Sie sind auf Seite 1von 12

GBTS and NodeB

BTS3900A/BTS3900

BTS AND NODEB RAN SHARING HARDWARE


INSTALLATION ACCEPTANCE PROTOCOL
A. SITE INFORMATION

Site ID 1102304
Site Name SUKAMENAK
BSC / RNC Area BSC_Bandung _2 / Huawei Bandung
BTS / Node B type 3900A / 3900A
Site Configuration □Single 2G □Single 3G √ Co-located 2G/3G /4G
Huawei Wireless Equipment □ 2G (3G Vendor ………..) □3G (2G Vendor……..……) √ 2G / 3G/4G
Subcontractor Company
Subcontractor Supervisor
Installation started date
Installation finished date

Type of Site Location and Coverage


□ Roof Top (Macro / IBC) _____ _______
√ Green field (Macro / IBC) _____ MACRO _________

Type of BTS/NodeB Cabinet


√ BTS3900A
□BTS3900

Type of Deployment
□Swap Site
√ New Deployment

Type of Power System


√ APM30
□TP Agisson Series (TP 48200A………………)
□Other (…………………………………)
B. EQUIPMENT
BTS and NodeB
Hardware on Main Rack Quantity Hardware in Power/Battery Rack Quantity

1. UMPT (3G) 1 1. APM 30 Cabinet 1

2. GTMU (2G) / Use UBBP 0 2. TP Cabinet 0


3. WBBP (3G)* 1 3. PMU 1

4. WRFU (3G) 3 4. PSU 3

5. GRFU (2G) / Use RRU 0 5. Battery 150 A 12 V) 4

6. DRFU (2G) 0 6. Battery Cabinet 1

7. MRFU (2G & 3G) 3 7. EMUA


8. UELP 1 8. Other (………………….)
9. UPEU 2
10. UEIU 0
11. USLP 1
12. UFLP 1
11. Fan 1
12. DDF 1
13. BBU Box 1
14. RF Cabinet 1
15. TMC Cabinet 1
16. SLPU
17. UBBP (4G)
18. Other (………………….)
* If new Site under PO MEGA2, Based on DSD, WBBP board number must be 2.

C. HARDWARE INSTALLATION CHECK ITEMS


1. Installation of Equipment
No Check content YES NO N/A
The parts of the rack should not be distorted and not affecting the equipment
1 appearance. √

The RF cable connector needs to be installed perfectly.


2 √
The existing RF cable needs to be adjusted.
3 √
Cables should be tiled with uniform spacing and moderate tightness. Cable ties
4 should be tied in a tidy way. √

The board can be plugged and unplugged smoothly. Its panel screws should have
5 appropriate tightness if they exist. √

The jumpers are properly connected according to the sector and master/diversity
6 relation, and are routed in a neat way. √
The cross RF jumper between the RFU which are in the same sector should be

7 installed perfectly.

2. Installation of Antenna and Feeder Cable


No Check content YES NO N/A
Waterproof and sealed measures for all outdoor jumpers and feeder cables should
1 be correctly adopted according to specifications. √

The feeder cables should not have obvious bending and twisting and bare copper
2 appearance. √

The connector of feeder cable is made in a standard way without any loose
3 connection. √

The connection between antenna support and tower should be reliable and firm.
4 The connection between antenna and its support should also be reliable and firm. √

The azimuth and tilt angle of the installed antenna must accord with design
5 specifications. √

The antennas mechanical down tilt angles should be correct.


6 √
When a feeder window is installed on the top of building to lead the feeder cable
7 √
into the room, it must be sealed well.
The jumpers are properly connected according to the sector and master/diversity
8 relation, and are routed in a neat way. √

The labels of communication cables, feeder cables and jumper should be stuck
and tied according to specifications. The labels should be arranged in an orderly
9 √
way with same direction.

The jumper of the antenna should be tied along the rail of the support to the steel
10 frame of the power. √

11 Jumper cable must connect tightly with the connector of the board (RFU)

The labels of the antenna system can be easily identified. The color rings are
12 stuck correctly according to the requirements. √

3. Others
No Check content YES NO N/A
The installation tools accord with the antistatic requirements.
1 √
Check that all installation and packing materials have been removed from the site
2 √
The equipment room should be neatness and tidy. Discarded packing materials
3 should be cleaned. Spare parts should be arranged in a tidy way after installation. √
C. ELECTRICAL CHECK

Type of Deployment
√ New Deployment
□Module Expansion
□Existing Power Check

No Check content YES NO N/A


Make sure the power cable from the power distribution panel to power rack
1. √
installed correctly
Measure the AC voltage on power rack available.
2. √
Number of Phases:_________
BTS Power Rack Nominal values 380Vac (A), 220Vac (B), 0Vac (C)
A 304-456V AC
L1-L2: 384 V AC L1-L3: 380 V AC L2-L3: 382 V AC
B 181-279V AC
L1-N: 219 V AC L2-N: 220 V AC L3-N: 221 V AC
C 0 V AC
N-PGND: ___0,1___V AC
NodeB Power rack Nominal values 380Vac (A), 220Vac (B), 0Vac (C)
A 304-456V AC
L1-L2:________ V AC L1-L3:________ V AC L2-L3:________ V AC
B 181-279V AC
L1-N:_________V AC L2-N:_________V AC L3-N:_________V AC
C 0 VAC
N-PGND:________ V AC
3. Measures the DC voltage on base and extension racks available : ____52.2_V DC (-40 to -60V DC)

Remarks: If 2G and 3G is combine cabinet, the power check only applies to BTS Power Rack.
D. ANTENNA AND FEEDERS INFORMATION

2G Combiners, Antennas and Feeders

Sector Combiner Type* Manufacturer Port Type UL/DL Frequency

WCDMA DCS Dual Band


Cell 0 Fingu 4 to 2 1710 – 1880 Mhz
Combiner
WCDMA DCS Dual Band
Cell 1 Fingu 4 to 2 1710 – 1880 Mhz
Combiner
WCDMA DCS Dual Band
Cell 2 Fingu 4 to 2 1710 – 1880 Mhz
Combiner
* The combiners’ information collection, only applicable to the scenario that install new combiners.

Sector Antenna Type * Height Direction Mech Tilt Elect Tilt

Cell 0 40 70 2 2

Cell 1 40 180 2 2

Cell 2 40 300 2 2
* put checkmark if applicable

Sector 0 Sector 1 Sector 2


Feeder Type 1-5/8 " 1-5/8 " 1-5/8

Feeder Length 50 50 50

Indoor Jumper Cable Length (m) 3 3 3

Outdoor Jumper Cable Length (m) 3 3 3

3G Combiners, Antennas and Feeders

Sector Combiner Type* Manufacturer Port Type UL/DL Frequency

WCDMA DCS Dual Band


Cell 0 Fingu 4 to 2 1710 – 1880 Mhz
Combiner
WCDMA DCS Dual Band
Cell 1 Fingu 4 to 2 1710 – 1880 Mhz
Combiner
WCDMA DCS Dual Band
Cell 2 Fingu 4 to 2 1710 – 1880 Mhz
Combiner
* The combiners’ information collection w, only applicable to the scenario that install new combiners.

Sector Antenna Type * Height Direction Mech Tilt Elec Tilt

Cell 0 40 80 2 2

Cell 1 40 180 2 2
Cell 2 40 300 2 2
* put checkmark if applicable

Sector 0 Sector 1 Sector 2


Feeder Type 1-5/8 " 1-5/8 " 1-5/8 "

Feeder Length 50 50 50

Indoor Jumper Cable Length (m) 3 3 3

Outdoor Jumper Cable Length (m) 3 3 3

E. SITE CLEANING

No Check content YES NO N/A


All rubbish in area Installation cleaned.
1. √

2. The rest of materials sent back to warehouse and inform person in charge. √
The site area/container keys should be available and secure.
3. √

F. HANDOVER DOCUMENTS
Yes No NA
√ □ □ Is the equipment inventory at the site in hard and soft copy?
(Attached with DN or PO)

J. SITE PHOTO CHECKLIST


√ Front view of Site or Building
√ Front view of Cabinet (2G and 3G) - door closed
√ Front view of Cabinet (2G and 3G) - door open
√ Front view of BBU Box (View off all board that Installed at BBU Box)
√ Front view of RFC Cabinet (View of All Board that Installed at RF Cabinet)
√ GSM / UMTS Antenna installed properly: Sector 0
√ GSM / UMTS Antenna installed properly: Sector 1
√ GSM / UMTS Antenna installed properly: Sector 2
√ GSM / UMTS Antenna direction (covered area) view: Sector 0
√ GSM / UMTS Antenna direction (covered area) view: Sector 1
√ GSM / UMTS Antenna direction (covered area) view: Sector 2
√ Feeder Cable laying straight on the runway and labeled
√ Feeder Jumper installed properly and labeled
√ Antenna Cable Jumper installed properly and sealed by rubber tape.
√ Tower/ Pole structure

G. CONCLUSION SUMMARY
Yes No NA
√ □ □ Does the inspection indicate that Commissioning can start?
H. FINAL DECISION
√ Accepted □Conditionally accepted □Rejected

Punch list BTS/NodeB Ran Sharing Hardware Installation ATP

Site ID 102304
Site Name SUKAMENAK

Severity
Item No.

Date to Date

Cosmetic
be Responsible
Description * Cleared** Supervisor

Minor
Major
cleared Group*

* Only fill Punch list that related to Wireless Equipment (BTS/NodeB)


** Date when deficiency cleared
Performed by:

(Vendor Name) Manage Service PT. Hutchison 3 Indonesia

Name: Name: Name:


Project Manager Roll-Out Region

Approved by:

FLM Manage Service PT. Hutchison 3 Indonesia

Name: Name:
Project Manager Operation Maintenance

PT. Hutchison 3 Indonesia

Name:
Technical Branch Manager

PICTURE BTS
View Tower View Site

View to BTS Position View BTS Closed

View Install Grounding View to BTS Open


View Jumper Installation View Combiner

View KWH View ACPDB

Antenna Installed Properly Sector 1 Feeder Cable Laying 1


Antenna Installed Properly Sector 2 Feeder Cable Laying 2

Antenna Installed Properly Sector 3 Feeder Cable Laying 3