Beruflich Dokumente
Kultur Dokumente
A) We are using crystalline Solar panels of higher efficiency . Single module will
generate low DC voltage. For higher system voltage, these modules are connected
in series to achieve lower current flows and reduced cable losses.
B) Here we are using structure stable for 25 years and galvanization of 85 micron.
D) These junction boxes are of IP65 / or IP54 depending upon location and
environment. The above compliances will help in achiveing fullfillment of
requirements like Dustfree, Vermin free and Weather proof.
E) We are using high quality poly carbonate AJB whose operating voltage is 1000V
& degree of protection is IP65 .
F) We are using 2 no. of 500 kW inverter for 1 MW solar plant . We are providing
proper protection to inverter including earth protection.
S
G) From the AC voltage side of the inverter the cables are fed into the Control panel
with protection switches and then connected to 1000 KVA Step Up transformer.
Here 350V AC side will be step upto 11KV using 1000 kVA transformer and then
connect to Grid .
H) Necessary Switch board or panel housing bus bars, MCBs, switches, fuses,
isolator circuit breaker etc are provided according to the detailed electrical
engineering . Metering device are provided at the end of the circuitory or at the plant
boundary limit for energy generation values and to understand the system generated
units that are fed into Grid .
J) In this project we are using TUV approved dc cable. These cables are UV
protected. Life of these cable are very good. For dc cable TUV approval is necessary.
Cable are flame resistant, Oil resistant, Ozone resistant and UV resistant and are
halogen free and to comply with DIN standards.
K) Sizing of cables are estimated on the design parameters like voltage, current,
losses, etc . Proper mechanical protection are also provided using conduit pipe.
S
DETAIL WORK ON AC SIDE:-
A) In this project we are using 1 nos. of 1000 KVA transformer. All protection
equipments as specified by the utility are provided for the transformers.
B) Transformers are with IP55 level of protection. The ratings of the transformer
have been designed based on the load from the solar farm and the grid ratings.
C) The meter we are using for energy measurement are CERC approved . These are
microprocessor based inverter . The meters are 3-Phase 4 wire 0.2s accuracy class
Static Electronic Tri-vector energy meters with ABT compatibility .
D) The meters are conform (for testing, performance and accuracy) in all respects
the relevant Indian/International standards with latest amendments thereof.
S
BOM FOR 1MW PLANT
S
b. Foundations for Module Structure
c. Inverter Room
d. Cable Trenches
e. Flooring
f. Foundations for Transformers
13 a. Accessories As Required
b. ACDB
c. Auxiliary Transformer
d. Inter Cablings
e. Conduits
f. Pipes
g. Chamber Boxes
h. Ducting in Inverter Room
i. 5 Solar Street Lights at the Station
j. Lighting Fixtures in Rooms
k. Ferules
l. MC4 Connectors
14 a. Installation Works As Required
b. Fitting of Module Mounting
c. Ramming Structures into Ground
d. Grouting in Cement of Structure
e. SS Nuts Bolts Supply
f. Erection of Structures
g. Modules Fitting
h. Modules Interconnection
i. DC Cabling from Module Strings
to Combiner Boxes
S
j. DC Cabling from Combiner
Boxes to Inverter
k. AC Cabling from Inverter to
Transformers and Breakers
l. All Associated Cabling
m. Mounting of Meters and CT-PT
Set
n. Transformer Installation
o. Inverter Installation
p. Testing of Equipments
S
COMMERCIAL PROPOSAL
Lump Sum Cost for EPC of 1 MW is Six Crores and Twelve Lakhs Rupees.
S
TERMS & CONDITIONS
1. Technical Data and scope of work: EPC contract for 1 MW Solar Project at Solar Park of Spar
Geo Infra Pvt. Ltd. includes following major Key features: Availability of clear title land with
proper earthwork suitable to install Solar Project. All project related documentation work.
EPC (Designing, Procurement & Construction) activity.
2. Completion Time: As per our expertise team we commit completion time of 8 months in all
favorable conditions from the date of award of contract.
3. Validity: This quotation is valid for a period of 15 days from the date mentioned.
4. Project Cost
5. Price: Our price is exclusive of all type of taxes other than TDS on income tax, others will be
borne extra such as Service Tax, WCT etc (If applicable). The above price is subjected to changes
if any item or terms and condition are changed from this Quotation.
S
6. Payment Schedule:
7. Force Majeure If at any stage during the period of the contracts, the performance of any
obligations under the contract is prevented or delayed wholly or partly be reasons of war, hostility,
fire, floods, lightning, epidemics, sabotages, quarantine restrictions or other acts of God,
Government or Law (herein after referred to as eventuates) then a notice of the happening of any
such eventuality will be given within 7 days from the date of occurrence of any such eventuality,
in such case neither party Shalt, by reasons of such eventuality, be entitled to terminate this
contract, nor shall any claim be made for damages against the order in respect of such
nonperformance or delay and the performance arid deliveries of the contract will be resumed as
soon as practicable after such eventuality has come to an end or ceased to exist.
8. Jurisdiction The courts in Chennai shall have the jurisdiction for any matter concerning this
contract.
Thanking You,