Details of Measurement

(CPWD Code paragraph-81)


STATE: Arunachal Pradesh Division:CCD
Branch: Urban Development & Housing

Name of Work: NH52A to to Tourism office Via Election office


SH: Road from NH52A to Tourism office (Dismanteling)

Item no Particular of Work No Length Breath Height unit quantity


1 Dismantling of Cement Concrete Pavement (Dismantling of
cement concrete pavement by mechanical means using
pneumatic tools, breaking to pieces not exceeding 0.02 cum in
volume and stock piling at designated locations and disposal of
dismantled materials up to a lead of 1000 metres, stacking
serviceable and unserviceable materials separately)

1 170 6.5 0.3 cum 331.5

Dismantling of Flexible Pavements (Dismantling of flexible


pavements anddisposal of dismantled materials up to a lead of
1000 metres, stacking serviceableand unserviceable materials
2 separately
a) Bituminous courses 1 330 6.5 0.15 cum 321.75

AUPO UPO
Itanagar sub Division Itanagar sub Division
Dept of UD & Housing, Itanagar Dept of UD & Housing, Itanagar
ABSTRACT OF COST ( Dismantling)
ABSTRACT OF COST
(CPWD Code paragraph-81)
STATE: A.P Division:CCD
Branch: UD&H

Name of Work: NH52A to to Tourism office Via Election office


SH: Road from NH52A to Tourism office( Dismanteling)

Item No Particula of Work Unit Rate Qty. Amount Reamrks


1 Dismantling of Cement Concrete Pavement (Dismantling of cement concrete
pavement by mechanical means using pneumatic tools, breaking to pieces not
exceeding 0.02 cum in volume and stock piling at designated locations and disposal
of dismantled materials up to a lead of 1000 metres, stacking serviceable and
unserviceable materials separately)

cum 933 331.5 309289.5


2 Dismantling of Flexible Pavements (Dismantling of flexible pavements and
disposal of dismantled materials up to a lead of 1000 metres, stacking
serviceableand unserviceable materials separately(By mechenical Means)

a) Bituminous courses
cum 207 321.75 66602.25

Grand total for 500mtrs of road length Rs. 375891.8

AUPO UPO
Itanagar sub Division Itanagar sub Division
Dept of UD & Housing, Itanagar Dept of UD & Housing, Itanagar
ABSTRACT OF COST
(CPWD Code paragraph-81)
STATE: A.P Division:CCD
Branch: UD&H

Name of Work: NH52A to to Tourism office Via Election office


SH: RCC Road from NH52A to Tourism office
Item No Particular of work Unit Rate Quantity Amount Remark
1 Preparation of sub grade (Preparation of sub grade by excavating earth to an average item no 4.18
depth of 22.50 cm, dressing to camber and consolidating with road roller, making good (A)@ page-33 Of
the undulations etc. and disposal of surplus earth, lead upto 50 m.) APSR2007(R&B)
sqm 28 600 16800
2 Dry Lean Cement Concrete Sub- base (Construction of dry lean cement concrete Sub-
base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383,
the size of coarse aggregate not exceeding 25 mm,aggregate cement ratio not to
exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement
content not to be less than 150 kg/ cum, optimum moisture content to be determined
during trial length construction, concrete strength not to be less than 10 Mpa at 7 days,
mixed in a batching plant,transported to site, laid with a paver with electronic sensor,
compacting with 8-10 tonnes vibratory roller, finishing and curing.) item no 6.1 @
page-40 Of
cum 2267 62 140554 APSR2007(R7B)
3 Cement Concrete Pavement (Construction of un-reinforced, dowel jointed, plain
cement concrete pavement over a prepared sub base with 43 grade cement @ 400 kg
per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse
aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved
mix design, transported to site, laid with a fixed form or slip form paver, spread,
compacted and finished in a continuous operation including provision of contraction,
expansion, construction and longitudinal joints, joint filler, separation membrane,
sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as
approved, curing compound, finishing to lines and grades as per drawing ) item no 6.2 @
page-40 Of
cum 4999 120 599880 APSR2007(R7B)
item no 13.6 @
4 Supplying, fitting and placing HYSD bar reinforcement in super-structure page-75 Of
complete as per drawing and technical specifications Tonne 48091 5.25 252456.5 APSR2007(R&B)
item no 10(a) @
5 Providing and laying up to floor two level cement 1 : 2 : 4 (1 cement : 2 coarse sand : 4 page-26 Of
stone aggregate 20 mm nominal size) including centring shuttering in : APSR2007(B)
Note: Work at or near ground level. cum 4164.9 10.00 41649
Total Rs 1051340
Cost per Meter Rs 10513.4
Add for carriage of material 356503.8 As per Annex I
Cost for 500mtrs Rs 5613201

AUPO UPO
Itanagar sub Division Itanagar sub Division
Dept of UD & Housing, Itanagar Dept of UD & Housing
Itanagar.
Details of Measurement
(CPWD Code paragraph-81)
STATE: Arunachal Pradesh Division:CCD
Branch: Urban Development & Housing

Name of Work: NH52A to to Tourism office Via Election office


SH: RCC Road from NH52A to Tourism office

Name of Work: Beautification of Internal Road


SH: Road from NH52A to Tourism office, Itanagar
Total length of road 500 m
Length of concrete panel 5 m
width of concrete panel 3 m
Length of CC pavement Consider for estimation 100 m
No. of CC panel per 100m length panel 40 nos
No of longitudinal reniforcement per panel 20 nos
Length of longitudinal reinforcement 4.99 m
No. of transverse reinforcement per panel 25 nos
Length of transvere reinforcement 2.99 m

Item No Particular of work no length breath hight unit quantity Remark


1 Preparation of sub grade (Preparation of sub grade by excavating
earth to an average depth of 22.50 cm, dressing to camber and
consolidating with road roller, making good the undulations etc. and
disposal of surplus earth, lead upto 50 m.)
1 100 6 sqm 600
2 Dry Lean Cement Concrete Sub- base (Construction of dry lean
cement concrete Sub- base over a prepared sub-grade with coarse
and fine aggregate conforming to IS: 383, the size of coarse
aggregate not exceeding 25 mm,aggregate cement ratio not to
exceed 15:1, aggregate gradation after blending to be as per table
600-1, cement content not to be less than 150 kg/ cum, optimum
moisture content to be determined during trial length construction,
concrete strength not to be less than 10 Mpa at 7 days, mixed in a
batching plant,transported to site, laid with a paver with electronic
sensor, compacting with 8-10 tonnes vibratory roller, finishing and
curing.)

1 100 6.2 0.1 cum 62


3 Cement Concrete Pavement (Construction of un-reinforced, dowel
jointed, plain cement concrete pavement over a prepared sub base
with 43 grade cement @ 400 kg per cum, coarse and fine aggregate
conforming to IS 383, maximum size of coarse aggregate not
exceeding 25 mm, mixed in a batching and mixing plant as per
approved mix design, transported to site, laid with a fixed form or
slip form paver, spread, compacted and finished in a continuous
operation including provision of contraction, expansion, construction
and longitudinal joints, joint filler, separation membrane, sealant
primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures
as approved, curing compound, finishing to lines and grades as per
drawing )

1 100 6 0.2 cum 120


4 Supplying, fitting and placing HYSD bar reinforcement in super-
structure complete as per drawing and technical specifications

a) longitudinal bar ( 8mm dia. Hysd bar) 800 4.99 @ 0.395kg/M Kg 1576.84
b) transverse bar ( 8mm dia. Hysd bar) 1000 2.99 @ 0.395kg/M Kg 1181.05
c) Dowel Bar (20mm dia bar) 1980 0.45 @ 2.470kg/M Kg 2200.77
d) Tie bar(10mm) 220 0.3 @ 0.620kg/M Kg 40.92
total 4999.58
add 5% wastage 249.979
G/total 5249.56 Kg
Say 5.25 tonnes
5 Plain Cement Concrete shouldering 1:2:4 2 100 0.5 0.1 cum 10

AUPO UPO
Itanagar sub Division Itanagar sub Division
Dept of UD & Housing, Itanagar Dept of UD & Housing, Itanagar
Theoritical Consumption statement

Name of Work: NH52A to to Tourism office Via Election office Division: Itanagar
SH: RCC Road from NH 52A to Tourism office
Aggregate
Description of Qty. Cement Aggregate 20mm Sand
Sl. No. Unit 40mm
Items ececuted T.C Qty. T.C Qty. T.C Qty. T.C Qty.

1 Dry lean
concrete sub- 310.00 Cum 0.220 68.20 - - 0.24 74.40 0.470 145.70
base in 1:3:6
RCC pavement
2 600.00 Cum 0.400 240.00 - - 0.85 510.00 0.425 255.00
in 1:1.5:3 CC

PCC shouldering
3 216.00 Cum 0.320 69.12 - - 0.22 47.52 0.445 96.12
in 1:2:4

Total 377.32 MT - Cum 631.92 Cum 496.82

AUPO UPO
Itanagar sub Division Itanagar sub Division
Dept of UD & Housing, Itanagar Dept of UD & Housing, Itanagar
Carriage Analysis statement Anex.- I

Name of Work: NH52A to to Tourism office Via Election office


SH : RCC road from NH52A to Tourism office, Itanagar

Distance
Sub-head and cover(K Rate(Rs./
Sl No items of work Lead m) Quantity Unit unit/km Amount (in Rs.) Remarks

1 Cement Up to 5.00km 1 377.32 MT 61.31 23133.49


( Lead 30Km ) 5.00to 10.00km 5 377.32 MT 4.99 9414.13
10.00to 20.00km 10 377.32 MT 4.21 15885.17
20.00to 30.00km 10 377.32 MT 3.63 13696.72

2 Steel Up to 5.00km 1 26.248 MT 61.31 1609.25


( Lead 30Km ) 5.00to 10.00km 5 26.248 MT 4.99 654.88
10.00to 20.00km 10 26.248 MT 4.21 1105.03
20.00to 30.00km 10 26.248 MT 3.63 952.79

4 Aggregate 20mm Up to 5.00km 1 631.92 cum 122.62 77486.03


( Lead 20Km ) 5.00to 10.00km 5 631.92 cum 9.99 31564.4
10.00to 20.00km 10 631.92 cum 8.44 53334.05

5 Sand Up to 5.00km 1 496.82 cum 122.62 60920.07


( Lead 20Km ) 5.00to 10.00km 5 496.82 cum 9.99 24816.16
10.00to 20.00km 10 496.82 cum 8.44 41931.61

Total Rs. 356,503.78

AUPO UPO
Itanagar sub Division Itanagar sub Division
Dept of UD & Housing, Itanagar Dept of UD & Housing, Itanagar
ABSTRACT OF COST

STATE: Arunachal Pradesh Div:CCD


Branch: Urban Development & Housing
Name of Work: NH52A to to Tourism office Via Election office
SH: Road from NH52A to Tourism office Itanagar

Sl. No Particular Quantity Amount Remarks

1 Dismantling of existing Pavement 500 meter Rs. 375,891.75

2 RCC Pavement 500 meter Rs. 5,613,201.49

3 Road side Drain with cover 800meter Rs. 1,824,183.21

4 FoothPath with side ralling over cover slab 995m Rs. 3,478,606.53
Total Rs. 11,291,882.98
Add 3% contingencies Rs. 338,756.49
1%cess Rs. 112,918.83
4% VAT Rs. 451,675.32
G/Total Rs. 12,195,233.62
Say Rs. 11,300,000.00

UPO ASW
Itanagar sub Division Capital Complex Division
Dept of UD & Housing, Itanagar Dept of UD & Housing, Itanagar

DY. Director
Capital Complex Division
Dept of UD & Housing, Itanagar
ABSTRACT OF COST
(CPWD Code paragraph-81)
STATE: A.P Division:CCD
Branch: UD&H

Name of Work: NH52A to to Tourism office Via Election office


SH: Road from NH52A to Tourism (Road side drain with cover)
Item No PARTICULAR OF WORK unit quantity Rate Amount Remark
1 APSR
Earth work in excavation in all kinds of soil (excluding soil containing 50% or 2007
more of shingle or small size boulders upto 30 cm size, saturated soil and (building)
rock) including banking in 20 cm layers and breaking clods, ramming and
dressing up for the purpose of making embankments or filling up ground
depressions, lead upto 50 m and lift upto 1.50 m. cum 5.50 47.00 258.5
2
Providing and laying in foundations and plinth cement concrete 1 : 5 : 10 (1
cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size)
excluding the cost of centring and shuttering. cum 1.00 1924.00 1924
3 Full Brick work with best available local bricks in foundations and plinth in
cement mortar 1:4 (1 cement : 4 fine sand). cum 2.30 3050.40 7015.92
4 Reinforced cement concrete in suspended floors, roofs, landings and
balconiesupto floor two level including finishing and plastering the exposed
surface with cement mortar 1 : 3 (1 cement : 3 fine sand) of thickness not
xceeding 6 mm togive a smooth and even surface but excluding cost of
centring and shuttering ndreinforcement with 1 : 2 : 4 (1 cement : 2 coarse
sand : 4 stone aggregate 20 mm nominal size).
cum 1.20 3988.00 4785.6
4 Reinforcement of RCC work including bending, binding and placing in
position complete.
a) cold twisted bar kg 126.73 42.90 5436.717
5 12 mm cement plastering in 1:4CM sqm 19.6 80.1 1569.96
6 Neat cement punning sqm 19.6 25.1 491.96
Cost per 10 meter of length Rs 21482.66
Cost per meter of length Rs 2148.266
Add cost of carriage for material As per
105570.7 Annex II
cost for 800meter of length Rs 1824183

AUPO UPO
Itanagar sub Division Itanagar sub Division
Dept of UD & Housing, Itanagar Dept of UD & Housing, Itanagar
Details of Measurement
(CPWD Code paragraph-81)
STATE: A.P Division:CCD
Branch: UD&H

Name of Work: NH52A to to Tourism office Via Election office


SH: Road from NH52A to Tourism office( Drain with cover slab)
Length of drain 800 m

Item
No particular of work No. length breath height unit quantity
1 Earth work in excavation in soils containing 50%
or more of shingle or small size boulders upto
30 cm size including banking in 20 cm layers
and breaking clods, ramming and dressing up
for the purpose of making embankments or
filling up ground depressions lead upto 50 m
and lift
upto 1.50 m.
1 10 1.1 0.5 cum 5.50
2
Providing and laying in foundations and plinth
cement concrete 1 : 5 : 10 (1 cement : 5 coarse
sand : 10 graded stone aggregate 40 mm
nominal size) excluding the cost of centring and
shuttering. 1 10 1 0.1 cum 1.00
3 Full Brick work with best available local bricks
in foundations and plinth in cement mortar 1:4
(1 cement : 4 fine sand). 2 10 0.23 0.5 cum 2.30
4 Reinforced 1 : 2:4cement concrete in
suspended floors, roofs, landings and balconies
upto floor two level including finishing and
plastering the exposed surface with cement
mortar 1 : 3 (1 cement : 3 fine sand) of
thickness not exceeding 6 mm to give a smooth
an
a)Drain cover slab 10 1.2 1 0.1 cum 1.20

5 Reinforcement of RCC work including bending,


binding and placing in position complete.

a)Drain cover slab


i) Longitudinal reinforcement( 8mm dia HSYD
Bar) 70 1.15 @ 0.395kg/M Kg 31.80

ii) Transverse reinforcement bar( 8mm dia bar) 80 0.95 @ 0.395kg/M Kg 30.02
Total 61.82
Add 5% for wastage 3.09
G/total 126.73
6 12 mm cement plastering in 1:4CM
top of drain 2 10 0.23 - sqm 4.6
inside 2 10 - 0.55 sqm 11
bed of drain 1 10 0.4 - sqm 4
total 19.6
7 Neat cement punning
top of drain 2 10 0.23 - sqm 4.6
inside 2 10 - 0.55 sqm 11
bed of drain 1 10 0.4 - sqm 4
total 19.6

AUPO UPO
Itanagar sub Division Itanagar sub Division
Dept of UD & Housing, Itanagar Dept of UD & Housing, Itanagar
Theoritical Consumption statement

Name of Work: NH52A to to Tourism office Via Election office


SH: Road from NH52A to Tourism office( road side drain with cover

Name of work: C/o compound wall at childrens's park cum community centre at P-sector Itanagar Division: Itanagar
Descripti Cement Aggregate 40mm Aggregate 20mm Sand
Qty.
Sl. No. on of Unit
ececuted T.C Qty. T.C Qty. T.C Qty. T.C Qty.
Items
CC
1 80.00 Cum 0.130 10.40 0.65 52.00 - - 0.470 37.60
1:5:10

Full brick
2 work in 184.00 Cum 0.095 17.48 - - - - 0.267 49.13
1:4

RCC
3 work in 96.00 Cum 0.220 21.12 - - 0.24 23.04 0.470 45.12
1:2:4
12 mm
cement
6 plasterin 1568.00 sqm 0.05470 85.77 - - - - 0.030 47.04
g in
1:4CM
Neat
6 cement 1568.00 sqm 0.009 13.33 0.02 31.36 0.015 24.15
punning
Total 148.10 MT 52.00 Cum 54.40 Cum 203.04

AUPO UPO
Itanagar sub Division Itanagar sub Division
Dept of UD & Housing, Itanagar Dept of UD & Housing, Itanagar
Carriage Analysis statement Anex. II

Name of Work: NH52A to to Tourism office Via Election office


SH: Road from NH52A to Tourism office( road side drain with cover Division: Itanagar

Dista
nce
Sl Sub-head and cover Rate(Rs./u Amount (in
No items of work Lead (Km) Quantity Unit nit/km Rs.) Remarks

1 Cement Up to 5.00km 1 148.10 MT 61.31 9079.86


( Lead 30Km )
5.00to 10.00km 5 148.10 MT 3695.04
4.99
10.00to 20.00km 10 148.10 MT 4.21 6234.91
20.00to 30.00km 10 148.10 MT 3.63 5375.94

2 Steel Up to 5.00km 1 10.138 MT 61.31 621.57


( Lead 30Km ) 5.00to 10.00km 5 10.138 MT 4.99 252.94
10.00to 20.00km 10 10.138 MT 4.21 426.81
20.00to 30.00km 10 10.138 MT 3.63 368.01

3 Aggregate
Up to 5.00km 1 52.00 cum 122.62 6376.24
40mm
( Lead 20Km ) 5.00to 10.00km 5 52.00 cum 9.99 2597.4
10.00to 20.00km 10 52.00 cum 8.44 4388.8

4 Aggregate
Up to 5.00km 1 54.40 cum 122.62 6670.53
20mm
( Lead 20Km ) 5.00to 10.00km 5 54.40 cum 9.99 2717.28
10.00to 20.00km 10 54.40 cum 8.44 4591.36

5 Sand Up to 5.00km 1 203.04 cum 122.62 24896.18


( Lead 20Km ) 5.00to 10.00km 5 203.04 cum 9.99 10141.61
10.00to 20.00km 10 203.04 cum 8.44 17136.17

Total Rs. 105,570.65

AUPO UPO
Itanagar sub Division Itanagar sub Division
Dept of UD & Housing, Itanagar Dept of UD & Housing, Itanagar
Details of Measurement
(CPWD Code paragraph-81)
STATE: A.P Division:CCD
Branch: UD&H

Name of Work: NH52A to to Tourism office Via Election office


SH: Road from NH52A to Tourism office( Footpath wit
Length of Footpath 995 m
Ite
m
No Particulars of work No Length Breath Height unit Qty Remarks
1

Earth work in excavation in all kinds of soil (excluding


soil containing 50% or more of shingle or small size
boulders upto 30 cm size, saturated soil and rock)
including banking in 20 cm layers and breaking clods,
ramming and dressing up for the purpose of making
embankments or filling up ground depressions, lead
upto 50 m and lift upto 1.50 m. 3 0.3 0.3 0.3 cum 0.081
2
Providing and laying in foundations and plinth cement
concrete 1 : 5 : 10 (1 cement : 5 coarse sand : 10 graded
stone aggregate 40 mm nominal size) excluding the cost
of centring and shuttering. 3 0.3 0.3 0.3 cum 0.081
3 Painting G.I. pipes and fittings with white paint over a
coat of ready mixed priming coat both of approved
quality for new work.
1 10 - - meter 10
4 Providing and fixing MS ralling of required design,
priming and direction of engineer-in-charge MS flat,
square or round bars with round headed bolts and nuts
or by screws.
a) Plain grill.
16mm MS square bar 30 0.85 @ 2.010kg/M Kg 51.26
20mmX4mm MS flat 40 0.2 @ 0.630kg/M kg 5.04
30mmX5mm MS flat 2 2 @ 1.200kg/M kg 4.80
Total 61.10
Add 5 % wastage 3.05
G/Total 64.15 Kg
5 Providing and fixing interlocking Tiles over footpath 1 4 1.2 - sqm 4.8 sqm

AUPO UPO
Itanagar sub Division Itanagar sub Division
Dept of UD & Housing, Itanagar Dept of UD & Housing, Itanagar
Abstract of cost
(CPWD Code paragraph-81)
STATE: A.P Division:CCD
Branch: UD&H

Name of Work: NH52A to to Tourism office Via Election office


SH: Road from NH52A to Tourism office
Item No Particulars of work Unit Rate Qty Amount Reamrks
1
Earth work in excavation in all kinds of soil (excluding soil containing 50% or
more of shingle or small size boulders upto 30 cm size, saturated soil and rock)
including banking in 20 cm layers and breaking clods, ramming and dressing up
for the purpose of making embankments or filling up ground depressions, lead
upto 50 m and lift upto 1.50 m. cum 80 0.081 6.48
2
Providing and laying in foundations and plinth cement concrete 1 : 5 : 10 (1
cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size)
excluding the cost of centring and shuttering. cum 47.00 0.081 3.807
3 Providing and fixing GI pipes complete with GI fittings including trenching and
refilling etc (external work).
Mtrs 365.8 10 3658
4 Providing and fixing MS ralling of required design, priming and direction of
engineer-in-charge MS flat, square or round bars with round headed bolts and
nuts or by screws.

Kg 52.7 64.15 3380.69


5 Chequered terrazzo tiles 22 mm thick with marble chips of sizes upto 6mm in
floors on 25 mm thick bed mortar 1 : 3 (1 cement : 3 coarse sand) jointed with
neat cement slurry mixed with pigment to match the shade of the tiles including
rubbing and polishing complete:b) Medium shade using approximately 50%
white cement and 50% ordinary cement.
Sqm 1438.8 4.80 6906.24
Cost per 4 meter Rs 13948.74
Cost Per 1 meter running length 3487
Add for carriage of materials 8858 Annex-III
Cost of 995meter length 3478606.53

AUPO UPO
Itanagar sub Division Itanagar sub Division
Dept of UD & Housing, Itanagar Dept of UD & Housing, Itanagar
Theoritical Consumption statement

Name of Work: NH52A to to Tourism office Via Election office


SH: Road from NH52A to Tourism office( road side drain with cover) Division: Itanagar

Description of Qty. Cement Aggregate 40mm Aggregate 20mm Sand


Sl. No. Unit
Items ececuted T.C Qty. T.C Qty. T.C Qty. T.C Qty.
1 CC 1:5:10 20.15 Cum 0.130 2.62 0.65 13.10 - - 0.470 9.47
Total 2.62 MT 13.10 Cum Cum 9.47

AUPO UPO
Itanagar sub Division Itanagar sub Division
Dept of UD & Housing, Itanagar Dept of UD & Housing, Itanagar
Carriage Analysis statement Anex. III

Name of Work: NH52A to to Tourism office Via Election office Division: Itanagar
SH: Road from NH52A to Tourism office( road side drain with cover)

Sub-head
and items of Distance Rate(Rs./uni
Sl No work Lead cover(Km) Quantity Unit t/km Amount (in Rs.) Remarks

1 Cement Up to 5.00km 1 2.62 MT 61.31 160.59


( Lead
5.00to 10.00km 5 2.62 MT 65.35
30Km ) 4.99
10.00to 20.00km 10 2.62 MT 4.21 110.27
20.00to 30.00km 10 2.62 MT 3.63 95.08

2 Steel Up to 5.00km 1 15.957 MT 61.31 978.34


( Lead 30Km ) 5.00to 10.00km 5 15.957 MT 4.99 398.13
10.00to 20.00km 10 15.957 MT 4.21 671.8
20.00to 30.00km 10 15.957 MT 3.63 579.25

3 Aggregate
Up to 5.00km 1 13.10 cum 122.62 1605.92
20mm
( Lead 20Km )
5.00to 10.00km 5
13.10 cum 9.99 654.18
10.00to 20.00km 10 13.10 cum 8.44 1105.36

5 Sand Up to 5.00km 1 9.47 cum 122.62 1161.2


( Lead 20Km ) 5.00to 10.00km 5 9.47 cum 9.99 473.02
10.00to 20.00km 10 9.47 cum 8.44 799.26

Total Rs. 8,857.75

AUPO UPO
Itanagar sub Division Itanagar sub Division
Dept of UD & Housing, Itanagar Dept of UD & Housing, Itanagar