SLNo Description of Snag Current Evidence Photograph ONEIC MZEC

Status Signature Signature


II 33kV ROOM
a Floor Finishes – For final epoxy coating. Check edges of the rubber mat Not Complied
area for damages. Skirting, doorjambs, doorstoppers and threshold to
be free from epoxy paint

b Skirting Finishes – For cleaning and final painting. Proper termination of Not Complied
paint to be implemented.

C Wall Finishes – 1, For final painting. Wall surfaces to be smooth prior Not Complied
to final painting. Switches, outlets and any device or equipment
attached to the wall must be free from paint.
2, Repair all cracks on surfaces and corners. Repair all damage edges,
gaps in switch & outlet covers.
3, Proper termination of paint between walls, doorjambs and skirting
to be implemented
d Ceiling Finishes – Check for areas to be touch up. Not Complied

III 11kv ROOM

a Floor Finishes - For final epoxy coating. Check edges of the rubber mat
area for damages.
Provide galvanized and epoxy painted chequered plate cover, Skirting,
doorjambs, doorstoppers and threshold to be free from epoxy paint.

b Skirting Finishes – For cleaning and final painting. Proper termination of


paint to be implemented.

c Wall Finishes – For final painting. Wall surfaces to be smooth prior to


final painting. Switches, outlets and any device or equipment attached
to the wall must be free from paint.
Repair all cracks on surfaces and corners.
Repair all damage edges, gaps in switch & outlet covers.
Proper termination of paint between walls, doorjambs and skirting for
implementation.
d Ceiling Finishes – For touch up paint.

IV Control and relay room:

a Floor Finishes – For final epoxy coating. Skirting, doorjambs,


doorstopper and threshold to be free from paint.

b Skirting – For cleaning and final painting. Proper termination of paint to


be implemented.

c Wall Finishes – For final painting. Wall surfaces to be smooth prior to


final painting. Switches, outlets and any device or equipment attached
to the wall must be free from paint.
Repair all cracks on surfaces and corners.
Repair all damage edges, gaps in switch & outlet covers.
Proper termination of paint between walls, doorjambs and skirting for
implementation.