ID Task Name Duration Start Finish Nov 17, '19 Nov 24, '19 Dec 1, '19 Dec 8, '19

Duration Start Finish Nov 17, '19 Nov 24, '19 Dec 1, '19 Dec 8, '19 Dec 15, '19 Dec 22, '19 Dec 29, '1
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
1 GSS Works DC - 3 39 days Tue 11/19/19 Sun 12/29/19
2 FF - Installtion 17 days Tue 11/19/19 Fri 12/6/19
3 Balance Works DC Hall 3 days Tue 11/19/19 Thu 11/21/19
4 Corridor Area 4 days Fri 11/22/19 Tue 11/26/19
5 Clearance for Below Ceiling Points 0 days Tue 11/26/19 Tue 11/26/19 11/26
6 Below Ceiling Supports & Pipe Installtion After Grid Ceiling Marking 10 days Tue 11/26/19 Fri 12/6/19
7 Ground Floor 17 days Tue 11/19/19 Fri 12/6/19
8 Cylinder Room 16 days Tue 11/19/19 Thu 12/5/19
9 Base Frame Fabrication & Installation 3 days Tue 11/19/19 Thu 11/21/19
10 Cylinder Shifitng & Fixing 2 days Fri 11/22/19 Sun 11/24/19
11 Manifold Piping - Fabrication 5 days Sun 11/24/19 Fri 11/29/19
12 Manifold Piping Erection 7 days Mon 11/25/19 Mon 12/2/19
13 Selector Valve Installtion 3 days Mon 12/2/19 Thu 12/5/19
14 ANR Hall 3 days Tue 11/19/19 Thu 11/21/19
15 Fabrication & Erection of Pipes 3 days Tue 11/19/19 Thu 11/21/19
16 Corridor Piping Upto Shaft 5 days Tue 11/19/19 Sun 11/24/19
17 Marking for Opening 0 days Tue 11/19/19 Tue 11/19/19 11/19
18 Getting Clearance 0 days Tue 11/19/19 Tue 11/19/19 11/19
19 Fabrication & Erection of Pipes 2 days Fri 11/22/19 Sun 11/24/19
20 Testing 1 day Thu 12/5/19 Fri 12/6/19
21 Pressure Testing 1 day Thu 12/5/19 Fri 12/6/19
22 Puff Testing 1 day Thu 12/5/19 Fri 12/6/19
23 2nd Floor 36 days Fri 11/22/19 Sun 12/29/19
24 DC Hall 1 & 2 15 days Fri 11/22/19 Sat 12/7/19
25 Crack Room 7 days Sat 12/7/19 Sat 12/14/19
26 UPS Room & Battery Room 7 days Sat 12/14/19 Sun 12/22/19
27 PDU Room 4 days Sun 12/22/19 Thu 12/26/19
28 Corridor Area 3 days Thu 12/26/19 Sun 12/29/19
29 Clearance for Below Ceiling Points 0 days Sun 12/29/19 Sun 12/29/19 12/29
30 Below Ceiling Supports & Pipe Installtion After Grid Ceiling Marking 0 days Sun 12/29/19 Sun 12/29/19 12/29
31 Riser Pipe Installtion 6 days Sun 11/24/19 Sat 11/30/19
32 Fabrication & Installation of Supports 4 days Sun 11/24/19 Thu 11/28/19
33 Fabrication & Installtion of Pipes 5 days Mon 11/25/19 Sat 11/30/19
34 Terrace Floor 3 days Thu 12/26/19 Sun 12/29/19

Project: MSProj11 Task Progress Summary External Tasks Deadline


Date: Tue 11/19/19 Split Milestone Project Summary External Milestone