Beruflich Dokumente
Kultur Dokumente
February 2017
ECCN EAR99
DEM1
All rights reserved. No part of this document may be reproduced, stored in a retrieval system, published or transmitted, in any form or by any means, without the prior
written permission of the copyright owner or Shell Global Solutions International BV.
This document contains information that is classified as EAR99 and, as a consequence, can neither be exported nor re-exported to any country which is under an
embargo of the U.S. government pursuant to Part 746 of the Export Administration Regulations (15 C.F.R. Part 746) nor can be made available to any national of such
country. In addition, the information in this document cannot be exported nor re-exported to an end-user or for an end-use that is prohibited by Part 744 of the Export
Administration Regulations (15 C.F.R. Part 744).
ECCN EAR99 DEP 01.00.01.30-SCAPSA
February 2017
Page 2
PREFACE
DEP (Design and Engineering Practice) publications reflect the views, at the time of publication, of Shell Global Solutions
International B.V. (Shell GSI) and, in some cases, of other Shell Companies.
These views are based on the experience acquired during involvement with the design, construction, operation and
maintenance of processing units and facilities. Where deemed appropriate DEPs are based on, or reference international,
regional, national and industry standards.
The objective is to set the standard for good design and engineering practice to be applied by Shell companies in oil and
gas production, oil refining, gas handling, gasification, chemical processing, or any other such facility, and thereby to help
achieve maximum technical and economic benefit from standardization.
The information set forth in these publications is provided to Shell companies for their consideration and decision to
implement. This is of particular importance where DEPs may not cover every requirement or diversity of condition at each
locality. The system of DEPs is expected to be sufficiently flexible to allow individual Operating Units to adapt the
information set forth in DEPs to their own environment and requirements.
When Contractors or Manufacturers/Suppliers use DEPs, they shall be solely responsible for such use, including the
quality of their work and the attainment of the required design and engineering standards. In particular, for those
requirements not specifically covered, the Principal will typically expect them to follow those design and engineering
practices that will achieve at least the same level of integrity as reflected in the DEPs. If in doubt, the Contractor or
Manufacturer/Supplier shall, without detracting from his own responsibility, consult the Principal.
The right to obtain and to use DEPs is restricted, and is typically granted by Shell GSI (and in some cases by other Shell
Companies) under a Service Agreement or a License Agreement. This right is granted primarily to Shell companies and
other companies receiving technical advice and services from Shell GSI or another Shell Company. Consequently, three
categories of users of DEPs can be distinguished:
1) Operating Units having a Service Agreement with Shell GSI or another Shell Company. The use of DEPs by these
Operating Units is subject in all respects to the terms and conditions of the relevant Service Agreement.
2) Other parties who are authorised to use DEPs subject to appropriate contractual arrangements (whether as part of
a Service Agreement or otherwise).
3) Contractors/subcontractors and Manufacturers/Suppliers under a contract with users referred to under 1) or 2)
which requires that tenders for projects, materials supplied or - generally - work performed on behalf of the said
users comply with the relevant standards.
Subject to any particular terms and conditions as may be set forth in specific agreements with users, Shell GSI disclaims
any liability of whatsoever nature for any damage (including injury or death) suffered by any company or person
whomsoever as a result of or in connection with the use, application or implementation of any DEP, combination of DEPs
or any part thereof, even if it is wholly or partly caused by negligence on the part of Shell GSI or other Shell Company. The
benefit of this disclaimer shall inure in all respects to Shell GSI and/or any Shell Company, or companies affiliated to these
companies, that may issue DEPs or advise or require the use of DEPs.
Without prejudice to any specific terms in respect of confidentiality under relevant contractual arrangements, DEPs shall
not, without the prior written consent of Shell GSI, be disclosed by users to any company or person whomsoever and the
DEPs shall be used exclusively for the purpose for which they have been provided to the user. They shall be returned
after use, including any copies which shall only be made by users with the express prior written consent of Shell GSI. The
copyright of DEPs vests in Shell Group of companies. Users shall arrange for DEPs to be held in safe custody and Shell
GSI may at any time require information satisfactory to them in order to ascertain how users implement this requirement.
All administrative queries should be directed to the DEP Administrator in Shell GSI.
ECCN EAR99 DEP 01.00.01.30-SCAPSA
February 2017
Page 3
TABLE OF CONTENTS
PART I INTRODUCTION ........................................................................................................ 4
1.1 SCOPE ....................................................................................................................... 4
1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS ......... 4
1.3 DEFINITIONS ............................................................................................................. 4
1.4 CROSS-REFERENCES ............................................................................................. 7
PART II DEFINITION OF PRESSURE AND TEMPERATURE ............................................... 8
1 PRESSURE SYSTEM ................................................................................................ 8
2 TEMPERATURE AND PRESSURE LEVELS ............................................................ 8
2.1 TEMPERATURE ......................................................................................................... 8
2.2 PRESSURE .............................................................................................................. 13
PART III DEFINITION OF TOXICITY ...................................................................................... 21
1 TECHNICAL ASSURANCE ..................................................................................... 21
2 BACKGROUND ........................................................................................................ 21
3 TOXICITY CLASSIFICATION OF SUBSTANCES .................................................. 21
3.1 GENERAL ................................................................................................................. 21
3.2 TOXICITY CLASSIFICATION OF SUBSTANCES UNDER THE GLOBALLY
HARMONISED SYSTEM OF CLASSIFICATION AND LABELLING (GHS) ............ 23
3.3 APPLICATION TO PETROLEUM SUBSTANCES ................................................... 24
4 SPECIFIED ENGINEERING CONTROLS BASED ON THE SHELL TOXICITY
DEFINITION .............................................................................................................. 24
5 SELECTION OF SHELL TOXICITY DEFINITION UNDER GHS ............................ 24
5.1 GENERAL ................................................................................................................. 24
5.2 EXPLANATION OF THE PROCESS STEPS ACCORDING TO GHS ..................... 26
PART IV REFERENCES ......................................................................................................... 29
ECCN EAR99 DEP 01.00.01.30-SCAPSA
February 2017
Page 4
PART I INTRODUCTION
1.1 SCOPE
This DEP specifies requirements and gives recommendations for determining temperatures
and pressures in design and operation (Part II). It also defines substances with regard to
their toxicity, for which other DEPs may specify additional design and engineering
requirements (Part III).
The custodianship and accountability for this DEP resides with the Process Engineering
discipline. However, the definition of toxicity is a technical competency that is maintained in
the Health discipline in Shell. As such, the relevant subject matter experts and the
custodianship for (Part III) of this DEP are with the Health discipline.
This DEP contains mandatory requirements to mitigate process safety risks in accordance
with Design Engineering Manual (DEM) 1 – Application of Technical Standards.
1.3 DEFINITIONS
1.3.1 General definitions
The Contractor is the party that carries out all or part of the design, engineering,
procurement, construction, commissioning or management of a project or operation of a
facility. The Principal may undertake all or part of the duties of the Contractor.
The Manufacturer/Supplier is the party that manufactures or supplies equipment and
services to perform the duties specified by the Contractor.
The Principal is the party that initiates the project and ultimately pays for it. The Principal
may also include an agent or consultant authorised to act for, and on behalf of, the
Principal.
The word shall indicates a requirement.
The capitalised term SHALL [PS] indicates a process safety requirement.
The word should indicates a recommendation.
The word may indicates a permitted option.
1.3.2 Specific definitions
Term Definition
ECCN EAR99 DEP 01.00.01.30-SCAPSA
February 2017
Page 5
Term Definition
Pressure Generic term for relief valves, safety valves or safety/relief valves.
relief valve
Pressure Generic term for pressure relief valves, pressure rupture disks, or other
relief device mechanical emergency relief appliances.
Very toxic Substances that are very hazardous for the environment or human
(substances) health.
NOTES: 1. "Toxic" substances are classified as such in databases
such as the European Chemical Substances
Information System (ESIS) and the Globally
Harmonised System of Classification and Labelling
(GHS).
2. This DEP further classifies very toxic substances as
"very toxic - acute", "very toxic - chronic" and "very toxic
- environment".
3. Where a substance has been deemed “very toxic
acute” on the basis of the definitions in (4) of this
document, there may be over conservativeness in
specifying equipment if the classification has been
reached as a result of R34, R35 (causes (severe)
burns) or H314/H318 (causes severe skin burns and
eye damage).
1.3.3 Abbreviations
Term Definition
Term Definition
DP Design Pressure
DT Design Temperature
OP Operating Pressure
1.4 CROSS-REFERENCES
Where cross-references to other parts of this DEP are made, the referenced section or
clause number is shown in brackets ( ). Other documents referenced by this DEP are listed
in (Part IV).
ECCN EAR99 DEP 01.00.01.30-SCAPSA
February 2017
Page 8
1 PRESSURE SYSTEM
A pressure system is an individual equipment item or a group of equipment including
associated piping that within its boundaries remains open under all conditions, and it can
be demonstrated that blockage due to freezing, solidification, fouling, sublimation,
damage of internals, scale, debris, foreign objects, etc., cannot occur.
6. If block (stop) valves are included in the system, the requirements of ASME VIII
Division 1 Appendix M-5 shall be met.
7. The system design pressure SHALL [PS] not be higher than the pressure rating of any
system component.
8. The effects of static head shall be taken into account.
9. When a system approach is taken, the hydraulics shall be evaluated to ensure that no
equipment exceeds its design pressure before a pressure relief device activates, and
during relieving conditions, no equipment exceeds the allowable accumulation
permitted by either the applicable code or local requirements.
2.1 TEMPERATURE
2.1.1 Operating temperature
The operating temperature is the temperature that prevails inside equipment and piping
during the predominant intended operation.
1. The process engineer shall determine the operating temperature.
2. Where vessel operation can be switched from a high pressure moderate temperature
operation to a lower pressure but higher temperature one (e.g., regeneration), then the
option of designing for those separate operating modes may be considered (e.g., dual
pressure/temperature ratings for the equipment).
2.1.2 Maximum operating temperature (MOT)
1. The MOT shall be established for operational flexibility and required control system
variations.
2. The MOT shall be greater than or equal to the operating temperature.
3. The maximum operating temperature SHALL [PS] cover intended operations.
This includes: start up, shut down, drying, regeneration, steam-air decoking,
heating up to maximum ambient temperature, including solar radiation, fouling of
heat exchangers, heat exchanger by-passing.
4. The MOT shall be determined by the process engineer in consultation with the
process control engineer.
5. The MOT is normally used as the basis for materials selection with respect to long
term corrosion and/or material degradation. Therefore, any subsequent proposed
change in MOT shall be reviewed to confirm the continued suitability of the material.
ECCN EAR99 DEP 01.00.01.30-SCAPSA
February 2017
Page 9
3. To prevent brittle fracture, the selected LDT SHALL [PS] be based on one of the
following criteria, in order of preference:
a. Option 1. The LDT is equal to or colder than the MMT;
b. Option 2. The LDT is equal to or colder than the MMT but the LDT is determined
on the basis of reduced design stress, relative to the maximum code allowable
stress, in accordance with the rules in the applicable design code:
i. the maximum temperature credit allowed is 50 °C (90 °F);
ii. temperature credits greater than 50 °C (90 °F) are justified on the basis of a
fracture mechanics analysis using internationally recognised standards, and
approved by the MMI Technical Authority of the Principal.
c. Option 3. The LDT may be warmer than the MMT, but only when the General
2
Membrane Stress is less than 50 N/mm (7250 psi) for the operating scenarios
where the fluid temperature is colder than the LDT;
Selecting this option would need to be justified by significant cost savings to
balance the cost of process control, instrumented safeguarding and production
2
restraints required to prevent operation at a stress level above 50 N/mm
(7250 psi).
d. Option 4. When the controlling MMT is associated with a depressuring scenario,
the selected materials may also be qualified on the basis of a comparison of the
MAT and CET curves.
Option 4 is only selected if justified by significant cost savings, including the
cost of process control and production restraints required to prevent operation
on the unsafe side of the MAT curve.
4. Where the selected LDT is based on Option 2, Option 3 or Option 4 in (2.1.6, Item 3),
the following requirements SHALL [PS] also apply:
a. identify scenarios that could lead to re-pressurisation, or pressurisation from
connected systems, whilst the equipment is colder than the LDT;
b. assess the Risk of each scenario and define the Risk mitigation in accordance
with the Managing Risk manual of the HSSE & SP Control Framework;
c. the resulting documented ALARP statements for these scenarios shall be
approved by the designated Technical Safety Technical Authority of the Principal.
5. For equipment or piping systems where the LDT is governed by LAT, the effect of heat
tracing, insulation, winterization, or implementation of procedures that require heat-up
prior to pressurization shall be evaluated in line with (2.1.6, Item 4).
In some cases, credit can be taken for one or more of these items, which will allow
the selected LDT to be warmer than LAT.
ECCN EAR99 DEP 01.00.01.30-SCAPSA
February 2017
Page 13
2.2 PRESSURE
2.2.1 Pressures in process design and in mechanical pressure system design
2.2.1.1 Operating pressure (OP)
The OP is the gauge pressure which prevails inside equipment and piping during any
intended operation.
1. The OP shall be determined by the process engineer.
2.2.1.2 Maximum operating pressure (MOP)
The MOP is typically at least 105% of the OP in order to provide sufficient flexibility for
the control of the intended operations.
1. The MOP shall be determined by the process engineer in consultation with the
process control engineer.
2. The MOP shall be not less than 1.0 bar (15 psi) above the OP, except in pressurised
LPG storage facilities, where the MOP is equal to the vapour pressure at the derived
maximum operating temperature (see (Part II, 2.1.2)) and assessed LPG composition:
a. if this margin is not sufficient for control, starting up, shutting down or other
specific operations, a higher MOP shall be specified and the reason for this
increased MOP stated in the pertaining documents.
For applications where slugging and surging is a concern (e.g., from deepwater
subsea wells), substantial margins above ‘steady state’ operating pressure could be
required.
3. For pipeline application Maximum Allowable Operating Pressure (MAOP) or MOP is
the maximum internal pressure at which a pipeline system or parts thereof is allowed
to be operated. MAOP should not exceed 80% of the hydrotest pressure.
4. Start-up conditions where gathering system flow lines and pipelines have ‘packed’
shall be evaluated.
2.2.1.3 Design pressure (DP)
ECCN EAR99 DEP 01.00.01.30-SCAPSA
February 2017
Page 14
2.2.1.3.1 General
The Design Pressure (DP) is the highest gauge pressure that, according to mechanical
design codes, a system or piece of equipment can be continually subjected to at or
below the Upper Design Temperature, and above the Lower Design Temperature. This
pressure typically provides the basis for relief valve set pressures, and actual operating
conditions (OP, MOP) are below this pressure.
The DP is initially selected by the process engineer and finally determined in close
consultation with the mechanical design engineer.
1. The maximum difference in pressure between the inside and outside of the equipment,
or between any two chambers in a combination unit, shall be considered.
2. The DP shall be rounded up to the next 0.5 barg (10 psig) increment.
3. For an individual piece of equipment the Design Pressure is defined at the highest part
of the equipment. The equipment designer shall account for static head in determining
mechanical requirements for the lower parts of the equipment.
4. For systems comprising multiple connected pieces of equipment, the Design Pressure
of the individual equipment shall be established accounting for maximum static head
imposed by fluids as well as frictional pressure drop in non-flowing and flowing
condition.
a. Refer to API STD 521 Appendix B-1 for methodology and criteria for systems with
multiple equipment protected by a single Pressure Relief Device.
5. For atmospheric vessels/equipment, the design pressure should be specified in order
to provide a basis for safeguarding.
Example - Atmospheric equipment connected to or controlled by a control/relief
valve such as gas blanket of a tank.
6. Equipment and piping at the discharge side of positive displacement compressors and
pumps shall have sufficiently high design pressures to prevent the opening of pressure
relief devices due to pressure fluctuations
ECCN EAR99 DEP 01.00.01.30-SCAPSA
February 2017
Page 15
3. Equipment that is part of a pressure system protected by a relief valve discharging into
a flare system or combined vent system SHALL [PS] have a minimum design pressure
of at least 3.5 barg (50 psig) due to the potential backpressure exerted on the relief
device. This requirement does not apply to systems comprising tanks and other
atmospheric systems with dedicated vapour collection systems and flare systems.
When using sonic flare tips, the minimum design pressure might need to be
considerably higher than 3.5 barg (50 psig).
4. Design pressures lower than 3.5 barg (50 psig) may be considered if the relief valve
discharges directly to atmosphere or is routed to a downstream system that has a
design pressure of less than 3.5 barg (50 psig).
5. The Contractor shall validate that the selected design pressure is sufficiently high to
allow pressure relief into the flare header at maximum calculated back pressure.
For flare KO Drums, refer to DEP 80.45.10.10-SCAPSA PQ2022. (Part IV, 5.7.9) for
additional requirements.
6. If a DP of 110% MOP is substantially more costly than a DP of 105% MOP (e.g.,
because of a step up in flange rating), then 105% MOP may be applied, subject to the
approval of the Principal, and subject to use of relief valves that can have their set
pressure adjusted to the required accuracy.
For example, pilot operated relief valves.
7. The DP shall be greater than MOP by sufficient margin to allow operation of any
instrumented high pressure alarms and trip functions that are set at or above MOP
and are intended to prevent over-pressurisation, or to avoid relief valves lifting.
This could require a bigger margin than the minimum in Table 1.
ECCN EAR99 DEP 01.00.01.30-SCAPSA
February 2017
Page 16
8. It should be evaluated whether the application of design pressures that are higher than
those that follow from (2.2.1.3.2, items 1 to 5) could result in an overall cost saving.
This is likely when the equipment's minimum wall thickness is determined not by
internal pressure, but by external pressure or external loads, e.g., wind load or
protection against deformation during transport and installation.
9. For systems in which a batch reaction takes place and a relief valve is not sized for
any potential thermal runaway, these cases shall be:
a. subject to the approval of the Principal;
b. in accordance with the requirements specified in ASME VIII, Div 1, UG-140.
For batch reactions, it is sometimes possible (when not prohibitively expensive) to
select a sufficiently high design pressure so that in the event of a runaway, the
system’s pressure still does not exceed the allowable pressure limits (e.g., reactors
and associated piping). In these special cases, the runaway relief case is not
included as a basis for sizing the relief system.
10. For pumps and compressors with an isolation valve between it and upstream system
(e.g., scrubber), the suction lines from and including the suction valve shall have the
same design pressure as on the discharge side.
11. The DP of compressor suction and intermediate stage systems, e.g., coolers,
condensers, knock-out drums, shall be sufficiently high to prevent the opening of
pressure relief valves through pressure equalization “settle out” after the compressor
has shut down.
12. The design pressures for multi-compartment equipment need not take account of
structural failure of separation walls. For heat exchangers refer to
DEP 80.45.10.11-SCAPSA PQ2022. (4.2) for requirements. See also (Part II,
2.2.1.3.5).
13. The design pressures of equipment handling explosive dusts and means of preventing
and mitigating dust explosions shall be subject to the approval of the Principal.
14. Design pressure and temperature should be optimised to eliminate and reduce relief
cases where practically possible, in order to provide an inherently safe and
sustainable unit design and to reduce costs.
Where permitted by local requirements, for the acceptance of occasional variations
of pressure and/or temperature above the design levels in piping systems,
reference is made to ASME B31.1, ASME B31.3, ASME B31.4 and ASME B31.8 as
applicable to the system under consideration.
Example: Higher design pressures could exclude certain large relief cases,
therefore reducing RV sizes, piping and potentially flare capacity.
ECCN EAR99 DEP 01.00.01.30-SCAPSA
February 2017
Page 17
1 TECHNICAL ASSURANCE
The definition of toxicity is a technical competency that is maintained in the Health
discipline in Shell. As such, the relevant subject matter experts and the custodianship for
(Part III) of this DEP are with the Health discipline. During project development, the
toxicity classification for a substance is specified by the Contractor and then reviewed by
the Principal for technical assurance and subsequent approval.
2 BACKGROUND
This DEP specifies the scheme for defining whether a process medium is deemed to be
very toxic (very toxic – environment, very toxic – acute and/or very toxic – chronic). The
Shell toxicity definitions are given in Table 1. Substances are classified in one or more of
these categories in accordance with (PART III).
Engineering design requirements triggered by these definitions are incorporated into
other DEPs that reference this DEP.
Previous editions of this DEP (prior to December 2008) made reference to "lethal"
service designation. This definition is no longer consistent with the definitions currently
used globally for the classification and labelling of hazardous substances. Internal
definitions have been aligned with those accepted internationally under the Global
Harmonisation System.
In addition, for human health, a distinction has been designated between compounds
with acute and chronic toxicity that may lead to a fatality in the short or longer term,
respectively, enabling more flexibility in specifying specific engineering requirements.
Table 1 Toxicity descriptions
3.1 GENERAL
Substances classified (according to Part III, Table 1) as very toxic-acute, very toxic-
chronic, and very toxic-environment, are those substances that are very hazardous for
the environment or human health. Process streams that contain very toxic-acute, very
toxic-chronic, or very toxic-environment substances require a specific design to limit
emissions and thereby potential exposure. Table 2 provides examples of substances
that are defined as Very Toxic (according to Part III, Table 1). Streams containing these
substances above the limits specified in the schemes are similarly classified.
ECCN EAR99 DEP 01.00.01.30-SCAPSA
February 2017
Page 22
4. The United Nations (UN) Globally Harmonized System of Classification and Labelling
of Chemicals (GHS) shall be used to determine the toxicity classification for a process
medium per (Part III, Table 1). Refer to (Part III, 5).
Table 2 Examples of substances with toxicity classifications per (Part III,
Table 1)
ECCN EAR99 DEP 01.00.01.30-SCAPSA
February 2017
Page 23
environment according to the classifications in (Part III, Table 1) under the GHS
scheme.
6. If no information on the process medium is available, the Principal shall be consulted.
5.1 GENERAL
A logic diagram for the selection of toxicity definition under the GHS classification system
is shown in Figure 1.
1. Refer to (Part III, 5.2) for an explanation of the process steps.
ECCN EAR99 DEP 01.00.01.30-SCAPSA
February 2017
Page 25
Step 15. Has a component in the process medium been previously classified as “Very
Toxic – Environment” or “Very Toxic – Acute”?
a. If No, the process medium is ‘Not Very Toxic’. If Yes, the previously assigned
classification stands.
ECCN EAR99 DEP 01.00.01.30-SCAPSA
February 2017
Page 29
PART IV REFERENCES
In this DEP, reference is made to the following publications:
NOTES: 1. Unless specifically designated by date, the latest edition of each publication shall be used,
together with any amendments/supplements/revisions thereto.
2. The DEPs and most referenced external standards are available to Shell staff on the SWW (Shell
Wide Web) at http://sww.shell.com/standards/.
SHELL STANDARDS
AMERICAN STANDARDS
BRITISH STANDARDS
CHINESE STANDARDS
EUROPEAN STANDARDS
INTERNATIONAL STANDARDS
Petroleum and natural gas industries - Pipeline transportation systems ISO 13623
- Second Edition
Globally Harmonised System (GHS) of classification and labelling of ST/SG/AC.10/30/Rev.4
chemicals
Issued by: United Nations Economic Commission for Europe
Information Service http://www.unece.org/trans/danger/danger.htm