Sie sind auf Seite 1von 10

,s[32J

Otlffical Engineering Sdmce Vol. 38, No.5, pp. 74~-763, 1983


J'rinted in Greal Britain.
CD 0009 2509/83/050745-19$03.00/0
Pergamon Press Ltd.

mgly
,tCO
Hp.
;cked THE PINCH DESIGN METHOD FOR HEAT EXCHANGER
NETWORKS
B. L1NNHOFP
Department of Chemical Engineering, University of Manchester Institute of Science and Technology
(UMIST), P.O. Box 88, Manchester M60 IQD, England

and

E. HINDMARSH
ICI New Science Group, P.O. Box II, The Heath, Runcorn, England

(Received 19 August 1981; accepted II October 1982)

Abstract·-A novel method is presented for the design of heat exchanger networks. The method is the first
to combine sufficient simplicity to be used by hand with near certainty to identify "best" designs, even
for large problems. "Best" designs feature the highest degree of energy recovery possible with a given
number of capital items. Moreover, they feature network pallerns required for good controllability, plant
layout, intrinsic safety, etc.

SCOPE and Flower[5}. Both procedures identify the best pos­


Heat exchanger network (HEN) design is a key aspect sible degree of process heat recovery as a function of
of chemical process design. Typically, 20-30% energy the minimum temperature dilTerence in exchangers,
savings, coupled with capital savings, can be realised heaters, and coolers, dTmin . The procedure by
in state-of-the-art f10wsheets by improved HEN LinnholT and Flower offers more information about
design[12]. The task involves the placement of process the availability of heat at different temperature levels.
and utility heat exchangers to heat and cool process Capital costs can be considered through targets for
streams from specified supply to specified target tem­ minimum overall surface area and minimum number
peratures. The objective is to minimise total costs, i.e. of units. However, as far as surface area is concerned
t.
.~i"
capital and operating costs expressed as annual it is easily established that widely differing solutions
charges. Development of systematic procedures to for the same problem generally feature similar overall
.meet this objective has been an active area of interest surface areas as long as their degree of energy recovery
Po! in the chemical engineering literature for more than is similar. What is important in the early stage of
ten years. A review was recently given by Nishida et network design is the target for the minimum number
'~ uf. [15]. of units. Units in excess of the minimum number
As stated in this review, the approach to the prob­ require more foundations., pipework, instrumen­
lem has been radically altered by two major discov­ tation, maintenance, etc. and lead to greatly increased
eries: network performance targets and the network capital cost[IO].
temperature pinch. Hohmann[2] observed that the minimum number
The network temperature pinch represents a bottle­ of units was generally a function of the number of
neck to feasible heat recovery in HEN design. Its process streams and utilities, expressed in the simple
location was first described by Linnhoff et al. [5, 6} and relationship
Umeda et al. [7, 8] although its full significance for the
design task was not recognised in either source. The Um,n = N-I (I)
present paper shows that by fully exploiting the prop­
erties of the pinch the task of optimal HEN design is where Urn," = the minimum number of units; N = the
greatly simplified. number of process streams and utilities.
Network performance targets exist for the min­ Later, LinnholT et al. [6] explained this equation as a
imum utility usage, the minimum overall surface area, special case of Euler's general network theorem[16].
and the minimum number of "units" (i.e. process and They also showed that the general form of Euler's
utility exchangers). Calculation of these targets is sim­ theorem relates the actual number of units in a net­
ple and is possible independent of design. Thus, tar­ work, as opposed to the minimum number, to the
gets can be used, first to stimulate the designer towards number of separate components into which the net­
beller designs, and second to give the designer work can be split and to the number of "loops" (or
confidence that his solution is near-optimal. feedback cycles). The theory was then extended fur­
Procedures to target for minimum utility require­ ther by Linnhoff[14] and, independently, by
ments were given by Hohmann [2] and by Linnhoff Grimes [13} demonstrating that, in problems featuring
a network pinch, minimum utility requirements and
minimum number of units are often mutually incom­
·AUlhor to whom correspondence should be addressed. patible. The present paper explains this situation and

745
746 B. LINNHOFF and E. HINDMARSH The pinch design method for heat exchanger networks 747
introduces a procedure for the controlled reduction of THE PINCH Note that to ensure the feasibility. of complete heat network (column 5). (Note in [5J "heat flows" were
the number of units starting from a minimum utility. In this section the phenomenon of the pinch itself' referred to as "heat fluxes". The term flow replaces
exchange hot and cold streams are separated by. tiTm,,·
design. discussed. The discussion is in five parts. First, a bri flux in this paper so as to avoid possible confusion
Forexample. the upper boundary. ofSN3 is defined by.
In general then, minimum cost networks feature the review is given of how the pinch is located. Second, the cold stream No.4 at 100°C while the hot stream at this with the term heat flux as used in the context of heat
correct degree of energy. recovery and the correct num­ phy.sical significance of the pinch and its implicationii transfer equipment)
point is at .'lO'c. .
ber of units. This is achieved in two stages with the on utility. usage are described. Third. a powerful reprc-. The feaSIbility. of complete heat exchange between The results of the problem table analy.sis in Table
design method presented in Ihis paper. First, the sentation for both the pinch and HEN stream data . all hot and cold streams is an important feature of the 2 are shown diagrammatically. in Fig. I (a). Each
method aims for a minimum energy solution. corre~ explained. This representation will be used extensive; problem table algorithm. It means that for each sub­ subnetwork is shown with all heat flows as calculated
sponding to a specified tiTm " , with no more units than in the paper. Fourth, the factors affecting the occu~ network there will either be a net heat deficit or surplus by. the problem table algorithm. Notice that the heat
is compatible with minimum energy.. This task is rence of pinches in induslrial HEN problems are hig; but never both. These deficit or surplus figures are flow from SN3 to SN4 is zero. All other flows are
achieved through a thorough understanding of the lighted and a reason is given why. the majority. shown in column I of Table 2. The sign convention is positive. The point of zero heat flow represents the
pinch phenomenon, hence the method is called the industrial HEN problems have pinches. Finally., t: such that a surplus is negative and a deficit positive. pinch.
pinch design method. We also show in this paper how implications of pinches on capital costs are consid. Another important feature of the problem table In Fig. l(b), the pinch is shown partitioning the
the pinch design method can be used to quickly. iden­ ered. algorithm is the feasibility. of heat transfer from problem into two regions. a hot and a cold end. The
tify. the best starting value of tiTm;,. Second, the higher to lower subnetworks (cascading). In other hot end, which comprises all streams or parts of
method involves a controlled reduction in the number Locating (he pinch (a review) words. heat surplus from higher temperature sub­ streams hotter than the pinch temperature, requires
of units. This may. require "backing-off" from min­ The task of locating the pinch and indeed the appH networks can be used to satisfy heat deficit of lower only. process exchange and utility heating. Utility.
imum utility. usage. Together, both stages represent cation of the pinch design method is illustrated by" temperature subnetworks. The calculation of the cooling is not required. The cold end. which com­
the only. design method published to date combining using an example problem for which stream data a~;, amount of heat which can be passed on in this pnses all streams or parts of streams cooler than the
an ease and speed of applicalion suitable for hand given in Table I. The example problem is called Test j,\ manner is performed in column 2 and column 3 of pinch temperature. requires only process exchange
calculation with near-certainty. of finding "best" solu­ Case No. 3 (TC3) following the convention of4 Table 2. It is initially. assumed that the heat input and utility. cooling. Utility. heating is not required.
tions. Previously. published methods were either fast LinnholT and Flower[5] who introduced Test Casc~' from external utilities is zero, This is represented in There is no heat transfer across the pinch. Also. both
but prone to failure[3, 4, 13J or dependable but cum­
bersome to use[5, 6J.
No. I and Test Case No.2. Note that the data for aU £ Table 2 by. a zero input for SN I (column 2). Having utility requirements are the minimum achievable.

As an added bonus, the pinch design method


Test Cases is based on constant CPo This feature is)' made this assumption, it is an easy. task to calculate
often referred to as a shortcoming of all early. work in .• the output from SN I by. simply. adding the surplus to Significana oj tile pinch
identifies situations where stream splitting is inevita. this area. However, every practical process. with and. ; the input. This then forms the input to SN2. The We are now in a position to discuss the causes and
ble for a minimum utility. design. A clear rationale is without phase changes, can easily be described in, procedure is repeated for all subnetworks. effects of using more than the minimum utility usage.
given c1arify.ing whether stream splitting can be terms of linearised. (i.e. CP = constant) temperature iii To be feasible, the flow of heat from high tem­ We shall use TC3, decomposed into its hot and cold
avoided or not. This represents a breakthrough in enthalpy. datafI7]. 11 perature subnetworks to low temperature sub­ ends as an example (see Fig. 2). Note that in Fig. 2
understanding. To date, many. published design The pinch locatIOn for a HEN problem, together j networks must not be negative. Thus if negative the hot end is referred to as a heat "sink" as only
methods have made use of stream splitting but none with the minimum utj!jty requirement. can be calcu.l: values are generated in columns 2 and 3 of Table 2 utility. heating is required. The cold end is referred to
could guarantee that, for the problem in question, lated using the problem table algorithm of Linnholf the heat input to SN I must be increased. The min­ as a heat "source" as only utility cooling is required.
there would not be another solution without stream and Flower[5] for a specified value of tiTm " . The imum increase is that which .uarantees that all heat First consider the effects of transferring heat across
splits. In other words, one could not be sure whether results of the procedure, when applied to TC3 with flows are positive Or zero-s"; columns 4 and 5. The the pinch (see Fig. 2(a)). Any. heat transferred must,
streams were split because of Ihe complexity. of the tiTm " of 20' C, are shown in Table 2. minimum hot utility usage is then given by. the input by enthalpy. balance around the Sink, be supplied
problem or because of the inadrquacy. of the method. In the table the stream data are shown on the left. to SNI (column 41. The minimum cold utility. usage from hot utility in addition to the minimum require­
This was an undesirable state of affairs as stream divided into six temperJture intervals. corresponding is given by the heat Aow out of the coldest sub­ ment. Similarly. enthalpy balance around the source
splits involve complications in pipework and conlrol to "subnetworks" and therefore called SNI-SN6.
and should only. be implemented if they. are necessary.. These intervals are defined by. process stream supply
Just as the pinch design method itself, the stream and target temperatures. For example. SN3 is defined
splitting rationale follows from a beller under­ by. the target temperature of stream No.4 and the Table 2. The problem table for Test Case No.
standing of the implications of the HEN pinch. supply. temperature of stream No.2.
;nu:A."IS Axn
DE~ICIT I ACCL~1't'l.ATED HEAT FtOIolS
SUB~En;rORK I COLD T (oC) HOT
STRfA."IS : STRfA"IS
(1) (2)
INPUT I OUTPt1T I I~PUT 10I:TPUT
(JJ (4) :

Table I. Stream data for lest case No,


150'

STRU1I
!'Il1!'!BlR.
ANtl
HEAT CAPACITY
!'LOVRATE TS TT
ss,
. 125 145
- 10 0 10 107,5 I 117.5
CP
TYn

(I) HOT
(Kv 1°c)

2
(oC)

tSO
(oC)

6O
SN2
T '.
. \00 lN,
+1:!.5 to -z'5 117,5 I lOS

(2) "OT 8 '0 6O


S~3
I T 7O ,0. + Ins -2.5 -to7.5 lOS

0)

('>
COLD

COLD
2. S

3.0
20

2S
125

100
SN4 I I I
40 6n; 1 ­ 135 -107.5 27,5 0 lJS

SNS
I II "
+82.5 27.5 -55 lJS 52,5

.e.T!,U1'f • 20°C
S~6
II 20
: +12.5 -55 -67.5 52,5 40

.
";'
748 B. LINNHOfF and E. HINDMARSH The pinch design method for heat exchanger networh 749

shows that heat transfer across the pinch also in­ analogous effect (see Fig. 2(c)). Thus for minimulll cold" cold stream (see Fig. 4(a)). The design for this
creases the cold utility above the minimum required. utiJity usage utility cooHng is not pennitted above the,; .£.!.. "network" consists of a single exchanger and a utility
In other words, heat transfer across the pinch incurs pinch and utility heating is not permitted below. , . II .0. .0' heater. The single exchanger completely satisfies the

~x~
2·0
the double penalty of increased hot and cold utility The above relationships between the pinch and' smaller of the two stream heat loads. The utility
requirement for the HEN design task [6]. utility usage are fundamental observations of which heater is required only to achieve the enthalpy bal­
.·0
Using an equivalent argument, the effect of utility the HEN designer ought to be aware if he is to ance for the total problem.
It is apparent from Fig. 4(a) that the hot utility
cooling above and utility heating below the pinch can produce optimal solutions to HEN problems. With_
~
70'
llJ- 2· 5
be assessed (see Figs. 2(b) and 2(c). Aremovalof heat out such knowledge. design for best energy per.' heat load remains constant, unaffected by any
I specification of Ii Tm ,,, providing the specified 6 Tm,. is
y from the sink increases both utililies by Y (see Fig. formance is very much a case of shooting in the dark. £,0· 70· I ~ 3·0
2(b)). A supply of heat Z to the source has the In complex networks. exchangers and utility heaterse NOT Ill0T
less than the smallest temperature driving force in the
' ...... lal,.1. I 0111",,'1,,1
and coolers will almost inevitably be placed in posi. i exchanger, which is 75'C in the example. (It is

OH WIN • /07-5
tions which violate the pinch. The result will be more I Fig. 3. Pinch di\'ision of TC3 shown in the grid.
assumed, for the purposes of this example. that the
hot utility supply temperature is such that the small·
ullhly healing and coohng than otherwIse would have',
est 6 T will always occur in the exchangeI'.) However,

dtJ
t 117·5 0"1roI ... • 107 · 5
been required. In retrofit studies the equivalent argu.l
ments apply. The pinch highlights existing utility ori
process exchangers which are "at fault", i.e. violate '
the pinch and prevent a minimum utility design. I.
indicate the relative magnitude of the stream CPs.
This added detail is not required in the present papeL
when the specified 6. T mID exceeds 6. Tthruh' as in Fig.
4(b), the need for both utility heating and cooling is
introduced. This is because complete heat exchange
{}
As in [5] heaters are represented ID the modified grid between the two streams is no longer feasible without
I SN 2
I violating 6 Tm". Notice also that a pinch has been

rill
The pinch in the grid representation .', by circles on the cold streams and coolers by circles
_0'
on the hot streams (see Fig. 4). As indicated in Fig. introduced into the problem.
'0'
It is desirable when developing a design, whether "i
t l05
new or retrofit. to do so on a representation which; 3, heat exchange from the cold end of the problem to A borderline situation occurs when the specified

I 6oT"" equals the threshold value (see Fig. 4(c)). The


c
shows the stream data and the pinch together. In the hot end is not feasible with liT... = 20 C. Ex­
j SN 3
addition. the presentation ought to be sufficiently change from the hot end to the cold end is not problem has become pinched but the utility usage is
_ _ <).0 _ _
"'~_.£!..o
- fleXIble to allow easy manipulation of matches.
The grid representation, first introduced by ~
, desirable as this would constitute heat transfer across
the pinch incurring the energy penalties shown in Fig.
the same as for lower values of 6 Tm ... This borderline
case is a general feature of a threshold problem.

~ ,."
I SN4
I Linnhoff and Flower[5], can be modified to achieve
these objectives. To illustrate this, Te) has been
2(a). Thus, Fig. ) proVides a "grid" for two com­
pletely separate design tasks, the hot end and the cold
Figure 5 shows the threshold behaviour in terms of
a plot of utility requirements vs 6 T"m for the HEN
flH .. (ND
drawn in the modified grid (see Fig. 3). Hot streams end. problem "7SP2". This problem was first introduced
by Masso and Rudd[l]. In Fig. 5{a), the specified
I sN •
I are grouped together at the top and run left to right '
from 'heir supply to targel temperatures. Cold Threshold proh!ems ~Trnln' at 20 C, is less than 6.Tthresh As a result there
o

is no pinch and only utility cooling is req U1red. When


~!2 . J streams beneath run countercurrent. In contrast to ; A pinch does not occur in all HEN problems.
OC W11iI - 40 [5J, the pinch division is represented in the diagram ~ Certain problems remain free of a pinch until the m.
6 T equals 6 T'h~h a pinch is introduced into the

9 Oe
w'o
_ 40
by dividing the stream data at the appropriate tern· ~
peratures, remembering to separate hot and cold,
streams by Armin'
Process exchangers are represented by vertical lines
.",
minimum allowed driving force, liT.,,, is increased
up to or beyond a threshold value Ii T'h~h' It is for
this reason that we call these problems "threshold
problems".
problem (see Fig. 5(b)). As for the simple two stream
problem discussed above, there is no increase In
utility usage. The utility usage only increases when
the minimum allowed driving force is increased above
10' Ibl and circles on the streams matched (see Fig. 4). This The concept of a threshold problem can be envis· 6 T""'h (see Fig. 5(c)). Both hot and cold utilities are
Fig. 1 (a) Subnetwork heat flow diagram ror TeJ. <bJ contrasts with the circle'triangle representation of[5] aged as a "very hot" hot stream matched to a "very then required and the problem is pinched.
Subnetwork.s combined into a hot and cold region. in which the orientation of triangles was used to :­
~
~ ~

1107·5 .. X) 1107·5 l' yl 107'5

~
G B'
...
0
-u x
-0::==1' =:I :1:1:::1=: -
.l} =
o
"'" == =
0
= - -
'0

6T ... 1111 ·200


101
.0

6T"'IN • IOO~

Ibl

"

~'
9 E;J
~
I

20 '0
(40 + xl 40 (40" II
0
(0 ) (b) (e) 6Tn~lIIUH _ 75
Ie I
Fig.:. (a) Effect of heat transfer across the pinch. (b) Effecl ofurility cooling above the pinch. (c) Effect
of utility heating below the pinch. Fig. 4. (a) A threshold problem. (b) A pinched problem. (c) The thre,hold l1Tmm ·
750
B. LINNHOFF and E. HINDMARSH The pinch design method for heat exchanger networks 751
utiLiTY
US. ... GE work in HEN' design generated much impact in. Capilal cosl implicalions of Ihe pinch o.
industrial practice. Linnhoff[I4] and Grimes[13] independently con­ ~"I"
~'lIIIIeN
cluded that the minimum number of units and the
The ulililY pinch minimum utility usage are often mutually incompat­
~
90· 60­
COLO In applying the problem table procedure to TC3 it ible in some HEN problems. This incompatibility was ~
was assumed that the utilities were available at shown by both authors to be the result of the pinch ~
~ ~
HOT
extreme temperatures, i.e. the hot utility was hot
enough and the cold utility cold enough for all
division of the problem. They showed that the "min­
imum number of units" targeting equation 'J'
100· 70·
, I '"
I~~
process requirements. In practice, this is rarely de­ "\J oc"'...
'0' so· 70· .6.T.,UN sirable as less extreme utilities tend to cost less, e.g. Um,,= N-l (I) ,,..
/

U WIN

Tr · .. H) ~ low pressure steam for process heating costs less


wU • UW'N H OT IlNO + U"'"COLD un'
lloT
than high pressure steam, cooling water costs less where Um ," = the minimum number of units; N = the

~ '-'7
so~o 2.376
--,,
II
~
I
--'I

than refrigeration, etc. There is often a good cost


incentive for reducing extreme temperature utility
number of process streams and utilities, must be
applied to the hot end and the cold end separately. IOH.UN +K I
lei

.. 'I..:..........!.· I' 577


- II
I 220-11220·

--li~
loads by the introduction of intermediate tem­ Figure 7(a) shows the results when the taTgeting ~
perature utilities. The reasoning in "significance of equation is applied in this manner to TC3. A target
SJ:J~·
,. 320 ~ --.2!£'II'~ the pinch", tells us that any new hot utility must be minimum of seven units is required to complete a
I' II

supplied above the pinch and any new cold utility minimum utility design, three units for the hot end,
__ IiII

"00· 200·
-- 1600 --III' must be supplied belOW the pinch. Failure to do so four units for the cold end. Note that by accepting the
~II
.'0· 100·
-- 1600 150.11',1'°. would incur the double penalty or increased utility pinch division, stream Nos. I, 3 and 4 are counted
---­
"OO~O·"·128 --'I II
healing and cooling. twice by the targeting equation. They exist in both the
",~o·2·62"
I --II In Fig. 6(a), a new hot utility supply has been hot and cold ends.
--II ,,0,1,
I
Ii
--Ii

Ii

introduced to the hot end of a hypothetical problem. Figure 7(b) shows the result when the targeting
equation is applied singularly to the whole problem.
~
As the heat load on this new utility increases, savings IOc + X)
~I~CH "'NCH wlti,
are made on the hottest utility supply (see Fig. 6(b)). Streams Nos. I, 3 and 4 are no longer counted twice U _ 5
W110I
0) b) c) There comes a point when the hottest utility load is and the larget for the minimum number of units to
reduced to such an extent that it just satisfies the complete the design is now five. To achieve a five unit Ibl
Fig. 5. (a> Data for 7SP2. (bl The thre.hold lJ.T~" for 7SP2. heating requirements in the hottest region of the design in practice means that either:
(c) ~TI'nIIl>~TIh.1ftIl for 7SP2. Fig. 7. (a)The number of unils for ma"imum energy recov­
problem (see Fig. 6(c)). The result is a division of the ery. (b) The overall minimum number of units.
• heat" X" must be transferred across the pinch,
hot end of the HEN design task into two separate
incurring the double penalty of increased hot and
regions, i.e. a new pinch has been created. As it is a
It is interesting to note that most of the early cold utility usage, see Fig. 7(b) or
direct consequence of the introduction of the new The philosophy
example problems in the literature on HEN design • the 6Tm,. constraint initially imposed can be
utility, we call it a utility pinch. The problem table
(i.e. 4SP2, SSP!. 6SP!. 7SPI, 7SP2, IOSPI, etc.) were relaxed in certain exchangers subject to 6.Tnll• > O. The pinch represents the most constrained region of
algorithm is easily adapted to calcUlate the maximum a design; afterall,6T,." exists between all hot and cold
threshold problems while at the same time the basic
loads on intermediate temperature utilities and the In the first case there is a cost trade-off between the
distinction between pinched and threshold problems streams at the pinch. As a result the number of feasible
resulting utility pinch locations [i 4]. number of capital items and the utility usage. In the
was not understood [6]. The full importance of this matches in this region is severely restricted. Quite
With this understanding it is hardly surprising to second case there is a cost trade-off between the
comment will become clear when considering that oflen there is a crucial or "essential" match. If this
find that, in industrial HEN design, the Occurrence of number of units and surface area. The exploration of
most industrial problems are pinched problems (see match is not made, this will result in heat transfer
an unpinched or threshold problem is extremely rare! these trade-offs is discussed in the section "sim­
below). This then explains why none of the early across the pinch and thus in increased hot and cold
The pinched problem is the norm. plifying the minimum utility design".
utility usage. The pinch design method, therefore
* recognises the pinch division
THE PINCH DESIGN METHOD
IOH~ ..... -V' • starts the design at the pinch developing it sepa­
The above discussion has dealt with the relationship
rately into two remaining problems.

a
between the utility usage, the number of capital items
OM ... I .. IOHloIi",X I MOTTU,.
AIGIO ... and the occurrence and location of the HEN pinch. This approach is completely different from the normal

cY 6
n

__ ~~ _ _ UTILITY With this understanding, a totally new design method intuitive approach of starting the design at the hot side
HOT
is now developed which yields, quickly, "best" solu­ and developing it towards the cold. When a design is
""eH
tIOns to HEN problems. The initial aim is to produce started at the hot side, initial design decisions may
designs using the minimum utility usage with as few later necessitate follow-up decisions which violate the
no """TV __ n~ -<7 •• 0e<5.
---~---- 't> n~ __ "'HeM capital items, i.e. units, as is compatible. pinch. On the other hand. when a design is started at

y y y
The design method is based on a fundamentally new the pinch, initial design decisions are made in the most
approach. This is discussed first under "the philos­ constrained part of the problem and are less likely to
ophy". The discussion is followed by details of the lead lo difficulties later.
actual procedure, namely, the development of "fea­ Thus, commencing a design at the pinch has the
sibility criteria" which quantify the restrictions placed distinct advantage of allowing the designer to identify
°C W1N
°CW'III °C W' N
on design by the pinch, the use of a "tick-off heuristic" essential matches or topology options in the most
to ensure the design is steered. towards the fewest constrained region of the design which are in keeping
1.1 (bl Ie I possible units and the solution of the "remaining with minimum utility usage. There is a further advan­
Fig. 6. (a) The correct placement ora new hot utility. (b) Distributing the minimum heating requirement. problem" allowing consideration of process con­ tage, namely the designer will always have the option
(c) The utility pinch. straints and other requirements. to violate the pinch if required with full knowledge of
752 B. LINNHOFF and E. HINOMARSH The pinch design method for heat e,;:changer networks 753
,
the final penalties to be incurred. When a match is The converse arguments apply below the pinch. To , The CP inequality for individual matches, The sec­
placed knowingly in violation of the pinch the
heat flow across the pinch can be quickly established.
• avoid utility heating each cold stream must be lond feasibility criterion is concerned with tem­

=tJ
'2" : brought to the pinch temperature by process ex­ :perature feasibility. As shown in Fig. II, temperature
This heat flow is equivalent to the final increase in hot
and cold utility (Fig. 2(a».
:t!j
'''T~'
,
I .:
q
change, see Fig. 10. As a result, a pinch match is 'driving fora: in a pinch match cannot decrease away

~
I • required for each cold stream at the pinch and this is om the pinCh. For this condition to be fulfilled the
Once away from the pinch the design task is no possible only if inequality (2b) holds ollowing CP inequalities must apply in every pinch
longer so constrained hence the number of topology • .--: \
I
.L~
'-.'
"
n
'

II
atch
options usually increases. This increase in the num ber NH;.NC. (2b)
of options can be used to advantage by the designer. 1.1 Ibl
" Hot end pinch match
After all, the design objective is not just the Once again stream splitting may be necessary to
PINCH
identification of a cost optimal topology but also one ensure that the inequality is fulfilled. CPH ",CPc. (3a)
which is safe and controllable. By discriminating be­
tween match options the designer can steer his design,
-::f)
using his judgement and process knowledge, towards :I PINCH

a safe, controllable and practical network. .',


In developing the pinch design method this benefit ~: ..,: I (
has been recognised. As a result, the method does not
"tell" the designer which matches to make but rather
it informs him of his options. In the temperature lei ~
J
constrained region near the pinch essential ,matches Fig. 8. (a) A pinch match. (b) Exchanger 2 is not a pinch .~
are identified using feasibility criteria. The same crite­ match. (c) Exchanger 3 is not a pinch match. 'J.
ria will inform the designer whether there are options
available at the pinch and whether stream splitting is
above the pinch to cool stream No. I to the pinch .'
t
required. When designing away from the pinch the
temperature. In such circumstances we say the origi. .Q
need for feasibility criteria diminishes and the method
nal stream data at the pinch is not compatible with
allows the designer to choose topologies based on
process requirements. a minimum utility design. .o.T"'IN • 10° .aT"'IN • 10°

To summarise, the pinch design method incorpo­ When this incompatibility occurs the streams at the
101 Ibl
rates two fundamentally important features. First, it pinch need "correcting" by stream splitting (see Fig. Fig. 10. (a) An infeasible cold end design at the pincll. (b) Stream splitting at the pinch.
realises the pinch is the most temperature constrained 9(b». By splitting a cold stream an extra cold,
region. The design is started at the pinch and devel­ "branch" is created, allowing a pinch match with hot '}
stream No. I. {:
oped moving away, Second, it allows the designer to
choose between options. To summarise. the hot end stream population at "
the pinch is compatible with a minimum utility design PINCH

Fea..ihility criteria at the pinch only if a pinch match can be found for each hot 1\

The identification of essential matches at the pinch, stream. For this to occur inequality (2a) must apply
m II
II

~
of available design options and of the need to split
streams. is achieved by applying three feasibility NH",NC (2a) I:CPH
II
criteria to the stream data at the pinch. In developing II
these feasibility criteria reference is made to "pinch where NH is the number of hot streams or branches
II
exchangers" (sometimes called "pinch matches"). As and NC is the number of cold streams or branches. II
Fig. 8 shows these are exchangers which have the Stream splitting may be needed to ensure that the
inequality is fulfilled.
I ill CPC
minimum temperature approach, dTmin • on at least Q II Q
one side and at the pinch. II
II
The number of proce.... streams and branches. The
~INCH "IHCM
first feasibility criterion concerns the stream popu­
lation at the pinch. The population of hot and cold
T T
streams has to be such that it will allow an arrange­

~
102 CPH ~ CPIC
ment of exchangers compatible with minimum utility
usage. I I
Consider a hot end design as in Fig. 9(a) (not TC3). I I

Utility cooling above the pinch would violate the I I..l. ~ CPH ~CPC
minimum utility objective. Therefore, each hot
stream has to be cooled to the pinch temperature by
~ ~
;CPC ~r
6T'''n
1..'
mn
6T • ~
"""""'l
~
process exchange. This is attempted in 'Fig. 9(a) by ,
, I
, I:: CPC ~
placing pinch matches between hot stream No.2 and
cold stream No.4 and hot stream No.3 and cold
I I 0
stream No.5. Notice, however, that having made 6.T.. ,".IOO 6.T MIN. 10°
o Q

these matches hot stream No. I cannot be matched {oj IbI


with either cold stream without violating the dTmm (0 I lb)
Fig. 9. (a) An infeasible hot end design at the pinch. (bl
constraint! Utility cooling would now be required Stream splitting al the pinch. Fig. 11. (a) A feasible plOch e,;:changer above the pinch. (b) A feasible pinch exchanger below the pinch.
754 B. LINNHOFf and E. HINDMAJlSH The pinch design method for heat ex.changer networks 755

Cold end pinch match Immediately above the pinch to the pinch temperature, is not feasible. We can The" rick -off" heuristic
eeneralise by saying that the CP differences of all Once a pinch topology has been chosen, the design
CPH;;.CPC (3b) !'IC IfH
pinch matches must always be bounded by the overall of both hot and cold ends must be continued in such
Overall CP difference = L CPC - L CPH. (Sa) CP difference. a manner as to keep capital costs at a minimum, i.e.
I I
where CPH is the heat capacity flow rate of a hot the final designs ought to be steered towards the
stream or stream branch and CPC is the heat capacity Immediately below the pinch The CP table minimum number of units. This can be achieved by
flowrate of a cold stream or stream branch. Figures 13(a) and 13(b) show a step-by-step pro­ employing a "tick-off" heuristic to identify the heat
tvH NC loads on the pinch exchangers.
If an arrangement of matches fulfilling these in­ cedure for applying the feasibility requirements listed
equalities is not possible then it is necessary to change
Overall CP difference = L CPH - L CPC. (5b) above. By following the sequence, the designer can The heuristic results directly from the targeting
I I
one or more CPs by stream splitting. equation for the minimum number of units
• identify essential matches at the pinch.
It should be noted that inequalities (3a) and (3b) Figure 12 illustrates how we can use the concept of
• identify available match options at the pinch. (I) repeat.
only apply at the pinch. Away from the pinch, the CP difference for an early identification of Umin=N-l.
• identify the need to split streams and generate
temperature driving forces may have increased matches that are feasible themselves but are not
stream splitting options at the pinch. The equation is satisfied if every match brings one
sufficiently to allow matches in which the CP's of the compatible with a feasible overall network. In Fig.
streams matched violate the inequalities. 12(a) a case is shown where the sum of the match CP The procedure is aided by the use of another new stream to its target temperature or exhausts a utility.
The CPo difference. To understand the third fea­ differences equals the overall difference. All streams concept, the "CP table". CP tables for the hot and In this case, the match is said to "tick-off" the stream
sibility criterion at the pinch it is convenient to define at the pinch are involved in pinch exchangers. Figure cold ends of TC3 are shown in Figs. 14 and 16 or utility, i.e. the stream or utility need no longer be
the "CP difference" 12(b) shows a hot end pinch design for a different respectively. In these tables hot and cold stream CPs considered part of the remaining design task.
problem where the pinch match CP differences at the pinch are separately listed in numerical order. The pinch exchangers can usually be made to
For a hot end pinch match amount to less than the total. In this case not .all The appropnate feasibLlity criteria are noted at the lick-off streams by choosing each exchanger load to
streams at the pinch are involved in pinch matches. top of the table and the CPs representing streams equal the smaller heat load of the two streams
CP difference = CPC ­ CPH. (4a) Figure 12(c) shows a different problem again where which have to be involved in process exchange at the matched. The CP inequalities (3a) and (3b) will
the pinch match CP difference exceeds the total. The pinch are boxed for emphasis. A pinch match is guarantee the possibility of choosing pinch exchanger
For a cold end pinch match pinch match shown is feasible by itself (it fulfills represented in the lable by pairing the CPs of a hot loads by ticking-off streams as long as the stream CP
inequality (3c) but it is incompatible with the overall and a cold stream. Stream splilS are represented by remains constant with varying temperature and as
CP difference = CPH ­ CPC. (4b) CP difference. (The pinch match has a CP difference writing the separate branch flowrate CPs adjacent to long as cold and hot stream temperature overlaps do
of 6 whereas the total available is only 4.) Thus, it will the original CP (see Fig. 16(c)). As will be demon­ not require an excessive number of shells for a single
Similar equations can be written for differences in the not be possible to complete this design. A match strated below (see "worked example"). the step by pinch match.
overall sum of hot stream CPs and cold stream CPs between the remaining hot stream and the remaining step procedure from' Fig. 13 is easily followed in the The tick-off heuristic is a "heuristic" as it can
at the pinch. cold stream, which is required to cool the hot stream CP table. occasionally penalise the design by introducing the

STA(A .. OATA

!! TH( PINCH ' ) ! t


, I 1
':''::;_ '1.2;

~
nc: AeOVE

I 2
II
COWItOSITI Cit OI'flIUNCI .. -..
TOTAL 11ICHA. .III' ell OI"III'INCI • I + I. "
. /.
"
\
CPH" CPC
FaA (VEAY PINCN IroIATCH
TH E
PINCH

r 1 'IUOUIAEO Fa"
f-4j~!)")
Ii s (ACH HOT STA(A'"

YlS
la'

I
II~ F(ASlal( TOPOLOGY
10(NTI'1(0
I•
I 2 CO .. "OSITI ell 01' , [lU ""CI .'-6.' lal
n TOTAL UCHANGIA ell OI"("I"'CI • I + I. "
STA(AIroI OATA
Is ~ THE PINCH ") I
I , ' I
II I
II BELOW
Ibl THE
(PH i!= CPC
cp PINCH

---113 I A(OUIA(O fOR [ACH

~i2
COIrolPOSIT( ell OI"FER''''Cl .'-5." COLO ST_(A" I

TOTAL EICH"'''''GIP' ell DI,FERENCE z 8-2.'

---II'
Ie I
t bI
Fig. 12. (a) Two feasible pinch topologies showing that the composite CPo (b) Difference bounds the total
exchanger difference. (c) An infeasible match based. on the CP difference. Fig. 13. (a) HOl end pinch design procedure. (b) Cold end pinch design procedure.
756 B. LINNHOFF and E. HINDMARSH The pinch design method for heat exchanger network.s 757
need for increased utility usage. Temperature driving and other constraints can be used to steer the place.
force. essential elsewhere, may be used up excessively ABOVE ABOVE ABOVE
ment of other matches.
in pinch exchangers that are extended too far into the [n addition, the remaining problem analysis tech. NH ~ He (20) NH .:S He 12al NH .c; NC 12a)
remaining problem. [n such cases the designer can nique discussed above is not only restricted to check.
choose either to ing the placement of pinch matches. It can also be CPH :E CPC 13aJ CPH -l$ CPC 13al CPH ~ CPC (lal

• reduce the load on the offending pinch match used to ensure that matches placed in the remaining

D LF ~
and run the risk of needing more than the minimum problem are compatible with the minimum utility 3
number of units objective.
,
• use another pinch topology in which the tick-off
heuristic does not cause essential driving force 10 be
Design method summary
The pinch design method incorporates five im._
I 2'S 2·S 2· S

used up. portant slages. These are 1


~ HOT COLD HOT COLD HOT COLD
The problem table algorithm can be used to check • The HEN problem is divided at the pinch into'
whether a maximised pinch match load is in keeping separate problems.
(0) Ib) (e)
with minimum utility usage. Consider, for example, • The design for these separate problems is started
a hot end design. Application of the problem table at the pinch and developed moving away from the Fig. 14. (a) The CP lable for TO hOI end. (b) and (c) Feasible pinch matches identified in the CP Table.
algorithm to the complete hot end would tell us that pinch. At the pinch essential matches, match options
utility heating would be required and no utility and stream splitting requirements are identified by .
cooling, i.e. the hot end effectively constitutes a applying the feasibility criteria.
tick-off heuristic. These two designs are shown in Figs. CP
threshold problem where the c.Tm • specified is the • When options exist at the pinch, the engineer is
PINCH
15(a) and 15(b).
threshold value. Now consider the situation where a free to base his selection to suit the process require. :
[n Fig. 15(a), the load of the pi nch rna tch identified 150 III
pinch match has been identified and its load has been ments. 0
in Fig. 14(b) has been maximised to tick-o IT stream I 2 '0
determined using the lick-off heuristic. There will • The heat loads of exchangers at the pinch are
No. I. The residual load of 17.5 units on stream No. II
exist a "remaining problem" of hot and cold streams determined using the stream "tick-oW' heuristic. [n II
3 then forms a new stream in the remaining problem.
(strictly speaking parts of streams) for which a net­ case of difficulty (increased utility usage) a different 70. 1t
t7~' s
Identifying a feasible topology for this remaining 2·5
work design is required. The problem table algorithm exchanger topology at the pinch can be chosen or the
can be applied to this remaining problem. One of two
resulls would then occur.
load on the offending match can be reduced.
problem is a trivial task. There are no options, i.e. the
remaining problem can only be solved by the place­ 12~'0 II~
'00"
~~I
-'-i,rJ"l

~I~
• Away from the pinch there is generally a "free 3·0
ment of two heaters.
First. the algorithm may calculate that no utility choice" of matches. The procedure does not insist on II
The other design option identified in Fig. l4(c) is
cooling is required to solve the remaining problem particular matches but allows the designer to discrim­
developed through to a final hot end design in Fig. 101 II
and the utility heating predicted would be the same inate between matches based on his judgement and
15(b). The pinch match load now ticks-off stream No.
as before. In this case the designer knows that the process knowledge. CP
4. This leaves a residual load on stream No. I of 30
pinch match load he has assigned, using the tick-off
heuristic, will not penalise the design in terms of
i
~
units with only stream No.3 to match against. Thus
2 ·0
the remaining problem is solved by the placement of
increased utility usage.
WORKED EXAMPLE: TEST CASE NO. 3
t'. one exchanger and one heater.
Second. the algorithm may calculate that utility
We will now demonstrate the pinch design method
cooling is required for the remaining hot end problem
using TC3 as the example problem. The calculation of Cold end design 2, 5
and that the hot utility usage would, accordingly, be
the pinch temperature, the minimum utility require­ An empty CP table for the cold end ofTC3 is shown
increased. In this case the designer knows that the
ments and the identification of the hot and cold end in Fig. 16(a). A pinch topology is identified in this
pinch match load he has assigned. using the tick-off
design tasks for TC3 have been discussed previously in table by applying the feasibility criteria according to 3 '0
heuristic. is not compatible with minimum utility
usage. this paper. The pinch design and completion of the' Fig. 13(b). The first feasibility requirement. inequality 90·0
remaining problem are considered below. Note that at (2b), shows that the stream population at the pinch is
The above lechnique has been called remaining
problem analysis for obvious reasons. It is a de­ this stage no attempt has been made to "optimise" the consistent with a minimum utility design. However. an IbI
C. T m " value. arrangement of pinch matches cannot be found since
pendable mechanism to check the consequences of Fig. 15. (a, bl Two hot end designs to TO.
feasibility criterion (3b) cannot apply to all pinch
the application of the tick-off heuristic. However, due
HOI end design matches simultaneously (see Fig. l6(b)). Stream split­
to the effort involved it should only be used in
The CP table for the hot end to TC3 is shown in Fig. ting is required if the problem is to be solved by using section:) It was then necessary to split the hot CP of 8
complex situations to confirm key design steps.
14(a). A plOch topology is identified in this table by the minimum utility usage and by observing the C. T m" in order to fulfil inequality (2a). Given this under­
applying the feasibility criteria according to Fig. l3(a). constraint. standing, it is preferable to split c hot stream right
The remaining problem The first feasibility check (2a) shows that the stream One might think that in this situation it would be away as this maintains compliance with inequality (2a)
[n accordance with the pinch design method's population at the pinch is consistent with a design advisable to split a cold stream so that the cold stream and may allow a solution to be found with only one
philosophy the designer is given a "free hand" once using the minimum utility usage. There are fewer hot CP becomes smaller. However, the situation is more stream split. Such a solution is shown in Fig. 16(d).
that temperature driving forces no longer restrlct streams than cold. Application of the second fea­ Complex than that. As the numb~r of hot and cold Two different cold end designs can be developed
topology options. sibility requirement (3a) shows that there are tWO streams in TC3's cold end pinch design' are equal we from this pinch topology depending on how the tick­
Thus when designing away from the pinch in the design options. (see Figs. 14(b) and l4(c». . know that if we were to split a cold stream we would off heuristic is applied. [n Figs. l7(a) and I 7(b),
"remaining problem" matches are chosen dis­ In the design ofan industrial HEN problem, process then, of necessity, have to split a hot stream to fulfill matches No. I and No. 2 are the essential pinch
crimately by the designer to satisfy the process objec­ requirements or preferences would lead to the choice inequality (2b). To demonstrate this Fig. 16(c) shows matches. The topology in Fig. 17(a) results when the
lives. For example, heaters and coolers can be placed of one of these options. For the purpose of this paper, a feasible pinch arrangement in which the cold CP of load on match I is chosen to tick-off cold stream No.
for direct control of stream target temperatures. however. both options have been deemed valid and 2.5 Was first split. (Note. the rationale behind settmg 4. The topology in Fig. 17(b) results when the load on
Preferred topology requirements or materials, safety developed through to final hot end designs utilising the the split stream branch flow rates is. covered in the next match No.2 is chosen to tick-off stream No.3.

CES Vol. 38. No. )......G


758 B. LINN HOFF and E. HINDMARSH The pinch design method for heat exchanger networks 759

design. Figure 18(a) shows such a combination in­ according to Fig. 7{b). Hence there must be two loops
BELOW BELOW BELOW
l volving the hot end design from Fig. 15(a) and the in the design. Figs. 18(a) and 18(b) show these loops.
{ cold end design from Fig. 17(a). The final overall
NH,. NC 12b1 NH ~ NC 12bl NH " N C 12 bl
An important feature of every loop is that heat
design features minimum utility usage and has a total loads can be shifted around the loop from one unit to
CPH~ CPC IHI CPH ,. CPC 13bl CPH " CPC 13bl of seven units. This is the minimum consistent with another. The load is subtracted from one unit, added
minimum utility usage. to the next in the loop. subtracted from the next and
8

HOT
D~ ~
COLD
2

HOT
2 ·5

COLD HOT
2

COLD
2·5
itl SI'\IPLIFYING THE MINIMUM UTILITY DESIGN
As already discussed, there will generally be scope
to simplify minimum utility designs by a controlled
reduction in the number of units. By transferring heat
across the pinch and therefore increasing the utility
so on around the loop. This load shift always main­
tains the correct stream heat loads but the exchanger
duties are changed and may cause a violation or.1 T m ,,,.
However, driving forces can be "restored" using heat
load paths.

\ I
Heal load palhs
Y usage the number of capital items can be reduced. A path is a continuous connection in the grid be­
(a) (b I There is a trade-off between units (capital cost) and the tween a heater, heat exchangers and a cooler[14J.
utility usage (energy cost). Figure 19(b) shows the simplest form of a path.
BELOW BELOW In order to explore the scope for a controlled reduc­ Load shifts along paths follow equivalent rules to
3: He (2bl NH ~ N C 12 bl
i. tion in the number or units it is important to under­ load shifts around a loop. Load is added to a heater.
~
NH
stand the concepts of heat load loops and heat load subtracted from an exchanger, added to the next ex­
CPH" CP C IHI CPH ~ CPCl3bl JJ.­ .~ paths. changer in the path. subtracted from the next, and so
. i on along the path until it is finally added to a cooler.
l..,r,

~
c"\ i··•. Heal load loops Stream enthalpy balance is maintained but exchanger
8 3 . (<"J-" ~. Whenever a design features more than the target loads and operating temperatures are changed. This
iJ.'~J- ., minimum number of units ror the whole problem. last feature means that a path can be used to restore
2 5 2.5

\;0
"t <, L
\ . ."vr
} ignoring the pinch. it is due to the existence of heat
loa(fToops~'j@s"",'asfirst stated as an observation by
driving forces.
We will now illustrate the use of heat load loops and
(J' Ifl P Hohmannp] who also introduced the term "heat load paths to reduce the number of units of the design in
HOT COLD HOT COLD ',t1'
, l.y.... ,'r "
1..\ ~
.:!f loop". Later, it was confirmed by Linnhoff et 01. [61 to Fig. 18 from seven to six.
(c) (d)

1
be generally true. booed on Eulers network theorem.
Fig. 16. (a, The CP 'able for TC3 cold end. Ib) infeasible pinch topologies. Ie) Feasible pinch 'apology There will be one loop for each extra unit. As an Example
with two stream splits. (d) Feasible pinch topology with one stream split. example. the minimum uti lily design to TC3 shown in It is apparent that load shifts around loops can form

Delerminin~ branch flow rales


i Fig. 18 has two more units than the definite minimum the basic mechanism for the reduction in the number

It should be noted that the identification of stream


PINCH
II
CPA PI~CH

splits in the CP table does not require the calculation


r.l llooo 1 LOOP I

of the actual branch CPs that would occur in the final L!.J I: ( 2· 0,
t
150·
~ . .0·
~:----1
design. It is sufficient merely to assign an initial
branch CP. The restrictions on this assigned branch ml~
II
8·0 .0·
CP are
II
• It must obey the CP inequalities (2a) or (2b). II US· o·
• The CP difference between the branch CP and its II lo ' I ( 2 ·5 ----<til'

~
"0 105 20
II 25· ' . '0
partner stream CP must not exceed the overall CP .0
difference for the problem (or that remaining if other
matches have already been identified).
"
II , 35
(01
3·0

."", "
,
..., ~:."J.v
101

In fact. when using the CP table, it is recommended 10 I


ft C-vi! .1/"...1 \ .., ~I' "i-{,
to set a branch CP equal to the CP of its partner ,j
stream or branch. This maintatns a good "stock" of
PINCH
II
£f PINCH (0 -1
overall CP difference for later matches. This was the
procedure adopted above when a pinch topology for r.I II 900
L!.JII (
2·0
:C .0·
the cold end ofTC3 was identified in the CP table (see
01~ 8·0
.0·
Fig. 16(d».
The final branch CP is chosen when the pinch
II
topology. identified in the CP table. is transferred to
II
12S­
'0· (11· S oj. xI
II 100· 2 so, 4
the grid and loads and temperatures are assigned to II'!~- I ( 2·5
100­
ZS-'4 H

...
;00 I J 5­
the pinch matches. Figures 17(a) and 17(b) show the II '0
results for the cold end of TC3.

Complete minimum utility solutions


"
II
II
!l5 20
3'0
LOOP 2

Ib I
Ib I
Fig. 19. (a) A six unit topology to TC3. the result of
Complete minimum utility designs are obtained by IbJ Fig. 18. (a. b) A minimum utility design to TC3 showing the breaking loop I. Fig. 18a. (b) Identifying a path to restore
combining any hot end design with any cold end Fig. 17. la. b) Two cold end designs to TC3. two heat load loops. the f1Tm,n constraint.
760 B. LINNHOFF and E. HINDMARSH The pinch design method for heal exchanger networks 761

v
of units. When the load shift around a loop leads to a COST TOTAL
reduction in the heat load of a unit which equals the
load on that unit then the unit is removed from the CAPITAL ~
design and the number of units is reduced by one. (Su .~ COST
CAPITAL
used this mechanism when he developed a loop break­
I.
II
ENERGY
ing evolutionary method for tbe synthesis of HEN
networks [9]).
Consider Fig. 18(a) which shows a minimum utility E NEP..G't'
design to TC3 with seven units. A good choice of
exchanger to remove is exchango:r No.4 as it has the
smallest load and fonns part of the simplest loop. Fig.
19(a) shows the topology and temperatures after the I I tt.T
load of match No.4 has been transferred to exchanger I • X
I
i
I.­
No. I. The heat loads of all other units in the design are
unchanged as they were not part of the original loop. OPT, .. u..
There is now a small violation in lI.Tm" as reflected by 6T MIN 6T ~IN
Fig. 20. Defining the optimum !1T after loop breaking. OPTIMUM
the difference in temperatures TI and T2.
However, lI. T m" can be restored using the heat load
Fig. 21. Network cost as a function of t:J.Trru.n'
path shown in Fig. 19(b). It is apparent that Tl is
fixed at 62"C. It is therefore T2 which must be achieved in a controlled manner. By this we mean l
changed to restore lI. T m,•• Requiring T2 to equal that the utility penalty incurred in reducing the~
82 'C, the heat load of individual units can now be number of units is minimised. For example in TC3 an' The method is so simple and straight-forward that it is occurrences are rare and when they do occur they can
changed while the stream heat loads are maintained exchanger of load 20 kW was removed but the in-: possible to produce such designs for large problems be rectified either by restricting the load on the
by using the path through exchanger No. I. It is a crease required in the utility usage to restore feas­ quickly and easily by hand. The method incorporates offending exchanger. or by using a different pinch
trivial task to calculate the hot and cold utility ibility was only 4 kW. . two fundamentally important elements. topology option.
increase X required. This load is 4 kW. In other • Not all units exist in a suitable loop or along a { First. the method recognises that the design objec­ The heuristic in no way interferes with the
words, by supplying a further 4 kW of utility heating suitable path. Thus, the procedure would not be;: tive is not just the identification of a "rigorous" cost method's ability to identify essential matches and
and cooling and by reducing the heat load on ex­ applicable to the "removal" of such units. t optimal topology-after all, we are dealing with pre­ options available at the pinch compatible with a
changer No. I by 4 kW, the solution is brought back • There is an optimum value of utility increase, liminary design-but one which is safe and control­ minimum utility design.
in line with the lI.Tm ,•• which establishes the correct trade-off between utility i lable. To achieve this, the method infonns the designer
It is important to distinguisb between the elimi­ costs and capital costs. This optimum value will when topology options exist. By discriminating be­ Stream splitting rationale
nation of units using heat load loops and paths and nearly coincide with lI.Tm" and has to be established tween these options the design can steer his design The pinch design method identifies situations
the mere replacement of units by heaters and coolers. by optimisation. t towards, controllable and practical topologies, using where stream splitting is essential to achieve a min­
Consider again the design shown in Fig. 18(a). The his judgement and process knowledge. imum utility solution observing the t:.Tmln constraint.
number of units can obviously be reduced by substi­ CHOICE OF &Tm..11 Second, the method recognises the fundamental im­ The rationale is rigorous. This represents a break­
tuting exchanger No.4 with an increased heater load Consider Fig. 21 which shows qualitatively the vari-! portance of the HEN pinch. At the pinch the choice of through in understanding. To date, many published
on stream No: 3 and an increased cooler load on ation ofa network's annualised capital cost and annu­ matches is severely restricted. Often there is only one design methods have made use of stream splitting but
stream No. I. The removal of exchanger No.4, in this alised utility cost with variation in lI.Tm". Obviously choice. an essential match, which if not made will none could guarantee that it could not perhaps have
case. would necessitate a 20 kW increase in both hot when J1Tm,n equals zero the heat exchanger network penalise the design by increasing utility usage above
been avoided.
and cold utility usage. By first redistributing the cost is infinite as infinite heat exchange surface area is t the minimu~. Thus. the design must be started at the
exchanger load using a loop as above we found that required. The utility usage and hence utility cost is at; pinch. and developed moving away from the pinch.
the hot and cold utility increase was only 4 kW. This a minimum. As t:.Tmm is increased the network capital This realisation is a completely new insight in HEN Threshold problems
is a substantial improvement over the 20 kW penalty cost initially falls sharply but at higher values of lI.T~. design and leads to the simple but enonnously Most of the early HEN problems presented in the
incurred ·if the exchanger is simply substituted. "flattens out" and in certain problems may tend to rise effective feasibility criteria which are summarised in literature were not pinched for the specified values of

Moreover, it is worth emphasising that the lI.Tm ,. again. Utility costs increase steadily with increase in Fig. 13 and form the basis of the actual procedure. lI. T m,•• We now recognise them as threshold problems

constraint should not always be restored after a load J1.Tmlr.o because of their relationship between minimum util­

shift around a loop. Consider again Fig. 19(a) which It is evident from Fig. 21 that total network cost The heuristic element ity usage and lI. Tm". This relationship can be sum­

shows a topology from TC3 after the loop load shift. (annualised utility and capital costs) passes through a The pinch design method employs the stream marised as follows:

Although a lI. Tm " violation occurs the network is minimum value which corresponds to a particular tick-off heuristic to speed up the procedure

thermodynamically feasible. In the example above utility usage and lI. T m". It is. therefore. necessary to SUfficiently for hand application and to steer the o ~ t:.T
mm < J1.T thrnh

J1Tmtn was restored for no other reason than it was ensure that networks are designed using a ~ T mln in the design rowards minimum number of units compatible

part of the original problem specification. In practice region of the optimum. This lI.Tm " is easily identified with minimum energy. This tick-off heuristic is not Either hot or cold utility usage (but not both) is
there will be an optimum value of T2-TI. This using the pinch design method by costing several de­ the same as that previously condemned by Linnhoff required and the problem is not pinched.
optimum value correctly trades energy and capital signs. et al. [6] as being partly responsible for the failure of
costs. see Fig. 20. Virtually all previous work in the area. In these t:.Tmm = t:.Tlh~~h
We can now summarise this section as follows previous sources. streams were ticked off by going
SUMMARY across the pinch and therefore incurring heat transfer The same hot or cold utility requirement as for lower
• There is generally scope to reduce the number of The pinch design method generates, with a high across the pinch. In the present paper, streams are values of lI. T m " is required but the problem is now
units in a pinched problem starting from a minimum degree of certainty, low cost solutions to HEN prob­ ticked-off either side of the pinch. However, even so pinched.
utility design. lems by producing minimum utility designs with as the heuristic can occasionally penalise the design by
• This reduction in the number of units can be few units as is compatible with minimum utility usage. introducing need for excess utility. Fortunately such tiTmm > ti.T 1hrnh

'.
762 B. LINNHOFF and E. HINDMARSH The pinch design method for heat e:<changer networks 763

Both hot and cold utilities are required. The problem sured that the pinch division was recognised. How.'
t TT stream target temperature. C [6] Linnhoff B.. Mason D. R. and Wardle I.. Comp"'.
is pinched. the actual temperature difference at Chem. Engng 19793 295.
ever. in [5] the insight of starting the design at the' aT
[7J Umeda T.. 1toh J. and Shiroko K. Ch£m. Engng Prog.
It is thus possible to apply the pinch design method pinch was missing. In addition the method, althOUgh:! one point of an exchanger. heater or
1978 75 70.
to threshold problems providing Ihe aTm;. is adjusted guaranteeing minimum utility designs. usually pro.; cooler [8) Umeda T.. Niida K. and Shiroko K.• A.I.Ch.E.J. 1979
to the threshold value. Obviously in this case the duced designs with more than the minimum numberl aTm ,. the minimum allowed temperature ap· IS 423.
designer would not be too contalled about a aTm," of units. This was despite the fact that the procedure~ proach in an exchanger. heater or [9) Su Tow-Lih. A loop breaking evolutionary method for
violation. the synthesis of heat exchanger networks. M.Sc. Thesis.
recommended making matches in subnetworks based 1: cooler, C Sever Institute of Washington University, SalOt Louis.
In industrial design. however. threshold problems on the neighbouring match principle. 6. Tthrnh the threshold value of aTm,. for a Missouri (1979).
are rare. This stems mainly from the fact that most Grimes[13] came close too. He recognised thi HEN problem. C [10] Boland D. and Linnhoff B.. Chem. Engr April 1979
industrial processes use more than one hot or cold importance of the pinch division and the need for' Urn .. the minimum number of exchangers. 222-228.
utility. There are often savings 10 be made by utilising heaters and coolers. [II] Flower J. R. and Linnhoff 8.. A lhermodynamic­
separate Urn;. targets above and below the pinch. combinatorial approach to the design of optimum heat
cheaper grade utilities. In this reper it is shown that However, he selected matches in the hot and cold . , the minimum number of exchangers,
Umi",,"U exchanger networks. A./.Ch.E.J. 198026 I.
each intermediate temperature utility. the use of ends on the basis of minimum average temperature l heaters and coolers in a pinched [12] Linnhoff B. and Turner J. A.. Chem. Engr December
which is maximised. introduces a "utility" pinch into
the problem.
difference. The decisive insight of starting a design at t problem which is consistent with the
minimum utIlity usage.
1980742-746.
ll31 Grimes L. E., The synthesis and evolution of networks
the pinch was missing and with it the recognition of!.
of heat exchanger that fealure the minimum number of
Moreover. even in cases WhCR only one hot and the feasibility criteria at the pinch. The present~ x. Y.Z heat Rows, kW. units. M.Sc. Thesis. Carnegie-Mellon Univ.. Pittsburgh
one cold utility are available. thmihold problems can authors found that as a result the method quite often 1 1980.
only exist if the underlying proa:ss (reactors. sepa­ fails to give minimum utility designs. , REfERENCES (14] Linnhoff B.. Process synthesis. Undergraduate lecture
rators. etc.) exists with large driving forces. Given All other methods published to date did not recog-S. [tJ Masso A. Hand Rudd D. F.. A.l.Ch. E. J. 1969 IS 10. nOles. Imperial College 1980/81.
today's energy costs. processes like that become less [11 Hohmann E. C. Optimum nctworks for heat exchange. [15J Nishida N.. Stephanopoulos G. and Westerberg A. W..
nise the need to divide a problem at the pinch and are! A.I.Ch.E.J. 1981 27311.
and less common. Ph.D. Thesis. Univcrsity of Southern California (1971).
therefore well and truly out of date. However. this is .. [3J Ponlon J. W. and Domlldson R. A. B.. Chern. Engn~ [l6J Harary F .. Graph Theory_ Addison-Wesley. Reading.
not to say that some of these methods could not now',' Sci. 197429 pp. 1375. Mass. 1972.
Efle'~.l'-('a"ital 'radeoffs be appli;d to solve the threshold problems of the t 14J Nishida N.. Liu Y. A. and Lapidus L.. A.I.Ch.E.J. 1977 [17J Cerda J.. Weslerberg A. W.. Mason D. R. and Linnhotf
B.. Chem. Engng Sci. 1983 38 373.
The minimum number of unilS required to com­ hot and of the cold ends separately. This may': 23 77.
plete a design can be assessed from the stream data. [5] Linnhoff B. and Flower J. R.. A.I.Ch.E.J. 197824633:
provide many a PhD project for all those who prefer
Due recognition must however be made of the pinch A.l.Ch.E.J. 1978 24 641.
exhaustive optimisation to the simple hand­
division of the HEN problem and the targeting calculation based approach presented here.
equation relating units to streams must be applied
separately above and below the pinch. Using the Acknol4'ledgrmrnu-The work desl:nbed in this paper was f'
equation in this way gives the target minimum num­ carried out while both authors were in [he employment of t:
ber of units required by a design which achieves rCI. The authors wish (0 (hank ail members of the leI l
~rocess Synthesis team [hal have crilicised and helped to ~,.;,
minimum utility usage. Improve the paper. Also they wish to thank leI for pennis- iK
The target numher of units obtained in this manner ~ion to publish this paper. Ii:
is usually greater than that for Ihe whole problem
undivided by the pinch. This is because some streams
NOTATION
exist on both sides of the pinch.
Designs with fewer units than is compatible with CP the heat capacity Rowrate of a stream, '"
the minimum utility usage must lransfer heat across kW/C ii,'
the pinch or certain exchangers must violate the 6. Tm1n CPC the heat capacity Rowrate of a cold
constraint. Thus there are often trade-offs between stream or a cold slream branch at ,f
utility usage. number of units and exchange surface the pinch. kW/C ~
area. These trade-offs can be explored by applying CPH the heat capacity Rowrate of a hot t
the properties of heat load loops and paths to a stream or a hot stream branch at the :;,'
minimum utility" design. pinch, kW/C :
N the number of process streams and ~
Comparison w;lh prev;auJ ,..'ark utilities
The strategy of the pinch design method. namely NC the number of cold streams and cold
dividing a HEN problem at the pinch. starting the stream branches at the pinch
design at the pinch and developing it into the remain­ NH the number of hot streams and hot
;ng problem is a completely ne.. approach different stream branches at Ihe pinch
to all other published design methods. It is the result Q heat exchanger load, kW
of recognising Ihe fundamenlal importance of the dQ small change in exchanger load, kW
HEN pinch and is the reason behind the ease of QH hot utility requirement for a HEN
application of the method. It is lIlis ease of applica­ problem. kW
tion which allows the designer 10 quickly explore QC cold utility requirement for a HEN
practical topologies for various ATmtn values. which problem. kW
ensures that "best" solutions are always found with QHm,., QCmm the minimum hot and cold utility re­
minimal effort. quirement
The TI Method by Linnhoff eJ al. [5J came close to T temperature. C
the above strategy. The subnetwork arrangement. dT small change in temperature. C
established using the problem table algorithm. en- TS stream supply temperature. C
II

Das könnte Ihnen auch gefallen