
similarity, otherwise known as the and the trial court, the delay or the non-
processual presumption, comes into completion of the Project was caused by
play. Where foreign law is not pleaded or, factors not imputable to the respondent
even if pleaded, is not proved, the contractor. It was rather due mainly to the
presumption is that foreign law is the persistent violations by SOB of the terms
same as ours. and conditions of the contract,
particularly its failure to pay 75% of the
(discussion on default) accomplished work in US Dollars.
Indeed, where one of the parties to a
Our law, specifically Article 1169, last contract does not perform in a proper
paragraph, of the Civil Code, provides: manner the prestation which he is bound
“In reciprocal obligations, neither party to perform under the contract, he is not
incurs in delay if the other party does not entitled to demand the performance of
comply or is not ready to comply in a the other party. A party does not incur in
proper manner with what is incumbent delay if the other party fails to perform the
upon him.” obligation incumbent upon him.

Default or mora on the part of the debtor As stated earlier, SOB cannot yet
is the delay in the fulfillment of the demand complete performance from
prestation by reason of a cause VPECI because it has not yet itself
imputable to the former. It is the non- performed its obligation in a proper
fulfillment of an obligation with respect to manner, particularly the payment of the
time. It is undisputed that only 51.7% of 75% of the cost of the Project in US
the total work had been accomplished. Dollars. The VPECI cannot yet be said to
The 48.3% unfinished portion consisted have incurred in delay.
in the purchase and installation of
electro-mechanical equipment and Dispositive: Petition DENIED.

Das könnte Ihnen auch gefallen