Beruflich Dokumente
Kultur Dokumente
1.1.1.2 The depreciation for the year 2004-05 for the individual
items in the stations have been taken as per CERC norms, and, the
actual depreciation in that year has been limited to the allowable
depreciation left to be claimed, after deducting the cumulative
depreciation upto 2003-04.
The capital cost in respect of the above offices has been allocated in
the ratio of the direct capital cost of the generating station and T&D
infrastructure.
1.1.4.2 The capital cost in respect of the Konar dam has been
allocated to the individual hydel stations in the ratio of the direct
capital cost of the station.
1.2.1 According to the Section 30 of the DVC Act 1948, the entire
capital requirement of the Corporation is to be provided by the
participating Govts. The total loan capital provided by the participating
Govts. till 1968-69 amounted to Rs.214.72 crores. There has,
however, been no contribution by participating Govts. after 1968-69.
The Corporation has been ploughing back power surplus and retained
interest each year. Further, the loan capital contributed by the
participating Govts. to meet the capital cost of the project has been
treated as DVC’s own resources.
1.2.2 In respect of majority of DVC’s assets, the market borrowings to
the extent availed in the past years have since been mostly repaid.
However, these assets which have either fully completed its technical
project life or are on the verge of completion, are continuing to
generate power with periodical additional capital expenditure required
for maintaining their health and being considered for R&M after RLA
Study during the Xth Plan Period. Due to this fact, the depreciation
reserves have been mostly invested in continuous Life Extension and
Improvement (E&I) of these vintage assets over the past years. Since
DVC is operating for about six decades, it is not possible to ascertain
the project-wise debt equity structure at the time of COD in respect of
these vintage Plants. The capital base and debt equity ratio as on 31st
March, 2004 has therefore been considered for the purpose of
ascertainment of allocation of return and interest recoverable through
tariff on actual basis.
1.2.4 As on March 2004, DVC’s net worth from power related activities
was Rs. 3844.46 crores. The outstanding market borrowings / loans
stood at Rs.679.09 crores, resulting in debt equity ratio of 15:85. This
capital structure has been assumed as a normative one, and, used as
the basis for arriving at the equity capital for the individual station
corresponding to its capital cost.
1.3.1 Majority of the loans raised by the Corporation are not project
specific. The normative loan outstanding for individual station, as on
March 2004, has been computed by applying the normative debt
equity structure of 15:85 (as mentioned above at Para 1.2.2) to the
capital cost of the station.
1.3.2 The yearly repayment against the normative loan outstanding
for individual station calculated, as per Para 5.3.1 above, have been
computed as follows:
1.4.1 The O&M cost in respect of the individual stations has been
tabulated, based on the Audited Accounts, for the period 1998 to
2003. The average of O&M expenses over these 5 years is taken as a
reference amount for the base year as 2000 -01. Further, as per the
CERC norms, these expenses have been increased by 4% on year-year
basis to arrive at the O&M expenses for the base year 2003-04.
1.4.2 As has been mentioned earlier, around 50% of the total installed
capacity has been commissioned more than 25 years back.
Considering the fact that the Hon’ble Commission has allowed the
plants of NTPC at Talcher and Tanda (which was commissioned about
25 years and 16 years back resp.) to use the actual O & M expenses
as a reference to project the O&M expenses for the subsequent years,
it is, therefore, submitted similar norms to the stations of DVC may be
allowed.
1.6.1 Around 50% of DVC’s generation comes from the plants, which
are much older than NTPC’s Talcher and Tanda plants. As the CERC
has allowed deviation from its norms in the case of these power plants
of NTPC, at Talcher and Tanda, it is submitted that the CERC may
allow DVC to follow the actual operating parameters.
1.6.2 Further, it may be mentioned that the CERC norms for SHR have
not been defined for plants with capacity below 210 MW. Since 45% of
the installed capacity of thermal plants of DVC are below 210 MW, the
fuel consumption has been arrived at, based on the actual operating
parameters.
1.6.3 All the thermal stations of DVC are non-pit head stations. The
coal transit loss, too, has been based as per actuals.