SATIP:
SATIP-T-151-01
Saudi Aramco Typical Inspection Plan Approved Date Discipline
Inspection
Check List and / Responsibility
Item No. Project Phase Task Activity Quality Record Risk Level Assignments Remarks
or Test Record
Cont Aramco
3.0 INSTALLATION
3.7 Storage Battery Installation and Identification Visual Inspection SAIC-P-3121 SAIC-P-3121 H W
4.0 PRE-COMMISSIONING
4.1 Cable Continuity and Insulation Testing (Installed Cable) See Remarks See Remarks
Energization
4.15 Quality Document Review and Energization Certificate EIL RH RH
Certificate
4.19 Energized DC System Functional Testing Vented Ni-Cad Wet Cell SATR-P-3113 SATR-P-3113 H H
4.2 Ground Resistance and Continuity Testing (Installed Grounding) See Remarks See Remarks
4.20 Energized DC System Functional Testing ented Lead-Acid Wet Cell SATR-P-3114 SATR-P-3114 H H
4.21 Energized DC System Functional Testing VRLA Gelatin Cell SATR-P-3115 SATR-P-3115 H H
4.22 Energized DC System Remote Indication and Alarm Testing See Remarks See Remarks H H
4.24 Quality Document Review and Mechanical Completion Certificate PMCC / MCC FEIL RH RH
4.3 Power Cable Termination Torque Testing See Remarks See Remarks