Beruflich Dokumente
Kultur Dokumente
ENTERING TASKS
1. On the File menu, click Save As. The Save As dialog box appears.
2. In the File name box, type Wingtip Toys Commercial 2, and then click Save.
3. If the Tasks pane is not already displayed in the Project Guide, on the Project Guide toolbar, click Tasks.
4. In the Tasks pane, click the List the tasks in the project link. The List Tasks pane appears.
5. Click the cell directly below the Task Name column heading.
6. Type “Pre-Production”, and then press Enter.
7. Click the name of the new task 1, “Pre-Production”.
Your screen should look similar to the following illustration:
Laboratory Activity#4
Your screen should look similar to the following illustration:
ESTIMATING
DURATIONS
When working in
Project, you can use
abbreviations for
durations.
ENTERING A MILESTONE
Laboratory Activity#4
In addition to tracking tasks to be completed, you might want to track an important event for your project, such as
when the pre-production phase of the project will end. To do this, you will create a milestone. Milestones are
significant events that are either reached within the project (completion of a phase of work, for example) or imposed
upon the project (a deadline by which to apply for funding, for example). Because the milestone itself doesn’t
normally include any work, milestones are represented as tasks with zero duration.
3. Type “Pre-Production complete!”, and then press the key to move to the Duration field.
4. Either type 0d in the Duration field, or in the List Tasks pane select the Make selected task a milestone
check box.
The milestone is added to your plan. Your screen should look similar to the following:
5. At the bottom of the List Tasks pane, click the Done link. The Tasks pane appears.
Laboratory Activity#4
3. In the Organize Tasks pane, click the Indent Tasks button. (You can also click this button on the Formatting
toolbar .)
Task 1 becomes a summary task, and a summary task bar for it appears in the Gantt chart. The summary task name
is also formatted in bold type. Your screen should look similar to the following illustration:
Laboratory Activity#4
6. At the bottom of the Organize Tasks pane, click the Done link. The Tasks pane reappears.
LINKING TASKS
1. In the Tasks pane, click Schedule tasks. The Schedule Tasks pane appears.
2. Select the names of tasks 2 and 3. Your screen should look similar to the following
illustration:
Laboratory Activity#4
Next you will link two tasks in a different way. You will make task 8 the predecessor of task 9.
6. Select the name of task 9.
7. On the Standard toolbar, click the Task Information button. The Task Information dialog box appears.
8. Click the Predecessors tab.
9. Click the empty cell below the Task Name column heading, and then click the down arrow that appears.
10. In the Task Name list, click “Rehearse”, and press Enter. Your screen should look similar to the following
illustration:
11. Click OK to close the Task Information dialog box. Tasks 8 and 9 are linked with a finish-to-start
relationship.
To wrap up this exercise, you’ll link the remaining production tasks and then link the two summary tasks.
Laboratory Activity#4