Beruflich Dokumente
Kultur Dokumente
SCOPE OF WORKS
2 PERFORMANCE BOND
4 SURETY BONDS
DIVISION 2. EARTHWORKS & SITE-WORKS (CONSTRUCTOR WILL SUPPLY EXCAVATOR, DUMP TRUCK
A CLEARING AND GRUBBING
DEMOLITION WORKS: Existing Structures on Site
1 Building A
2 Building B
3 Building C
4 Driveway & Drainage
EXCAVATION WORKS & BACKFILL (IMPORTED FILL MATERIALS WILL BE PROVIDED
B
BY OWNER) (CUT, FILL & COMPACTION BY CONSTRUCTOR)
C LINEAR EXCAVATION WORKS (STORM DRAINAGE)
HAULING & DISPOSAL OF ALL UNSUITABLE MATERIALS (THIS INCLUDES WASTE
D MATERIALS FROM OTHER SUB CONSTRUCTORS AND OWNER SUPPLIED
MATERIALS)
EARTH FILL (IMPORTED FILL SHALL BE SUPPLIED BY WILCON OR SOURCED
E
FROM OTHER SUPPLIER)
F LEVELING AND COMPACTION (BASE PREPARATION & TRIMMING)
G SAND BEDDING
H GRAVEL BEDDING ( 100mm Thk )
SOIL POISONING (MAIN BUILDING) (COORDINATE WITH SERVICE PROVIDER
I
PRIOR TO CONCRETING)
J VAPOR BARRIER (POLYETHELYN SHEET OWNER SUPPLY)
K OTHERS (PLEASE SPECIFY)
DIVISION 2 EARTHWORKS & SITEWORKS COST SUB-TOTAL :
DIVISION 3. CONCRETE WORKS (CONSTRUCTOR SHALL BID LABOR AND CONSUMABLES ONLY) (O
A FOUNDATION FOOTING
Page 2
Contract Reference
1 F-1
2 F-2
3 F-3
4 F-4
5 F-5
6 F-6
7 SF-1
B PEDESTAL COLUMN
1 PD-1
2 PD-2
3 PD-3
4 PD-4
5 PD-5
6 PD-6
7 PD-7
8 PD-8
9 PD-9
10 PD-10
11 PD-11
12 PD-12
13 PD-13
14 PD-14
STIFFENER COLUMN (NOTE: STIFFENER CONCRETE COLUMN SHALL BE
C ATTACHED TO ALL PERIMETER STEEL COLUMNS & IN-BETWEEN STEEL
COLUMNS AS PART OF OUR WALL SYTEM)
1 SC
D CONCRETE BEAMS
1 FOOTING TIE BEAM
MID HEIGHT BEAM (NOTE: STIFFENER BEAMS SHALL BE ATTACHED TO ALL
2 PERIMETER STEEL COLUMNS & IN-BETWEEN STEEL COLUMNS AS PART OF
OUR WALL SYTEM, VERIFY LOCATION IN ARCHITECTURAL ELEVATION)
3 PARAPET CAP BEAM
SLAB-ON-FILL (INCLUDES CONCRETE CUTTING FOR THE CONSTRUCTION
E
JOINTS)
1 GROUND FLOOR SLAB ( Trowel Finish Only )
2 MAIN ENTRANCE ( Stair, Landing & Ramp )
SUSPENDED SLAB (INCLUDE SHORING & SCAFFOLDINGS IN CONSUMABLES)
F (NOTE: SEE TYPICAL METAL DECK DETAILS, METAL DECK INCLUDED IN
STEEL STRUCTURE SUPPLY)
1 MEZZANINE (Trowel Finish)
2 SECOND FLOOR (Trowel Finish)
Page 3
Contract Reference
G OTHERS (PLEASE SPECIFY)
1 CISTERN & RAINWATER TANK
a. GBB-1
b. GBB-2
c. SLAB ON GRADE, WALL & SUSPENDED SLAB
2 SEPTIC TANK
a. GBB-1
b. GBB-2
c. SLAB ON GRADE, WALL & SUSPENDED SLAB
3 FIREWALL (8” THK)
4 Vault Room
DIVISION 3 CONCRETING COST SUB-TOTAL :
Page 4
Contract Reference
STIFFENER COLUMN (NOTE: STIFFENER CONCRETE COLUMN SHALL BE
C ATTACHED TO ALL PERIMETER STEEL COLUMNS & IN-BETWEEN STEEL
COLUMNS AS PART OF OUR WALL SYTEM)
1 SC
D CONCRETE BEAMS
1 FOOTING TIE BEAM
MID HEIGHT BEAM (NOTE: STIFFENER BEAMS SHALL BE ATTACHED TO ALL
2 PERIMETER STEEL COLUMNS & IN-BETWEEN STEEL COLUMNS AS PART OF
OUR WALL SYTEM, VERIFY LOCATION IN ARCHITECTURAL ELEVATION)
3 PARAPET CAP BEAM
SLAB-ON-FILL (INCLUDES CONCRETE CUTTING FOR THE CONSTRUCTION
E
JOINTS)
1 GROUND FLOOR SLAB ( Trowel Finish Only )
2 MAIN ENTRANCE ( Stair, Landing & Ramp )
SUSPENDED SLAB (INCLUDE SHORING & SCAFFOLDINGS IN CONSUMABLES)
F (NOTE: SEE TYPICAL METAL DECK DETAILS, METAL DECK INCLUDED IN
STEEL STRUCTURE SUPPLY)
1 MEZZANINE (Trowel Finish)
2 SECOND FLOOR (Trowel Finish)
G OTHERS (PLEASE SPECIFY)
1 CISTERN & RAINWATER TANK
a. GBB-1
b. GBB-2
c. SLAB ON GRADE, WALL & SUSPENDED SLAB
2 SEPTIC TANK
a. GBB-1
b. GBB-2
c. SLAB ON GRADE, WALL & SUSPENDED SLAB
3 FIREWALL (8” THK)
4 Vault Room
DIVISION 4 STEEL REINFORCEMENT COST SUB-TOTAL :
Page 5
Contract Reference
B PEDESTAL COLUMN
1 PD-1
2 PD-2
3 PD-3
4 PD-4
5 PD-5
6 PD-6
7 PD-7
8 PD-8
9 PD-9
10 PD-10
11 PD-11
12 PD-12
13 PD-13
14 PD-14
STIFFENER COLUMN (NOTE: STIFFENER CONCRETE COLUMN SHALL BE
C ATTACHED TO ALL PERIMETER STEEL COLUMNS & IN-BETWEEN STEEL
COLUMNS AS PART OF OUR WALL SYTEM)
1 SC
D CONCRETE BEAMS
1 FOOTING TIE BEAM
MID HEIGHT BEAM (NOTE: STIFFENER BEAMS SHALL BE ATTACHED TO ALL
2 PERIMETER STEEL COLUMNS & IN-BETWEEN STEEL COLUMNS AS PART OF
OUR WALL SYTEM, VERIFY LOCATION IN ARCHITECTURAL ELEVATION)
3 PARAPET CAP BEAM
SLAB-ON-FILL (INCLUDES CONCRETE CUTTING FOR THE CONSTRUCTION
E
JOINTS)
1 GROUND FLOOR SLAB ( Trowel Finish Only )
2 MAIN ENTRANCE ( Stair, Landing & Ramp )
SUSPENDED SLAB (INCLUDE SHORING & SCAFFOLDINGS IN CONSUMABLES)
F (NOTE: SEE TYPICAL METAL DECK DETAILS, METAL DECK INCLUDED IN
STEEL STRUCTURE SUPPLY)
1 MEZZANINE (Trowel Finish)
2 SECOND FLOOR (Trowel Finish)
G OTHERS (PLEASE SPECIFY)
1 CISTERN & RAINWATER TANK
a. GBB-1
b. GBB-2
c. SLAB ON GRADE, WALL & SUSPENDED SLAB
2 SEPTIC TANK
a. GBB-1
Page 6
Contract Reference
b. GBB-2
c. SLAB ON GRADE, WALL & SUSPENDED SLAB
3 FIREWALL (8” THK)
4 Vault Room
DIVISION 5: FORM WORKS COST SUB-TOTAL :
STANDARD LINTEL BEAM, STIFFENER COLUMN, STIFFENER BEAMS and WALL FOOTING.
3 INCLUDES STANDARD STIFFENER COMUNS AND BEAMS @ TARP. ADS., LINTEL BEAMS AT
DOORS AND WINDOW OPENNINGS, etc. Concreting
STANDARD LINTEL BEAM, STIFFENER COLUMN, STIFFENER BEAMS and WALL FOOTING
4 INCLUDES STANDARD STIFFENER COMUNS AND BEAMS @ TARP. ADS., LINTEL BEAMS AT
DOORS AND WINDOW OPENNINGS, etc. Rebars
STANDARD LINTEL BEAM, STIFFENER COLUMN, STIFFENER BEAMS and WALL FOOTING.
5 INCLUDES STANDARD STIFFENER COMUNS AND BEAMS @ TARP. ADS., LINTEL BEAMS AT
DOORS AND WINDOW OPENNINGS, etc. Formworks
Page 7
Contract Reference
STANDARD LINTEL BEAM, STIFFENER COLUMN, STIFFENER BEAMS and WALL FOOTING.
2 INCLUDES STANDARD STIFFENER COMUNS AND BEAMS @ TARP. ADS., LINTEL BEAMS AT
DOORS AND WINDOW OPENNINGS, etc. Concreting
STANDARD LINTEL BEAM, STIFFENER COLUMN, STIFFENER BEAMS and WALL FOOTING
3 INCLUDES STANDARD STIFFENER COMUNS AND BEAMS @ TARP. ADS., LINTEL BEAMS AT
DOORS AND WINDOW OPENNINGS, etc. Rebars
STANDARD LINTEL BEAM, STIFFENER COLUMN, STIFFENER BEAMS and WALL FOOTING.
4 INCLUDES STANDARD STIFFENER COMUNS AND BEAMS @ TARP. ADS., LINTEL BEAMS AT
DOORS AND WINDOW OPENNINGS, etc. Formworks
Page 8
Contract Reference
DIVISION 7: STRUCTURAL STEEL WORKS COST SUB-TOTAL :
OTHERS
M ADVERTISEMENT FRAMES
1 TARPAULINE AD FRAMES
N INDOOR UNITS AIRCON PLATFORMS (COORDINATE WITH MECHANICAL)
O OTHERS (PLEASE SPECIFY)
3 FIRE EXIT STAIRS
OTHER STEEL WORKS COST SUB-TOTAL :
DIVISION 8: ROOFING WORKS (CONSUMABLES: TEKSKREW AND SEALANT) (OWNER WILL PROVID
MAIN BUILDING INSTALLATION
A
(WILCON WILL PROVIDE ROLL FORMING MACHINE ON-SITE)
1 Ga#24 Prepainted Spanlock Roofing (1/40” thk)
2 1.2mm Stainless Gutter / Valley Gutter / Side Gutter
3 Ga#24 Prepainted Ridge Roll (1/40” thk)
4 Ga#24 Prepainted Side Flashing (1/40” thk)
5 Roof Insulation
6 Gutter Hanger
7 Wire Mesh Gauge22 Insulator Support
8 Tig-Welding Of Stainless Gutter Joints
9 OTHERS (PLEASE SPECIFY)
B ENTRANCE AND RECEIVING CANOPY
1 Ga#24 Prepainted Spanlock Roofing
2 0.6mm Prepainted Apron & Wall Flashing
3 Roof Insulation
4 Gutter Hanger
5 Wire Mesh Gauge22 Insulator Support
C OTHERS (PLEASE SPECIFY)
DIVISION 8: ROOFING WORKS COST SUB-TOTAL :
DIVISION 10: PAINTING WORKS ( 1Coat – Primer, And 2 - Coats – Final Top Coating ) ( Include all
A INTERIOR Wall Painting (Boysen Flat latex primer, and Semi Gloss Latex Top Coat)
B EXTERIOR Wall Painting (Boysen Acrytex primer, and Arcytex Top Coat)
C INCLUDES ALL STEEL SURFACES (1 Coat–Primer, and 2-Coats – Final Top Coating)
E PERIMETER FENCE (LEFT, REAR & RIGHT SIDE) (3.00m Above Retaining Wall)
Page 12
Contract Reference
TOTAL LABOR AND CONSUMABLES
+12% VAT
GRAND TOTAL
FINAL CONTRACT
GENERAL COND
A INCLUSIVES
1 VAT inclusive
2 Wilcon Strictly impose a Construction Period of (6) Six months
Down payment will be released upon signing of construction contract & submission of required
3
documents 10%
Welding test will be conducted by Wilcon(assistance on access & clearing for the test area by
4
Contractor)
5 Cutting of slab shall commence 24hrs. After completion of concreting(concrete cutter by contractor)
B EXCLUSIONS :
Page 13
Contract Reference
WILCON CORPO
TECHNICAL QUERIES:(Architectural plans, Plumbing & Structural plans) 634-
8387 local 1625
CONFORME:
WILLIAM T. BELO
CHAIRMAN
( THIS DOCUMENT SHALL SERVE AS AN OFFICIAL C
Page 14
Contract Reference
ZANINE
M.
P.M.
1.00 LOT - - - -
WILCON WILCON
- - - - - - - -
1.00 LOT - -
- -
WILCON WILCON
WILCON WILCON
1.00 LOT - - -
-
WILCON WILCON
1.00 LOT - - - -
- - - - - - - -
1.00 LOT - - - -
WILCON WILCON
1.00 LOT - - - -
1.00 LOT - - - -
1.00 LOT - - - -
1.00 LOT - - - -
1.00 LOT - - - -
Page 15
Contract Reference
1.00 LOT - - - -
1.00 LOT - - - -
1.00 LOT - - - -
- - - - - - - -
1.00 LOT - - - -
1.00 LOT - - - -
1.00 LOT - - - -
1.00 LOT - - - -
1.00 LOT - - - -
CU.M. SQ.M.
1.00 LOT - - - -
OTHERS OTHERS
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
OTHERS OTHERS
SQ.M. SQ.M.
SQ.M. SQ.M.
ONSUMABLES ONLY) (OWNER SUPPLY MATERIALS : READY MIX, BOOM PUMP, ADMIX, ETC.)
- - - - - - - -
Page 16
Contract Reference
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
- - - - - - - -
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
- - - - - - - -
CU.M. CU.M.
- - - - - - - -
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
- - - - - - - -
SQ.M. SQ.M.
SQ.M. SQ.M.
- - - - - - - -
CU.M. CU.M.
CU.M. CU.M.
Page 17
Contract Reference
- - - - - - - -
- - - - - - - -
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
- - - - - - - -
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
CU.M. CU.M.
E QUOTATION COST FOR TIE WIRES, CONCRETE & STEEL BAR SPACERS)
- - - - - - - -
KG KG
KG KG
KG KG
KG KG
KG KG
KG KG
KG KG
- - - - - - - -
KG KG
KG KG
KG KG
KG KG
KG KG
KG KG
KG KG
KG KG
KG KG
KG KG
KG KG
KG KG
KG KG
KG KG
Page 18
Contract Reference
- - - - - -
- -
KG KG
- - - - - - - -
KG KG
KG KG
KG KG
- - - - - - - -
KG KG
KG KG
- - - - - - - -
KG KG
KG KG
- - - - - - - -
- - - - - - - -
KG KG
KG KG
KG KG
- - - - - - - -
KG KG
KG KG
KG KG
KG KG
KG KG
Page 19
Contract Reference
- - - - - - - -
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
- - - - - - -
-
SQ.M. SQ.M.
- - - - - - - -
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
- - - - - - - -
SQ.M. SQ.M.
SQ.M. SQ.M.
- - - - - - - -
SQ.M. SQ.M.
SQ.M. SQ.M.
- - - - - - - -
- - - - - - - -
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
- - - - - - - -
SQ.M. SQ.M.
Page 20
Contract Reference
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
- - - - - - - -
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
- - - - - - - -
SQ.M. SQ.M. Php12.50
SQ.M. SQ.M. Php12.50
L.M. L.M. Php12.50
CU.M. CU.M.
KG KG
SQ.M. SQ.M.
- -
Page 21
Contract Reference
- - - - - - -
-
SQ.M. CU.M.
KG. KG.
SQ.M. SQ.M.
SQ.M. SQ.M.
CU.M. CU.M.
KG KG
SQ.M. SQ.M.
- -
PAINT BY CONSTRUCTOR)
753.43 MT 753.43 MT
60.10 MT 60.10 LOT
35.57 MT 35.57 LOT
1.00 LOT 1.00 MT
1.00 LOT 1.00 LOT
1.00 LOT 1.00 LOT
8,563.00 SQ.M. 8,563.00 SQ.M.
- - - included - - - included
- - - included - - - included
- - - included - - - included
- - - included - - - included
- - - included - - - included
Page 22
Contract Reference
- - -
- - - - - - - -
- - - - - - - -
2.00 Sets - - - -
OTHERS OTHERS
- -
Sets - - - -
- - -
(OWNER WILL PROVIDE ROLL FORMING MACHINE ON SITE AND STEEL COIL)
- - - - - - - -
- - - - - - - -
59.00 SQ.M. 59.00 SQ.M.
37.00 SQ.M. 37.00 SQ.M.
40.00 SQ.M. 40.00 SQ.M.
240.00 SQ.M. 240.00 SQ.M.
300.00 SQ.M. 300.00 SQ.M.
25.00 SQ.M. 25.00 SQ.M.
- - - - - - - -
Page 23
Contract Reference
350.00 SQ.M. 350.00 SQ.M.
250.00 SQ.M. 250.00 SQ.M.
180.00 SQ.M. 180.00 SQ.M.
50.00 SQ.M. 50.00 SQ.M.
OTHERS OTHERS
OTHERS OTHERS
OTHERS OTHERS
OTHERS OTHERS
OTHERS OTHERS
- - - - - - - -
4.00 Sets 4.00 Sets
1.00 Sets 1.00 Sets
1.00 Sets 1.00 Sets
10.00 Sets 10.00 Sets
2.00 Sets 2.00 Sets
1.00 Sets 1.00 Sets
2.00 Sets 2.00 Sets
- - - - - - - -
59.00 SQ.M. 59.00 SQ.M.
37.00 SQ.M. 37.00 SQ.M.
300.00 SQ.M. 300.00 SQ.M.
650.00 SQ.M. 650.00 SQ.M.
100.00 SQ.M. 100.00 SQ.M.
4.00 SQ.M. 4.00 SQ.M.
1,000.00 SQ.M. 1,000.00 SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
- - - - - - - -
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
Page 24
Contract Reference
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
- - - - - - - -
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
Sets Sets
SQ.M. SQ.M.
Sets SQ.M.
LM SQ.M.
LM LM
LM LM
LM LM
OTHERS OTHERS
Sets Sets
- - - - - - - -
SQ.M. SQ.M.
SQ.M. SQ.M.
- - - - - - - -
2,458.00 SQ.M. 2,458.00 SQ.M.
405.00 SQ.M. 405.00 SQ.M.
199.00 SQ.M. 199.00 SQ.M.
- - - - - - - -
KG KG
KG KG
KG KG
KG KG
- - - - - - - -
SQ.M. SQ.M.
- - - - - - - -
SQ.M. SQ.M.
Page 25
Contract Reference
SQ.M. SQ.M.
SQ.M. SQ.M.
OTHERS OTHERS
- - - - - - - -
- - - - - - - -
160.00 LM 160.00 LM
53.00 LM 53.00 LM
CU.M CU.M
CU.M CU.M
CU.M CU.M
SQ.M. SQ.M.
KG KG
SQ.M. SQ.M.
SQ.M. SQ.M.
SQ.M. SQ.M.
- - - - - - - -
CU.M CU.M
CU.M CU.M
LM LM
PCS PCS
PCS PCS
CU.M CU.M
- - - - - - - -
- - - - - - - -
LM LM
LM LM
SQ.M. SQ.M.
Sets Sets
1.00 L.S. 1.00 L.S.
- - - - - - - -
1.00 L.S. 1.00 L.S.
1.00 L.S. 1.00 L.S.
1.00 L.S. 1.00 L.S.
- - - - - - - -
1.00 L.S. 1.00 L.S.
Page 26
Contract Reference
Php0.12
LY, EXCEPT OTHERS AND “ – “ AREAS, INCOMPLETE INPUT WILL NOT BE ACCEPTED )
LANS, BUT NOT REFLECTED IN THIS FORM SHALL BE INCLUDED IN THE FINAL CONTRACT)
GENERAL CONDITIONS
CONSUMABLES INLUDED IN THIS CONTRACT / BIDFORM
REBAR WORKS
a. G.I. Tie Wire #16
STRUCTURAL STEEL
ROOFING WORKS
a. Tekscrew
b. UV Resistant Silicon Sealant (ABC construction sealant or equivalen
c. Duct Tape
PAINTING WORKS
PLUMBING WORKS
a. PVC solvent cement & teflon tape(NELTEX)
ALL FORMWORKS; SHORINGS & SCAFFOLDINGS ARE CONSIDER
CONSUMABLES
a. Nails ( CWN and Concrete Nails )
Page 27
Contract Reference
WILCON CORPORATION
ADDRESS BID TO
ARCH. NISSI B. DEL ROSARIO
PROJECT MANAGER: ENGR. ISAGANI V. ROBLES
A.V.P. NICHOLAS AGBING
ENGINEERING DEPT. 5TH FLOOR WILCON BUILDING #90 E.RODRIGUEZ JR. AVE., UGON NORTE LIBIS Q.C.
L SERVE AS AN OFFICIAL CONTRACT UPON APPROVAL OF OWNER )
Page 28
Contract Reference
TOTAL
Page 29
Contract Reference
EQUIPMENTS)
Page 31
Contract Reference
-
-
Page 32
Contract Reference
-
-
CAFFOLDINGS)
-
Page 33
Contract Reference
-
-
-
Page 34
Contract Reference
Page 35
Contract Reference
-
-
-
-
-
Page 36
Contract Reference
-
Page 37
Contract Reference
Page 38
Contract Reference
Page 39
Contract Reference
Page 40
Contract Reference
STRUCTURAL STEEL
ROOFING WORKS
a. Tekscrew
b. UV Resistant Silicon Sealant (ABC construction sealant or equivalent)
c. Duct Tape
PAINTING WORKS
PLUMBING WORKS
a. PVC solvent cement & teflon tape(NELTEX)
ALL FORMWORKS; SHORINGS & SCAFFOLDINGS ARE CONSIDERED
CONSUMABLES
a. Nails ( CWN and Concrete Nails )
Page 41
Contract Reference
Page 42