PER MANDAYS
DISMANTLING & REMOVE QT OUTLET HEADER 4
1
CLEANING THE MS TOP FLANGE & READY PLACING HEADER
ERECTION OF NEW HEADER 6
INSTALLATION OF BEND & ELBOW 90 2
JOINING WORK OF FRP 4
COMMISSIONING 3
ADDITIONAL BUFFER 3
TOTAL NO. OF DAYS REQUIRED 23
TOTAL NO. OF MANPOWER ASSIGNED 12
FITTER 2 2600 5200
RIGGER 2 3000 6000
METAL FITTER 1 3000 3000
MOULDER 4 2200 8800
HELPER 3 2000 6000
PER DAY MAN POWER EXPENSE 29000 29000
TOTAL MANPOWER RATE FOR ASSEMBLE THE QT TOP
667000
COVER HEADER
TOTAL RAW MATERIAL RATE FOR ASSEMBLE THE QT TOP
235000
COVER HEADER
TOTAL COST FOR ERECTION OF QT HEADER 902000
NOTE:-
1) NOT ALL WORKERS ARE NOT 10TH PASSED.
2) NO CRANE / HYDRA IN POLYPLAST SCOPE.
3) NO PLATFORM WORKS / NO PRIMARY METAL SUPPORT WORKS IN PPCL SCOPE
4) ERECTION MATERIALS FROM STORE TO ERECTION LOCATION WILL BE HZL SCOPE.
5) NO FASTNERS , NO GASKETS SUPPLY WILL NOT BE OUR SCOPE.
6) ABOVE MENTIONED MANDAYS ARE ASSUMED IF THE MANDAYS INCREASE THAT REFLECT IN
THE FINAL BILLING.