Sie sind auf Seite 1von 52

The Electric Distribution System 1

EE 153
Electric Power Distribution Systems

Lecture Notes No. 1

The Distribution System

Prof. Rowaldo del Mundo


Electrical & Electronics Engineering Institute
College of Engineering
University of the Philippines

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 2

The Electric Power System


(Embedded Generator)
Coal Plant
Wind Farm

End
Hydro Plant Users

End
Users
Generation Transmission Distribution
System System System
Small-Hydro

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

1
The Electric Distribution System 3

Distribution of Electricity
Primary Distribution Lines
Subtransmission Lines
(Main Feeder)
Substation
Power Primary Distribution Lines
Transformer (Laterals)

Misc Loads

Distribution Secondary Distribution Lines

System Service
Drop

Residential Commercial Industrial


Distribution
Transformer

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 4

Distribution Substation

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

2
The Electric Distribution System 5

Primary Distribution Lines

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 6

Service Drop & Metering

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

3
The Electric Distribution System 7

Electricity Consumers

RESIDENTIAL

COMMERCIAL

INDUSTRIAL

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 8

Load Characteristics

100 PEAK

80
Percent of Peak Load

60

40 OFF-
20 PEAK Load Profile of
Residential
Customer
12 4 8 12 4 8 12

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

4
The Electric Distribution System 9

Load Characteristics

100 PEAK
80
Percent of Peak Load

60

OFF-
40

Load Profile of
20 PEAK Commercial
Customer
12 4 8 12 4 8 12
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 10

Load Characteristics

100 PEAK
80
OFF-
Percent of Peak Load

60 PEAK
40

20
Load Profile of
Industrial
0 Customer
12 4 8 12 4 8 12
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

5
The Electric Distribution System 11

Load Characteristics
Average Demand
Load Factor  PEAK
Peak Demand

Energy
Average Demand  AVERAGE
Time
Annual kWh

8760 hrs

Annual kWh / 8760


Load Factor 
Peak Demand
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 12

The Distribution Substation


 Combination of switching, controlling and voltage step-down
equipment arranged to reduce sub-transmission voltage to
primary distribution voltage for distribution of electrical energy
to customers
 PURPOSE
 To take power at high voltage from the transmission
and/or subtransmission level, reduce its voltage, and
route it onto a number of primary voltage feeders for
distribution in the area surrounding it.
 To perform operational and contingency switching and
protection duties at both the transmission and feeder
levels

Also provides a convenient local site for additional


equipment such as communications, storage of tools, etc.
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

6
The Electric Distribution System 13

Types of Substation

Gas-Insulated Substation (GIS)


INDOOR

Air-Insulated Substation (AIS)


OUTDOOR

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 14

Types of Substation

Air-Insulated Substation (AIS) Gas-Insulated Substation (GIS)


OUTDOOR INDOOR

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

7
The Electric Distribution System 15

Distribution Substation Design


 Air-Insulated Substation (AIS)
 Minimum phase-to-phase and phase-to-ground clearances must
be maintain using air as insulation.
 Air-Insulated Substation open design must not be touched.
 Always set up in the form of fenced-in electrical operating area,
to which only authorized personnel have access.
 Directly exposed to the effects of the environment, such as
weather, and especially lightning.
 It has to be designed based not only on the electrical but also
environmental specifications.
 Requires bigger land area than the GIS.

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 16

Distribution Substation Design


 Gas-Insulated Substation (GIS)
 Uses a superior dielectric gas (SF6) at a moderate pressure for
phase-to-phase and phase-to-ground insulation.
 The high-voltage conductors, circuit breaker interrupters, switches,
current transformers, and voltage transformers are in SF6 gas inside
grounded metal enclosures.
 The atmospheric air insulation used in a conventional, air-insulated
substation (AIS) requires meters of air insulation to do what SF 6 can do
in centimeters. GIS can therefore be smaller than AIS by up to a factor
of 10.
 In a GIS, the active parts are protected from deterioration due to
atmospheric air, moisture, contamination, etc. As a result, GIS is more
reliable and requires less maintenance than AIS.
 GIS is mostly used where space is expensive or not available.
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

8
The Electric Distribution System 17

The Distribution Substation


Incoming Transmission
FUNDAMENTAL PARTS
OF A SUBSTATION
1. HV Side Buswork and HV SIDE
Protection
The
2. The Transformer TRANSFORMER Site

3. LV Side Buswork and


Protection LV SIDE

4. The Substation Site


itself
Outgoing Feeders

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 18

HV Side Buswork & Protection


Functions:
 Termination for incoming (Sub)transmission
 Protection
 Switching
 Monitoring and Control
 Metering
 Represents from 1/4 to 1/3 of a substation’s total cost.

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

9
The Electric Distribution System 19

Distribution Substation
Substation Bus Arrangements
1. Single-Bus Single-Breaker
2. Double-Bus Double Breaker
3. Double-Bus Single-Breaker
4. Main and Transfer Bus
5. Ring Bus
6. Breaker-and-a-Half Bus

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 20

Distribution Substation
1. Single Bus Single Breaker – involves one
main bus with all circuits connected
directly to the bus. The reliability of this
type of an arrangement
Line
is very low.
CB Lowest Cost

Bus
DS

Line

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

10
The Electric Distribution System 21

Distribution Substation
2. Double Bus Double Breaker – provides a very
high level of reliability by having two separate
breakers available to each circuit.
Bus 1

Line Line
CB

Most expensive
& High reliability

Bus 2

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 22

Distribution Substation
4. Double Bus, Single Breaker – has two main
buses connected to each line CB and a bus tie
breaker.
Bus 1

Bus 2

Bus Tie Breaker

Line Line

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

11
The Electric Distribution System 23

Distribution Substation
3. Main and Transfer Bus

Main Bus

Bus
Tie CB
Incoming
CB Line

Outgoing
Line

Transfer Bus

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 24

Distribution Substation
5. Ring Bus – all breakers are arranged in a ring
with circuit tapped between breakers.

Line
Line

Line
Line

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

12
The Electric Distribution System 25

Distribution Substation
6. Breaker-and-a-half – each circuit is
between two circuit breakers and there are
two main buses.

Bus 1

Line

Tie Breaker

Line

Bus 2

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 26

The Distribution Substation


Substation bus/switching arrangements
Config. Reliability Cost Required Area
Single Bus Least reliable - single failure can cause Least cost (1.0)- fewer Least area - fewer
complete outage components components

Double Bus, Highly reliable - duplicated High cost (1.8) - Greater area - twice
Double components; single failure normally duplicated components as many components
Breaker isolates single Component

Main Bus and Least reliable - same as Single Bus, High cost (1.76) - Low area requirement-
Transfer but flexibility in operating & fewer components fewer component
maintenance with transfer bus

Double Bus, Moderately reliable - depends on High cost (1.78) - Moderate area - more
Single Breaker arrangement of components and bus more components components

Ring Bus High reliability - single failure isolates Moderare cost (1.56) - Moderate area -
more components increases
with number of circuits

Breaker-and-a- Highly reliable - single circuit failure Moderare cost (1.57) - Greater area - more
Half isolates single circuit, bus failures do breaker-and-a- half for components per circuit
not affect circuits each circuit

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

13
The Electric Distribution System 27

HV Switchyard Control System


Interlocks

Q15 Q25 Q1 Q2 Q1 Q2
Q15
Q0
Q0 Q25
Q9

Q8
– Disconnect Switches Q1, Q2 and Q9 can be operated only
when breaker Q0 is open (protection against switching under
load)
– Breaker Q0 cannot be closed with disconnect switches Q1, Q2
and Q9 in the intermediate position (fault location)
– Disconnect switches Q1 and Q2 are mutually interlocked so
that only one can be closed at a time
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 28

HV Switchyard Control System


Interlocks

Q15 Q25 Q1 Q2 Q1 Q2
Q15
Q0
Q0 Q25
Q9

Q8
– When the bus-ties is closed, a second disconnect switch (Q1 or
Q2) belonging to the tied system can be closed, one of the closed
disconnect switches can then be opened (change of bus under
load)
– Disconnect switches Q1 and Q2 can be operated only if the related
bus earthing switch Q15 or Q25 is open

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

14
The Electric Distribution System 29

HV Switchyard Control System


Interlocks

Q15 Q25 Q1 Q2 Q1 Q2
Q15
Q0
Q0 Q25
Q9

Q8

– Disconnect switch Q9 can be operated only when earthing


switch Q8 is open (taking account of other end if necessary)
– Earthing switch Q8 can be operated only when disconnect
switch Q9 is open (taking account of other end of outgoing
line if necessary)

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 30

HV Switchyard Control System


Interlocks

Q15 Q25 Q1 Q2 Q1 Q2
Q15
Q0
Q0 Q25
Q9

Q8

– Disconnect Switches Q1, Q2 and Q9 can be operated only


when maintenance earthing switches Q51/Q52 are open
– Maintenance earthing switches Q51/Q52 can be operated only
when disconnect switches Q1, Q2 and Q9 are open

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

15
The Electric Distribution System 31

HV Switchyard Control System


Interlocks

Q15 Q25 Q1 Q2 Q1 Q2
Q15
Q0
Q0 Q25
Q9

Q8
– The tie-breaker Q0 can be opened only if not more than one
bus disconnect switch in each branch is closed (tie-breaker
lock-in)
– One bus earthing switch Q15 or Q25 can be operated if in
the respective bus section all bus disconnect switches of
the corresponding bus system are open

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 32

HV Switchyard Control System


Interlocks

Q15 Q25 Q1 Q2 Q1 Q2
Q15
Q0
Q0 Q25
Q9

Q8

– All interlocks remain active if the auxiliary power fails


– An interlock release switch cancels the interlock conditions.
Switching operations are then the responsibility of the authorized
person

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

16
The Electric Distribution System 33

The Transformer
 Distribution Substations utilize
one (1) to six (6) Transformers to
convert incoming power from
sub-transmission voltage to the
primary distribution voltage.
 Transformers are not only the
raison d’ etre for distribution
substations but often represent the
largest portion of the cost, typically
representing from 1/2 to 2/3 of the
total substation cost.

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 34

LV Side Buswork & Protection


 Termination for outgoing Feeders
 Protection
 Switching OUTDOOR
 Voltage Regulation
 Monitoring and Control
 Metering
 Representing 1/15 to 1/5
of a substation’s total cost

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

17
The Electric Distribution System 35

LV Side Buswork & Protection

INDOOR INDOOR
GAS-INSULATED SWITCHGEAR AIR-INSULATED SWITCHGEAR

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 36

The Substation Site


Elements of Site Costs
 Land
 Civil/Mechanical/Electrical
 Feeder Gateway
 Public Safety and Aesthetic
 Taxes and Permits

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

18
The Electric Distribution System 37

The Substation Site


Land
 Identify siting needs far in advance through long-term planning.
 Buy sites at whatever time provides the lowest present-worth cost
(taking into account the expected escalation in price and the risk that
current forecasts and plans may not be perfect).
 Fence immediately and store several pieces of spare or surplus
substation equipment: a fenced yard with breakers and transformer
inside makes it clear that the site is a utility substation, avoiding
accusations of non-disclosure later on.

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 38

The Substation Site


Civil/Electrical/Mechanical
 Preparation includes providing
- Grounding grid
- Foundations for racks and equipment
- Underground electric cables (T&D)
- Underground ductwork for control and
communications cables
- Control house
- Other facilities to support the electrical
function of the substation

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

19
The Electric Distribution System 39

The Substation Site


Feeder Gateway
 Routing of large number of feeders out of a
substation
- Challenging in congested and restricted
sites.
- If not carefully picked far in advance,
the sites available to a utility may have
severe limitations on the routing of the
distribution ROW and easements out of
the site.
- Even though all construction is intended
to be overhead, feeders may have to be
routed several meters in underground
ducts before space above ground
becomes available.

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 40

The Substation Site


Public Safety and Aesthetic
 Site includes, at a minimum, a fence or wall around the site to
secure it from public access.
 In problem areas, fence may need to be up to 10 meters high.
 Utility may be required to landscape the site.
 Substation may be enclosed in
what appears to be a building
(“Cottage Substation”) to hide it.

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

20
The Electric Distribution System 41

The Substation Site

Site for Outdoor Site for Indoor


Substation Substation

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 42

Substation Size and Spacing


 The set of substation service areas for a T&D system must “tile”
the utility service territory, covering all locations where there is
any demand, and each substation must have sufficient capacity
to serve the load in its service area
As the distance between substations
(SPACING) is increased, fewer
substations are needed, but the
average substation service area
becomes larger, and substations will
need a greater individual capacity to
serve their loads.
Example
6 S/S serving an area of 108 sq. miles, evenly spaced in a hexagonal pattern 4.56 miles apart.
Each S/S serves 18 sq. mi. with a peak load of 58.5 MW (65 MVA) with 80 MVA capacity at 80% util.
If the capacity of each S/S were doubled, to 162 MVA, each could serve twice the area (36 miles) and
only half as many substations would be needed

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

21
The Electric Distribution System 43

Substation Size and Spacing


 Area, and load, increase with the square of the spacing
 Doubling the capacity will result in an increase of 41% in permissible substation
spacing (e.g., 4.56 mi – 6.45 mi.)

4.56 mi 6.45 mi

80 MVA S/S 160 MVA S/S

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 44

Substation Size and Spacing


 Area, and load, increase with the square of the spacing
 Doubling the spacing, to 9.12 miles, would require construction of substations
with four (4) times the capacity, or 324 MVA each, but on average only 1/4 as
many would be needed

4.56 mi
9.12 mi

80 MVA S/S 320 MVA S/S

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

22
The Electric Distribution System 45

Substation Size and Spacing


 Cost Impact of Changing Substation Size

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 46

Subtransmission System
 Different Types of Subtransmission Systems
 Radial-Type Subtransmission
 Loop-Type Subtransmission
 Grid or Network-Type

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

23
The Electric Distribution System 47

Subtransmission System
 Radial-type Subtransmission

Bulk power
source bus

Substransmission
Circuits

Distribution
Substations

The radial system is simple and


has a low first cost but it also
has a low service continuity.

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 48

Subtransmission System
Dual-source Single-source,
Subtransmission radial
More reliable: Subtransmission
Faults on one Least reliable:
of the radial Faults on the
subtransmission radial
circuits should subtransmission
not cause circuit
interruptions to can cause
substations. interruptions to
Double-circuit multiple
faults can substations.
cause multiple
station
interruptions. *Short, 2006

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

24
The Electric Distribution System 49

Subtransmission System
 Loop-type Subtransmission
Bulk power
source bus

In this design, a single


Subtransmission circuit originating from a
Circuits bulk power bus runs through
a number of substations and
Distribution returns to the same bus.
Substations

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 50

Subtransmission System
 Grid-or-Network-Type Subtransmission
Bulk power
source buses

Distribution
Substations

Subtransmission
Circuits Has more than one bulk power
source. It has the greatest service
reliability but it requires costly
control of power flow and relaying.

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

25
The Electric Distribution System 51

Subtransmission Cost vs.


Substation Size and Spacing
Each Voltage
has a range
over which it is
best suited to
application

Cost per MW of the subtransmission necessary to


feed distribution substations, as a function of size
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 52

Substation Spacing and


Feeder System Interaction

81 MVA 54 MVA
15.6 sq. mi. 10.4 sq. mi.

4.56 mi
3.72 mi

A reduction in size from 81 MVA to 54 MVA, with all other


aspects of the substation held the same, results in 33%
reduction in substation service area, and
A reduction in the required reach of the feeder system.

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

26
The Electric Distribution System 53

Substation Spacing and


Feeder System Interaction

Cost of the Feeder System (on a per MW basis) increases


linearly up to a maximum economical reach of the primary
voltage being used, then increases exponentially.
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 54

Substation Size and Spacing


Composite cost of the Entire T&D System

Cost per MW of the combined Subtransmission-Substation-Feeder System


as a function of size and spacing.
Solid line represents the cost with 138 kV. Dotted line represents the cost, assuming that planners
can choose the best subtransmission voltage appropriate to the spacing.

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

27
The Electric Distribution System 55

Substation Siting and Sizing

Where to locate the substation and what capacity?

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 56

Substation Siting and Sizing


There is an “Optimal”
Site, Size and
Service Area

Cost of an Entire Substation


Equipment Initial PW
Subtransmission, per S/S 8% 8%
A “Substation” Consists of Three
Substation, incl. Site 16% 22%
“Levels” of Equipment
Feeder system for S/S area 76% 70%
Total 100% 100%

Substation Planning is best done by considering the impact of


any siting or sizing decision on all three levels.
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

28
The Electric Distribution System 57

Substation Siting and Sizing


TYPE COST SENSITIVITIES INVOLVED IN SUBSTATION SITING
Primary Feeder The biggest impact in changing site and size is on the feeder system. This is always the
Impact dominating variable cost in substation siting studies.
Subtransmission Some sites are near available transmission lines or can be reached at low cost. Others require
Impact lengthy or underground-only access – adding to cost.
Feeder Gateway Getting feeders out of a substation requires available routes with sufficient clearance. Confined
Costs or restricted sites mean higher costs in taking feeders underground or over non-optimal routes
around nearby barriers to get power out of the substation.
Geographic Nearby terrain or public facilities may constrain feeder routing costs. Close proximity to a large
Constraints park or cemetery means feeders must be routed around them on the way to the load, which
generally raises feeder costs.
Site Preparation The slope, drainage, underlying soil, and rock determine the cost of preparing the site for a
substation and of building the basic foundations, etc. The cost of transporting material to the site
may also differ from one site to another by significant amounts. Aesthetic requirements also
vary.
Land Cost The cost of the land is a factor. Some sites cost much more than others.
Weather Sites on hilltops and in some other locations are more exposed to lightning and adverse
Exposure weather than average, slightly increasing repair and O&M costs.

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 58

The Feeder System


 Mission
 To distribute power from a few system sources
(substations) to many service (distribution)
transformers, that are scattered throughout the service
territory, always in close proximity to the customer.
 Goals
 Economy – Total cost must be kept as low as possible
 Electrical – Deliver power required by all customers
 Service Quality – Reliability of service must be high and
voltage quality must be satisfactory

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

29
The Electric Distribution System 59

The Feeder System

Substations and Feeders


Idealized Distribution Feeder Route Covering Substation Service Area
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 60

The Feeder System

Substations and Feeders


Feeders emanate from substations that are optimally located.
But some circumstances forces planners not to follow an optimal
route EE153 – Electric Power Distribution Systems
Electrical & Electronics Engineering Institute
University of the Philippines Prof. Rowaldo del Mundo

30
The Electric Distribution System 61

The Feeder System


 Central Location for the Substation
 Arrange feeder system so that the substation serves the
distribution needs of the area all around it
 Feeders must reach between Substations
 Interaction of substation spacing and feeder reach economics
 Feeder line types and loading criteria used in the design of the
feeder system must be able to move power reliably, economically,
and within engineering criteria (loading and voltage drop) to all
locations between substations

 Contiguous, exclusive service areas


 Lay out substations and feeders so that all have exclusive,
contiguous areas

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 62

The Feeder System


Vaguely Circular Service Area of Substations

Substations and Feeders


Feeders Must Cover Service Area of Substations
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

31
The Electric Distribution System 63

The Feeder System


 A majority of the load is relatively far from the
substation
 Vaguely circular substation service area
 Each feeder serves roughly triangular ‘slices’
 Feeders will have to carry more than half
of the substation’s load more than half
of the distance to its boundary with other
substation service areas

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 64

The Feeder System


 Power must be delivered to the proximity of the
Customer
 Feeders must reach each of the service (distribution) transformer
along their routes

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

32
The Electric Distribution System 65

The Feeder System


 Branching and Splitting Structure
 To cover its service area so that primary-level delivery reaches
sufficiently close to all customers, the feeder system typically
splits its routes many times in ‘dendrillic configuration’

 Feeder consists of a single route


leaving the substation, which
branches and re-branches, gradually
splitting the power flow into more but
smaller-capacity routes for delivery
as power moves from the substation
to the customer

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 66

The Feeder System


 Feeder Distance
 Lebesgue 1 metric (taxicab cab travel measure) works better than
Euclidian metric
 There are usually many routes, all the same shortest distance,
between a substation and a particular customer or service point
 But, which route is the least cost?

D   X  Y 

D  X 2  Y 2
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

33
The Electric Distribution System 67

The Feeder System


 Most Feeders are the same “size”
 Feeders are planned by starting with the
premise that the main trunk (the initial
segment out of the substation, through which
all the power is routed) will be the largest
economical conductor in the conductor set.
 The feeder layout is arranged so this segment
picks up enough load for its peak load to fall
somewhere in the middle or upper half of that
largest conductor’s economical range

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 68

The Feeder System

Developing Feeder System: Interaction Between Substation and Feeders


Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

34
The Electric Distribution System 69

Distribution Feeder Categories

Capacity
Constrained

Voltage
Drop
Constrained

Three Categories of Planning Situations with Respect to Feeder Layout

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 70

Distribution Feeder Categories


 Feeder Layout in Rural Areas
 Rural distribution systems are often not profitable
 Voltage drop limits design
 Losses costs are high
 Loads vary from very small single-phase to medium sized three-
phase
 Distances are tremendous
 Reliability requirements are below average
Two Principles of Best
Practices in Rural Distribution
1. Application of higher voltage
2. Use of single-phase feeders

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

35
The Electric Distribution System 71

Distribution Feeder Categories


 Feeder Layout in Rural Areas (Characteristics)
1. High primary voltage are favored
2. Single phase feeders are common
3. Extreme and innovative measures are often used
4. No provision is made for contingency backup of feeders
5. Very branch-like planning

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 72

Distribution Feeder Categories


 Underground Feeder Layout in Urban Areas
 Capacity limits design
 Layout is restricted to the street grid
 Loads are large and invariably three-phase
 Fixed cost is very high
 The cost of capacity shortfall is extremely high
 Reliability requirements are above average

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

36
The Electric Distribution System 73

Distribution Feeder Categories


 Underground Feeder Layout in Urban Areas
(Characteristics)

 Loop Feeders are the rule


 Maximum size cable is
often installed every where
 Very grid-like planning

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 74

Feeder Layout
 Distribution Configuration

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

37
The Electric Distribution System 75

Feeder Layout
 Radial Feeder Layout

Multi-Branch Layout Big Trunk Layout

Basic Feeder Routing Schemes

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 76

Feeder
Layout
 Radial
Feeder
Layout

Which is
best?

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

38
The Electric Distribution System 77

Feeder Layout
 Sectionalization Targets SAIFI & MAIFI
 Designing the protection scheme for the feeder so that it limits the
number of customers interrupted by any failure as much as practicable
 Divides a feeder into “sections” in order to isolate faults

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 78

Feeder Layout
 Switching Design Targets SAIDI
 Providing for alternate feed routes and a way to bring them into
operation so that the system can tolerate the outage of a major
component(s) while still providing good service
 Switchable zones are contiguous portions of a feeder that lie between
switches

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

39
The Electric Distribution System 79

Feeder Layout
FOUR ASPECTS OF THE PLANNING CONSIDERATIONS
FOR FEEDER SECTIONALIZATION AND SWITCHING
 CONFIGURATION
 Does the feeder system have alternate pathways through which power
can be routed when outages close off normal pathway?
 Are there switch points provided so that instantly, automatically, or
manually power can be re-routed as needed?
 Configuration planning involves selecting layouts that fit the needs and
approach to contingency backup planning being used in the area.

 CAPACITY
 Do the alternative pathways that are being arranged for switchable
zones have sufficient capability, both in terms of current (load) and
voltage (load reach), to meet at least temporary (emergency,
contingency) criteria when serving the additional load?
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 80

Feeder Layout
 SECTIONALIZATION
 Isolate any fault or equipment malfunction in a manner that minimizes
the number of customers whose service is interrupted
 At the poor end of the sectionalization scale:
• A fault anywhere results in loss of service to all customers
served by the feeder
 At the other end of the sectionalization scale:
• A feeder where any fault can be isolated while interrupting
service to no more than one customer

 SWITCH TIMING
 “Restore then Repair” Strategy: Switching time affects only the duration
of interruptions
• Hours (for manual operation of switch)
• Instantaneous (with fast automatic rollover switch)

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

40
The Electric Distribution System 81

Feeder Layout
OVERALL
PLANNING
APPROACH

FOUR ASPECTS OF
THE PLANNING
CONSIDERATIONS FOR
SECTIONALIZATION
AND SWITCHING
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 82

Contingency Support and


Switching Design

 Planning for Alternate routes of service during


equipment outages or emergencies is the major
aspect influencing selection of a feeder’s capacity,
type of route, or layout
 In the event of the outage of a major feeder
segment, service can be restored by:
1. Opening switches to isolate the portion which is out of service
2. Closing switches to connect the rest of the feeder to other source(s)

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

41
The Electric Distribution System 83

Contingency Support and


Switching Design
 Support from the Same Substation is Desirable due to
the following reasons:
 Substation Load Balance
 Feeder Load Reach
 Make Before Break Switching

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 84

Contingency Support and


Switching Design
 Single-Zone or Loop Contingency Backup
 Simplest approach to feeder contingency backup

 During contingencies, the feeder faces four times the total burden
(i.e. it must move twice its normal load, on average twice as far)
and it will cost nearly double what it would otherwise cost
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

42
The Electric Distribution System 85

Contingency Support and


Switching Design
 Single-Zone or Loop Contingency Backup

Initial PW Cost of
Feeder increase
by 10% to
provide the
Contingency
Support

 Points A (tie-point) & B (point of worst voltage drop during


contingency operation)
 Dotted Lines show the points where voltage drop reaches Range
B (ANSI Standard – 10.8%)

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 86

Contingency Support and


Switching Design
 Switched Contingency Zones
 Alternative arrangement for Contingency Backup

Advantages:
• Additional load
transferred to any
neighboring feeder is
only a fraction of a full
feeder load
• Load reach increase for
power flow during Disadvantages:
emergency
• More switch have to be operated
in order to restore service

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

43
The Electric Distribution System 87

Contingency Support and


Switching Design

Normally open
switch

Switching flexibility “around the


substation” is often provided by
installing lines and switches near
the substation. Any one feeder
can be isolated near the
substation and switched onto
either of two neighbors
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 88

Contingency Support and


Switching Design
 Multi-Zone Contingency Scheme

Three-Branch/Three-Zone scheme with nine switches

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

44
The Electric Distribution System 89

Contingency Support and


Switching Design
 Multi-Zone Contingency Scheme
Low Capital Cost

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 90

Contingency Support and


Switching Design
 Required Number of Zones
to meet feeder-level contingency requirements

 E  1 
MAX 1   
 T  E ,  D  1.125 
Zones Required 
B2

Where E – the economical rating of lines used for tie support


T – the thermal rating of lines used for tie support
D – ratio of maximum voltage drops permitted under
emergency and normal operation
B – Ratio of capital cost, contingency plan over no
contingencies planned
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

45
The Electric Distribution System 91

Contingency Support and


Switching Design
 Required Number of Zones
EXAMPLE
Line Type Low Loading High Loading Load Reach
#2 0 MW 1.6 MW 3.5 Miles
4/0 1.6 MW 3.7 MW 3.6 Miles To be used


336 3.7 MW 5.1 MW 3.6 Miles
for
switchable
636 5.1 MW 8.5 MW 3.5 Miles
trunks and
1113 8.5 MW 12.4 MW 2.7 Miles feeder ties
Thermal Limits: For 336 = 10.3 MW & For 636 = 14.3 MW @ 12.47 kV
Contingency/normal voltage drop ratio = 10.8%/7.5% = 1.44
Desired Budget Ratio for Contingency/No Contingency = 1.1
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 92

Contingency Support and


Switching Design
 Required Number of Zones
Averaging the economical loading points and thermal limits of the line
types,
E = (5.1 + 8.5)/2 = 6.8 MW
T = (10.3 + 14.3)/2 = 12.3 MW

Then,  6.8   1 
MAX 1   
 12.3  6.8 ,  1.44  1.125 
Zones Required 
1.12
MAX 2.24,3.17
  2.62  3 Zones
1.21

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

46
The Electric Distribution System 93

Contingency Support and


Switching Design
 Required Number of Zones
If the Utility is willing to spend 1.8 times the minimum possible feeder
layout cost in order to gain contingency support, then

MAX 2.24,3.17
Zones Required   0.97 1 Zone
3.24

And the system can support contingency operation of feeders


and transformers with single zone/loop configurations

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 94

Contingency Support and


Switching Design

Alternating the feeders from


different transformers by
rotation makes contingency
support for the transformer level
via feeder switching somewhat
easier to arrange. If either
transformer is lost, each of its
feeders lies between feeders
which are still in service, making
the job of picking up its load
from those remaining in service
somewhat easier.

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

47
The Electric Distribution System 95

Protection and Sectionalization


of the Feeder System
The primary purpose of protection engineering is safety and
protection, not customer service reliability

Protection Coordination of the distribution system is an


Engineering Department Function and not a Planning
Department Function

The manner in which the protection is applied, particularly the


determination of the number and locations of protective devices
installed in the distribution system and the coordination of their
operating characteristics, has a great deal to do with the
reliability of service that the utility’s customers see.

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 96

Protection and Sectionalization


of the Feeder System
 Feeder System Protection
 Over-voltage protection
 Over-current protection Has something to
do with
 Protective Equipment Sectionalization
 Breakers
 Switches
 Fuses
 Cutouts
 Automatic Line Reclosers
 Sectionalizers

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

48
The Electric Distribution System 97

Protection and Sectionalization


of the Feeder System
A 600A breaker relay at the
substation will pick-up
current above 600A.
Fuse at A must have three
characteristics:
a) It must be able to
interrupt at least 700A;
b) It must interrupt when
the current is 160A or
more; and
c) It must not operate
when the current is 58A
58A
700A Fault

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 98

Protection and Sectionalization


of the Feeder System
The 600A breaker relay and the
fuse at A povides protection for
the entire feeder.
But, it is not necessarily
sectionalized!
If a fault occurs from Point A to
the dotted line, and the breaker
relay picks up and opened the
breaker, it will interrupt 162 DTs.
If the Fuse at A operates
instead, only 47 DTs will be
interrupted

58A
Optimal location of
600A Fault line
700A Fault
fuse
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

49
The Electric Distribution System 99

Protection and Sectionalization


of the Feeder System

Customer minutes of interruption avoided due to the installation


of each of the 33 fuses that can be installed on the feeder
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 100

Protection and Sectionalization


of the Feeder System

Alternative protection and sectionalization scheme using one fuse to protect “the pair”
of lateral extensions on both sides of the trunk. Requires only 1/2 of the devices

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

50
The Electric Distribution System 101

Protection and Sectionalization


of the Feeder System
Large-trunk feeder with
the mid-trunk fuse at its
optimal sectionalization
position along with
switches, added there
and at the end of the
trunk end, so that the
farther section can be
restored through tie
switching in the event of
an outage of the near-
substation trunk section

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

The Electric Distribution System 102

Protection and Sectionalization


of the Feeder System

Large trunk design requires 34 Three-branch design requires 56


protective devices protective devices, but delivers 5%
better SAIDI. In addition, a further
three devices can be added for a
total of 20% better SAIFI
Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

51
The Electric Distribution System 103

Electrical & Electronics Engineering Institute EE153 – Electric Power Distribution Systems
University of the Philippines Prof. Rowaldo del Mundo

52

Das könnte Ihnen auch gefallen