6B Users Conference
California, USA
June 2019
Michael A. Cocca
New Technology Discussion
GE Power
All relative statements are with respect to GE technology unless otherwise noted.
35
© 2019 General Electric Company. Confidential information. All rights reserved.
www.slido.com
Agenda – New Technology #6BUC2019
36
© 2019 General Electric Company. Confidential information. All rights reserved.
6B Fleet: 40+ years of Rugged Reliability
Improve performances by: 6B Fleet Evolution
• Improving cooling flows
• Changing materials on hot gas path
• Increasing firing temperature
Increase maintenance
intervals with:
• Extendors*, new architecture, new
materials
Combustion upgrades to:
• Adapt to new fuels
• Reduce NOx/CO emissions
• Reduce water usage
Rotor life solutions:
• Hours base rotor life extension
• Flange-to-flange replacement
Control upgrades:
• Gain operating flexibility
• Manage controller obsolescence
New Technology
for Hot Gas Path
~75% reduction in planned maintenance outages and lower capital spare investment
40
© 2019 General Electric Company. Confidential information. All rights reserved.
www.slido.com
Stage 1 Architecture Changes #6BUC2019
• Stage 1 nozzle
− Reduced leakage with laminate seals
− Seal geometry re-configuration
− Newly engineered cooling passages for extended life
• Stage 1 bucket Stage 1
− Improved cooling hole technology nozzle
− Enhanced dovetail sealing
− Slot seal & pin modifications
Stage 1
− Squealer tip optimization bucket
− Wheelspace purge flow swirler
• Stage 1 shroud
− Laminate sealing Stage 1
− Extra thick GE proprietary Gen3+ coating shroud
− Seal slot modification
− Seal geometry redesign
• Stage 2 nozzle
– Laminate Seals
– Sealing Geometry modification
Stage 2
• Stage 2 bucket nozzle
– Enhanced Dovetail sealing
– Sealing pin modification
• Stage 2 shroud
– Newly Engineered geometry for
performance Stage 2
– Seal slot modification bucket
– Laminate seals
– Aluminized coating
Stage 2
shroud
• Stage 3 nozzle
– Maintain Advanced Aero pedigree
– Seals geometry modification Advanced Aero stage 3
nozzle - dovetail sealing
– Laminate seals
• Stage 3 bucket
– Maintain Advanced Aero pedigree
– Sealing pin modification
• Stage 3 shroud Advanced Aero
– Newly engineered geometry stage 3 bucket
– Seal slot modifications
– Laminate seals
– Aluminized coating
Stage 3 shroud
Situation:
Customer has an original 6541B coming up on HGP inspection and needs new
replacement-in-kind parts. Unit has Mk VI controls with DLN1 Advanced Extendor,
operating 8000 baseloaded hours per year on Natural Gas.
Economic assumptions:
• current price for power is $50/MWhr
• Fuel cost is $5/mmbtu for fuel
• Sells steam at $5/m-lb with no steam production hardware limitations
Oct ‘18 ✓ Reached ~2500 fired hours. Enhanced Borescope completed; no findings.
Dec ‘18 2nd unit install. Restart early January. Met output & heat rate estimates.
3rd unit install, finish March ’19. Met output & heat rate estimates.
Mar ‘19
1st unit has reached 8000 fired hours
Apr ‘19 4th unit install. North America region
AGP configured for performance, maximum intervals…. Exhaust energy +2% to +7%
45
© 2019 General Electric Company. Confidential information. All rights reserved.
6B AGP Fleet Leader: 8000 FFH Borescope
S1 Nozzle S1 Bucket
Operating Hours to date
>8000 FFH Fleet leader
~ 11,000 FFH Total Fleet
Performance to date
Met or exceeded all
performance metrics
5 AGP sets delivered
New Unit will be standard
with AGP in 2020
4x6B AGP in operation by
April 2019
3x in Middle East
1x in North America
www.slido.com
#6BUC2019
46
© 2019 General Electric Company. Confidential information. All rights reserved.
New Technology
for Compressors
49
© 2019 General Electric Company. Confidential information. All rights reserved.
www.slido.com
6B Compressor Superfinish #6BUC2019
Benefits
- Output & Heat Rate Improvement
- Better compressor Efficiency
- Lower degradation
- Low dust accumulation
- Consider for application during RLE,
rotor repairs, major inspections
without affecting outage duration
* 6B.03 Baseline: AGP, 86° IGV, ISO conditions , DLN, Natural Gas
50
© 2019 General Electric Company. Confidential information. All rights reserved.
Compressor blades and vanes with GECC-1
Compressor coated with Background
GECC-1 • GECC-1, a slurry coating with ceramic top layer,
provides improved erosion and corrosion resistance,
with minimal impact to compressor performance
• Moisture may be present in the compressor during
operation up to stage 5, where it usually becomes
warm enough to prevent condensation
Test Site
• Extremely corrosive environment, with previous
associated airfoil events
• No inlet air treatment used on site
• Hydrophobic HEPA inlet filtration system
• Minimal to no wet operations
Findings
GECC-1 coating • Unit operated for >25,000 hours
applied to a 6B
• No visible corrosion pitting was seen
Blade
• Minor coating erosion noted on forward
compressor airfoil leading edges
• Significant corrosion resistance improvement over
uncoated parts 51
© 2019 General Electric Company. Confidential information. All rights reserved.
Stainless steel rings for Stator Vane 1 -4
www.slido.com
ATQi now, available now #6BUC2019
• GE has introduced new SS stator vane ring segments for the Stage 1 stator
• Ring material changed from carbon steel to stainless steel
• SS rings have better resistance to corrosion and oxidation between the vane/ring
and the ring/casing interface
• Increased the number of ring segments from 6 to 12 → Easier to remove during
maintenance
• Direct replacement to the existing ring segments
• Shimless configuration
52
© 2019 General Electric Company. Confidential information. All rights reserved.
9E/6B Blade Health Monitoring (BHM)
Solution
Data Acquisition System
• Non-contacting blade monitoring system (DAQ) - Site
• Sensors installed over airfoils A/D converter
Amplitude, Volts
blades measured
R R R
1 2 3
Benefits Expected
Measured Blade
Passing Signal
• Protects the Gas Turbine
against costly Time, Milliseconds
R2 probe
R1 probe
aligned with
aligned with
leading edge
leading edge R3 probe aligned with
leading edge
Probe locations
Drilling of probe
locations at site
www.slido.com
#6BUC2019
54
© 2019 General Electric Company. Confidential information. All rights reserved.
Hybrid units &
Capacity Ideas
56
© 2019 General Electric Company. Confidential information. All rights reserved.
Applications of GE’s Enhanced Gas Turbine
Technical Flexibility Improvements
58
© 2019 General Electric Company. Confidential information. All rights reserved.
Capacity play: Unlocking Inherent Value of a
site Start
Calendar Hours
Based? Maintenanc Based?
e Intervals?
61B – Potential solutions
No Known
Sunset Date? Scope Description Value
Why?
Yes • Increase Max Increase
Legal/ #1
output - Peak Tfire Capacity
Able to BOP
Yes Excess Custom
• Find other value
reposition
Spares? streams – Hybrid? New
unit? YES #2
Increase Peak Revenue
Tfire
NO NO
• Maintenance Reduce
#3
Scope Scope Scope Scope Scope Scope Optimization O&M
#2 #1 #3 #1 #4 #3 • Extendor Reduce
#4
• Life Odometer O&M
59