Duration Start Finish Nov 17, '19 Nov 24, '19 Dec 1, '19 Dec 8, '19 Dec 15, '19 Dec 22, '19 Dec 29, '1
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
1 GSS Works DC - 3 39 days Tue 11/19/19 Sun 12/29/19
2 FF - Installtion 17 days Tue 11/19/19 Fri 12/6/19
3 Balance Works DC Hall 3 days Tue 11/19/19 Thu 11/21/19
4 Corridor Area 4 days Fri 11/22/19 Tue 11/26/19
5 Clearance for Below Ceiling Points 0 days Tue 11/26/19 Tue 11/26/19 11/26
6 Below Ceiling Supports & Pipe Installtion After Grid Ceiling Marking 10 days Tue 11/26/19 Fri 12/6/19
7 Ground Floor 17 days Tue 11/19/19 Fri 12/6/19
8 Cylinder Room 16 days Tue 11/19/19 Thu 12/5/19
9 Base Frame Fabrication & Installation 3 days Tue 11/19/19 Thu 11/21/19
10 Cylinder Shifitng & Fixing 2 days Fri 11/22/19 Sun 11/24/19
11 Manifold Piping - Fabrication 5 days Sun 11/24/19 Fri 11/29/19
12 Manifold Piping Erection 7 days Mon 11/25/19 Mon 12/2/19
13 Selector Valve Installtion 3 days Mon 12/2/19 Thu 12/5/19
14 ANR Hall 3 days Tue 11/19/19 Thu 11/21/19
15 Fabrication & Erection of Pipes 3 days Tue 11/19/19 Thu 11/21/19
16 Corridor Piping Upto Shaft 5 days Tue 11/19/19 Sun 11/24/19
17 Marking for Opening 0 days Tue 11/19/19 Tue 11/19/19 11/19
18 Getting Clearance 0 days Tue 11/19/19 Tue 11/19/19 11/19
19 Fabrication & Erection of Pipes 2 days Fri 11/22/19 Sun 11/24/19
20 Testing 1 day Thu 12/5/19 Fri 12/6/19
21 Pressure Testing 1 day Thu 12/5/19 Fri 12/6/19
22 Puff Testing 1 day Thu 12/5/19 Fri 12/6/19
23 2nd Floor 36 days Fri 11/22/19 Sun 12/29/19
24 DC Hall 1 & 2 15 days Fri 11/22/19 Sat 12/7/19
25 Crack Room 7 days Sat 12/7/19 Sat 12/14/19
26 UPS Room & Battery Room 7 days Sat 12/14/19 Sun 12/22/19
27 PDU Room 4 days Sun 12/22/19 Thu 12/26/19
28 Corridor Area 3 days Thu 12/26/19 Sun 12/29/19
29 Clearance for Below Ceiling Points 0 days Sun 12/29/19 Sun 12/29/19 12/29
30 Below Ceiling Supports & Pipe Installtion After Grid Ceiling Marking 0 days Sun 12/29/19 Sun 12/29/19 12/29
31 Riser Pipe Installtion 6 days Sun 11/24/19 Sat 11/30/19
32 Fabrication & Installation of Supports 4 days Sun 11/24/19 Thu 11/28/19
33 Fabrication & Installtion of Pipes 5 days Mon 11/25/19 Sat 11/30/19
34 Terrace Floor 3 days Thu 12/26/19 Sun 12/29/19