Contract No:
7200035001
Approved
Prepared By: Checked By: Reviewed By:
By:
Marafiq Project
Coordinating Department
Jonathan Camba George Nehme Amr Mustafa Zaki Eng. Malik Hasnain Abdulkarim Mohammed
(Nesma HSE-LEAD) (PM) (PM) (PMC-HSE) Al-Mobayyedh
Note: Marafiq Procedures shall supersede in case of any confusion and short comes in Nesma Program
INTEGRATED SECURITY SYSTEM &
ACCESS CONTROL @ MARAFIQ – JUBAIL
Date Issued: Page 2 of 14
13th January 2019
SITE SECURITY PLAN
Rev. 01
CONTENTS
Note: Marafiq Procedures shall supersede in case of any confusion and short comes in Nesma Program
INTEGRATED SECURITY SYSTEM &
ACCESS CONTROL @ MARAFIQ – JUBAIL
Date Issued: Page 3 of 14
13th January 2019
SITE SECURITY PLAN
Rev. 01
1. INDUCTION
The proposed project is to upgrade a security system and access control for
Marafiq SWC Facilities. Nesma scope includes Installation of New Security Class 4
and Class 1 fence, Installation of CCTV system, Construction of new Security Gates
and Security Buildings. NESMA Trading is awarded this Contract as Main
Contractor.
4. DEFINITIONS
Marafiq Premises- The whole area for the core business (operating plants,
buildings and off-site facilities supporting plant operations) that may or may not be
fenced, including pipelines/tank terminals, the Administration/ other buildings and
facilities in that area. The facilities may be within one or several sites.
Laydown Yard- A place located near or at the construction site that is for the
receipt, storage and partial assembly of the project equipment and materials to be
installed or constructed
Jubail Site Office- A place where site offices are located
Note: Marafiq Procedures shall supersede in case of any confusion and short comes in Nesma Program
INTEGRATED SECURITY SYSTEM &
ACCESS CONTROL @ MARAFIQ – JUBAIL
Date Issued: Page 4 of 14
13th January 2019
SITE SECURITY PLAN
Rev. 01
5. RESPONSIBILITIES
Note: Marafiq Procedures shall supersede in case of any confusion and short comes in Nesma Program
INTEGRATED SECURITY SYSTEM &
ACCESS CONTROL @ MARAFIQ – JUBAIL
Date Issued: Page 5 of 14
13th January 2019
SITE SECURITY PLAN
Rev. 01
5.4 Employees:
Note: Marafiq Procedures shall supersede in case of any confusion and short comes in Nesma Program
INTEGRATED SECURITY SYSTEM &
ACCESS CONTROL @ MARAFIQ – JUBAIL
Date Issued: Page 6 of 14
13th January 2019
SITE SECURITY PLAN
Rev. 01
6. REQUIREMENTS
Nesma will provide temporary fencing to secure the Work Site prior to remove the
existing fence, will safeguard the area assigned to it, and will prevent access to adjoining
property of Marafiq. NESMA will comply with HCIS standard.
NESMA will provide in consultation with Marafiq, an adequate, continuous, and effective
guard force to the Marafiq premises under this project including Jubail Site Offices and
Laydown Yards.
NESMA will maintain a list of the names and address of its Subcontractors, field
employees of NESMA or its Subcontractors, or other who have performed or are performing
work on the Work site. The list shall be available for MARAFIQ review.
NESMA will require that its employees and those of its vendors and Sub-Contractors,
and all others permitted by NESMA to enter the Work Site comply with MARAFIQ
regulations and requirements. All access to the Work site shall be via routes prescribed by
MARAFIQ and no deviations from these routes shall be permitted.
Note: Marafiq Procedures shall supersede in case of any confusion and short comes in Nesma Program
INTEGRATED SECURITY SYSTEM &
ACCESS CONTROL @ MARAFIQ – JUBAIL
Date Issued: Page 7 of 14
13th January 2019
SITE SECURITY PLAN
Rev. 01
7.5. VISITORS
Visitor admission to the site office will require permission to enter by the NESMA
management.
A visitor passes/temporary ID must be submitted Security Gate prior to exiting
the gates.
Visitors will be accompanied while on site or the lay-down facilities. Visitors
must have the required personal protective equipment while being on site.
Note: Marafiq Procedures shall supersede in case of any confusion and short comes in Nesma
Program
INTEGRATED SECURITY SYSTEM &
ACCESS CONTROL @ MARAFIQ – JUBAIL
Date Issued: Page 8 of 14
13th January 2019
SITE SECURITY PLAN
Rev. 01
Note: Marafiq Procedures shall supersede in case of any confusion and short comes in Nesma
Program
INTEGRATED SECURITY SYSTEM &
ACCESS CONTROL @ MARAFIQ – JUBAIL
Date Issued: Page 9 of 14
13th January 2019
SITE SECURITY PLAN
Rev. 01
All tools and materials, other than trash, that is removed from the project must
be accompanied by a material exit pass. This Pass shall obtain from storekeeper on
site office. All trash that is removed from site will be checked by security to verify the
content.
All packages for delivery to personnel on site office and laydown yards shall be
inspected by the security guards at the access gates. The addressee shall be
informed about the arrival of the package prior to inspection. After inspection, the
package may be collected by the addressee, or stored in the Security office,
depending on the addressee’s advice or the contents of the package.
All incoming deliveries of supplies, materials and equipment for the project at
site office shall be accompanied by a material entry pass, or a delivery note, if from
a vendor.
Prior to bringing the hazardous chemicals, the communication shall be
conducted with Nesma Safety department and relevant department.
Security will examine the material and/or equipment and compare with the
delivery note or material entry pass and notify site management of the delivery.
Security will retain a copy of the material entry pass or delivery note. Delivery
materials will have to be escorted from the main gates by a representative, to the
warehouse or its final destination.
Note: Marafiq Procedures shall supersede in case of any confusion and short comes in Nesma
Program
INTEGRATED SECURITY SYSTEM &
ACCESS CONTROL @ MARAFIQ – JUBAIL
Date Issued: Page 10 of 14
13th January 2019
SITE SECURITY PLAN
Rev. 01
8. TRAFFIC REGULATIONS
8.1.1. DRIVER’S LICENSE
Motor vehicle drivers and equipment operators shall be qualified and licensed
in accordance with the regulations of Saudi Law. Vehicle drivers will be in
possession of a valid Saudi driver’s license and equipment operators will be in
possession of a valid Saudi equipment operator license specific to the type of
equipment operated and a competency certificate issued by management.
8.1.2. WARNING AND BEACON LIGHTS
Beacon lights are mandatory for all heavy vehicles on the site. Flashing and
warning lights shall place on construction area and blind spot area during night
time. Red flags shall be used during hours of daylight and red lights during the
hours of darkness on any load that extends beyond the front, side, or rear of any
vehicle.
8.1.3. TRAFFIC SIGNS
All traffic signs and signals, whether fixed or portable, shall be obeyed, and
drivers shall cooperate with representatives appointed to direct traffic.
8.1.4. SPEED LIMITS
All vehicles shall be operated within the 30-kilometer per hour posted speed
limits on the project and 20kph loaded for heavy equipments and in site office
8.1.5. WALKS AND ROADWAYS
All personnel and/or subcontractors will use only designated walks and
roadways, on the slope side of the road opposite to water in canal area, when
entering or leaving the job site, when moving from one area to another, or when
obtaining material. The use of short cuts or undesignated pathways is prohibited.
Entry and exit gates at laydown yard and site offices shall be clear from pedestrian,
personnel and visitors shall use the side of the gate for access.
8.1.6. DRIVING AND PARKING
Vehicles shall be driven on the right side of street. Parking will be permitted in
designated areas only. Vehicles shall not be parked in such a manner as to slow
down, hinder, or interfere with the free flow of traffic. Vehicles shall not be parked
so as to block or interfere with the use of fire hydrants or fire equipment. Vehicles
shall not be left unattended with the motor running.
Vehicles parked on site shall be left open with the keys in the ignition switch
should it be necessary to move it in case of an emergency.
8.1.7. RIGHT OF WAY
All motor vehicles shall give right-of-way to pedestrians, ambulances, and
firefighting equipment and other emergency vehicles. All drivers of motor vehicles
shall practice extra ordinary driving courtesy.
Note: Marafiq Procedures shall supersede in case of any confusion and short comes in Nesma
Program
INTEGRATED SECURITY SYSTEM &
ACCESS CONTROL @ MARAFIQ – JUBAIL
Date Issued: Page 11 of 14
13th January 2019
SITE SECURITY PLAN
Rev. 01
8.1.8. PASSENGERS
Passengers shall be limited to the number according to the design of the
vehicle and manufacturer’s specification and the vehicle shall not be overcrowded.
Drivers of motor vehicles shall not permit passengers to ride on fenders,
running boards, tops, or bumpers of motor vehicles and in the back of pick-up
trucks. Passengers shall keep all parts of their bodies inside the cab or body of
vehicles and must be seated while vehicle is in motion. Tailgates must be kept
closed. Passengers shall not get on or off a vehicle while it is in motion.
Note: Marafiq Procedures shall supersede in case of any confusion and short comes in Nesma
Program
INTEGRATED SECURITY SYSTEM &
ACCESS CONTROL @ MARAFIQ – JUBAIL
Date Issued: Page 12 of 14
13th January 2019
SITE SECURITY PLAN
Rev. 01
9. SECURITY OFFICER
NESMAS shall appoint a security officer who shall administer the guard force and be
responsible for the Work Site security function, including the following:
Identification of guard posts with limits of the posts and hours of manning.
Identification (badge and pass) system for site personnel, visitors, tours, vehicles,
materials receipts (gate passes), etc. including inspection and identification of same when
leaving Work Site.
The security officer shall be responsible for maintenance of the following records:
Chronological record of security events by shifts.
Key log for buildings when emergency key at Guard Supervisor post is issued.
Note: Marafiq Procedures shall supersede in case of any confusion and short comes in Nesma
Program
INTEGRATED SECURITY SYSTEM & ACCESS CONTROL @ MARAFIQ - JUBAIL
OLD
SECURITY
LAYDOWN MOHAMMED ZAMAN (6pm-6am) 0580138706
YARD
Note: Marafiq Procedures shall supersede in case of any confusion and short comes in Nesma Program
INTEGRATED SECURITY SYSTEM &
ACCESS CONTROL @ MARAFIQ – JUBAIL
Date Issued: Page 14 of 14
13th January 2019
SITE SECURITY PLAN
Rev. 01
Jonathan Camba
HSE Supervisor
(0553269239)
Marafiq Security
013 343 1111
(Call this hotline in case of critical
security situation and all contacts
above not available)
Note: Marafiq Procedures shall supersede in case of any confusion and short comes in Nesma
Program