QT TOP COVER REPLACEMENT

PER MANDAYS
DISMANTLING & REMOVE QT OUTLET HEADER 4
1
CLEANING THE MS TOP FLANGE & READY PLACING HEADER
ERECTION OF NEW HEADER 6
INSTALLATION OF BEND & ELBOW 90 2
JOINING WORK OF FRP 4
COMMISSIONING 3
ADDITIONAL BUFFER 3
TOTAL NO. OF DAYS REQUIRED 23
TOTAL NO. OF MANPOWER ASSIGNED 12
FITTER 2 2600 5200
RIGGER 2 3000 6000
METAL FITTER 1 3000 3000
MOULDER 4 2200 8800
HELPER 3 2000 6000
PER DAY MAN POWER EXPENSE 29000 29000
TOTAL MANPOWER RATE FOR ASSEMBLE THE QT TOP
667000
COVER HEADER
TOTAL RAW MATERIAL RATE FOR ASSEMBLE THE QT TOP
235000
COVER HEADER
TOTAL COST FOR ERECTION OF QT HEADER 902000

QT HEADER SUCTION & DISCHARGE LINE REPLACEMENT


PER MANDAYS
DISMANTLING & REMOVE PIPING 2
MEASURING & ASSEMBLE OF THE LINE 4
ERECT THE SUCTION & DISCHARGE PIPING 3
COMMISSIOING 1
TOTAL MANDAYS REQUIRED 10
TOTAL MANPOWER REQUIRED 8
FITTER 2 2600 5200
RIGGER 1 3000 3000
METAL FITTER 0 3000 0
MOULDER 5 2200 11000
HELPER 3 2000 6000
PER DAY MAN POWER EXPENSE 25200 25200
TOTAL MANPOWER RATE FOR ASSEMBLE THE QT TOP
252000
COVER HEADER
TOTAL RAW MATERIAL RATE FOR ASSEMBLE THE QT TOP
55000
COVER HEADER
TOTAL COST FOR ERECTION OF SUCTION & DISCHARGE
307000
PIPING
MRT OUTLET TO DT INLET DUCT REPLACEMENT INCLUDING GAS TO ACID VALVE INLET DUCT
MODIFICATION
PER MANDAYS
DISMANTLING & REMOVE TEE 4
REPLACING OF NEW DUCT -TWIN ELBOW 5
MODIFICATIONS WORKS 4
REMOVAL OF COMPLETE DUCT FROM GAS TO ACID ALVE
5
TO D INLET
ERECTION OF NEW DUCT AND CONNECTION WITH
7
DILUTION AIR LINE DUCTING
COMPLETE PADDING & FINISING 4
COMMISSIONING 2
TOTAL MANDAYS REQUIRED 31
TOTAL MANPOWER REQUIRED 8
FITTER 4 2600 10400
RIGGER 3 3000 9000
METAL FITTER 2 3000 6000
MOULDER 7 2200 15400
HELPER 4 2000 8000
PER DAY MAN POWER EXPENSE 48800 48800
TOTAL MANPOWER RATE FOR ASSEMBLE THE QT TOP
1512800
COVER HEADER
TOTAL RAW MATERIAL RATE FOR ASSEMBLE THE QT TOP
324555
COVER HEADER
TOTAL COST FOR ERECTION OF SUCTION & DISCHARGE
1837355
PIPING

ERECTION & COMMISSIONING.


QT TOP COVER REPLACEMENT 902000
307000
QT HEADER SUCTION & DISCHARGE LINE REPLACEMENT

MRT OUTLET TO DT INLET DUCT REPLACEMENT INCLUDING 1837355


GAS TO ACID VALVE INLET DUCT MODIFICATION
GRANT TOTAL 3046355

NOTE:-
1) NOT ALL WORKERS ARE NOT 10TH PASSED.
2) NO CRANE / HYDRA IN POLYPLAST SCOPE.
3) NO PLATFORM WORKS / NO PRIMARY METAL SUPPORT WORKS IN PPCL SCOPE
4) ERECTION MATERIALS FROM STORE TO ERECTION LOCATION WILL BE HZL SCOPE.
5) NO FASTNERS , NO GASKETS SUPPLY WILL NOT BE OUR SCOPE.
6) ABOVE MENTIONED MANDAYS ARE ASSUMED IF THE MANDAYS INCREASE THAT REFLECT IN
THE FINAL BILLING.