Beruflich Dokumente
Kultur Dokumente
Q 2001 IEEE
0-7803-77-2/01/$10.00
1801
As a rule, the penalty from early or late delivery In the model SCo, the first item of the objective
is proportional to the supply unit price, and the function is the penalty cost of late delivery; the
transportation rate is proportional to transportation second item is the penalty cost of early delivery; the
p
time. Suppose that a, is respectively the penalty third item is the production cost; the fourth item is
the transportation cost of products. The constraint (3)
factor of early or late delivery per unit time, and
expresses the quantity of all the products ordered
a < ; 3/1 is the transportation rate factor of from all the retailers are supplied by all the
product i per unit time; the transportation capacity is warehouses; the constraint (4) states that the plan
enough to all the products. supply quantity of each warehouse should satisfy its
relevant supply capacity constraint; the constraint ( 5 )
3 Model Building ensures that the s u m of purchase quantity that each
warehouse is required to finish meets the constraint
From the delivery location A, of retailer k and of the s u m of supply quantity.
location Bj of warehouse j , we can easily
4 Model Conversion and Algorithm
formulate the transportation time s@,which The objective function of model SCo is non-
describes the time of warehouse j supplying continuous, so it is not solved with the general
mathematical program. Thus, such conversion is
products to retailerk. made to the model SCo as follows:
Definition 1: define z:,( t ) as the purchase quantity Define xii( t )as the over-supply quantity of
,'.
of product i of retailer k that supply center requires
product iof warehousejat time t , y;(t)as the
warehouse j to supply at time t ,and p ; ( t ) as the
short-supply quantity of product i of warehouse j at
plan supply quantity of product i of warehouse j at
time t ,then
[EP::(7) - cc
time t . I f I
Definition 2: defme the function hi ( t ) as follows: x; ( 4 = 2
; (Ql'
r=1 r = l k=l
(1)
h: ( t )=
i"'
0
t=d/
t#d/
f l
1
t
multi-retailer supply and demand problem can be
described with model SG,
v;(0 = [y ?=l k=l
4 j (z) -
5=1
P ; (z)l+
5=l
p ; (z) = cc
f l
r=1 k=l
2; (z) + x; ( t )- y ; ( t )
p ; ( t )= $ p ; ( z )
r=l
- 2p ; (z)
5=1
1
+
= C Z k ( t ) x; (t)- x; (t - 1) - y; (t)+ y; (t - 1)
k=l
(10)
T I T So, the model SCois equivalent to the model SC:
x x z k . ( t )Ix b f i ( t ) Model SC:
t=1 k=l
(5)
t =1
p ; ( t )2 0, z:, ( t )2 0
T
ccw;.;+ LYj5; (4 c(ff
n m
k=l
+ YPU 1.6. @>I
(6) (11)
Vi = 1,...,n,j = /2 ,...,m,k= 52,...,1,t = /2 ,...,T. s.t.
1802
_ - -
As can be seen, ( x, y , z ) meets constraints of
- - -
model SC. If ( x , ~ , z )is substituted into
F(x, y , Z ) ,the following formula is obtained.
F(x,y,z) = F ( x ' , y ' , z ' ) - ( a + P ) f f y j ( t ) IF(x',y',z'
ccz;(t)
T
1=1
I
k=l
T
ICbi.(t)
I =I
(22)
Obviously, that is inconsistent with the fact that
( x*,y * ,Z* ) is the optimal solution of model SC. So
(14)
I we can conclude X* (t)y*( t )= 0 if ( x* ,y * ,z*) is
C Z & ( t ) x;+ ( t )- x; (t - 1) - y i ( t )+ y j (t - 1) 2 0
the optimal solution of model SC.
k=l
(16)
Although the number of variables of model SC is
p ; ( t )= cI
k=1
z; ( t )+ x; ( t )- x; ( t - 1) - y; (t)+ y ; (t - 1)
x; ( k ) > y ; ( k ),and =
t I
{C[Cz;(f)+ x ; ( t ) - x; (t - 1) - y ; (f) + y; (t - 1)]- cp; I 1
(t)}'
i
zrl krl <=I k=l
.,( t ) =
x; ( t ) - y; ( t ) .
x; ( t ) ,
where j = g , and
other
t =k +
= [x; ( t ) - x ; (0)- y ; ( t ) y ; (O)]' = [xj ( t )- y j (t)]'
(24)
(1 7) Based on the lemma stated early, the following
formula can be obtained
t = l k=l t=l
(26)
Comparing the objective function of model SC
with that of model SCo, we can conclude that formula
( 2 ) is equivalent to formula (1 l), so p is the optimal
solution of model SCo,
Algorithm
Model SC is equivalent to a general linear
programming model by the above model conversion,
1803
and it can be solved with the general linear
programming software. The detailed procedures are Table 3 Computation Result (The minimized
shown as follows: obiective value is 1671.7)
Stepl: Build model SC according to the known
conditions such as ordering information of retailers
and supply capacity constraint of warehouses.
Step2: Call the general linear program, and
compute x* ,y*,z* and F ( x * ,y * , z*) .
Stepf: Based on formula (23), compute the plan 1 0 25 10 0 0
supply quantity of each product of all the warehouses 2 3 0 0 10 0
in every time period.
5 An Empirical Case
The algorithm mentioned above is implemented
with Visual C++ program, and run in a PC/586
computer. We have simulated various examples and
obtained satisfactory results. Below is a small-scale
example.
Suppose that a supply network consisting of two
warehouses provides two retailers with two kinds of
products in the plan period [1,5]. The unit price of 1 12 12 15 10 0
product and deliverability of each warehouse are 2 8 8 10 10 10
shown as Table 1. a ,/? are respectively penalty
factor of early or late delivery of a warehouse, and
j $0) 4(3) 44) 40
1 1 n in 0 0 0
a = 0.1, p = 0.5 . "/1, y2are respectively
transportation rate per unit time for each product, and
"/1 =1,y2 = 0 . 5 .
10
2 n n 5 n 0
\ 1 10 5 12 12 15 12
2 8 6 8 8 10 10
1 12 10 10 8 10 10
2 1 0 8 8 6 6 6 1 I 10 10 8 10 0
2 1 8 8 6 5 0
Table 2 shows the ordering quantity of each
retailer, delivery time and transportation time of Compare Table 3 with Table 1, we can conclude
products. that the punctuality distribution requirement planning
approach minimizes the sum of penalty costs of early
Table 2 Ordering Information and Transportation or late delivery, transportation cost and production
Time cost in the precondition of the balance of supply and
demand capacity. In the mean time, the business goal
1 / 6 0 40 3 4 1 2 of supply chain - supplying punctually and earning
the maximal profits is achieved.
2 135 25 5 4 3 1
6 Conclusion
Table 3 shows the result of requirements plan
made by the above-stated punctuality distribution Supply chain is implemented under the mutual
requirement planning approach. action of materials flow, funds flow and information
1804
flow, and the value of materials is added after the
process of production, transportation and so on. Since
usable resources ability of each enterprise in supply
chain is limited, it becomes more and more important
to solve the supply and demand problem under the
limited resources ability in the supply chain. This
paper just researches on the distribution requirement
planning based on the limited supply ability. An
optimum model is built, and is converted into the
linear program by the mathematical deduction.
Finally, the punctuality distribution requirement
planning is introduced, and various cases show that it
can make the distribution requirement plan exactly
and rapidly, which lays foundation for the production
application, and provides managers with some
research direction of supply chain.
References
1 . S. Tzafestas, G. Kapsiotis, Coordinated control of
manufacturing/supply chains using multi-level
techniques, Computer Integrated Manufacturing
Systems, 1994, 7(3): 206-212.
2. J. F. Willianms, A hybrid algorithm for
simultaneous scheduling of production and
distribution in multi- echelon structures, Management
Science, 1983,29( 1): 77-92.
3. H.L.Lee, C . Billington, material management in
decentralized supply chains, Operations Research,
1993,41(5): 835-847.
4. Lei Lin, Wang Wei, Ren Shouju, Liu Wenhuang,
Research of Supply Chain Decision Supporting
System Based on Self-organization, Proceedings of
the 3d World Congress on Intelligent Control and
Automation, IEEE Catalog Number: 00EX393, Vol
3Of5, pp1926-1930,2000.7.
1805