Sie sind auf Seite 1von 4

Ensure all Safetys are acknowleged.

All sub support utilities are online and ready (Compressed Air, Water for
Cooling or NOx Reduction, Power Supplies).

Press the Start button.

Power from the DG/GRID allows starting Motor to bring Gas Turbine up to
certain speed. After 66% Engine Speed the Turbine Bleed Valve closes equalizing
all Stages of the Compressor and Exhaust Stages and the Turbine can sustain
itself...if not it will go into Stall and Fail start-up.

Before reaching 100% Turbine Engine Speed the Generator Field is Flashed to
energize the Electrical Field.

The SS clutch is over ridden and the Turbine reaches 100% Engine Speed.

Once the Turbine reaches 100% the Heat Recovery diverters slowly adjust open
to direct Heat to the Boiler Section. Once the Boiler Pressure increases past 25%
Load the Main Generator Breaker can be Closed and provide Power to the LOAD.

It is now safe to establish Water Injection to the Gas Turbine for NOx Reduction
because it will not Flameout as long as the Turbine is running at 100% Engine
Speed.

The Steam Pressure should now be reaching maximum Steam Pressure Setpoint
and the Diverters will noticeably back off to maintain setpoint.

Once we have a good Steam Supply you can now bring online the Steam
Turbine.

Reset all Safety Trips. Open the Steam Turbine Chest valves to remove all built
up Condensate. As the draining become full steam and no water -we can close
the Turbine Chest Valves and the Turbine should begin to build momentum and
increase in RPM.

Once at 50% speed the Governor can be reset and Turbine will reach 100%.

We should now be burning Fuel to sustain the Gas Turbine which is providing
Electrical Power. And building Steam Pressure to sustain the process operations
further.
SIPROTEC FEATURES & FUNCTIONS-

 Overcurrent protection (definite-time/inverse-time/user-def.)


 Directional overcurrent protection (definite-time/inverse-time/user-def.)
 Sensitive dir. earth-fault detection
 Displacement voltage
 Intermittent earth-fault protection
 Directional intermittent ground fault protection
 High-impedance restricted earth fault
 Inrush restraint
 Motor protection
 Overload protection
 Temperature monitoring
 Under-/overvoltage protection
 Under-/over frequency protection
 Rate-of-frequency-change protection
 Power protection (e.g. reverse, factor)
 Undervoltage controlled reactive power protection
 Breaker failure protection
 Negative-sequence protection
 Phase-sequence monitoring
 Synchro-check
 Auto-reclosure
 Fault locator
 Lockout
Control functions/programmable logic
 Commands for control of a circuit-breaker and of isolators
 Position of switching elements is shown on the graphic display
 Control via keyboard, binary inputs, DIGSI 4 or SCADA system
 User-defined logic with CFC (e.g. interlocking)
Monitoring functions
 Operational measured values V,l,f
 Energy metering values Wp,Wq
 Circuit-breaker wear monitoring
 Slave pointer
 Trip circuit supervision
 Fuse failure monitor
 8 oscillographic fault records
 Motor Statistics
HRSG & BOP SYSTEM

2 INCOMERS 350A

1 BUS COUPLER 350A

IMP. LOADS ARE AS FOLLOWS

LUBE OIL PIRIFIER CONTROL PANEL SUPPLY 80A

HP DOSING AGITATOR 0.75KW

LP CIRCULATING PUMP 22KW

MOV IN POLISH WATER HEATER 0.64KW

LP CONTROL STATION LCV BY PASS 0.18KW

ECO-1 BY PASS MOV INTEGRAL 0.06KW

PSH DRAIN MOV 0.12KW

100% FCV ISOLATION MOV. 1.1KW

BOILER BLOWDOWN PUMP 1.5KW

LP DOSING PUMP 0.37KW

PH DOSING SKIP PUMP 0.55KW

HP DOSING PUMP 0.37KW

STEAM VENT DRUM 0.06KW

ATTEMPTERATOR 0.37KW

SUPPLY TO HOIST FOR CRANE 63A

ISOLATION DAMPER SEALING FAN MOTOR

SSD DRAIN MOV

SUPPLY TO EOT CRANE

MSS LINE DRAIN