Beruflich Dokumente
Kultur Dokumente
marked
CERTIFICATE of
Design Assessment
by ABS
American Bureau of Shipping & Affiliated Companies
Proprietary Information
Contents
Introduction Slide 3
Synchronization 4
Breaker Logic 9
FAQ 31
Exercises 32
Proprietary Information
Introduction
Introduction The easYgen-3200 is able to perform synchronization of the generator
Synchronization across the generator circuit breaker to a common bus as well as
Breaker logic
synchronizing the common bus to a utility across the mains circuit
breaker. It is possible to configure the easYgen-3200 for either slip or
FAQ
phase matching synchronization and the acceptable breaker closure
Exercise
window.
3
Proprietary Information
Synchronization
Introduction The easYgen-3200 has a synchroscope in the display
Synchronization
Breaker logic
Bus/mains Bus/mains
FAQ voltages frequencies
Exercise
Voltage/
frequency Phase
differential angle L1
4
Proprietary Information
Synchronization
Introduction
Slip synchronization
• Configurable frequency window
o
Synchronization 0
-90 +90
FAQ • Configurable synch. frequency differential
Exercise • Configurable breaker closing time 180
o
Example:
Phase angle = 360o * (0.3 Hz) * (0.2 sec) = 21.6°
5
Proprietary Information
Synchronization
Introduction
Slip synchronization
o
Synchronization 0
-90 +90
FAQ • Define stable timer
Exercise • Define maximum voltage differential 180
o
6
Proprietary Information
Synchronization
Introduction
Phase matching
Synchronization
-90 +90
FAQ
Exercise
• Define voltage differential window
• Define positive and negative phase angle window limits
o
180
7
Proprietary Information
Synchronization
Introduction
Multiple synchronization modes
Synchronization
-90
o
+90
FAQ
governor and voltage regulator are active and breaker
Exercise close commands are issued.
• PERMISSIVE
o
180
8
Proprietary Information
The synchronization modes can be changed via a LogicsManager output
Breaker logic
Introduction The following MCB/GCB transition modes are available:
Synchronization
5 External
• External breaker control (PLC)
Synchronization
Breaker logic
FAQ
Exercise
10
Proprietary Information
Breaker logic
Introduction
1. Parallel
Synchronization
Baseload Import / Export
Breaker logic
FAQ
Exercise
CT
2
CT
3
Load
11
Proprietary Information
Breaker logic
Introduction
2. Interchange
Synchronization
Breaker logic
FAQ
1
Exercise
220 kW
2
CT
3
220 kW
Load
12
Proprietary Information
Breaker logic
Introduction
2. Interchange
Synchronization
220 kW
2
CT
3
220 kW
Load
13
Proprietary Information
Breaker logic
Introduction
2. Interchange
Synchronization
Breaker logic
Generator soft
110 kW loads
FAQ
1
Exercise
110 kW
2
CT
3
220 kW
Load
14
Proprietary Information
Breaker logic
Introduction
2. Interchange
Synchronization
110 kW
0 kW
2
CT
3
220 kW
Load
15
Proprietary Information
Breaker logic
Introduction
2. Interchange
Synchronization
Breaker logic
Generator soft
110 kW loads
FAQ
1
Exercise
0 kW
110 kW
2
CT
3
220 kW
Load
16
Proprietary Information
Breaker logic
Introduction
2. Interchange
Synchronization
0 kW
110 kW
2
CT
3
220 kW
Load
17
Proprietary Information
Breaker logic
Introduction
2. Interchange
Synchronization
110 kW
2
CT
3
220 kW
Load
18
Proprietary Information
Breaker logic
Introduction
3. Closed transition
Synchronization
Breaker logic
Both breakers closed
FAQ
for max 500 ms
1
Exercise
220 kW
2
220 kW
Load
19
Proprietary Information
Breaker logic
Introduction
3. Closed transition
Synchronization
220 kW
2
220 kW
Load
20
Proprietary Information
Breaker logic
Introduction
3. Closed transition
Synchronization
Breaker logic
220 kW
FAQ
1
Exercise
220 kW
Load
21
Proprietary Information
Breaker logic
Introduction
3. Closed transition
Synchronization
Breaker logic
110 kW
FAQ
1
Exercise
110 kW
2
3 Synchronize GCB
220 kW
Load
22
Proprietary Information
Breaker logic
Introduction
3. Closed transition
Synchronization
Breaker logic
110 kW
FAQ
1
Exercise
110 kW
2
220 kW
Load
23
Proprietary Information
Breaker logic
Introduction
4. Open transition
Synchronization
Breaker logic
FAQ
1
Exercise
220 kW
2
220 kW
Load
24
Proprietary Information
Breaker logic
Introduction
4. Open transition
Synchronization “Transfer time GCBMCB”
Breaker logic controls how long the load bus
FAQ
1
is de-energized
Exercise
220 kW
Load
25
Proprietary Information
Breaker logic
Introduction
4. Open transition
Synchronization
220 kW
Load
26
Proprietary Information
Breaker logic
Introduction
4. Open transition
Synchronization
Breaker logic
110 kW
FAQ
1
Exercise
0 kW
2
3
Synchronize GCB
220 kW
Load
27
Proprietary Information
Breaker logic
Introduction
4. Open transition
Synchronization
Breaker logic
110 kW
FAQ
1
Exercise
110 kW
2
3
Generator soft loads
220 kW
Load
28
Proprietary Information
Breaker logic
Introduction
5. External
Synchronization
• Breaker control performed externally (PLC)
Breaker logic
• Breaker open command depending on alarm class
FAQ
29
Proprietary Information
Breaker logic
Introduction
The MCB operates only if “Enable MCB = TRUE”
Synchronization
The default configuration is as follows:
Breaker logic
FAQ
Exercise
Closing of MCB stops
if alarm occurs
No closing if field
rotation is wrong
30
Proprietary Information
FAQ
Introduction How do I define the operating ranges for synchronization ?
Synchronization The operating ranges are utilized for permitting breaker closures and defining when
an emergency mode should be initiated.
Breaker logic
FAQ
Exercise
Generator Mains
31
Proprietary Information
Exercise
Introduction
Configure the following application:
Synchronization
1. You are commissioning an emergency standby generator for a manufacturing
Breaker logic plant. Select a “breaker logic” for the test run where the generator assumes the
FAQ
entire plant load and then separates from the utility. The test mode must be
initiated via a discrete input.
Exercise
2. A second “breaker logic” mode is desired where the generator assumes the
entire plant load but still remains paralleled with the utility.
Load
32
Proprietary Information
Solution
Introduction 1) Test mode with the generator running isolated from mains
Synchronization
FAQ
Exercise
33
Proprietary Information
Solution
Introduction 1) Test mode with the generator running isolated from mains
Synchronization
Select transition mode “Interchange” to open the breaker at zero power
Breaker logic
FAQ
Exercise
Mains CT required!
34
Proprietary Information
Solution
Introduction 1) Test mode with the generator running isolated from mains
Synchronization
Use discrete input 10 also as start command via “Start in Auto”
Breaker logic
FAQ
Exercise
35
Proprietary Information
Solution
Introduction 2) Test mode with the generator running parallel to mains
Synchronization
Select “Parallel” transition mode and configure the “Load set point” to Import 0 kW
Breaker logic
FAQ
Exercise
36
Proprietary Information
Solution
Introduction 2) Test mode with the generator running parallel to mains
Synchronization
Use discrete input 10 also as start command via “Start in Auto”
Breaker logic
FAQ
Exercise
37
Proprietary Information
End of this presentation
Other sections are :
1 Overview 6 LogicsManager
2 Hardware and I/O 7 Analog Manager
3 Operational Modes 8 Controller
4 Configuration and ToolKit 9 Synchronization and breaker
5 Communication 10 Application
11 Sequencing
38
Proprietary Information